This is a Specifications Package for a construction project involving Sarasota County, Florida, and prepared by Cummins Cederberg, Inc., a professional engineering firm. The project consists of maintenance dredging of approximately 77,160 cubic yards over approximately 33,000 linear feet of Phillippi Creek between U.S. 41 and South Beneva Road to restore a permitted design elevation of -4 feet Mean Low Water (MLW) and improve stormwater conveyance and mitigate flooding potential. The work includes mobilization and demobilization, mechanical and/or hydraulic sediment removal, temporary staging area acquisition and construction, retention pond construction, dewatering operations, sealed truck transport of sediment, disposal at County-designated sites (Lorraine Road disposal site or Sarasota County Landfill), dredge material management area (DMMA) preparation on seven County-owned properties, erosion and turbidity control, environmental and wildlife monitoring and reporting, and site restoration. The Contract Documents specify that the bidder's offer shall remain irrevocable for 180 days from bid opening or until the County issues Notice to Proceed, whichever occurs first, and that the County anticipates executing a construction contract for the duration of the project.
The specifications establish comprehensive requirements for dredging operations, environmental protection, surveying and as-built documentation, project signs, maintenance of traffic, and clearing and grubbing activities. Contractor responsibilities include obtaining all necessary permits (NPDES, maintenance of traffic, tree permits) at no cost to the County, coordinating with the United States Coast Guard for navigational requirements, and complying with all federal, state, and local permit conditions issued by the Florida Department of Environmental Protection and U.S. Army Corps of Engineers. Mobilization and demobilization costs are included in a lump sum bid item, with 60 percent payable after commencement of dredging and disposal of a minimum of 200 cubic yards at an approved site, and the remaining 40 percent included in final payment. The specifications include detailed measurement and payment provisions for various dredging components, surveying work (including as-built plans, monumentation, and corner certification), environmental monitoring and compliance, and site restoration, with all work to be performed in accordance with the January 2026 Edition of Florida Department of Transportation Standard Specifications as revised by the specifications package.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date:_____________________
PREPARED BY:
SPECIFICATIONS PACKAGE
Name of Project, CIP #
The January 2026 Edition of the Florida Department of Transportation Standard Specifications is revised as follows:
I hereby certify that this specifications package has been properly prepared by me, or under my responsible charge.
This item has been digitally signed and sealed on the date adjacent to the seal. Printed copies of this document are not considered signed and sealed and the signature must be verified on any electronic copies.
Signature and Seal:
Date:
State of Florida, Professional Engineer, License No:
Firm Name: Cummins Cederberg, Inc Firm Address: 111 2nd ST Ave NE, Suite 1100 City, State, Zip Code: St Petersburg, FL 33701 Pages: 65
SPECIAL PROVISIONS
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC – PRESERVATION OF EXISTING PROPERTY –
UTILITIES - UTILITY ADJUSTMENTS (NO UTILITY WORK SCHEDULE)
