This is Addendum Number 1 to Request for Quotes 27-01 issued by the Town of Ridgefield Office of the Purchasing Manager for construction of a stone boundary wall at the Peter Parley Schoolhouse located on West Lane along Route 35 in Ridgefield, Connecticut. The addendum clarifies specifications and requirements for the project, including details on wall construction materials, walkway specifications, and contractor responsibilities. The project involves construction of a new stone wall in the approximate location of an existing partial wall, approximately 75 feet in length, utilizing local field stone provided by the Town of Ridgefield in a dry-set construction method. Additionally, the contractor must construct an ADA-compliant walkway approximately 80 feet in length and 36 inches in width using bluestone set on an appropriate base material, with the contractor responsible for providing walkway materials. No construction will occur within the state right-of-way, and therefore no DOT encroachment permit is required. All bids must be submitted on company letterhead using a lump-sum pricing format.
The contractor is responsible for obtaining all necessary permits prior to the start of construction, including coordination with the Town of Ridgefield's designated representative who will be available throughout the project duration. Erosion control measures must comply with Town of Ridgefield zoning regulations. Existing stone from the current wall may be reused as appropriate. No estimated contract value, specific award date, or contract term details are provided in this addendum. Inquiries regarding the bid should be directed to David McFate, Ridgefield Town Purchasing, at 203-431-2720 or purchasing@ridgefieldct.gov.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Town of Ridgefield
Office of the Purchasing Manager
Addendum Number 1
Bid Number 27-01
Request for Quotes
Peter Parley Schoolhouse Stone Wall
To All Bidders:
The following questions have been received;
As this property is along Rt35 is a DOT Encroachment permit required? No construction will occur within the state right-of-way. As such, no encroachment permit is required.
Can you provide a detail for the wall? Historical walls do not use concrete. What type of stone do you want to match the area? The wall will be dry-set and will utilize local field stone. Stone for the wall will be provided by the Town of Ridgefield.
What erosion control measures are required? Erosion control measures will be in accordance with Town of Ridgefield zoning regulation, which is available at https://www.ridgefieldct.gov/departments/planning_and_zoning/zoning_regulations.php#outer -132
What type of stone do you want for the ADA walkway? The walkway will be bluestone set on an appropriate process material base. Contractor will provide materials for walkway.
How many square foot is the walkway? The walkway will be approximately 80 feet in length and 36 inches in width.
Is this to be priced lump sum or unit price? Can you please provide a bid form. Bids should be lump sum. Bids will be submitted on company letterhead.
Existing wall is approx 123' long, please clarify as specs indicate to construct a 75' long wall. Will the contractor be reinstalling the existing stone? New wall will be in the approximate location of the existing partial wall along Rte. 35. Existing stone may be reused us appropriate.
Will there be a designate contact person throughout the project duration if direction is needed? The Town of Ridgefield’s designated representative will be available throughout project duration as needed.
Who is responsible for obtaining permits? Per Instructions to Bidders, paragraph 7, it is the Contractor’s responsibility to obtain any necessary permits prior to the start of construction.
https://www.ridgefieldct.gov/departments/planning_and_zoning/zoning_regulations.php#outer-132 https://www.ridgefieldct.gov/departments/planning_and_zoning/zoning_regulations.php#outer-132