Parking_Lot_Striping_SOW(2).pdf

PDF 574 KB Posted

Attached to
Parking Lot Painting & Redesign
Solicitation number
26QA002
Issued by

About this file

This is a Statement of Work (SOW) for parking lot striping and painting services at the U.S. Army Corps of Engineers, Norfolk District, located at 803 Front Street, Norfolk, Virginia 23510. The contractor must complete all work within 30 calendar days from contract award. The scope encompasses site preparation including power sweeping and blacking out existing markings, submission of two distinct striping layout options within 5 calendar days for Government approval, and application of new striping and stenciling in accordance with the approved design. The contractor is responsible for furnishing all labor, equipment, materials, tools, transportation, and supervision required.

The work includes striping standard parking spaces, handicap spaces, van-accessible spaces, and four electric vehicle charging station spaces marked in green paint. Reserved spaces must be stenciled in yellow paint. All striping must comply with Americans with Disabilities Act (ADA) requirements, Occupational Safety and Health Administration (OSHA) regulations, and Virginia Department of Transportation standards. The contractor must conduct a joint final inspection with the Government's Contracting Officer's Representative and correct any unsatisfactory markings at no additional cost. Paint must be uniform, weather-resistant, durable, and applied under proper surface temperature conditions. No Government-furnished property or materials will be provided.

View the file

Other files

File Type Posted
Parking Layout Oct 2025-1.pdf PDF
Parking Lot- PWS(3).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW) Parking Lot Striping and Painting – One-Time Service

Location: U.S. Army Corps of Engineers, Norfolk District 803 Front Street, Norfolk, Virginia 23510

Period of Performance: One-time service to be completed within 30 calendar days from contract award

1.0 Purpose

This Statement of Work (SOW) defines the requirements for cleaning, painting, and restriping of the parking lot located at the U.S. Army Corps of Engineers, Norfolk District. The objective is to restore and improve the visibility, organization, and compliance of parking lot markings in accordance with industry standards and Americans with Disabilities Act (ADA) requirements.

2.0 Scope

The contractor shall furnish all labor, equipment, materials, tools, transportation, and supervision necessary to complete the parking lot cleaning, black-out, and restriping work as specified in this SOW. The work includes providing design layout options, preparing the surface, and applying new striping and stenciling in accordance with the Government-approved layout.

3.0 Applicable References

• Americans with Disabilities Act (ADA) Accessibility Guidelines

• Occupational Safety and Health Administration (OSHA) Regulations

• Federal and Virginia Department of Transportation (VDOT) standards for pavement markings

• Manufacturer’s specifications for paint and materials used

4.0 Tasks and Requirements

Task 1: Site Preparation

1. Clean the entire parking lot surface using a commercial-grade power sweeper and blower to remove dirt, debris, and loose materials.

2. Black out all existing pavement markings and lettering using black paint or approved sealant to ensure a clean surface for new striping.

Task 2: Design Layout Submission

3. Develop and provide two (2) distinct parking lot striping layout options for

Government review and approval.

4. Each layout shall include all required parking spaces, traffic flow arrows, handicap spaces, van-accessible spaces, and designated reserved and electric vehicle (EV) charging areas.

5. The Government will select one layout prior to the start of painting.

Task 3: Striping and Painting

6. Stripe all standard parking spaces, handicap spaces, and van-accessible spaces in accordance with the approved design layout and ADA requirements.

7. Stencil the word “RESERVED” in designated areas using yellow paint.

8. Stencil and paint four (4) Electric Vehicle (EV) charging station spaces using green paint and appropriate EV markings.

9. Ensure all striping is straight, uniform, and free from overspray.

Task 4: Quality Assurance and Final Inspection

10. Upon completion, conduct a joint inspection with the Government representative to verify compliance with layout, color, and spacing specifications.

11. Reapply or correct any markings found to be unsatisfactory at no additional cost to the Government.

5.0 Deliverables

Deliverable Description Due Date

Layout Options Two (2) striping design layouts submitted for review and approval

Within 5 calendar days of contract award

Completed Work All striping and stenciling completed in accordance with approved layout

Within 30 calendar days of contract award

6.0 Government Furnished Property and Services

No Government-furnished property, materials, or utilities will be provided under this contract. The contractor is responsible for all tools, materials, and equipment necessary to complete the work.

7.0 Quality Standards and Acceptance

All work shall meet industry standards for parking lot striping and ADA compliance.

Paint must be:

- Uniform, sharply defined, and free of irregularities

- Weather resistant and durable for high-traffic environments

- Applied in dry conditions with surface temperatures meeting manufacturer recommendations

Final acceptance will be determined by the Contracting Officer’s Representative (COR) following successful inspection of the completed work.

8.0 Safety Requirements

The contractor shall comply with all OSHA safety regulations and implement appropriate safety measures to protect personnel, Government property, and the public during the performance of this contract.

9.0 Period of Performance

All work described in this Statement of Work shall be completed within 30 calendar days from the date of contract award.

Statement of Work (SOW)
1.0 Purpose
2.0 Scope
3.0 Applicable References
4.0 Tasks and Requirements
Task 1: Site Preparation
Task 2: Design Layout Submission
Task 3: Striping and Painting
Task 4: Quality Assurance and Final Inspection
5.0 Deliverables
6.0 Government Furnished Property and Services
7.0 Quality Standards and Acceptance
8.0 Safety Requirements
9.0 Period of Performance

File details come from the government source that posted it. Updated .