This Invitation for Bid (IFB) 27-18 is issued by the Columbia Association, a nonprofit community services corporation serving Columbia, Maryland, to solicit bids for Board Room Audiovisual Systems Modernization. The project encompasses the design, procurement, installation, integration, configuration, programming, testing, commissioning, training, and documentation of a comprehensive audiovisual system serving the Columbia Association Board Room and associated support spaces. The scope includes installation of three 98-inch and three 75-inch Samsung professional displays, five Panasonic AW-UE160 and three HP Poly PTZ cameras, Microsoft Teams Rooms and Zoom Rooms conferencing codecs with touch panels, sixteen Clock Audio gooseneck microphones with wireless backup systems, QSC audio processing and amplification equipment, Crestron control systems, production equipment including a TriCaster Mini 4K system, networking infrastructure, cabling, and all related accessories and equipment. A pre-bid meeting is scheduled for December 3, 2026, at 11:00 AM at Columbia Association Headquarters in Columbia, Maryland. Bids must be submitted electronically through the PlanetBids e-procurement portal by December 17, 2026, at 4:00 PM ET, with the question deadline set for December 10, 2026, at 4:00 PM. The anticipated Notice to Proceed is January 2027, with final completion required by April 5, 2027. All work must be performed during normal business hours of 9:00 AM to 5:00 PM, Monday through Friday, while coordinating around monthly Board meetings held the fourth Thursday of each month from 7:00 PM to 10:00 PM.
Bidders must submit a single firm, fixed lump-sum price covering all labor, materials, equipment, licenses, shipping, installation, programming, integration, testing, commissioning, training, documentation, warranty obligations, overhead, profit, applicable taxes, permits, and tariffs. The bid price breakdown workbook must accompany the lump-sum proposal for review purposes. Required bid submittals include acknowledgment of all addenda, three minimum project references from audiovisual projects completed within the past five years, and copies of Minority Business Enterprise (MBE), Women Owned Business Enterprise (WOBE), or Disabled Owned Business Enterprise (DBE) certifications if applicable. Bidders must demonstrate a minimum of five years' experience performing similar work, hold all applicable Maryland State and Howard County licenses, maintain comprehensive insurance including $2,000,000 general liability and $2,000,000 umbrella coverage, and provide a two-year warranty on workmanship, installation, programming, and system integration. The Contractor is responsible for all permits and fees, project management, coordination with existing equipment including a recently installed Vertiv Liebert UPS and Crestron CP4N processor, cleanup and debris removal, and must include two training sessions of up to two hours each for Columbia Association personnel. Awards will be made to the lowest responsive and responsible bidder unless the amount is unreasonable or not in the Association's best interest, with no bid and performance bonds required.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Reference Form.docx | DOCX document | |
| AV Construction Drawings.pdf | ||
| Minority Business Enterprise (MBE) Participation Form.docx | DOCX document | |
| BID PRICE BREAKDOWN.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IFB 27-18: Board Room AV Modernization
November 20, 2026
Project: Board Room Audiovisual Systems Modernization
Invitation for Bid (IFB): 27-18
For The Attention of All Bidders:
The following information related to the above project is provided to all prospective Bidders:
1. Invitation for Bid This section contains the description of the specific project, the time, date and location for submission of the bid, and the Columbia Association representatives to whom inquiries may be made regarding the bid.
2. General Instructions
This section contains the procedures for submitting the bid, receipt, withdrawal, rejection and award of the bid.
3. General Conditions
This section contains the general conditions regarding ethics, the specifications, estimates made by the Columbia Association, tax information, payment terms and completion of work.
4. Special Conditions
This section contains certain specific conditions, if any, that are required in the bid and changes, if any, to the general conditions.
5. Specifications
This section gives the detailed specifications for this project to enable the vendor to submit a responsive bid.
6. Bid Pricing and Required Submittals This section establishes the bid pricing requirements and identifies the documents and information that Bidders must submit with their Bid.
Section 1. INVITATION FOR BID
Project: Board Room Audiovisual Systems Modernization
IFB No.: 27-18
Columbia Association is seeking bids from qualified audiovisual systems contractors to furnish all labor, supervision, project management, engineering, equipment, materials, programming, configuration, installation, integration, testing, commissioning, training, documentation, and incidental work necessary to complete the Board Room audiovisual modernization in accordance with the Solicitation Documents.
The project includes work in the Board Room and associated audiovisual support spaces, including the equipment rack area and Production Studio, as shown in the Construction Drawings and technical specifications prepared by Cerami & Associates.
PRE-BID MEETING
An onsite pre-bid meeting will be held at 11:00 AM on December 3, 2026 at the Columbia Association Headquarters building located 6310 Hillside Court, Columbia Maryland, 21046. Bidders will be allowed to ask questions and inspect the work site at this time. Attendance at the pre-bid meeting is strongly encouraged but not mandatory.
BID SUBMISSION
Each bid must be submitted via Columbia Association’s PlanetBids e-procurement portal site. Bids submitted must include the Pricing Schedule, any explanatory comments or materials, and other attachments as required.
Each bid must be received as follows:
Submission Platform: PlanetBids e-Procurement System
Date: December 17, 2026
Time: At or before 4:00 P.M. ET
Vendor Registration URL: https://vendors.planetbids.com/portal/77636/portal-home
All interested vendors must register on the PlanetBids portal in order to view bid documents and submit a response. Registration is free and can be completed by visiting the URL above. Vendors are strongly encouraged to register and become familiar with the system well in advance of the submission deadline.