PROSECUTION AND PROGRESS – PROVISION FOR CONVENIENCE OF PUBLIC (COUNTY SPECIFIC REQUIREMENTS). 6 MEASUREMENT AND PAYMENT – SCOPE OF PAYMENTS, BITUMINOUS MATERIALS (COUNTY SPECIFIC
REQUIREMENTS)
SUPPLEMENTAL SPECIFICATIONS
DEFINITIONS AND TERMS - DEFINITIONS (COUNTY SPECIFIC REQUIREMENTS)
SURVEYING AND AS-BUILT SURVEYS (COUNTY SPECIFIC REQUIREMENTS). (REV 02-07-17) (7-22)
SECTION 57 SURVEYING AND AS-BUILT SURVEYS
57-1 Description 57-2 Personnel, Equipment, and Record Requirements 57-3 Protection and Restoration of Property Markers and Survey Monuments 57-4 As-built Plans 57-5 Method of Measurement 57-6 Submittals 57-7 Basis of Payment
PROJECT SIGNS (COUNTY SPECIFIC REQUIREMENTS). (REV 12-06-21) (7-22) (4-22)
SECTION 98 PROJECT SIGNS
98-1 Description 98-2 Materials 98-3 Construction Requirements
MAINTENANCE OF TRAFFIC (COUNTY SPECIFIC REQUIREMENTS). (REV 09-30-21) (7-22)
PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION (COUNTY SPECIFIC
REQUIREMENTS)
CLEARING AND GRUBBING (COUNTY SPECIFIC REQUIREMENTS). (REV 05-01-20) (7-22)
EXCAVATION AND EMBANKMENT (COUNTY SPECIFIC REQUIREMENTS). (REV 06-06-18) (7-22)
TECHNICAL SPECIAL PROVISIONS
1 GENERAL CONDITIONS
1.1 Definitions
1.2 Scope of Work
1.3 Permits and Responsibilities
1.3.1 Environmental Permits
1.3.2 Other Permits
1.3.3 Coast Guard Coordination
1.6 Project Management
1.6.1 Order of Work and Work Schedule
1.6.1.1 Continuous Construction
1.6.2 Submittals
1.6.2.1 Safety Plan
1.6.3 Notification
1.6.3.1 Notifications
1.9 Quality Control
1.9.1 Weekly Summary Report
1.9.2 Daily Quality Control Report
1.9.3 Water Quality Monitoring by the Contractor
1.9.4 Field Quality Control Testing and Monitoring
2 DREDGING OPERATIONS
2.1 Mobilization / Demobilization
2.2 Pre-Construction Submittals and Work Plans
2.2.1 Dredging Work Plan
2.2.1.1 Project Schedule
2.2.1.2 Pre-construction Documentation
2.2.1.3 List of Subcontractors
2.2.2 Fuel Handling and Storage
2.2.3 Utility Coordination
2.2.4 Vibration Monitoring
2.3 Layout of the Work
2.3.1 Character of Materials
2.4 Navigational Aids and Waterway Markers
2.4.1 Boat Traffic and Navigation
2.5 Dredging Requirements
2.5.1 Dredge Plant Requirements
2.5.2 Dredge Template
2.5.2.1 Dredge Tolerance
2.5.2.2 Side Slopes
2.5.2.3 Shoaling
2.5.3 Excessive Dredging
2.5.4 Bridge-Specific Dredging Restrictions
2.5.5 Supplemental Private Dredging
2.5.6 Dredging Specific Reporting Requirements
2.6 Disposal of Debris and Obstructions
2.6.1 Sediment Accumulation
2.6.2 Sediment Accumulation Outside of Dredge Footprint During Construction
2.6.3 Rock Excavation
2.6.4 Differing Site Conditions and Obstructions
2.7 Surveys and Acceptance Requirements
2.7.1 Survey Deliverables
2.7.1.1 Design Survey
2.7.1.2 Pre-construction Before Dredge (BD) Survey
2.7.1.3 After Dredge (AD) Survey
3 DREDGED MATERIAL MANAGEMENT AREAS (DMMAS) AND HAULING
3.1 DMMA Submittals and Work Plans
3.1.1 DMMA Preparation Plan
3.1.2 Hauling and Maintenance of Traffic (MOT)
3.1.3 Work Site Requirements
3.1.3.1 Limits of Construction
3.1.3.2 Security and Restriction of Public Access
3.1.3.3 Construction Access
3.1.3.4 Signal Lights
3.1.3.5 Staging and Storage Areas
3.1.3.5.1 Privacy Fence Requirement
3.1.4 Dewatering
3.1.5 Stockpiling
3.2 Final Disposal
3.2.1 Approved Final Disposal Locations
3.2.2 Alternate Disposal Locations
3.2.2.1 Use of Private Property for Disposal
3.3 Contaminated Material Handling
3.3.1 Dredged Material Testing
4 MEASUREMENT AND PAYMENT
4.1 Pay Quantities
4.2 Non-Pay Quantities
