3-01 Contract and Special Provisions.pdf

PDF 7 MB Posted

Attached to
Bridge Street Roadway and Pedestrian Improvements
Solicitation number
US.264203
Issued by
Cumberland County, Pennsylvania

About this file

This is a Proposal and Contract Instructions document for the Construction of Roadway and Pedestrian Improvements on Bridge Street (SR 2035) in New Cumberland Borough, Cumberland County, Pennsylvania, prepared by Bowman Consulting Group, LTD. The project involves the removal of existing stamped asphalt crosswalks and installation of updated crosswalk markings, construction of approximately 300 feet of concrete sidewalk, design-build ADA curb ramps, and striped curb extensions along Bridge Street. The project also includes an optional Add Alternate 1 for painting the interior of curb extensions with colored methyl methacrylate (MMA) coating. Sealed bids will be received electronically via PennBid until 11:00 AM on Tuesday, December 22, 2026, with bids opening at approximately 11:00 AM the same day. Clarifications from bidders must be submitted in writing by 5:00 PM on Thursday, December 17, 2026, through the PennBid Messages/Vendor Discussions feature. No pre-bid meeting will be held. The contract is anticipated to be awarded at the Borough's January 13, 2027 Council meeting. Work is scheduled to begin on February 1, 2027 (or at the discretion of the Borough) and must be substantially completed by May 28, 2027, with liquidated damages assessed at $825.00 per working day for failure to complete on time. An 18-month warranty period begins after acceptance of work, during which the contractor must maintain the performance bond as a maintenance bond at 10 percent of construction cost.

The bid structure requires pricing for the Base Bid (excluding crosswalks), Crosswalk Option A (Piano Keys Type B), Crosswalk Option B (Preformed Thermoplastic Decorative Crosswalk in Maroon Herringbone with White Grout), and Add Alternate 1 (MMA Curb Extension Coating). The owner will calculate two combined bids for evaluation purposes and will select the lowest responsible bidder based on combined bid amounts within available funds, with the crosswalk selection and base contract award potentially going to different bidders. All bids must include a proposal guarantee of 10 percent of the greater of Combined Bid A or Combined Bid B. The project is funded in part by a Community Development Block Grant (CDBG) from Cumberland County and a Multimodal Transportation Fund (MTF) grant from the Commonwealth Financing Authority. Davis-Bacon wage rates (federal wage determination No. PA20260006, modification 2, dated September 17, 2026) apply to all workers on the project, with weekly certified payroll submissions required. Contractors and all subcontractors must comply with the Prohibition of Illegal Alien Labor on Assisted Projects Act and all requirements related to the Right-to-Know Law. Performance and payment bonds, each in an amount equal to 100 percent of the contract price, and evidence of all required insurance must be provided by the successful bidder. Proof of PennDOT Pre-Qualification K and O, a signed Non-Discrimination/Sexual Harassment Clause, a Non-Collusion Affidavit, and a Public Works Employment Verification Form are required with all bids.

View the file

Other files

File Type Posted
8-CFA Requirements.pdf PDF
9-00 Plans.pdf PDF
4-04 Attachment 4.pdf PDF
6-CDBG Contractor Packet.pdf PDF
1-HOP Permit.pdf PDF
5-2026.11.23 Davis-Bacon Wage Rates.pdf PDF
2-02 Attachment 2.pdf PDF
7-03 Attachment 3.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROPOSAL AND CONTRACT INSTRUCTIONS

PROPOSAL AND CONTRACT

ATTACHMENT 1-A (SPECIAL PROVISIONS)

ATTACHMENT 1-B

ATTACHMENT 2

ATTACHMENT 3

ATTACHMENT 4

Construction of Roadway and Pedestrian Improvements on Bridge Street

NEW CUMBERLAND BOROUGH, CUMBERLAND COUNTY, PA

All documents prepared by Bowman Consulting Group, LTD. are instruments of service in respect of the project. They are not intended or represented to be suitable for reuse by Owner or others on extensions of the Project or on any other project. Any reuse without written verification or adaptation by Bowman Consulting Group, LTD will be at Owner's sole risk and without liability or legal exposure to Bowman Consulting Group, LTD; and Owner will indemnify, and hold harmless Bowman Consulting Group, LTD from all acts, claims, damages, losses and expenses arising out of or resulting therefrom

ENGINEERS:

Bowman Consulting Group, LTD.

415 Fallowfield Road Camp Hill, PA, 17011 CONTACT: Danielle Derolf, P.E.

PHONE: (717) 409-5472

EMAIL: danielle.derolf@bowman.com

OWNER:

New Cumberland Borough 1120 Market Street New Cumberland, PA 17070 CONTACT: Nathaniel Dysard, Borough Manager

PHONE: (717) 774-0404

EMAIL: manager@newcumberlandborough.com

BOWMAN PROJECT NO.: 314694-02-001

PA One Call Design Serial Numbers: 202428430005, 20263090846 Project Advertised in local paper of general circulation and on Penn Bid.

Project Bid and Let on Penn Bid (https://pennbid.bonfirehub.com/portal)

Instructions to Bidders

I. BID SUBMISSION - Bids signed and under seal, executed, and dated will be received online via PennBID until 11 AM, Tuesday, December 22, 2026. Following this, Bids will be made publicly available via PennBid as stipulated herein.

II. INQUIRIES/ADDENDA

a. Bidder shall submit all questions about the meaning or intent of the Bidding

Documents via the “Messages/Vendor Discussions” feature in PennBid.

b. Addenda may be issued during the bidding period. All Addenda become part of the

Contract Documents. Include resultant costs in the Bid Amount.

c. Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents

d. Clarifications requested by bidders must be in writing by 5 PM on Thursday, December 17, 2026. The reply will be in the form of an Addendum, a copy of which will be posted on PennBid.

e. Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.