Late submissions will not be accepted. Please allow ample time for system registration, document upload, technical difficulties, unexpected delays and submission prior to the deadline.
Bids delivered by any other means will not be considered. Oral, telephonic and facsimile bids will not be accepted.
All questions regarding this Invitation for Bid must be submitted through the PlanetBids e- Procurement System by 4:00 PM on December 10, 2026.
https://vendors.planetbids.com/portal/77636/portal-home
Section 2. GENERAL INSTRUCTIONS
PRESUBMISSION INFORMATION
Examination of Bid Documents
Bidders must examine the complete solicitation documents very carefully and must make their bid after examination of the location and/or nature of the proposed work. The submission of a bid indicates that the Bidder thoroughly understands all the terms and conditions, instructions, and specifications of the bid.
Assistance in Bid Preparation
Columbia Association staff will not assist any bidder or bidder's agent in the actual preparation of the bid.
Interpretation and Correction of Bid Documents
Should a Bidder require an interpretation or clarification of any provisions of the solicitation documents or related information provided by the Columbia Association, or believe that there is an ambiguity, error, inconsistency or discrepancy in these documents or information, the Bidder must notify the Columbia Association in writing prior to the date set for the question deadline.
A Bidder who fails to request any such interpretation or clarification waives any claim for additional cost or time spent addressing any ambiguity, error, inconsistency or discrepancy in any such documents or information which is found to have been apparent at the time of receipt of bids.
All interpretations, clarifications, corrections, changes or other directions related to these requests of Bidders will be provided in writing by the Columbia Association and sent to all prospective Bidders who obtained copies of the documents and information from the Columbia Association.
Extension of Bid Due Date
The Columbia Association may extend the bid due date at its option. If the date is extended, the Columbia Association will notify all prospective bidders who have obtained copies of the bid documents.
Response to Solicitations
In the event a vendor does not submit a bid on this solicitation, the vendor should return the No Bid Response form with an explanation as to why the vendor is unable to do so. If a vendor does not respond to three consecutive bid invitations the vendor’s name may be removed from the Columbia Association’s master list.
PREPARATION AND SUBMISSION OF BIDS
All bids must be:
Submitted electronically through the PlanetBids e-Procurement System using the official bid forms provided in the solicitation documents. Bids submitted on any form other than the official forms will not be considered.
Submitted by authorized principals.
Fully completed, including all required attachments and forms specified in the IFB. All such documents must be uploaded and submitted through the PlanetBids portal.
Received electronically on or before the date and time specified in Section 1, via the PlanetBids e- Procurement System. Late submissions will not be accepted. Bids delivered by any other means, including mail, email, or in person, will not be considered.
MODIFICATION AND WITHDRAWAL OF BIDS
All bids shall be valid for a minimum period of ninety (90) calendar days following the date established for receipt of bids, unless otherwise stated in Section 4, “Special Conditions.”
Bidders may modify or withdraw their bids at any time prior to the bid submission deadline through the PlanetBids e-Procurement System. Bidders are responsible for ensuring that any modifications or withdrawals are completed and confirmed in the system before the deadline.
No modifications or withdrawals will be permitted after the bid due date and time.
LATE BIDS, MODIFICATIONS AND WITHDRAWALS
If a bidder submits a bid, modification, or request for withdrawal after the time set for receipt of bids, the following applies:
• Late bids, late modifications, and late withdrawal requests will not be considered. Any bid, proposal, or modification submitted through the PlanetBids e-Procurement System after the deadline is considered late and will not be evaluated or accepted for award.
• Any request for withdrawal or modification submitted after the deadline in the PlanetBids system will also be considered late and will not be permitted.
• Exceptions may be made only when a late bid, modification, or withdrawal would have been timely but for documented action or inaction by Columbia Association’s procurement personnel.
• In the event that Columbia Association's business operations are impacted by a closure (e.g., due to inclement weather or other emergencies), the bid deadline may be extended to 10:00 A.M. on the next full Columbia Association business day. Any such changes will be communicated through the PlanetBids system.
MISTAKES IN BIDS
After receipt of bids, Columbia Association staff shall examine all bids for mistakes. In cases of apparent mistakes, other than those involving extension of unit prices or other arithmetic errors, when Columbia Association staff has reason to believe that a mistake may have been made, staff shall request from the bidder a verification of the bid. If the bidder alleges a mistake, the matter shall be brought to the attention of the Director of Purchasing. Such actions shall be taken prior to award.
The Director of Purchasing is required to make the administrative determinations necessary in cases of alleged bid mistakes. The authority permitting correction of bids is limited to bids which are responsive as submitted and shall not be used to permit correction of bids to make them responsive.
If the Director of Purchasing knows or has reason to conclude that a mistake in a bid may have been made, the Director of Purchasing shall require that the bidder confirm the bid. Confirmation by the bidder of the bid will be requested when the bid reflects either an obvious, apparent error on its face or the bid amount is unreasonably lower than those of either the other bids submitted or Columbia Association’s estimate.
If the bidder fails to respond to a request for confirmation of an apparent mistake within the time allotted to the Director of Purchasing, the bid may be considered as originally submitted or may be rejected as non-responsive at the discretion of the Purchasing Manager. If the bidder confirms his bid, the Director of Purchasing shall consider it as originally submitted.