4.2.1 Excessive Dredging
4.2.2 Dredge Material Overflow
4.2.3 Misplaced Dredge Materials
5 MEASUREMENT AND PAYMENT
5.1 As-Built Survey
5.2 Demobilization
5.3 Site Restoration
5.3.1 Cleanup
5.3.2 Site Restoration Plan
5.3.3 Riprap Shoreline Stabilization Delivery and Installation (above MHW)
5.3.3.1 Work Included
5.3.3.2 Submittals
5.3.3.3 Riprap Rock Materials
5.3.3.4 Installation
5.4 Project Closeout
5.4.1 Damages and Site Restoration
5.4.2 Final Clean Up
6 ENVIRONMENTAL PROTECTION
6.1 Scope
6.2 Quality Control
6.3 Permits
6.4 Noncompliance
6.5 Protection of Environmental Resources
6.5.1 Water Resources
6.5.1.1 General
6.5.1.2 Violations
6.5.1.3 Reporting
6.5.1.4 Wastewaters
6.5.2 Land Resources
6.5.2.1 General
6.5.2.2 Work Area Limits
6.5.2.3 Erosion & Sedimentation Control
6.5.3 Fish & Wildlife Resources
6.5.3.1 General
6.5.3.2 Manatee
6.5.3.3 Sea Turtle, Smalltooth Sawfish, and Birds
6.5.4 Seagrass Resources
6.5.4.1 Protected Species & Avoidance
6.5.4.2 Minimum Vessel Clearance
6.5.4.3 Documentation
6.5.5 Air Resources
6.5.6 Wetland Resources
6.5.6.1 General
6.5.6.2 Shoreline Vegetation
6.5.7 Historical, Archaeological, and Cultural Resources
6.5.7.1 Inadvertent Discoveries
6.5.7.2 Claims for Downtime Due to Inadvertent Discoveries
6.5.8 Sound Intrusions
6.5.9 Oyster Resources
6.6 Post-Construction Cleanup
6.7 Hazardous Materials
6.7.1 Spills & Containment
6.7.2 Storage of Lubricants
6.7.3 Disposal of Chemical Waste
6.7.4 Disposal of Solid Waste
6.7.5 Disposal of Discarded Materials
6.8 Training of Contractor Personnel
6.9 Environmental Protection Plan
6.10 Temporary Turbidity Control Systems
6.11 Turbidity Monitoring and Reporting
6.12 Environmental Monitoring
6.12.1 Dredged Sediment Testing
6.12.2 Return Water Testing
6.12.3 Reporting
THIS COMPLETES THIS SPECIFICATIONS PACKAGE
SPECIAL
PROVISIONS
LEGAL REQUIREMENTS AND RESPONSIBILITY TO THE PUBLIC –
PRESERVATION OF EXISTING PROPERTY – UTILITIES - UTILITY
ADJUSTMENTS (NO UTILITY WORK SCHEDULE).
(REV 2-10-94) (7-22)
SUBARTICLE 7-11.5.3 is expanded by the following:
For utility work involving facilities owned by other agencies, refer to
Technical Special Provisions Section 2.2.3.
PROSECUTION AND PROGRESS – PROVISION FOR CONVENIENCE OF PUBLIC
(COUNTY SPECIFIC REQUIREMENTS).
(REV 05-01-20) (7-22)
SUBARTICLE 8-3.4 is expanded by the following:
Notice all adjacent properties prior to any work beginning by placing door hangers, provided by the County, at least 24 hours prior to but no earlier than 3 work days prior to any construction activities. Failure to distribute the notices as outlined above shall result in an immediate suspension of work. No additional days or monetary compensation for this suspension shall be granted.
MEASUREMENT AND PAYMENT – SCOPE OF PAYMENTS, BITUMINOUS
MATERIALS (COUNTY SPECIFIC REQUIREMENTS).
(REV 09-30-21) (7-22)
SUBARTICLE 9-2.1.2 is expanded by the following:
Include as part of this bid, an allowance for bituminous material adjustment. Any funds remaining in this pay item shall not be paid out as part of the final payment but shall remain with the contract; any adjustments in excess of the provided allowance shall be paid under an IFCA or Change Order.
Pay Items: Payment will be made under:
Item No. SP-1 Bituminous Material Adjustment Allowance – Allowance.
SUPPLEMENTAL
SPECIFICATIONS
DEFINITIONS AND TERMS - DEFINITIONS (COUNTY SPECIFIC
REQUIREMENTS).
(REV 03-10-20) (7-22)
ARTICLE 1-3, definition for Substantial Completion is further defined as follows:
Substantial Completion.