III. PREBID MEETING - No Pre-bid meeting will be held for this project.

IV. SUBMISSION PROCEDURE

a. Bidders shall be solely responsible for submitting their bids in the manner and prescribed. Bidders can submit, update, and withdraw bids until the date and time described in the Invitation to Bid.

b. Sealed bids shall be submitted online via the PennBid Program (https://pennbid.bonfirehub.com).

c. If more than one proposal on any project is submitted by an individual, firm or partnership, corporation or association under the same or different names, only one lowest proposal will be considered.

d. Each bidder must submit the following, contained in the attachments:

i. Signed and executed Contract by Contractor including Proposal Guarantee

ii. Signed and executed Special Provisions to Contract (Attachment 1-A)

iii. Signed and executed Non-Discrimination/Sexual Harassment Clause

iv. Signed and executed Non-Collusion Affidavit

v. Signed and executed Public Works Employment Verification Form

vi. Proof of PennDOT Pre-Qualification K and O

V. EVALUATION AND AWARD

a. Bid Structure. The Bid Form consists of (1) Base Bid Pricing, which does not include crosswalks; (2) Crosswalk Option A: Piano Keys (Type B); (3) Crosswalk Option B:

Preformed Thermoplastic Decorative Crosswalk (Maroon Herringbone with White Grout – No Stamping); and (4) Add Alternate 1: MMA Curb Extension Coating.

Bidders shall price the Base Bid, both crosswalk options, and Add Alternate 1. A Bid that omits a price for any of these may be rejected as non-responsive.

b. Combined Bids. For evaluation, the Owner will calculate two Combined Bids for each responsive Bid:

i. Combined Bid A = Base Bid + Crosswalk Option A

ii. Combined Bid B = Base Bid + Crosswalk Option B

Add Alternate 1 is not included in either Combined Bid.

c. Order of Evaluation. The Owner will evaluate and award in the following order, completing each step before proceeding to the next:

i. Crosswalk Selection: The owner will first determine the lowest responsible

Bidder on Combined Bid B. If that Bidder’s combined Bid B is within the funds available to the Owner at the time of award, the Owner will select Crosswalk Option B. If it is not, the Owner will select Crosswalk Option A and determine the lowest responsible Bidder on Combined Bid A.

ii. Award of Base Contract: The Contract will be awarded to the lowest responsible Bidder on the Combined Bid selected in step 1. The lowest responsible Bidder may differ between Combined Bid A and Combined Bid B.

iii. Add Alternate 1. After Step 2, the Owner may accept Add Alternate 1, in whole, if funds are available at the time of award. Add Alternate 1 will not be considered in determining the lowest responsible bidder.

d. Funds available means the funds the Owner has determined are available for the

Project at the time of award. The Owner’s determination is final.

e. The proposal guarantee shall be 10% of the greater of Combined Bid A or Combined Bid B.

f. The Owner reserves the right to reject any or all Bids and to waive informalities as stated in the Invitation to Bid.

MS-944 (7-09)

TIME

, on the above Letting Date.

TIME

and specifications on file at as well as the supplements complete all work within calendar days. If all work is not completed on time, liquidated damages will be assessed at the rate of $825.00 per working day.

3 Accompanying this proposal is a certified check or bid bond in the amount of made payable to the municipality as a proposal guarantee which, it is understood, will be forfeited in case the contractor fails to comply with the requirements of the proposal.

B. PROPOSAL OF:

1 The only person interested in the proposal as principal (s) is (are):

2 None of the above persons are employees of the municipality.

3 This proposal is made without collusion with any other person, firm or corporation.

December 22, 2026

PROPOSAL AND CONTRACT

( WHEN EXECUTED ) THIS PROPOSAL INCLUDES

INSTRUCTIONS TO BIDDERS

INSTRUCTIONS ON PAGE 4

A. DEPOSIT OF PROPOSALS.

Sealed bids shall be submitted online via the New Cumberland Borough PennBid Program by MUNICIPALITY (NAME & TYPE)

DATE Nathaniel Dysard

MANAGER

Sealed Proposals will be received on or before 11:00 AM on the above Letting Date. 1120 Market Street

New Cumberland, PA 17070

ADDRESS

Bids will be opened and read at approximately

11:00 AM

The contractor proposes to furnish and deliver all materials ( including Form CS-4171, CERTIFICATE OF COMPLIANCE and/ or TR-465 DAILY BITUMINOUS MIXTURE CERTIFICATION ) and to do and perform all work on the following project as more specifically set forth in the Schedule of Prices (Attachment), in accordance with drawings

PennBid and special requirements contained herein and/ or attached hereto and current PennDOT Specifications (Publication 408), except (a) bidders need not be prequalified by PennDOT (Sec.102.01), and (b) Volumetric testing of bituminous paving materials is not required (Sec. 409).

If designated as the successful bidder, the contractor will begin work on the date specified in the notice to proceed, or as otherwise provided in the special requirements, and will see attachment 1-A

10% OF BID

All plans and specifications referred to above and the site of the work have been examined by the contractor. The contractor understands that the quantities indicated herein are approximate and are subject to change as may be required; and that all work is payable on the basis of the unit price listed on the Schedule of Prices.

NAME / ADDRESS OF CONTRACTOR

CONTRACTORS CERTIFICATION

It is hereby certified as follows:

BY: DATE:

TITLE:

DATE:

TITLE:

TITLE:

TITLE:

TITLE:

The contractor will comply with all requirements of the laws and implementing regulations of the Commonwealth of Pennsylvania and the United States relating to human relations, equal opportunity and non-discrimination in employment, and will pay to workmen employed in the performance of the contract the wages to which they may be entitled.

The contractor will provide the municipality with a performance bond, conditioned upon the faithful performance of the contract in accordance with the plans, specifications and conditions thereof, and a payment bond, conditioned on the prompt payment of all material furnished and labor supplied or performed in the prosecution of the work, in accordance with the Public Works Contractors’ Bond Law of 1967; and an affidavit accepting the provisions of the Workmen’s Compensation Act of 1915, as amended.