If the bidder alleges a mistake, the Director of Purchasing shall advise him to support the allegation by statements concerning the alleged mistake and by all pertinent evidence, such as the bidder’s file copy of the bid, original worksheets and other data used in preparing the bid, such as Subcontractor’s and supplier’s quotations, if any, published price lists, and any other evidence which will serve to establish the mistake, the manner in which it occurred, and the bid actually intended.
Additionally:
• A determination may be made permitting the bidder to correct his bid if the bidder requests permission to do so and clear and convincing evidence establishes both the existence of a mistake and the bid actually intended. In lieu of bid correction, Columbia Association may permit a low bidder alleging a material mistake of fact to withdraw his bid if there is reasonable proof that a mistake was made and the intended bid cannot be ascertained.
• A determination may be made permitting the bidder to withdraw his bid if the bidder requests permission to do so and clear and convincing evidence establishes the existence of a mistake.
However, if the evidence is clear and convincing both as to the existence of a mistake and as to the bid actually intended, and if the bid, both uncorrected and corrected, is the lowest bid received, a determination may be made to correct the bid and not permit withdrawal.
• If the evidence does not warrant a determination under the two paragraphs above, a determination may be made by the Director of Purchasing that a bidder may neither withdraw nor correct his bid.
• Any clerical mistake, apparent on the face of a bid, may be corrected by Columbia Association prior to award, if the staff member has first obtained from the bidder verification of what was actually intended. Examples of such apparent mistakes are obvious misplacement of a decimal point, typographical errors, and mistakes in the designation of the unit of measure. Correction shall be reflected in the award document.
• After bid receipt of bids an otherwise low bidder shall not be permitted to delete exceptions to the bid conditions or specifications, which affect price or substantive obligations.
• Nothing in this Section is intended to prohibit Columbia Association from accepting a bid correction resulting in a reduction in price from the low bidder after the bid due date, provided that such reduction is not conditioned on or does not result in, the modification or deletion of any condition contained in the Invitation for Bids.
AWARD OF BIDS
The award shall be made to the lowest responsive and responsible Bidder unless the Bid amount is determined to be unreasonable or Columbia Association determines that an award is not in its best interest.
A Bid may be rejected as non-responsive if it fails to conform to the material requirements of the IFB, including the specifications, schedule, bid forms, pricing requirements, or other material terms and conditions. A Bid may also be rejected as non-responsive if the Bidder takes material exceptions to the IFB, imposes conditions that modify the requirements of the IFB, or limits the Bidder’s obligations or liability under the Contract.
“Responsible” means that the Bidder is capable of fully performing the Contract requirements and possesses the experience, financial capacity, resources, integrity, and reliability necessary to assure good-faith performance. If Columbia Association determines that a Bidder is not responsible, the Bid may be rejected.
Columbia Association may request information or clarification reasonably necessary to determine a Bidder’s responsiveness or responsibility. Failure to provide requested information within the time established by Columbia Association may result in a determination that the Bidder is non-responsive or not responsible, as applicable.
Columbia Association reserves the right to waive minor informalities or irregularities in bids when reviewing bids for award.
Section 3. GENERAL CONDITIONS
ETHICS IN PROCUREMENT
By submitting a Bid, the Contractor agrees to adhere to Columbia Association’s policy on ethics in purchasing. This policy prohibits an employee and any immediate family member from receiving incentives, gifts, gratuities or favors of any kind from Contractors seeking business or engaged in business transactions with Columbia Association. Neither the employee nor any of the employee’s immediate family had or will have involvement in or influence in any way the selection of a Contractor to do business with Columbia Association whereby the employee or the employee’s immediate family will receive personal benefit.
MINORITY BUSINESS ENTERPRISE POLICY
Minority Business Enterprises, Women Owned Business Enterprises and Disabled Owned Business Enterprises will be afforded equal opportunity to submit Bids or Proposals in response to this Procurement and will not be subject to discrimination on the basis of race, color, sex, or national origin in consideration for award.
Columbia Association will establish guidelines and document efforts to attain its goal to procure Twenty Three percent (23%) of the total dollar value in eligible procurements from MBEs, WBEs and DBEs.
Columbia Association recognizes Minority Business Enterprise (MBE) certification from the State of Maryland, Howard County, MD and the City of Baltimore. Please provide with your Bid a copy of your certificate if you are certified with any of these governmental agencies.
SUSTAINABILITY
Columbia Association is committed to the procurement of goods and services that have less detrimental environmental and social impacts than competing goods and services. IFBs and RFPs shall endeavor, to the extent possible, to specify sustainable goods and services, and at the same time consider the value received and benefit to the environment in return for the expenditure. Goods and services should, for example, be more energy efficient, conserve water, reduce the use of fuel, generate less pollution and toxins, use recycled materials, and/or minimize waste.
SPECIFICATIONS
All work must be furnished in accordance with the Solicitation Documents.
PRODUCT REQUIREMENTS AND POST-AWARD SUBSTITUTIONS
Bidders shall base their bids on the manufacturers, models, products, equipment, and technical requirements identified in the Construction Drawings and other applicable Solicitation Documents.
Alternate products and substitutions will not be considered or approved before contract award.