Substantial Completion shall be achieved when the Work, or an approved portion thereof, has been completed in accordance with the Contract Documents and is available for its intended use.
At a minimum, the following conditions shall be satisfied prior to a determination of Substantial Completion:
a) All dredging required under the Contract has been completed
b) Required channel depths, widths, and side slopes have been achieved in accordance with the Contract Documents.
c) Dredged material has been placed at the approved final disposal site.
d) Required After Dredge (AD) surveys have been completed and submitted.
e) Required environmental monitoring, turbidity monitoring, and permit compliance activities have been completed.
f) Major dredging, hauling, disposal, and DMMA operations have been completed.
g) Site restoration has been substantially completed.
h) The Work is available for its intended public use
When the Contractor believes the Work is substantially complete, the Contractor shall submit a written request for inspection to the Engineer and County.
The Engineer, County, and Contractor shall jointly inspect the Work within a reasonable period following receipt of the request. If the Work is determined to be substantially complete, the Engineer shall issue a Certificate of Substantial Completion and prepare a punch list identifying any remaining work required for Final Completion.
Prior to requesting Substantial Completion, the Contractor shall submit:
a) Updated contract accounting and payment documentation.
b) A list of incomplete or corrective work items, if any.
c) Required lien releases.
d) Final survey data and supporting documentation.
e) Environmental monitoring and permit-compliance records.
f) Warranties, certifications, and maintenance agreements required by the Contract
Documents.
g) Documentation demonstrating completion of site cleanup and restoration requirements.
In no case shall substantial completion be given without the submittal of preliminary as-built drawings which shall contain all information as required by Sarasota County Standard Specification 57. If the Work is determined not to be substantially complete, the Engineer shall provide the Contractor with a written list of deficiencies requiring correction. Upon completion of the identified items, the Contractor may request a follow-up inspection.
Final Completion.
Final Completion shall occur when:
a) All punch-list items have been completed.
b) All required surveys, reports, and closeout documentation have been submitted and accepted.
c) All site restoration requirements have been completed.
d) All temporary facilities, staging areas, DMMAs, temporary access routes, and construction-related improvements have been removed or restored as required by the Contract Documents.
e) All environmental permit requirements and regulatory obligations have been satisfied.
f) The Work has been accepted by the County.
Upon receipt of written notice from the Contractor that the Work is complete, the Engineer shall perform a final inspection within seven (7) calendar days and notify the Contractor of any remaining deficiencies. The Contractor shall promptly correct all identified deficiencies.
SURVEYING AND AS-BUILT SURVEYS (COUNTY SPECIFIC REQUIREMENTS).
(REV 02-07-17) (7-22)
Page 111. The following new Section is added after Section 9.
SECTION 57
SURVEYING AND AS-BUILT SURVEYS
57-1 Description.
Perform survey work in compliance with the Standards of Practice for Professional
Surveyors and Mappers (Chapter 5J-17, Florida Administrative Code, pursuant to Section 472.027, F.S.), includes As-Built Surveys and final survey monumentation.
57-2 Personnel, Equipment, and Record Requirements.
Keep adequate field notes for all permanent control points that are referenced and reset. Make these field notes available for the County Surveyor’s review as the work progresses and furnish a complete scanned copy in Adobe PDF to the County Surveyor at the time of completion of the project. The County Surveyor’s inspection, checking, or acceptance of the Contractor’s field notes, or survey work does not relieve the Contractor of his responsibility to achieve the lines, grades, and dimensions shown in the Contract Documents.
GPS is not acceptable for resetting monuments.
57-3 Protection and Restoration of Property Markers and Survey Monuments.
The Contractor shall employ a Florida-licensed Professional Land Surveyor satisfactory to the Engineer to perform all witnessing, restoration, setting or resetting of land boundary monuments and markers as required by this Specification.
The Contractor shall be responsible for the preservation of all public and private property markers and shall protect carefully from disturbance or damage all survey monuments and property markers until their locations are witnessed or otherwise referenced by a Florida-licensed Professional Land Surveyor so the surveyor can restore them in their original location as the pertinent portions of project construction are completed.
All survey monuments, property markers, and benchmarks disturbed or destroyed by the Contractor or his forces through accident or negligence shall be replaced by a Florida-licensed Professional Land Surveyor at the Contractor’s expense.
