27-0052 Q&A.pdf

PDF 163 KB Posted

Attached to
27-0052 Roof Replacement for Cass, Emerson, Priest, Clippert
Solicitation number
RFP DET 270000000308 1
Issued by
Wayne County, Detroit City, Michigan

About this file

This is a Questions and Answers document from the Detroit Public Schools Community District (DPSCD) Procurement Department regarding RFP 27-0052 for FMP Series 6 Roof Replacement projects at four schools: Cass Technical High School, Emerson Elementary, Priest Elementary, and Clippert Elementary. The project scope includes roof replacement work at all four buildings, with a school-specific allowance for solar panel removal and reinstallation at Cass Technical High School. The Owner reserves the right to award the contract to a single or multiple vendors, with all building allowances included in the base bid. For bidding purposes, vendors must assume that existing roofing systems contain asbestos-containing material (ACM) unless confirmed otherwise by Owner testing or documentation. Any product substitutions not listed in the approved manufacturers section must be accompanied by supporting documentation demonstrating comparable or superior performance, installation efficiencies, operational efficiencies, warranty information, manufacturer support, and cost justification, along with proof of certified installer status. The roofing work is anticipated during summer months when school activities are minimal, and concurrent capital projects at Cass Technical High School include athletic field renovation and elevator modernization that must be coordinated with the roofing activities.

The Owner has established a $50,000.00 owner-controlled allowance for removal and reinstallation of the existing commercial solar photovoltaic system at Cass Technical High School to address system-age risks, concealed conditions, component incompatibility, access constraints, and required commissioning or closeout work. The awarded vendor is responsible for developing a site-specific logistics plan for Owner review and approval, including crane placement and coordination with concurrent projects. During pre-construction kickoff, the vendor must conduct interior inspections directly below and adjacent to the roof scope, photograph and document existing conditions, and provide appropriate temporary protection for interior areas, finishes, equipment, and furnishings against dust, debris, insects, and other potential disturbances from roofing activities. Updated project manuals with core information and attachment details have been uploaded to DemandStar for all four schools to support accurate bidding.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Procurement Department

Fisher Building • 3011 West Grand Blvd., 11th Floor • Detroit, MI 48202

Detroitk12.org

Students Rise.

We all Rise

DPSCD does not discriminate based on race, color, national origin, sex, disability and/or religion. Contact Compliance for more information at

(313) 240-4377 or detroitk12.org/admin/compliance.

RFP 27-0052

FMP Series 6 Roof Replacement for Cass Tech, Emerson, Priest, and Clippert

Questions and Answers

Q: • With the allowances, is it the intent to award all these projects to 1 contractor or separately? And if it's separate, where do we divvy up those allowances?

A: The Owner reserves the right to award a contract to a single or multiple vendors. All building allowances shall be included in the Base Bid. The only school-specific allowance is for Cass Technical High School and shall cover the solar panel scope of work.

Q: • Are vendors to assume the asbestos is within the roofs, not necessarily just the flashings?

A: For bidding purposes, vendors shall assume that existing roofing systems contain asbestos-containing material (ACM) unless confirmed otherwise by testing or documentation provided by the Owner.

Q: Can Versace Roofing Systems be added to the Low Slope roofing specs as a manufacturer?

A: As part of bid submission, bidders are required to provide all product information for all products that are not listed in the approved manufacturers section of the contract specifications. All product substitution requests are to be accompanied with backup speaking to why the product will benefit the Owner, including but not limited installation efficiencies, operational efficiencies, warranty and manufacturer support, cost, identifying as a comparable or superior product, etc. The bidder must also submit proof that they are a certified installer of the substitute product.

Q: Where is the crane able to be set up at Cass tech? Can we set this up on the NE and SW side of the building? These seem to be school drives and would eliminate cost with road closures.