After contract award and before procurement or installation begins, Columbia Association may consider a Contractor-requested substitution. The Contractor shall submit complete supporting documentation demonstrating that the proposed substitute meets or exceeds the specified product's performance, functionality, compatibility, interfaces, programming and licensing requirements, warranty, and other applicable technical requirements. Columbia Association is not obligated to approve a proposed substitution.
A substitution request will be considered only for one or more of the following reasons, which the Contractor shall document in writing:
(a) the specified product has been discontinued or is no longer available from the manufacturer or authorized distributors;
(b) the specified product's lead time would delay the Contract Time through no fault of the Contractor, as demonstrated by written manufacturer or distributor documentation;
(c) the manufacturer has issued a safety notice, recall, or end-of-life notice for the specified product or
(d) the substitution would provide equal or better performance, functionality, and compatibility at no added cost to Columbia Association, or at a credit to Columbia Association.
A request based solely on the Contractor's cost savings, convenience, or purchasing preference will not be considered.
TAX STATUS
The Columbia Association is a non-profit corporation under the laws of the State of Maryland.
Columbia Association is subject to sales tax. Contractor shall be responsible for the payment of all taxes associated with this project. Bid price shall be inclusive of all applicable taxes.
AUTHORITY OF THE PROJECT MANAGER
The Project Manager shall, among other things, decide all questions which may arise under the Contract regarding the interpretation of any or all plans and specifications and shall furnish with reasonable promptness such clarifications and changes as are consistent with the intent of the Solicitation Documents which the Manager may deem necessary for the proper execution of the Work. The Project Manager shall have the authority to issue direction, instruction or authorization necessary for the Contractor’s immediate performance of work pending negotiation, execution and Contractor’s receipt of written change order for changed or additional work. The Contractor shall proceed diligently with the performance of the Contract and any changes or additional work in accordance with the Project Manager's instructions.
The Project Manager shall also decide all questions which may arise during the performance of the Contract as to the quality and acceptability of materials furnished and Work performed, the amount and quantity of Work performed and materials furnished, payments to be made to the Contractor, the rate of progress of the Work, the conformance of the Contractor to the requirements of the Contract and satisfactory completion of the Work thereunder, and all Contractor requests or claims for additional compensation and extensions of time under the Contract. Directives given by the Project Manager to the Superintendent constitute notice to the Contractor.
CONTRACT TERM
The Contract will commence upon execution and issuance of a Notice to Proceed and will continue through final completion, acceptance, and closeout. The Contractor shall submit a detailed project schedule after award.
TERMINATION FOR CONVENIENCE
Columbia Association may terminate the Contract for convenience in which case the Contractor shall be paid only for properly completed and accepted work through the effective date of termination, and no anticipatory profits shall be due.
MANNER OF PAYMENT
Proper invoices submitted on the AIA G702 Application for Payment Form and G703 Continuation Form or other approved format will be paid in approximately thirty (30) days. All invoices shall include lien releases from Subcontractors and suppliers for previous applications. The Columbia Association may retain ten percent (10%) of all progress payments until substantial completion is achieved by the contractor. The Columbia Association will be the sole determinate as to when the project is substantially complete. Retention will be released to the contractor upon the final completion of all work and submission and acceptance of the following project closeout documents:
1. Final Release of Liens from Subcontractors and Suppliers
2. As-builts
3. Cut Sheets & Specifications of all materials used in the project
4. Warranties
TARIFF RESPONSIBILITY
All pricing submitted in response to this solicitation and reflected on any resulting purchase orders must be inclusive of any applicable tariffs, duties, or related import fees. Suppliers are solely responsible for factoring all known or anticipated tariffs into their pricing at the time of submission.
Tariffs identified or presented after award or issuance of a purchase order will not be honored or accepted as grounds for price adjustment. Failure to account for tariffs in the submitted pricing may result in contract non-compliance or cancellation.
Section 4. SPECIAL CONDITIONS
BACKGROUND
Columbia Association is a nonprofit community services corporation that works in the service of Columbia, Maryland, a nationally recognized planned community that’s home to approximately 100,000 people and several thousand businesses. The mission of this unique organization is to enhance the quality of life for people living and working in Columbia. It has grown with the community into a multimillion-dollar operation that is integrated into nearly every aspect of Columbia life.
The Columbia Association team strives each and every day to enrich the quality of life in Columbia by cultivating meaningful experiences and providing unique opportunities in our community, all through the lens of responsible stewardship. Columbia Association is committed to offering a wide range of services, programs and facilities that prioritize inclusion, protect the environment and promote wellness in all aspects. Columbia Association owns and operates a comprehensive network of community facilities and amenities, many of which are free and accessible to anyone who wishes to utilize them. These spaces ensure we are respecting and protecting the environment while giving people of all ages and backgrounds a place to learn and grow. That includes:
● Three lakes and more than 40 ponds
● Nearly 3,600 acres of open space
● 165 play areas
● 95 miles of pathways
● 23 outdoor pools
● An indoor swim center and Splashdown
● Three large fitness/recreation clubs
● Columbia Ice Rink, an indoor Olympic-sized facility
● Columbia Art Center
● Youth & Teen Center
● Two indoor tennis clubs, including the nationally recognized Long Reach Tennis Club
● Three outdoor tennis clubs
● Two golf clubs
● SportsPark with mini-golf, batting cages, a skate park and picnic pavilions
In addition to managing these facilities and open space assets, which includes a large selection of classes, workshops, coaching and social leagues, Columbia Association provides a wide variety of programming across Columbia, including year-round events at the Downtown Columbia Lakefront, before and after school care, international and multicultural events and a variety of summer camps.