CONTRACTOR

President

WITNESSED OR ATTESTED BY:

TO BE EXECUTED ONLY IN THE EVENT THE ABOVE PROPOSAL IS ACCEPTED

ACCEPTED ON : January 13, 2027

DATE

New Cumberland Borough

MUNICIPALITY

BY:

BY:

ATTESTED BY:

Borough Manager

SEAL

X Traffic Control and Safety Devices to be provided by the Contractor.

X Delivery tickets for all materials.

X CS-4171 Certificate of Compliance and/ or TR-465 Daily Bituminous Mixture Certification required for all materials.

X 10 working days prior to start of project.

X 5/28/2027 . After 5/28/2027 the rate of $ 825.00 per calendar day. (Substantial Completion definition of Completed)

Roadway to be power broomed by (contractor municipality )prior to start of project.

X Excess material to be removed by (contractor X municipality .)

X Municipality to inspect project.

X Need Bill of Lading for each shipment of bituminous material per Section 702.1(c) of Specifications 408.

X Tack Coat required per Section 460, or 409 for superpave, of Specifications 408 and is incidental to paving item unless noted otherwise.

X Prime Coat required per Section 461 of Specifications 408.

X Bituminous Seal on all abutting pavement and curbs required.

X Saw cut or Milled Paving Notch required and incidental to paving item unless noted otherwise.

Scratch/ Leveling Courses to be placed at the discretion of appointed inspector(s).

Municipality reserves the right to limit work completed.

Taper pavement the last 3 feet to curb.

For FOB Source bids, hauling distance will determine selection of bid award.

Municipality reserves the right to procure material which best suits their requirements after all bids and items are reviewed.

X Incidental Preparation and clean up required. ( Project Construction Materials )

The municipality reserves the right to make an award on the basis of the aggregate total for all like items on which quotations are received.

Provide design, which meets Specifications Form 408 to the municipality 5 days prior to start of work.

Contractor responsible for defects that occur within one year of applications.

Contractor required to review proposed project with Municipality’s Representative prior to bidding.

Oil Samples required from each distributor truck by contractor (1) one quart : A.M. & P.M. and witnessed by municipality and retained by municipality. (Oil samples must be placed in an approved type container that is compatible with oil sample.)

At least three random stone samples to be taken by contractor on project site witnessed by municipality and retained by municipality.

X Complete all testing in accordance with Publication 408 except for superpave volumetric testing.

X Notice to Proceed will be the date of Contract acceptance.

X Final Completion Certificate & Notice of Completion required.

X Future award of Contract will be based on quality of work as determined by the municipality.

X Contractor, notify all residents and businesses of pending work to be performed.

X persons performing any aspect of work pursuant to this contract who are required to have a commercial driver's license are in a program for drug & alcohol testing in accordance with the Omnibus Transportation Employee Testing Act of

1991 and the Federal Regulations adopted pursuant thereto. PLEASE SEE ALL SPECS & ATTACHMENTS.

ATTACHMENT 1-A CONTINUED ON NEXT PAGE

Work to be completed on or before Liquidated damages apply at

Full width pavement with one pass required.

Parties agree that the relationship between the contractor and the employer is one of independent contractor and not employer/employee and the individual employees of the contractor who will be performing the work pursuant to this con-tract are not employees of the employer. Contractor hereby certifies, represents, and warrants to the employer that all

Notify the Municipality

(5-06) SPECIAL PROVISIONS TO CONTRACT MS-944 ( ATTACHMENT 1-A )

CONTAINS IMPORTANT INFORMATION FOR THE CONTRACTOR

The Prime Contractor and subcontractors must comply with all of the following provisions that are marked with an "X".

( Maintenance and Protection of Traffic to comply with current MUTCD, Publication 212 and Publication 213.)

Special Provisions to Contract – Governing Specifications

(5-06) SPECIAL PROVISIONS TO CONTRACT MS-944

CONTINUED FROM PREVIOUS PAGE ~ ATTACHMENT 1-A

GOVERNING SPECIFICATIONS AND APPLICABLE DESIGNATED SPECIAL PROVISIONS

Section Includes:

I. GOVERNING SPECIFICATIONS

II. APPLICABLE DESIGNATED SPECIAL PROVISIONS

III. STATUTORY REQUIREMENTS

IV. TECHNICAL SPECIFICATIONS

V. NON-STANDARD BID ITEMS

I. GOVERNING SPECIFICATIONS. This bid proposal is made under, subject to, and governed by:

PennDOT Publication 408/2026, Current Edition at time of bid opening shall govern all work for this Contract (Sect 105.04). Within these Specifications where dual measurement and tabular options are presented, English standards apply.

Contractor shall comply with all aspects of the Contract, to include making all required notifications on behalf of the Owner.

Wherever the word Department or State is utilized in Publication 408 or other contract documents in reference to owner name, and owner duties, procedures, responsibilities, limitations, liabilities and actions, replace with the words "New Cumberland Borough". In general, wherever Publication 408 specifies actions to be taken by the Owner it shall mean by “New Cumberland Borough.” All other uses of Department shall mean Department of Transportation (Sect 101.03).

Revise Section 101.03 to read:

AGENCY HEAD- Borough Manager, or designated person, when in reference to the owner leadership.

CONTRACTING OFFICER- Borough Manager, or designated person, when in reference to the owner leadership.

OWNER- New Cumberland Borough Cumberland County, Pennsylvania ENGINEER- An individual licensed and registered under the Laws of the Commonwealth of

Pennsylvania.

ONLINE BID- A bid submitted via the internet using PENNBID- Pennsylvania’s Electronic Document and Bid Management Program.

REPRESENTATIVE- The authorized representative acting on behalf of the OWNER or PENNDOT.

SECRETARY- Borough Manager, or designated person, when in reference to the owner leadership.