A: The awarded vendor shall be responsible for developing a site-specific logistics plan for review and approval by the Owner. The roofing work is anticipated to occur during the summer months when school activities are minimal. Concurrent capital projects at Cass

Technical High School will include the athletic field renovation and elevator modernization. The awarded Vendor shall coordinate its work with all concurrent projects and promptly communicate any anticipated conflicts, impacts, or disruptions to the Owner and Project Team.

http://detroitk12.org/admin/compliance

We all Rise

DPSCD does not discriminate based on race, color, national origin, sex, disability and/or religion. Contact Compliance for more information at

(313) 240-4377 or detroitk12.org/admin/compliance.

Q: Is the roofing contractor responsible for removal and reinstallation of the solar panels at

Cass tech?

A: The Contractor shall include a $50,000.00 owner-controlled allowance for the existing commercial solar photovoltaic system affected by the Cass Technical High School roof replacement to the base bid contract. This allowance is intended to support the defined removal and reinstallation activities and to provide controlled funding for system-age risks, concealed conditions, component incompatibility, access constraints, and required commissioning or closeout work.

Q: Detail 11 for Cass tech shows us flashing up and over the walls on the parapets. Are we to remove the existing siding, install plywood, and flash up and over? Existing is metal siding with counter flashings.

A: The existing metal siding does not need to be removed. Plywood can be placed over the existing siding.

Q: For priest and Clippert. There is no good core cut info like there is for the other 2 schools.

Can we get core info for these? Also, priest inspection report calls out steel deck, but was noticed to be concrete deck on site.

A: Updated project manuals have been uploaded to DemandStar which includes updated core info on plans. Steel deck was noted in cores.

Q: Is shop fabricated coping and edge metal acceptable if it meets ES-1 standards?

A: Yes, with a current ES-1 certification from the shop.

Q: For Priest, do we need to remove the stone coping, or can we install the new wood nailer over it?

A: If the stone coping is sturdy enough to receive the wood nailer and it can be fabricated so that the drainage is sloped back towards the roof, then the stone coping does not need to be replaced.

Q: Page 2 on Emerson and Cass have core and new roof make up, fastening patterns, etc.

Can we get these for Priest and Clippert?

A: Updated project manuals have been uploaded to DemandStar which includes updated core info on plans. Steel deck was noted in cores.

We all Rise

DPSCD does not discriminate based on race, color, national origin, sex, disability and/or religion. Contact Compliance for more information at

(313) 240-4377 or detroitk12.org/admin/compliance.

Q: Can you confirm that page 2 of the drawings for Cass and Emerson is correct? The attachment requirements have the cover board being adhered to in the field and the perimeter but fastened at the corners.

A: Yes, the drawings for Cass Technical High School and Emerson are correct. Gang fastening in the corners is for wind uplift.

Q: The core information is provided, but it states "tapered Iso" with no thickness provided. Can we have the thinnest and thickest measurements of the Iso layer or at least an average thickness?

A: The cores were not done at exactly the high and low points but were done 12 feet apart to determine what is there. The math can be done with a 12 foot lateral distance.

Q: Sheet 02 of 06 on "Attachment G - Emerson EMS Drawings" shows attachment for steel decks but does not show for concrete decks or wood decks. Can you please advise the insulation over concrete and wood decks for bottom layer of insulation, top and intermediate insulation layers, and cover board at the attachment rates?

A: Attachment for concrete and wood decks have been added to the drawing sheet 02 for

Emerson.

Q: Do you want drain inserts at all roof drains on concrete deck?

A: Yes, if the in-place drains are functioning and can have the clamping ring placed properly.

Q: The specifications state interior protection is to be used as discussed during the pre bid.

None of the locations had discussed interior protection to be needed. Can we define where and if this is up to the contractor as to not damage anything?

A: As part of the pre-construction kickoff walkthrough, the awarded vendor(s) shall inspect all interior areas located directly below and adjacent to the roof scope of work. The vendor shall photograph and document existing conditions prior to commencing construction. The awarded vendor shall also be responsible for providing and maintaining appropriate temporary protection for interior areas, finishes, equipment, furnishings, and other building contents that may be impacted by the roofing activities. Protection shall address potential dust, debris, insects, and other materials or disturbances resulting from the roof construction. Any areas or items requiring additional protection identified during the pre-construction walkthrough shall be coordinated with the Owner and Project Team prior to the start of work.