For additional information about Columbia Association, visit our website at ColumbiaAssociation.org.
INTENT
Columbia Association is seeking a qualified audiovisual systems contractor to complete the modernization of the audiovisual systems serving the Columbia Association Board Room and associated AV support areas. The Contractor shall furnish, install, integrate, configure, program, test, commission, and provide training and closeout documentation for the audiovisual systems in accordance with this IFB and the final drawings and technical specifications prepared by Cerami & Associates.
The Work includes installation and integration of new audiovisual equipment with designated existing equipment; audiovisual cabling and connectivity; displays; cameras; microphones and audio systems;
conferencing and collaboration systems; audiovisual control and signal-processing systems;
http://www.columbiaassociation.org/ http://www.columbiaassociation.org/ equipment rack and production system components; programming and configuration; testing and commissioning; training; and other work assigned to the AV Contractor by the Contract Documents.
REFERENCES
Bidder must complete the Project References page which is included as a separate attachment with the bid documents.
Bidder shall provide a minimum of three (3) references for audiovisual projects completed within the past five (5) years. References should demonstrate Bidder’s experience with projects involving commercial audiovisual installation and integration, including, as applicable, conferencing systems, control systems, audio and video systems, programming, system integration, testing, and commissioning. Referenced projects should be comparable in overall scope and complexity to Columbia Association’s Board Room AV Modernization project described in this IFB.
Columbia Association reserves the right to contact any or all references and to consider information obtained from references when determining whether the Bidder is responsible and possesses the experience, capability, and resources necessary to successfully perform the Contract.
Columbia Association may also consider its own documented experience with the Bidder, if applicable, when determining bidder responsibility.
Failure to provide the required references, inability of Columbia Association to reasonably verify the information submitted, or information demonstrating that the Bidder does not possess sufficient relevant experience may be considered in Columbia Association’s determination of bidder responsibility.
PRE-AWARD FINANCIAL DUE DILIGENCE
Prior to contract award, Columbia Association will conduct financial due diligence to determine whether the apparent successful Bidder has adequate financial resources and capacity to perform the Contract.
Upon request by Columbia Association, the apparent successful Bidder shall provide financial information for its two most recently completed fiscal years, including:
• Balance Sheet;
• Income Statement (Profit and Loss Statement); and
• Statement of Cash Flows, if prepared as part of the Bidder's financial statements.
Columbia Association may request additional information reasonably necessary to complete its financial responsibility review. Financial information submitted in response to this requirement will be used solely for purposes of determining the Bidder's financial responsibility and will be handled in accordance with Columbia Association's applicable confidentiality and records requirements.
Failure of the apparent successful Bidder to provide the requested information within the timeframe established by Columbia Association may result in a determination that the Bidder is not responsible and may result in Columbia Association proceeding to the next eligible Bidder.
EMPLOYER IDENTIFICATION NUMBER
Columbia Association requires all invoices be identified with the vendor’s Federal Tax Identification number or Social Security number.
QUALIFICATION OF BIDDERS
Bidders may be required to furnish satisfactory evidence that they are qualified dealers or manufacturers of the items listed, or regularly engaged in performing the services on which they are bidding, and in both cases maintain a regularly established place of business. An authorized representative of Columbia Association may visit any prospective bidder’s place of business to determine ability, capacity, reliability, financial stability and other factors necessary to perform the contract.
INSPECTIONS
Columbia Association has the right to monitor, inspect and evaluate or test all supplies or services called for by the contract at all reasonable places (including the bidder’s place of business) and times (including the period of preparation or manufacture).
SAFETY STANDARDS
The equipment, to include components, furnished under these specifications shall comply with all applicable Federal and Maryland State standards. Likewise, all work performed by the Contractor shall be in compliance with the prevailing State and Federal laws, including, but not limited to OSHA and EPA.
NEW MATERIALS
Unless this contract specifies otherwise, the contractor represents that the supplies and components are new and are not of such age or so deteriorated as to impair their usefulness or safety.
GUARANTY – WARRANTY
Contractor warrants and guarantees its workmanship, installation, programming, configuration, and system integration for a period of two (2) years from the date of Columbia Association’s final acceptance of the completed project. During the warranty period, Contractor shall, at its own expense, promptly correct any defect or deficiency attributable to Contractor’s workmanship, installation, programming, configuration, or system integration.
All equipment furnished under the Contract shall be covered by the applicable manufacturer’s warranty. Contractor shall provide Columbia Association with all applicable manufacturer warranty documentation and shall assist Columbia Association with warranty claims for equipment furnished under the Contract.
Contractor shall be responsible for troubleshooting reported system issues during the warranty period to determine whether the issue results from equipment failure, installation, programming, configuration, or system integration.
Columbia Association retains the right to make emergency repairs without relieving Contractor of its warranty obligations. If Contractor does not respond to Columbia Association’s request for warranty service within forty-eight (48) hours, Columbia Association may take reasonable action necessary to address the issue and may recover from Contractor the reasonable costs attributable to Contractor’s warranty obligations.