Special Provisions to Contract – Applicable Designated Special Provisions

II. APPLICABLE DESIGNATED SPECIAL PROVISIONS. The following Designated Special Provisions are found in Appendix C to the above Governing Specifications. Those that apply to this bid proposal are preceded with a check (i.e., “X”). Goals, minimum levels of participation, or other project specific requirements associated with these documents are also established where applicable:

(_) DSP4. Diverse Business (DB) Requirements for Non-Federally Funded Construction Projects. This provision is applicable to contracts funded with state funds, without federal funds.

(_) DSP7. Disadvantaged Business Enterprise (DBE) Requirements for Federally funded Construction Projects. This provision is applicable to any Federally funded (in part or whole) contract for a construction project.

(_) DSP8. F. A. R.—Required Contract Provisions Federal-Aid Construction Contracts – FHWA-1273 (Revised October 23, 2023). See attachments to the Proposal. This provision is applicable to any federally funded (in part or whole) contract for a construction project.

(X) DSP9. Special Supplement—Anti-Pollution Measures – August 26, 1999. This provision is applicable to all contracts.

(_) DSP12. Executive Order 11246, with Appendices A and B. This provision is applicable to contracts with federal funds (in part or whole).

(_) DSP13. Buy America. This provision is applicable to contracts with federal funds (in part or whole, and to state-funded projects when any federal funds were allocated at any phase of the work on the overall project but not under the current contract (for example, design), even if the construction contract is 100% state funded.

(_) DSP15. Commonwealth Standard Terms and Conditions. This provision is applicable to all contracts.

(_) DSP16. Lobbying Certification Form. This provision is applicable to contracts with federal funds and a contract amount of $100,000 or greater. If applicable, the Contractor shall complete this form and return it to PennDOT during contract execution. (Form is located in ECMS File Cabinet and must be completed and uploaded to the Contractor Checklist in ECMS).

(_) DSP17. Federal Audit Clause. This provision is applicable to contracts with federal funds. As used in this DSP, “[Name of Subrecipient]” refers to the Contractor.

(_) DSP19. The United States Department of Transportation (USDOT) Standard Title VI/Non- Discrimination Assurances. This provision is applicable to contracts with federal funds. The Contractor’s signature on an agreement will be deemed a signature on this exhibit. As used in this DSP, the term “Subrecipient” refers to the Contractor.

(X) DSP20. FAR 52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act-Covered Foreign Entities. This provision is applicable to contracts with federal funds (in part or whole).

Special Provisions to Contract – Statutory Requirements

III. STATUTORY REQUIREMENTS

A. WAGE REQUIREMENTS: FEDERAL DAVIS-BACON ACT

1. Applicability and Controlling Wage Rates

a. This Project is subject to the federal Davis-Bacon and Related Acts ("Davis-Bacon") because it is funded in part with Community Development Block Grant funds administered by the Housing and Redevelopment Authorities of Cumberland County ("CCHRA") and with a Multimodal Transportation Fund grant from the Commonwealth Financing Authority ("CFA"). The Pennsylvania Department of Community and Economic Development ("DCED") has authorized the use of Davis- Bacon wage rates in place of the rates under the Pennsylvania Prevailing Wage Act, 43 P.S. §§ 165-1 through 165-17, for this Project.

b. The federal wage determination No. PA20260006, modification 2, dated

September 17, 2026, is attached.

c. The Contractor and all Subcontractors shall pay each worker not less than the Davis-Bacon rate for the classification of work performed.

d. If a classification is not listed in the wage determination, or the Contractor is unsure which classification applies, the Contractor shall notify the Engineer and CCHRA before the work begins. Additional Davis-Bacon classifications are approved only through the procedure in the HUD Federal Labor Standards Provisions.

e. The rates in effect are those in the wage determination as attached to the Contract Documents at bid opening. If the Owner notifies the Contractor in writing that a determination has been modified, the modified rates apply from the date stated in the notice.

1. Post the general prevailing minimum wages for each craft and classification involved, as determined by the Secretary of Labor and Industry, for the entire period of construction in a prominent and easily accessible place at the Site of the Work. The posted notice shall contain at least the following:

(i) Name of Project;

(ii) Name of the public body for which it is being constructed;

(iii) The crafts and classifications listed in the Secretary's determination for this Project;

(iv) The general prevailing minimum wage rates for each craft and classification and the effective date of any changes; and

(v) A statement advising workmen that if they have been paid less than the general prevailing minimum wage rate for their classification, or if the Contractor or a Subcontractor is not complying with the Act or its regulations in any way, they may file a protest with the Secretary of Labor and Industry.

Workmen paid less than the specified rate have a civil right of action for the difference, which must be exercised within six months of the event creating the right.

2. Davis-Bacon Act

a. The HUD Federal Labor Standards Provisions (HUD-4010) are included in the project manual and are part of this Contract. The Contractor shall comply with them and with 29 CFR Parts 1, 3, and 5, which are incorporated by reference. Key requirements include:

1. Laborers and mechanics shall be paid weekly, without deductions other than those permitted by 29 CFR Part 3, at not less than the applicable wage determination rate and fringe benefits.

2. The Contractor shall submit certified payrolls weekly, with a signed Statement of Compliance, for each week in which work is performed, in the manner required by Section II.b. The Contractor is responsible for submission of its Subcontractors' payrolls. Payrolls shall identify employees by an individual identifying number (for example, the last four digits of the Social Security number), not by full Social Security number or home address. Form WH-347 may be used.

3. Apprentices and trainees may be paid less than the journeyman rate only as permitted by HUD-4010 and 29 CFR Part 5 and as registered with an approved program.

4. If the prime Contract exceeds $100,000, the overtime requirements of the

Contract Work Hours and Safety Standards Act apply (1.5 times the basic rate for hours over 40 in a workweek).

5. The federal wage determination and the Davis-Bacon poster (WH-1321) shall be posted at the Site of the Work, together with the other notices listed in the CCHRA Contractor Labor Compliance Packet.

6. The Contractor certifies that neither it nor any person or firm with an interest in it is ineligible to receive federally assisted contracts, and shall not subcontract to any such person or firm.

b. b. The Contractor shall insert the provisions of this Section A, HUD-4010, the applicable wage determination, and a requirement that lower-tier subcontractors do the same, in every subcontract. The Contractor is responsible for compliance by its Subcontractors at every tier.