No special compensation will be made to the Contractor to defray time or monetary costs of any delays occasioned by protection of land boundary markers, survey monuments, or benchmarks, witnessing existing markers, setting of new benchmarks, setting of survey monuments or re-setting of land boundary monuments and markers.
If a property corner is destroyed and replaced, submit a copy of the Boundary Survey to the Engineer.
57-3.1 Section and ¼ Section Corners: All section corners and ¼-section corners disturbed shall be reset with monuments (iron rod and cap or concrete monument). The Surveyor employed by the Contractor shall re-reference section corners and ¼-corners within the project limits and submit a Certified Corner Record in accordance with Chapter 177.507, Part III, Certification of Corners, Florida Statutes to the Florida Department of Environmental Protection (FDEP) and the County.
Contractor must submit confirmation that the Certified Corner Record has been sent to the FDEP.
57-3.2 Benchmarks: Any federal, state, or county benchmark monument disturbed or destroyed by construction shall be replaced in a nearby location.
National Geodetic Vertical Datum (NGVD) 1929 benchmarks need to be protected, or if destroyed need to be moved to a nearby location. Establish a new benchmark offsite prior to destroying the NGVD29 and run a closed level loop back to the original NGVD29 benchmark. Supply the County Surveyor with the field book notes and to obtain a county benchmark number.
North American Vertical Datum (NAVD) 1988 benchmarks need to be protected, or if destroyed disc must be submitted to the County Surveyor. Establish a new benchmark offsite prior to destroying the NAVD88 and run a closed level loop back to the original NAVD88 benchmark. Supply the County Surveyor with the field book notes and to obtain a county benchmark number.
57-3.3 Right-of-Way Monumentation: All right-of-way owned by the County including right-of-way for lateral ditches, environmental impact mitigation sites, storm water management pond sites and other drainage facilities shall be monumented in accordance with the information shown on the Right-of-Way Map. The right-of-way will be monumented using markers provided by Sarasota County Survey-Mapping, SARCO Aluminum R/W Markers, to be stamped with the Contractor’s Surveyors P.S.M. or L.B.
Number. Those markers shall be set on the right-of-way as shown on the Right-of- Way Map. The final field location of the right-of-way markers installed will be shown on a Right-of-Way Monumentation Map (Specific Purpose Survey) and the monumentation installation shall be certified by the Contractor’s Surveyor. One Mylar signed and sealed copy of the Right-of-Way Monumentation Map will be submitted to the Engineer.
57-3.4 Point of Intersection (P.I.) Monumentation: All disturbed centerline P.I. monumentation for the right-of-way of all intersecting roads, canals and railroads, unless a section or ¼-section corner, shall be reset with a nail and disc, and four straddlers. The location of these PIs shall be re-established by using the references previously established in the field or on the right-of-way control survey.
57-3.5 Permanent Control Point (PCP) Monumentation: Reference and replace existing PCPs found at intersecting streets, point of curvature, point of tangency, point of compound curve, point of reverse curve and angle breaks or jogs in the roadway centerline alignment. The exact number and locations are not known and must be identified by the Contractor prior to construction activities.
57-4 As-built Plans.
57-4.1 General: One complete set of the signed and sealed Contract Plans on 11” by 17” plan sheets shall be maintained as the “As-Built” Plans and be “red-lined” on an on-going basis to reflect completed construction conditions. These plans shall be made immediately available to the Engineer upon request throughout the life of the Contract.
Contents of the Final “As-Built” Plans will vary, but shall always contain those sheets necessary to completely cover all work performed. The Final “As-Built” Plans shall include all changes, both design and construction, including adequate sketches, dimensions, and notes. The Contract Plans including all changes are the Final “As- Built” Plans after construction is complete. All revisions including those occurring during construction will be included in the Final “As-Built” Plans set.
57-4.1.1 Maintaining the Set of Contract Plans: The complete set of the Contract Plans shall be kept in a place that protects the plans but allows ready access.
Any and all changes made to the project will be reflected on these plans. No pages shall be discarded from this set. This set of plans will be the Final “As-Built” Plans.
