27 SPM 001 HalekII Pihana Addendum RFI Response.pdf

PDF 142 KB Posted

Attached to
Roadway and Parking Lot Resurfacing and Restriping
Solicitation number
B26002636
Issued by
Maui County, Hawaii

About this file

This is an Addendum and Request for Information (RFI) Response document for solicitation B26002636, issued by the State of Hawaii Department of Land and Natural Resources, Division of State Parks, for roadway and parking lot resurfacing and restriping at the Haleki'i-Pihana Heiau State Monument in Wailuku, Maui County. The project encompasses site preparation and demolition, asphalt resurfacing of approximately 16,605 square feet with a minimum 2-inch compacted Hot Mix Asphalt overlay, and comprehensive pavement markings including restriping standard and handicap parking stalls, crosswalks, loading zones, directional arrows, and stop bars. The RFI responses clarify that no detailed plans are available with layout to be similar to existing conditions, a porta-potty must be placed outside the main gates with appropriate erosion control measures, existing asphalt curbs will be removed and replaced, vegetation control will include 3-foot crusher rock rolled and tapered from asphalt edges, parking lot stoppers are to be removed and left on-site for DLNR to retrieve, and saw cuts near sidewalks should be squared to allow clean asphalt joints. The contract completion timeline is 180 consecutive calendar days from the date of written notice to proceed, with liquidated damages assessed at $150 per calendar day for delays. Requests for information were due by 4:00 p.m. on May 15, 2026, with bid submissions due by 4:00 p.m. on May 22, 2026.

The estimated construction cost is $245,000. Contractors must possess a valid State of Hawaii Contractor's License classification General B and comply with prevailing wage requirements. High-durability striping paint is required, with the RFI response confirming that contractors must include the cost of thermoplastic pavement marking material in their bids. Successful bidders must maintain Hawaii residents as at least 80 percent of the workforce in accordance with Act 68, SLH 2010. Insurance requirements include comprehensive general liability with minimum limits of $1,000,000 per occurrence and $2,000,000 aggregate, along with workers' compensation, auto liability, and other specified coverages. Certificates of Insurance must additionally insure both DHHL and Maui County. A Class A Community Noise Permit from the Hawaii Department of Health is required for paving and construction activities. Contract award is subject to the availability of funds and compliance with all provisions in the Hawaii Revised Statutes Chapter 103D General Conditions template.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions for solicitation: B26002636 Roadway and Parking Lot Resurfacing and Restriping

05/15/2026

1. Will a proposal schedule be released for this project?

Start date TBD once PO is issued. Contractor is responsible for confirming with DLNR and B+K on proposed construction start date before scheduling.

2. Are there plans for this project?

No plans available, layout to be similar to existing, stripping to be like for like.

3. Confirm Porta Potty will need to be placed OUTSIDE the entrance gate and BMPs will be needed to secure it

Yes, porta-potty to be placed outside of the main gates.

4. Confirm Vegetation control - 3 ft crusher rock, rolled, tapered down from Asphalt edges - Crusher rock near bottom stops at existing curbs

Yes, this is confirmed for shoulder work.

5. Existing asphalt curbs at key locations will be removed and replaced with new

Yes, plan on removing existing asphalt curbs and installing new ones.

6. Confirm needing COI to add DHHL/County and any others

Yes, please include the DHHL and Maui County as additionally insured under your COI.

7. Are there noise permit requirements

As per Hawaiʻi DOH Noise Permits and Variances, the contractor will need to obtain a Class A Community Noise Permit for the paving/construction activities associated with the project.

8. Confirm parking lot stoppers are not being replaced.

As per District Superintendant, stoppers are to be removed and left on the side for them to take away.

9. Clarification on saw cut near top sidewalk to be squared to allow for clean Asphalt joint

Yes, the saw cut should be squared oƯ to allow a clean asphalt joint meeting up to the sidewalk.

10. In the SOW, it was called out to use high-durability striping paint, please specify if we're to include the cost of Thermoplastic material.

YES, CONTRACTOR TO INCLUDE COST OF THERMOPLASTIC PAVEMENT MARKING

MATERIAL.