PROTECTION OF WORK AND PROPERTY
Contractor shall be liable for any damage resulting from Contractor’s operations to existing buildings, equipment, electrical systems or structure of any kind, occurring during the course of or as a result of Contractor’s work, whether through negligence or otherwise. Such damaged property shall be replaced or repaired by Contractor at Contractor’s own expense in a manner sat isfactory to Columbia Association, which repair, or replacement shall be a condition precedent to Columbia Association's obligation to make final payment under the Contract.
Contractor shall be responsible for damage to any work, completed or otherwise covered by this specification before final acceptance of the work.
Contractor shall adequately protect adjacent property as provided by law and the Contract Documents.
MATERIAL AND EQUIPMENT FURNISHED BY OTHERS
In the event the scope of work includes installation of materials or equipment furnished by others, it shall be the responsibility of the Contractor to examine the items so provided and thereupon handle, store, and install the items with such skill and care as to ensure satisfactory completion of the Project.
Loss or damage due to acts of Contractor shall be charged to the account of the Contractor and deducted from moneys due by Columbia Association to the Contractor under this Agreement; or, if exceeding the amount due the Contractor, shall be payable by the Contractor to Columbia Association upon demand.
DAMAGES
The Contractor shall be responsible for loss or damage to Columbia Association property, existing work, equipment, materials, finishes, furnishings, or other property caused by the Contractor or its employees, agents, or Subcontractors in connection with the Work. The Contractor shall promptly repair or replace damaged property to Columbia Association’s reasonable satisfaction or reimburse Columbia Association for the reasonable cost of repair or replacement.
The Contractor shall also be responsible for damages incurred by Columbia Association resulting from the Contractor’s unexcused failure to complete the Work within the Contract Time. The Contractor shall promptly notify Columbia Association in writing of circumstances beyond the Contractor’s reasonable control that may delay performance and shall take reasonable measures to mitigate the delay.
CLEAN-UP OF WORK SITE
The Contractor shall, during the course of construction and on a daily basis at the end of each workday remove all waste materials from the site recurrently as is necessary to maintain the site in a clean and orderly condition at all times.
Upon completion of the work under this contract, the Contractor shall remove from the work site all temporary structures, debris, and waste due to the Contractor’s operations and clean all surfaces, equipment, etc., relative to the performance of this Agreement.
If the Contractor fails to perform a clean-up function within forty-eight hours after notification by Columbia Association to do so, Columbia Association may proceed with the clean-up function as it deems necessary and in the manner deemed most expedient, and all costs thereof shall be at the sole expense of the Contractor, and shall be deducted from moneys due under this contract by Columbia Association to the Contractor; and, if exceeding the amount owed the Contractor, shall be payable by the Contractor to Columbia Association upon demand.
CHANGES TO THE CONTRACT
When changes in the Work require modification of the contract price, such modifications shall be accomplished as follows:
A. Itemization - The Contractor shall promptly submit to the Project Manager a fully itemized breakdown of the quantities and prices used in computing the value of the requested change, along with a detailed explanation of and justification for the proposed change, regardless of the nature of the change.
For all changes in the Work to be performed by a Subcontractor, the Contractor shall furnish the Subcontractor's fully itemized breakdown of quantities and prices, which shall bear the original signature of a representative of the Subcontractor authorized to act for the Subcontractor. If requested by the Project Manager or Contract Administrator, proposals from suppliers or other supporting data required to substantiate costs shall be furnished.
B. Calculation of Change in Price - Modification of the contract price, when required, shall be determined as follows:
1. When unit prices are stated in the Contract, or have been subsequently agreed upon, by application of such unit prices.
2. A lump sum price agreed upon by both the Columbia Association and the Contractor.
3. If the change involves only a credit, the Contract Price will be reduced by the amount it would have cost the Contractor to perform the Work plus overhead and profit.
4. If the change involves both a reduction and an increase in Contract Price, both sums shall be shown and the two sums shall then be balanced to determine the adjusted total cost of or credit due for the change. No allowance to the Contractor shall be made or allowed for loss of anticipated profits on account of any change in the Work.
5. Unless otherwise specified, the allowable mark-up for combined overhead and profit for Work performed by the Contractor with the Contractor's own forces will be based upon the monetary value of the Work, in accordance with the following schedule:
Value of Work
Combined Overhead and Profit
$0 - $1,000
20%
$1,001 - $10,000
17%
$10,001 - $25,000
15%
Over $25,000
Negotiated but not more than 15%
6. For work performed by a Subcontractor with the Subcontractor's own forces, the percentages for combined overhead and profit for a Subcontractor will be as stated in paragraph 5 above. On Work partly or solely performed by a Subcontractor, the Contractor will be allowed 8% of the total cost of the Subcontractor's labor and materials for overhead including taxes and insurance required by statute for labor.
7. The provisions of paragraphs 5 and 6 above shall apply only to modifications of contract price negotiated prior to completion of the changed Work.
8. On all changes in the Work, no Contractor or Subcontractor will be allowed any profit for employment of another contractor to perform Work for the Contractor or Subcontractor.
9. On all changes in the Work, the Contractor will be reimbursed for the Contractor's expenditures for Workmen's Compensation Insurance, Social Security Taxes and Unemployment Compensation Taxes covering persons actually engaged upon the Work as part of the labor burden and overhead.
10. The cost of foremen and superintendents may be added only when the Change Order makes necessary the hiring of additional supervisory personnel or requires their continued employment for time additional to that originally required by the Contract.