3. Enforcement and Payment

a. The Owner and CCHRA may withhold payment as necessary to cover unpaid wages, as provided in HUD-4010. A discrepancy in payroll or compliance documents not corrected within two weeks of notification may result in payment being withheld.

b. Final payment and release of retainage is conditioned on CCHRA's written acceptance of all labor compliance documents, including the Final Certification – Labor Compliance.

c. Labor standards disputes arising under Davis-Bacon shall be resolved under the

U.S. Department of Labor procedures in 29 CFR Parts 5, 6, and 7, and not under the Contract's general disputes clause. The cost of compliance with the Davis- Bacon wage requirements is included in the Contract price, and no additional compensation will be allowed.

4. Records

a. The Contractor and each Subcontractor shall retain payroll and basic records for the longest of: (i) three years after completion of the work (HUD-4010); and (ii) [five years from the date of final audit or closeout of the CFA grant]. Longer retention applies if audit questions, claims, or litigation remain unresolved.

Records shall be available for inspection and copying by the Owner, CCHRA, HUD, the U.S. Department of Labor, and the CFA, and the Contractor shall permit interviews of employees during working hours on the job.

B. CONTRACT PROVISIONS - RIGHT TO KNOW LAW

1. Contract Provisions – Right to Know Law 8-K-1532

a. The Pennsylvania Right-to-Know Law (RTKL), 65 P.S. §§ 67.101-3104, applies to this

Contract.

b. If the Borough needs assistance in any matter arising out of the RTKL related to this Contract, the Borough will notify the Contractor using the legal contact information provided in this Contract. The Contractor, at any time, may designate a different contact for such purpose upon reasonable prior written notice to the Borough.

c. Upon written notification from the Borough that it requires assistance in responding to a request under the RTKL for information related to this Contract that may be in the Contractor’s possession, constituting, or alleged to constitute, a public record in accordance with the RTKL (“Requested Information”), the Contractor will:

1. Provide the Borough within 10 calendar days after receipt of written notification, access to, and copies of, any document or information in the Contractor’s possession arising out of this Contract that the Borough reasonably believes is Requested Information and may be a public record under the RTKL; and

2. Provide such other assistance as the Borough may reasonably request, in order to comply with the RTKL with respect to this Contract.

d. If the Contractor considers the Requested Information to include a request for a

Trade Secret or Confidential Proprietary Information, as those terms are defined by the RTKL, or other information that the Contractor considers exempt from production under the RTKL, notify the Borough and provide, within 7 calendar days of receiving the written notification, a written statement signed by a representative of the Contractor explaining why the requested material is exempt from public disclosure under the RTKL.

e. The Borough will rely upon the written statement from the Contractor in denying a RTKL request for the Requested Information unless the Borough determines that the Requested Information is clearly not protected from disclosure under the RTKL. Should the Borough determine that the Requested Information is clearly not exempt from disclosure, provide the Requested Information within 7 calendar days of receipt of written notification of the Borough’s determination.

f. Failing to provide the Requested Information within the time period required by these provisions, indemnify and hold the Borough harmless for any damages, penalties, costs, detriment or harm that the Borough may incur as a result of this failure, including any statutory damages assessed against the Borough.

g. The Borough will reimburse the Contractor for any costs associated with complying with these provisions only to the extent allowed under the fee schedule established by the Office of Open Records or as otherwise provided by the RTKL if the fee schedule is inapplicable.

h. The Contractor may file a legal challenge to any Borough decision to release a record to the public with the Office of Open Records, or in the Pennsylvania Courts, however, indemnify the Borough for any legal expenses incurred by the Borough as a result of such a challenge and hold the Borough harmless for any damages, penalties, costs, detriment or harm that the Borough may incur as a result of the failure, including any statutory damages assessed against the Borough, regardless of the outcome of such legal challenge. As between the parties, agree to waive all rights or remedies that may be available as a result of the Borough’s disclosure of Requested information pursuant to the RTKL.

i. The Contractor’s duties relating to the RTKL are continuing duties that survive the expiration of this Contract and continue as long as the Requested Information remains in the Contractor's possession.

C. PENNSYLVANIA “UNDERGROUND UTILITY LINE PROTECTION ACT”, (P.L. 852, NO. 287, AS

AMENDED)

1. Refer to the Pennsylvania Underground Utility Line Protection Act, (Act) (P.L. 852, No. 287, as amended) for the definition of all technical terms used in this paragraph. It shall be the duty of each Contractor who intends to perform excavation or demolition work to:

a. Ascertain the location and type of users' lines either by inspection of the attached drawing with referenced PA One Call Serial Number;

b. If there be no such drawing, by contacting all users as listed in the County Recorder of Deeds for the appropriate political subdivision;

c. And, notify all users not less than three (3) days prior to the day of beginning of such work and to request information regarding underground utilities at the work location.

d. Contractor must comply with all requirements of the Act, as amended.

2. Underground Utilities Not Governed by the Act: The Owner and Contractor agree that certain underground utilities or facilities, including but not limited to, on lot septage systems, water well supply lines, buried roof leaders, and foundation drains, and private electrical or communication lines, that serve private residential or commercial uses are not governed by the Act and therefore such lines may not be located in accordance with the Act. In cases where the Contractor encounters and damages such lines, he shall repair the same when directed by the Engineer and shall be compensated in accordance with the unit prices established in the Contractor’s Bid.

3. Un-Marked Utilities: Un-marked utilities are those underground facilities which are governed by the Act, and which have not been located by the Facility Owner in accordance with the Act. Should the Contractor be in compliance with the Act and should he damage such un-marked underground facilities, his sole recourse for costs associated with delay is to the Facility Owner. The Owner and Engineer shall have no liability to the Contractor for such occurrences.