57-4.1.2 Updating the Set of Contract Plans: Notify the Engineer of Record if changes are required under his responsibility.
57-4.2 Final “As-Built” Plans Revisions: The following information shall be considered minimum standard for preparing Final “As-Built” Plans:
57-4.2.1 The Key Sheet: The Key Sheet of the Final "As-Built" Plans shall show the following data:
(A) Final "As-Built" Plans shall be prominently inked or stenciled across the top of the sheet in place of or above the “Contract Plans” preprinted line and those words shall be lined through or completely deleted.
(B) On the right side and near the lower corner, the following information shall be lettered, stamped, or typewritten on white paper and securely pasted or taped on the Key Sheet:
(1) Name of Contractor
(2) Name of all consultants involved in construction. (If none, so state)
(3) Name of County Project Manager
(4) Date Work Started
(5) Date Work Final Acceptance or Completed
(6) Certification Final "As-Built" Plans signed by Surveyor
(C) A complete Index of the Final "As-Built" Plans shall be shown on the left side of the Key Sheet.
(D) All major revisions to the Final "As-Built" Plans during construction shall be added to the revision list on the left side of the sheet below the Dredging Plan Sheets. This information shall be lettered or typewritten on a piece of white paper and securely pasted or taped on the Key Sheet. The information shall include:
(1) Sheet number on which the change is shown in the plans
(2) Effective date of the sheet revision
(3) A brief description of the revision
(E) All project descriptions, length, etc., shown on the Key Sheet shall be corrected to agree with the actual construction before the Final "As-Built" Plans are submitted.
(F) Other Final “As-Built” Plans or Drawings such as Jack & Bore, Plowing, for Signalization shall be included with the Final “As-Built” plan set and listed in the Index of Roadway Plan Sheets on the Key Sheet of the Final “As-Built” Plans. Any Boring Path Reports, Bore Logs associated with these plans shall also be included and scanned with the Final “As-Built” plan set.
57-4.2.2 Typical Section Sheets: Authorized revisions to the typical section shall be marked on these sheets. Some typical examples include:
(A) An increase or decrease in thickness
(B) A change in type of material
(C) Substitution of pay items
(D) Change in limits of work
(E) Addition/Deletion of items of work
(F) Other Geometric designs (such as varied cross slope)
(G) Tolerance of + 6” above the dredge template
57-4.2.3 Plan Sheets: The plan sheet details for all the major groups of plans become the permanent historical record of the construction project. All changes in construction that would constitute a conflict in this record shall be clearly delineated on the Final Plan Sheets. Insert revisions and cross out all incorrect data. The following revisions must be noted:
(A) Revisions to the horizontal and vertical alignments as shown on the original plans.
(B) Stations or equations that have been introduced or revised during construction.
(C) Intersection and crossover details that have been modified or relocated.
(D) Inlets, manholes, box culverts, and end walls that were added, relocated, revised, or deleted.
(E) All sidewalk that was modified in thickness or otherwise, and all curb and gutter, and shoulder gutter, that was added, revised, or deleted.
(F) All driveways that were not shown on the original plans, or were shown but are no longer in existence, or were modified in thickness or otherwise.
(G) All ditch locations and grades that were adjusted during construction.
(H) Changes in fencing items.
(I) Sign locations changed and pavement markings that were modified.
(J) All signal details that change during construction.
(K) All Bridge, Approach Slab, and Lighting details that are different from the actual construction.
(L) Benchmarks (BM) and their descriptions that were set during construction shall be added to the profile portion of the Plan Sheets.
(M) All Utility relocates and/or conflicts shall be reflected on the Utility
Adjustment Sheets.
57-4.2.4 Summary of Drainage Structures, Optional Materials
Tabulations and Drainage Structure Sheets: Revisions shall be made on the Final "As-Built" Plans set, to reflect:
(A) Plan lengths changed to reflect the actual construction length when an authorized field change is made, or a plan error is noted.
(B) Changes in flow line elevations shall be shown on the plan profile sheets.
(C) Changes in stations or offset dimensions.
(D) Changes in size of structures.
(E) Added/Deleted structures.
(F) Type of pipe material and thickness used at each structure shall be shown on the Drainage Structures Sheets and the Optional Materials Tabulation Sheets. The “as-built” column will be checked to indicate what type of pipe material and thickness was used at each structure.
