This document is an Existing Equipment Removal Requirements specification for a federal contract at the Trident Refit Facility (TRF) Bangor.
The contractor is required to remove a HAAS ST-20Y CNC Turning Center (NID# 68438C0038) and all associated equipment, electrical gear, and disconnects from Room S101 at TRF Bangor, located at 7000 Finback Circle, Silverdale, WA 98315, Naval Base Kitsap – Bangor. The scope includes coordinating removal with the Prime Contractor installing new equipment, scheduling work to minimize disruption to shop operations, and conducting all work per site-specific requirements in Project Document Attachment A. Upon receipt of an approved Plan of Action and Milestones (POA&M), the contractor shall disassemble the machine as necessary for transport and transport it to scrap. The contractor must also manage waste as designated by the Government and is responsible for cleaning any residual fluids, dirt, and debris found to have leaked from the removed equipment for 15 calendar days following removal. The Government will disconnect utilities and bring the machine to a Zero-Energy State by removing or relieving all sources of stored energy (gravitational, mechanical, electrical, etc.), provide a laydown area for contractor equipment, and remove bulk fluids.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Trident Refit Facility
pg. 1
TRF Bangor – Project #379-320 – CNC Universal Turning Center
Attachment B
Existing Equipment Removal Requirements
LOCATION:
TRF Bangor, B7000 Rm S101
7000 Finback Circle, Silverdale, WA 98315
Naval Base Kitsap – Bangor, in Silverdale, Washington
1. REQUIREMENTS
1.1. Scope. The Government’s installation site for the equipment specified herein is currently occupied by a
HAAS ST-20Y CNC Turning Center (NID# 68438C0038). The machine with all associated equipment and electrical gear, including disconnects, shall be removed. The contractor shall coordinate/schedule the removal and disposition of the machine as follows:
1.1.1. Coordinate equipment removal with Prime Contractor for the new equipment being installed in conjunction with this contract document.
1.1.2. Schedule and conduct work in such a manner that minimizes, to the greatest extent possible, any downtime and/or disruption to shop production operations as a result of the collective effort required to remove and install the new equipment.
1.1.3. All work shall be conducted IAW the site-specific requirements as detailed in Project Document
Attachment A.
1.2. Equipment Removal. Upon receipt of an approved Plan of Action and Milestones (POA&M) per contract, the contractor shall be responsible for completion of the following:
1.2.1. The machine with all associated equipment and electrical gear, including disconnects, shall be removed.
1.2.2. Manage waste as designated by the Government in Attachment A.
1.2.3. The machine shall be disassembled as necessary for transport.
1.2.4. Transport machine to scrap.
2. GOVERNMENT RESPONSIBILITIES:
2.1. Disconnect utilities and bring the machine to a Zero-Energy State.
2.1.1. Remove or relieve any sources of stored energy (gravitational, mechanical, electrical, etc.) that remain within the equipment.
2.2. Provide laydown area for contractor equipment.
2.3. Remove bulk fluids.
2.4. The contractor shall be responsible for cleaning any residual fluids, dirt, and debris found to have leaked from the removed equipment for a period of 15 calendar days after removal.