4. Underground Facilities Whose Locations Cannot Be Provided: When the information required from the Facility Owner under the Act cannot be provided or it is reasonably necessary for the Contractor to ascertain the precise location of an underground utility through prudent techniques, the Contractor shall, only after providing written notice to both the Engineer and the Owner, receive additional compensation for additional work as provided in the latest edition of the Pennsylvania Department of Transportation Form 408 specifications for extra work performed on a force account basis. In cases where additional compensation is provided, the quantities for unit price work under the Contract shall be adjusted so as to avoid duplicate payment to the Contractor. In order to receive additional compensation, Contractor shall comply and shall document compliance with all the requirements of Form 408. Additional compensation shall be paid after execution of a Change Order to the Contract. This shall be the Contractor’s sole and exclusive right to additional compensation and no other additional compensation shall be provided.

D. PROHIBITION OF ILLEGAL ALIEN LABOR ON ASSISTED PROJECTS ACT (P.L. 173, NO. 43, OF MAY 11, 2006)

1. The Contractor shall comply with all requirements of the Prohibition of Illegal Alien Labor on Assisted Projects Act, Act of May 11, 2006, P.L. 173, No. 43, as amended.

2. No person shall knowingly employ or knowingly permit the labor services of an illegal alien on any project.

3. The contractor shall not knowingly permit any of its subcontractors to knowingly employ the labor services of an illegal alien on activities funded as a whole or in part by a grant or loan issued by an executive agency of the Commonwealth of Pennsylvania

Special Provisions to Contract – Technical Specifications

IV. TECHNICAL SPECIFICATIONS

A. Work is to start (Notice to Proceed) on 2/1/2027 or at the discretion of the Borough and shall be substantially complete by 05/28/2027 and ready for Final Acceptance.

B. Borough to issue all required municipal Permits to Contractor as part of Notice to Proceed. Permit fees will be waived. Contractor is responsible for meeting all permit conditions including notification procedures. Permits for this project include:

a. HOP Permit number 08120744

C. Contractor shall provide an 18-month warranty on all work to begin after Acceptance of Work.

Contractor shall maintain the Performance Bond as a maintenance bond at 10% of construction cost during the warranty period.

D. Work shall be performed in accordance with ITEM 0901-0001, typically between 7 AM to 7 PM Monday – Friday. Weekend work and evening work is permitted with advance notice to the Owner and PennDOT. State Road Lane closures are not permitted between the hours of 6:00 AM to 9:00 AM and 3:00 PM and 6:00 PM.

E. Contractor is responsible for receiving and unloading products at Site and arranging for storage of all materials and products. The gravel parking lot on Front Street adjacent to the area of new sidewalk may be used by the Contractor.

F. Work shall remain within all right-of-way or temporary construction easements.

G. Protect and maintain existing access drives, driveways, sidewalks, doors, and parking areas adjacent to the work and used by the public. If needed, coordinate with property owners for obstructions. Do not close or obstruct walkways or driveways without permission from the property owner.

H. Contractor responsible for scheduling a pre-construction meeting with the Borough prior to beginning work.

I. This work is funded in part through a CDBG grant from Cumberland County and an MTF grant from the Commonwealth Financing Authority. Contractor is responsible for meeting the requirements of each grant including, but not limited to, wage verifications, subcontract requirements, and jobsite postings.

Special Provisions to Contract – Non-Standard Bid Items

V. NON-STANDARD BID ITEMS

ITEM 0901-0001 - MAINTENANCE AND PROTECTION OF TRAFFIC DURING CONSTRUCTION

901.3 CONSTRUCTION- In accordance with Section 901.3 and as follows:

Maintain and protect traffic in accordance with the following:

• Publication 212 Subchapter E, Temporary Traffic Control

• Publication 408, Section 901, Maintenance and Protections of Traffic During Construction

• Publication 213, Temporary Traffic Control Guidelines

• PATA Drawings 101-A and 102 of Publication 213

• Publication 46, Traffic Engineering Manual – Chapter 6

• Publication 35, Approved Construction Materials (including Bulletin 15)

• Publication 72M, Standards for Roadway Construction

• Publication 111, Traffic Control Pavement Markings and Signing Standards

• Publication 236, Handbook of Approved Signs

• PennDOT Standard Drawings TC-8600S and TC-8700S

• MUTCD 11th Edition (Manual on Uniform Traffic Control Devices) – Chapter 6

• Approved Traffic Control Plan

Furnish and place "THIS ROADWAY TO BE UNDER CONSTRUCTION" (W23-1) signs on S.R. 2035 at limits of work of project one week in advance of start of construction, as directed. Remove signs at start of project construction.

Provide at least two weeks advance notice to New Cumberland Borough, state police, fire, EMS, school district, local post offices, the PennDOT District 8-0 Permit Manager, the PennDOT District APRAS Coordinator, and all affected property owners prior to beginning work or imposing any traffic restrictions.

Provide written documentation of the notifications to the Inspector-in-Charge, including all, but not limited to, the following:

New Cumberland Borough Nathaniel Dysard, Borough Manager

(717) 774-0404

New Cumberland Borough Police Department Chief Richard Wiley

(717) 774-0400

New Cumberland EMS Deputy Chief, EMS Edward Erlsten

(717) 774-0193

New Cumberland Fire Department Chief Jeff Gouldy

(717) 774-0193

U.S. Post Office 46 S Market Street New Cumberland, PA 17070

(800) 275-8777

West Shore School District Wendy Rupp Transportation Director

(717) 938-9577

PennDOT Notifications and Submittals

Coordinate all PennDOT notifications through the Inspector-in-Charge (IIC). In addition to the notifications above, provide the following:

• Notify the IIC at least two (2) weeks (excluding holidays) prior to any significant traffic control or traffic pattern change, and confirm intentions with the IIC two (2) days in advance.

• Notify the IIC at least three (3) days in advance of any roadway restriction or closure, and at least thirty (30) minutes prior to placing traffic control devices.