(G) Types of inlets and manholes constructed shall be indicated.
(H) When the method of measurement is on the basis of plan quantity for cross drain and storm sewer pipes, plan errors shall be distinguished from field revisions due to different tolerances being applicable.
(I) Lateral Ditch Sheets: All adjustments in horizontal alignment of flow line grade shall be delineated on the plan and profile sheets. The cross section shall be adjusted to reflect the revision if a pay quantity adjustment is required.
57-4.2.5 Cross Section Sheets: The disposition of the Cross Section Sheets with regard to a set of Final "As-Built" Plans depends on the method of payment set up for the earthwork items.
(A) Excavation Borrow Pits (Pond Sites), Excavation Subsoil, and Excavation Channel on Cubic Yard Basis: Final cross section sheets and volumetric computations are to be prepared and included in the Final "As-Built" Plans. They are required to reflect the actual work accomplished and are the basis of final pay quantities. The original plan cross sections shall remain a part of the Final "As-Built" Plans.
(B) Embankment, Regular Excavation, and Lateral Ditch Excavation on Cubic Yard Plan Quantity Basis: The original design cross sections are used as the basis for both plan and final pay quantities and to control grading operations. They are to be retained as part of the Final "As-Built" Plans. Additional cross sections to correct plan errors and/or to reflect field revisions are prepared and added to the Final "As-Built" Plans.
57-5 Method of Measurement.
57-5.1 Section and ¼ Section Corners. When direct payment is provided in the Contract, the quantity to be paid for will be the number of Section or ¼ Section Corners appropriately referenced, reset, and Certified Corner Record.
57-5.2 Benchmarks. When direct payment is provided in the Contract, the quantity to be paid for will be the number of benchmarks acceptably set.
57-5.3 Right-of-Way Monumentation. When direct payment is provided in the Contract, the quantity to be paid for will be lump sum quantity.
57-5.4 P.I. Monumentation. When direct payment is provided in the Contract, the quantity to be paid for will be the number of P.I. monumentation acceptably referenced and reset.
57-5.5 PCP Monumentation. When direct payment is provided in the Contract, the quantity to be paid for will be the number of PCP monumentation acceptably referenced and reset.
57-5.6 Reset Property Corners with Boundary Survey. When direct payment is provided in the Contract, the quantity to be paid for will be the number of properties monumented, acceptably referenced and reset, including submission of a Boundary Survey per property.
57-5.7 Final As-built Plans. When direct payment is provided in the Contract, the quantity to be paid for will be lump sum quantity.
57-6 Submittals.
57-6.1 Monumentation. Submit certified copy of field book notes to the Engineer for acceptance of referencing and resetting of the monuments.
57-6.2 As-Built Surveys. The electronic design files for the contract plans shall be updated to reflect "as-built" conditions in the native format. "As-Built" Plans shall be prepared and updated electronically (CADD) during the construction process. A draft of the plans on 11” by 17” paper shall be submitted as a condition to the Engineer issuing substantial completion. The acceptance of the Final As-Built plans is a condition of the Engineer issuing the Final Acceptance of the entire project. The final submittal shall include electronic submissions via email and Trimble containing a pdf copy and a CADD copy, and one complete paper set of Final As-Built Plans (11” by 17”) signed and sealed by the Florida Licensed Professional Surveyor.
57-6.3 Boundary Surveys. Submit Boundary Surveys on 11” by 17” paper to the Engineer for acceptance of setting property corner monumentations and electronically through email and Trimble.
57-7 Basis of Payment.
57-7.1 Section and ¼ Section Corners. Price and payment will be full compensation for all work specified in this Specification including, but not limited to labor, professional services, equipment, incidental materials, devices, and operations needed to complete the work as specified herein and on the plans. 30% payment of the per each price will be payable for each monument witnessed or referenced when the certified field notes of the witness or reference ties are approved by the County Surveyor. The remaining 70% payment will be payable for each monument reset when the certified field note of the monument installation are approved by the County Surveyor.