11. The Contractor shall be allowed the actual cost of any rental of machine power tools or special equipment, including fuel and lubricants, which are necessary to execute the Work required on the change, but no percentages shall be added to this cost. Equipment rental rates are to be agreed upon by the Project Manager and the Contractor. The rates agreed upon shall, generally, approximate those contained in the latest publication of the Associated Equipment Distributors or other published index as decided by Columbia Association.
12. No order for any change shall in any manner or to any extent relieve the Contractor of any of its obligations under the Contract.
13. The Project Manager shall have the authority to make minor changes in the Work, not involving increases in either contract price or Time, which are not inconsistent with the purposes of the Work. Otherwise, except in any emergency endangering life or property, no extra Work or changes in the Work shall be performed by the Contractor unless previously authorized in writing by the Columbia Association.
C. The allowable percentages of cost for overhead and profit are deemed to include, but not be limited to, job supervision and field office expense required by the Contract, expenses for timekeepers, clerks and watchmen, labor burden, costs of correspondence of any kind, any insurance not specifically mentioned herein, all expenses in connection with the maintenance and operation of the field office, the use of small tools, any cost of small trucks generally used for transporting either workmen, materials, tools or equipment to the job location, and all incidental job burdens. No percentage allowances will be making for maintenance or operation of the Contractor's regularly established principal office, branch office or similar facilities.
INSURANCE
The Contractor shall maintain the following insurance policies during the term of this Contract: Broad Form General Liability $2,000,000 combined single limit for property damage and bodily damage;
Business Automobile $1,000,000 combined single limit for property damage and bodily injury;
Workers’ compensation statutory limits; and an Umbrella of at least $2,000,000. All policies shall name Columbia Association as an additional insured and in the event that the Contractor receives from an insurer any notice of cancellation, non-renewal or any other modification of any of the insurance policies required under this contract, Contractor shall give written notice to Columbia Association within 24 hours of receipt of such document. Certificates of insurance evidencing such coverages are to be supplied to Columbia Association at the time of Contractor’s execution of the Contract.
OWNER’S RECOURSE
If the Contractor fails to properly and diligently perform the Work, provide sufficient qualified personnel, equipment, or materials, correct defective or nonconforming Work, or otherwise materially perform its obligations under the Contract, Columbia Association may provide written notice describing the default and requiring the Contractor to correct the default within a reasonable period specified by Columbia Association.
If the Contractor fails to timely correct the default, Columbia Association may terminate the Contractor’s right to proceed with all or any portion of the Work and may engage others to complete or correct the Work. Columbia Association may deduct the reasonable costs incurred from amounts otherwise due to the Contractor. If such costs exceed the unpaid Contract balance, the Contractor shall be responsible for the difference.
SCHEDULING
Columbia Association anticipates issuing the Notice to Proceed in January 2027. Contractor shall achieve Final Completion no later than April 5, 2027, unless otherwise modified in writing by Columbia Association. Normal project work hours are 9:00 A.M. to 5:00 P.M., Monday through Friday, unless otherwise approved by Columbia Association.
Columbia Association hosts Board meetings in the Board Room on the fourth Thursday of each month from 7:00 P.M. to 10:00 P.M. Contractor shall coordinate its work schedule with Columbia Association in advance to accommodate these meetings, including any related setup and rehearsal time. Work that would affect the Board Room or its audiovisual systems on a Board meeting day shall not proceed without prior coordination and written approval from Columbia Association, and Contractor shall plan system shutdowns, cutovers, and testing around the Board meeting schedule. Columbia Association may adjust meeting dates and will notify Contractor of any changes.
Prior to commencing Work, Contractor shall submit a detailed project schedule for Columbia Association’s review. The schedule shall identify, at a minimum, submittals and approvals, equipment procurement and anticipated lead times, installation, programming and configuration, testing and commissioning, training, punch-list completion, and final closeout.
CONSULTANT
The audiovisual design consultant for this project is Cerami & Associates. The Consultant may assist Columbia Association with bidder questions, technical review, substitutions, submittals, installation observations, testing, commissioning, and acceptance.
Section 5. SPECIFICATIONS
CURRENT ENVIRONMENT
Columbia Association operates audiovisual systems supporting Board meetings, presentations, hybrid conferencing, audio reinforcement, video capture, and production functions in the Board Room and associated support spaces at Columbia Association Headquarters. Portions of the existing environment will remain and be integrated with new equipment as identified in the Construction Drawings and other applicable Contract Documents.
Following equipment failures and a power fluctuation, Columbia Association installed a Vertiv Liebert GXT5 1000VA/1000W online double-conversion UPS, replaced an existing Crestron CP3 processor with a Crestron CP4N, and replaced several damaged power supplies. The Construction Drawings issued with the IFB will reflect or otherwise address these current conditions.
PROJECT OBJECTIVE AND FUTURE STATE
The purpose of the project is to implement the Consultant-designed modernization and deliver a complete, reliable, integrated, and operational audiovisual environment. The completed installation is intended to coordinate the Board Room display, camera, microphone, loudspeaker, conferencing, control, signal-processing, AV networking, rack, and production functions established by the Contract Documents.
SYSTEM TECHNICAL NARRATIVE
This narrative is provided as a functional overview and does not replace or modify the detailed requirements of the Construction Drawings and other Contract Documents. In the event of an apparent discrepancy, the Bidder shall submit a written request for clarification before the Bid Due Date.