• Notify the PennDOT District 8-0 Traffic Management Center (TMC) at 717-265-7600 two (2) days in advance of any lane or shoulder restriction and fifteen (15) minutes prior to the actual restriction.

Provide Highway Occupancy Permit No. 08120744 to the TMC operator prior to setting up any lane closure or restriction. Call the TMC again when the closure or restriction is removed and the roadway is restored to normal operation.

• Submit Form M-937R (Route/Bridge Restriction) to the County Permit Inspector a minimum of twelve (12) working days (excluding holidays) in advance of any lane restriction, lane closure, or approved detour. The Inspector will forward the request to the District Hauling Unit for approval.

• Contact the County Permit Supervisor, Nicholas Jones, at (717) 787-2522 at least five (5) workdays prior to the start of work.

• Provide the proposed work schedule and an emergency phone contact number to PennDOT at least three (3) days before the start of work.

• Arrange for PennDOT inspection of all traffic control devices prior to the start of work.

• If a signalized intersection falls within the work zone, notify New Cumberland Borough, and do not flag the intersection unless the signal has been placed on flash. If a traffic signal is within 500 feet of the work, call the PennDOT District Traffic Engineer at least three (3) days prior to the start of work.

Work shall be performed, typically between 7 AM to 7 PM Monday – Friday. Weekend work and evening work is permitted with advance notice to the Owner and PennDOT. Bridge Street (SR 2035) lane closures are NOT permitted between the hours of 6:00 AM to 9:00 AM and 3:00 PM and 6:00 PM.

All costs for work required by the Traffic Control Plan, including costs for work referenced in the above listed publications and manuals are considered incidental to the Maintenance and Protection of Traffic During Construction, unless otherwise specified.

Furnish to the Department, New Cumberland Borough, and the Pennsylvania State Police the names of Traffic Control Supervisor(s) and telephone numbers where they can be reached at all times. The Traffic Control Supervisor(s) is to be on call twenty-four (24) hours a day, seven (7) days a week, and to be required to have a pager or cell phone. The Traffic Control Supervisor(s) is to be available to respond to calls involving damage to temporary traffic control devices from causes of vandalism, traffic accident, or weather.

Provide knowledgeable Traffic Control Supervisor(s) with sufficient labor and equipment to expeditiously install, clean, straighten, repair, and maintain signs, and change traffic control patterns. The Traffic Control Supervisor(s) is responsible for coordinating all traffic control installations, pattern changes and removals.

Have the Traffic Control Supervisor(s) inspect the entire traffic control pattern every work shift: once prior to start of each work shift operation, at least once during each work shift, and once after conclusion of each day operations. Have the Traffic Control Supervisor inspect the entire traffic control pattern at least twice every non-workday when long-term traffic control signing or devices are in place. Undertake immediate corrective action of all deficiencies found during inspections including reported deficiencies in accordance with Section 901.3(t). Document, in a diary kept current at all times, all inspection reviews and corrective actions taken pertaining to placement of signs and devices and directing of traffic.

Mount all signs on Type III Barricades unless otherwise noted or directed.

Maintain access to all business and private driveways within the work area. Use fluorescent orange retroreflective sheeting material on all long-term traffic control signs. Use orange retroreflective sheeting material on all other traffic control devices. Use prismatic retroreflective sheeting listed in Publication 35 (Bulletin 15) on all channelizing devices, barricades, and signs.

All signs and traffic control devices are to be in new condition and maintained as such.

Remove short-term work zone signing at the end of each work period. Remove all traffic control devices immediately upon completion of the work. Traffic control devices left in place after completion of the work may be removed by Department forces.

Cover or remove all conflicting signs. When covering conflicting signs, do not place adhesive on the sign face. Place adhesive on the back of the sign. Any reflective sheeting damaged by adhesive constitutes damage to the sign. Replace the sign at no additional cost to the Department. For signs which are frequently covered and uncovered based upon work schedules, provide a cover which permits the entire sign face (including the border and margin) to be visible when the sign is uncovered.

Provide new or like new traffic control signs and devices. Do not use reflective sheeting that is scratched, scarred, dirty, or shows evidence of loss of reflectivity. Do not use signs or devices that are cracked, bent, dented, or broken.

Locate all signs and devices so that sight distance is not obstructed at driveways and side streets.

Do not interfere with the open traffic lane(s) at any time. This includes, but is not limited to, equipment counterweights swinging into the lane(s), etc.

Restrict traffic flow within the work area to minimize traffic congestion and unsafe traffic conditions. Treat drop-offs created by construction operations in accordance with Section 901.3(j) of Publication 408.

Limit disruption to pedestrian facilities to the extent practicable. Where extended disruption of a pedestrian facility cannot be avoided, provide alternate pedestrian routes.

Comply with Act 229 of December 2002 during construction activities within PennDOT right-of-way.

All flaggers must be certified and carry the certification with them while performing flagging operations.

Equip all construction equipment that travels in any traffic lane open to public use with high intensity flashing lights. Use flashing lights of an amber color. Have flashing lights operating when vehicle is entering, leaving, or traveling on any traffic lane open to public use. Provide lights which have a 360-degree field of vision.

Magnetically attach signs, or approved equals, to all vehicles excluding concrete delivery trucks used on this project during construction operations which travel the project on any traffic lane open to public use.

Attach sign to rear of vehicles in a prominent position. Maintain signs in a condition suitable to the Representative.

Provide a sign with black letters on an orange retro-reflective background, readable at a distance of 200 feet during daylight hours. Signs for pick-up trucks and smaller vehicles should be designed with minimum 3-inch letters. Signs for larger trucks should be designed with a minimum 6- inch letters. Provide sign lettering which reads as follows:

CONSTRUCTION VEHICLE - KEEP ALERT FOR SUDDEN STOPS AND TURNS

Flaggers shall be required to wear ANSI/ISEA Class 2 vests (orange or florescent yellow green) when performing flagger operations.

Unless otherwise specified or directed, Traffic Control Devices shall have Type III or better Retro-Reflective sheeting and use rigid signs. They are to be in excellent condition acceptable to the Inspector-In-Charge and maintained as such for the life of the project.

