27-0705 NH100 REPLACE EXTERIOR WINDOWS AT GREEN ROOF - SUBMITTAL REGISTER.pdf

PDF 105 KB Posted

Attached to
Replace Exterior Windows at Green Room
Solicitation number
N4008524R2810
Issued by

About this file

This document is a Submittal Register for Contract No. 27-0705 for the project to "Replace Exterior Windows at Green Roof". It lists various submittals required from the contractor, such as schedules, plans, reports, certificates, and closeout documents. The key submittals include a Crane Work Plan, Activity Hazard Analysis, Accident Prevention Plan, Equipment Delivery Schedule, Crane Critical Lift Plan, Crane Operator qualifications, Quality Control Plan, and Environmental Protection Plan. The project is being managed by the Department of the Navy's Naval Facilities Engineering Command and is limited to M&R MACC Contractors listed on the General Requirements cover page. No additional details about the contract opportunity are provided in this document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT NO.

CONTRACTOR

SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A

C

T

I

O

N

C

O

D

E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A

C

T

I

O

N

C

O

D

E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

01 20 00

1.3

01 30 00

1.4.1

01 31 50

1.2

01 32 16

1.2

1.3

01 33 00

1.4.1

1.6.1

01 35 29

1.9

1.10

1.9.1

1.9.1

1.7.1.4

1.14

1.14.1

1.14.3

1.14.4

1.14.5

1.11

Crane Reports

SD-07 CERTIFICATES

Confined Space Entry Permit

Approving Authority Contractor

Schedule Dates

SD-11 CLOSEOUT SUBMITTALS

Interim DD1354, Transfer & Acceptance

SD-11 CLOSEOUT SUBMITTALS

Submittal Register

Complete Submittal Package

TITLE AND LOCATION

Lighting Inverter Replacement G644

Schedule of Prices

List of Contact Personnel

Construction Schedule of Military Real Property (If Applicable)

A

C

T

I

V

I

T

Y

N

O

T

R

A

N

S

M

I

T

T

A

L

N

O

(d)

Contractor

Action

DESCRIPTION

ITEM SUBMITTED

(Enter Contractor Name Here)

Crane Work Plan (If Applicable)

Activity Hazard Analysis (AHA)

SD-06 TEST REPORTS

SD-01 PRECONSTRUCTION SUBMITTALS

23-0401

SD-01 PRECONSTRUCTION SUBMITTALS

Accident Prevention Plan (APP)

SD-01 PRECONSTRUCTION SUBMITTALS

Equipment Delivery Schedule

SD-01 PRECONSTRUCTION SUBMITTALS

SUBMITTAL REGISTER

P

A

R

A

G

R

A

P

H

N

O

S

P

E

C

S

E

C

T

C

L

A

S

S

I

F

I

C

A

T

I

O

N

G

O

V

T

O

R

A

E

R

E

V

W

R

Crane Critical Lift Plan (If Applicable)

Crane Operators (If Applicable)

Reports

Accident Reports

Monthly Exposure Reports

Regulatory Citations and Violations

1.14.6

1.14.7

01 45 10

1.6

01 50 00

1.6.2.1

2.1

3.1

1.3

01 57 19

1.6.1

1.6.4

1.7.2

1.7

1.7

PAGE 1 OF _

Third Party Certification of Barge-

Mounted Movile Cranes

SD-11 CLOSEOUT SUBMITTALS

Qaulity Control Plan (QC Plan)

Certificate of Compliance

Backflow Tester Certification (If Applicable)

Backflow Preventer Tests (If Applicable)

SD-01 PRECONSTRUCTION SUBMITTALS

Traffic Control Plan (If Applicable)

SUBMITTAL FORM, JAN 96 PREVIOUS EDITION OBSOLETE

MSDS for Class I ODS Waivered Product

SD-01 PRECONSTRUCTION SUBMITTALS

Permit for Storm Water Discharge (If applicable)

Environmental Protection Plan

Preconstruction Survey

Notice of Intent (If applicable)

SD-03 PRODUCT DATA

Backflow Preventers (If Applicable)

Backflow Preventers Certificate (If Applicable)

SD-06 TEST REPORTS

SD-07 CERTIFICATES

File details come from the government source that posted it. Updated .