System Overview. The Board Room and associated production spaces are designed as a highly integrated audiovisual environment supporting in-room presentations, Microsoft Teams and Zoom conferencing, live video production, content distribution, and assistive listening. The system combines professional displays, networked audio and video transport, advanced camera systems, wired and wireless microphones, and centralized control.
Video Display System. The design includes three Samsung QM98C 98-inch professional 4K UHD displays as the primary visual destinations and three Samsung QM75C 75-inch displays serving audience areas. Content from presentation sources, conferencing systems, production systems, and network video sources will be dynamically routed throughout the facility.
Video Conferencing System. The system supports Microsoft Teams Rooms and Zoom Rooms through two HP Poly G62 conferencing codecs and HP Poly TC10 touch panels.
Camera System. Five Panasonic AW-UE160 PTZ cameras support conferencing, recording, and TriCaster production workflows. Two HP Poly E60 PTZ cameras and one HP Poly E70 intelligent ePTZ camera support the Microsoft Teams environment. Camera connectivity is supported through PoE++ infrastructure and a dedicated Netgear XSM4316PB network switch.
Video Distribution and Production. Video transport is provided through seventeen Crestron DM- NVX-363 encoder/decoder endpoints. A TriCaster Mini 4K production system supports multi-camera switching, recording, streaming, and content integration. Magewell NDI-to-HDMI and Inogeni 4K2USB3 HDMI-to-USB conversion devices support interoperability.
Audio System. A QSC Core 110F digital signal processor with Dante capability serves as the central audio-processing platform. Audio networking is supported through a Netgear GSM4352PB switch.
Loudspeaker coverage includes existing ceiling loudspeakers and QSC AD-P6T pendant loudspeakers, with amplification through a QSC MPA-Q 8X125 amplifier and an existing Crestron AMP-3210T amplifier.
Microphone Systems. The design includes sixteen Clock Audio gooseneck microphones with Clock Audio CDT100 AES67 transport devices, one Shure MXA925 ceiling array microphone, a Shure ULXD4Q quad-channel receiver, four Shure ULXD8 wireless gooseneck microphones, four Shure ULXD2 handheld microphones with Beta 58 capsules, Shure UA864 antennas, charging stations, and rechargeable batteries.
Assistive Listening. The existing assistive listening transmitter/radiator system will remain integrated as required by the Contract Documents.
Control System. System-wide control is provided through a Crestron CP4N processor and two Crestron TS-T080 wired tabletop touch panels. The control interface will operate displays, source selection, audio levels, camera presets, conferencing functions, and system power management.
Infrastructure and Equipment Rack. Central AV equipment will be housed within the existing 35RU equipment rack. The Contractor shall provide all cabling, connectors, termination hardware, interface plates, configuration, and documentation required for a complete and maintainable installation.
CONTRACTOR RESPONSIBILITIES
Project Management and Coordination
• Provide a qualified project manager and on-site supervision.
• Review the Construction Drawings and verify existing conditions before installation.
• Coordinate with Columbia Association, Cerami & Associates, Columbia Association Information Technology, and other trades or contractors.
• Coordinate power, network/data, pathways, junction boxes, floor boxes, furniture interfaces, mounting conditions, access, and shutdowns.
• Maintain and update a project schedule, submittal log, issue log, and punch list.
Equipment, Materials, and Accessories
• Furnish the new AV equipment and materials identified in the Construction Drawings and other applicable Contract Documents.
• Provide all mounts, brackets, adapters, connectors, patching components, labels, fasteners, licenses, power supplies, and incidental accessories required for a complete installation.
• Verify product availability and promptly notify Columbia Association of supply-chain conditions that may affect the schedule.
Existing Equipment and Demolition
• Protect existing equipment and finishes.
• Test, remove, relocate, reinstall, and integrate existing equipment as assigned by the
Construction Drawings.
• Coordinate intended reuse of the recently installed UPS and Crestron CP4N as reflected in the Construction Drawings.
• Remove abandoned AV equipment and cabling where required and deliver salvageable equipment to a location designated by Columbia Association.
• Dispose of debris and non-salvageable materials in accordance with applicable requirements.
Board Room AV Systems
• Install and integrate the displays, video-presentation systems, cameras, microphones, loudspeakers, audio processing and amplification, conferencing components, AV networking components, control interfaces, and signal-distribution equipment shown in the Construction Drawings.
• Coordinate final mounting locations and installation details with room conditions and the approved submittals.
Rack Room and Production Studio
• Install, dress, label, configure, and integrate rack-mounted equipment and production-system components.
• Maintain service access, ventilation, power distribution, grounding, and cable management required by the Construction Drawings.
• Integrate designated existing rack and production equipment with the new system.
Cabling and Connectivity
• Furnish, install, terminate, label, test, and document AV cabling in accordance with the Construction Drawings, technical specifications, and other applicable Contract Documents.
• Use appropriate cable types and ratings, including plenum ratings where required.
• Coordinate cabling with pathways, conduits, boxes, floors, walls, ceilings, furniture, equipment racks, and network infrastructure.
• Provide test results and cable schedules as part of closeout.
Programming, Configuration, and Integration
• Provide all programming, configuration, and system integration required by the Contract Documents.
• Develop user interfaces and operational workflows consistent with the design intent and Columbia Association-approved submittals.
• Provide all source code,…