HOLIDAY RESTRICTIONS

No lane closures will be allowed during the following Holiday periods:

Easter: Friday 6:00 AM March 26, 2027, until 9:00 AM Tuesday, March 30, 2027 Memorial Day: Friday 6:00 AM May 28, 2027, until 9:00 AM Tuesday, June 1, 2027 Independence Day: 6:00 AM July 2, 2027, until 6:00 AM July 6, 2027

Remove all lane restrictions and closures prior to the start of each holiday period listed above. Additional traffic restrictions may apply for special events that attract large volumes of traffic in the area of the work;

coordinate with the IIC.

The contractor shall adhere to local noise and/or night work restrictions. Deviations for the indicated lane restrictions on State Roads require prior written approval from the Representative and the District Traffic Engineer, or his designated representative. Remove any conflicting pavement markings as specified in Section 963.3 of PennDOT Publication 408 (90% material removal). Restore pavement marking in a timely manner as directed by the Representative. Replace access signing and pavement markings disturbed by the work in kind.

901.4 MEASUREMENT AND PAYMENT- Lump Sum (LS)

Revise Section 901.4 as follows:

Replace 901.4(a) with the following, “If an item, action or device is required for maintenance and protection of traffic, the cost of the item, action or device is incidental to Item 901-0001.

Delete 901.4(b).

ITEM 4677-0002 – SELECT MATERIAL SURFACING (USE 2A SUBBASE)

In accordance with Section 677 and as follows:

677.1 DESCRIPTION – Add the following:

This work includes constructing gravel drives and parking areas, as indicated.

677.2 MATERIAL – Revise as follows:

Delete Section 703.3 Add No. 2A Subbase – Section 350.2

677.3 CONSTRUCTION – Revise by adding the following:

a. Perform excavation or embankment operation for drives to the elevation and slope required to provide a foundation and smooth transition from the edge of sidewalk to match the existing drive elevation.

ITEM 9000-0001 – CURB RAMP ENGINEERING

In accordance with PennDOT Pub. 72M: RC-67M. Work generally includes:

Design and detailing of plain cement concrete curb ramps at the locations identified in the approved Drawings and as shown on the Standard Drawings RC 67M by a Professional Engineer. On Standard Drawings RC 67M, the details depicted are most appropriate for New Construction.

Alterations to existing facilities must meet the requirements to the maximum extent feasible. New curb ramps must be complete and in-place no more than ten (10) calendar days after removal of existing curb ramps/sidewalk. For alterations where it is technically infeasible to meet these requirements, the contractor will prepare and submit a Technically Infeasible Form to the Engineer for approval to authorize the construction of the ramp and to document that access has been provided to the maximum extent feasible. If an alternate curb ramp type is beneficial to the specific site, notify the Engineer of this proposed change.

A “Technically Infeasible Form" (TIF) must be fully completed (sheets 1 and 2) for each curb ramp when a design value(s) is not compliant with the regulations. The TIF must include sufficient justification to clarify why the proposed design is the best alternative (color photos are also required). The TIF should evaluate at least three alternatives and a summary must be provided.

Submit color hard or electronic copies of the TIF form with the design drawing details to the Engineer for review and approval.

Drawings for each ramp/intersection must include the following:

1. A sheet showing the overall intersection geometry information such as intersection layout, curb ramp alignment, pedestrian crosswalks, utilities, right-of-way lines, pavement edge and type, existing features (buildings, entryways, steps, walls, trees, shrubs/hedges) and traffic control devices (traffic signal poles, equipment, stop signs). This information shall be obtained via construction survey and prepared by a Professional Land Surveyor registered in Pennsylvania.

2. A sheet showing all pertinent spot elevations and all the Curb Ramp Details.

3. The design drawing must conform to the following requirements:

A. Draw details at a minimum scale of 1.0 inch per 10.0 feet. If possible, each detail sheet should depict an entire intersection with all applicable ramps and enough detail to illustrate any impediments to providing ramps fully compliant with RC-67M.

The design and drawings must be prepared using English units. All drawing details must be legible.

B. Provide a NORTH arrow on the drawings.

C. Include a title block in the lower right-hand corner containing the County, SR- Section, Project Number, date of submittal, a block for date of resubmittal(s), the name of the designer and firm along with the appropriate sheet number(s).

D. Identify the type of curb ramp proposed and ramp location.

E. The right-of-way lines and construction easements must be clearly identified in the drawings.

F. Depict the existing/proposed vertical elevations of the finished grade of roadway directly at the corners of the proposed ramp and transition ends (designated to the nearest 0.01 foot).

G. Depict the existing and proposed longitudinal and cross slopes of the roadway directly in front of and at the center of the proposed curb ramp (designated to the nearest 0.010%).

H. Depict proposed running and cross slope percent of the ramp (designated to the nearest 0.010 %).

I. Depict existing and proposed running slopes of the sidewalk transitions to the ramp and/or landing area (designated to the nearest 0.010 %).

J. Depict running and cross-slopes of the existing sidewalk adjacent to the sidewalk transitions.

K. Depict the longitudinal slope along the Detectable Warning Surface (DWS) or transition strip.

L. Depict limits of removal of existing sidewalk (designated to the nearest 0.010 foot).

M. Depict proposed length and width of the ramp.

N. Depict proposed horizontal location of the landing area.

O. Depict proposed slopes of the landing area (designated to the nearest 0.010 %).

P. Depict proposed slopes of flares (designated to the nearest 0.010 %).

Q. If large triangular areas are proposed, depict the lateral slope of the flare between the sidewalk and the bottom of the DWS.

R. Depict proposed horizontal measurement(s) of flares along the curb line (designated to the nearest 0.010 foot).

S. Depict the proposed placement of DWS.

T. Depict horizontal and vertical relationships to the pedestrian push buttons

(designated to the nearest 0.010 foot).

U. Depict the proposed/existing crosswalk line striping on…