57-7.2 Benchmarks. Price and payment will be full compensation for all work specified in this Specification including, but not limited to labor, professional services, equipment, incidental materials, devices, and operations needed to complete the work as specified herein and on the plans. 30% payment of the per each price will be payable for each monument witnessed or referenced when the certified field notes of the witness or reference ties are approved by the County Surveyor. The remaining 70% payment will be payable for each monument set when the certified field note of the monument installation are approved by the County Surveyor.
57-7.3 Right-of-Way Monumentation. Price and payment will be full compensation for all work specified in this Specification including, but not limited to labor, professional services, equipment, incidental materials, devices, and operations needed to complete the work as specified herein and on the plans. 30% payment of the per each price will be payable for each monument witnessed or referenced when the certified field notes of the witness or reference ties are approved by the County Surveyor. The remaining 70% payment will be payable for each monument reset when the certified field note of the monument installation are approved by the County Surveyor.
57-7.4 P.I. Monumentation. Price and payment will be full compensation for all work specified in this Specification including, but not limited to labor, professional services, equipment, incidental materials, devices, and operations needed to complete the work as specified herein and on the plans. 30% payment of the per each price will be payable for each monument witnessed or referenced when the certified field notes of the witness or reference ties are approved by the County Surveyor. The remaining 70% payment will be payable for each monument reset when the certified field note of the monument installation are approved by the County Surveyor.
57-7.5 PCP Monumentation. Price and payment will be full compensation for all work specified in this Specification including, but not limited to labor, professional services, equipment, incidental materials, devices, and operations needed to complete the work as specified herein and on the plans. 30% payment of the per each price will be payable for each monument witnessed or referenced when the certified field notes of the witness or reference ties are approved by the County Surveyor. The remaining 70% payment will be payable for each monument reset when the certified field note of the monument installation are approved by the County Surveyor.
57-7.6 Reset Property Corner with Boundary Survey. Price and payment will be full compensation for all work specified in this Specification including, but not limited to labor, professional services, equipment, incidental materials, devices, and operations needed to complete the work as specified herein and on the plans. 30% payment of the per each price will be payable for each property, which may be a single or multiple property corners, witnessed or referenced when the certified field notes of the witness or reference ties are approved by the County Surveyor. The remaining 70% payment will be payable for each monument reset when the Boundary Survey and certified field note of the monument(s) installation are approved by the County Surveyor.
57-7.7 Final As-built Plans. Price and payment will be full compensation for all work specified in this Specification including, but not limited to labor, professional services, equipment, incidental materials, devices, and operations needed to complete the work as specified herein and on the plans. Submit one draft set of as-builts on 11” by 17” paper and a PDF copy as a condition of Substantial Completion for a 50% payment. Once the “As-Builts” are completed and accepted by the Engineer, the other 50% will become payable. The Engineer will take 10 working days to review and provide comments on any drafts submitted.
57-7.7 Payment Items: Payment will be made under:
Item No. 57-1 Certified Section and ¼ Section Corners Referenced and
Reset – each.
Item No. 57-2 Certified New Benchmark Monumentation – each.
Item No. 57-3 Certified New Right of Way Monumentation – lump sum.
Item No. 57-4 Resetting of P.I. Monumentation – each.
Item No. 57-5 Resetting of Permanent Control Points (PCP) – each. Item No. 57-6 Reset Property Corner with Boundary Survey – each. Item No.
57-7 Final As-Built Plans – lump sum.
PROJECT SIGNS (COUNTY SPECIFIC REQUIREMENTS).
(REV 12-06-21) (7-22) (4-22)
Page 111. The following new Section is added after Section 57.
SECTION 98
PROJECT SIGNS
98-1 Description.
Furnish and install project signs at locations indicated in the plans. Furnish one copy of the shop drawing to the Engineer for approval before manufacturing the project signs.
98-2 Materials.
98-2.1 General: Meet the material requirements shown below and any additional requirements which the plans might show.
98-2.2 Posts: Use aluminum tubing materials meeting the general provisions of Section 965 for all single column ground signs.
98-2.3 Panels: All sign panels shall be aluminum unless otherwise shown in the Plans. Sheets and plates for sign panels shall meet the requirements of ASTM B209, Aluminum Association Alloy 6061-T6, 5154-H38 or 5052-H38. Sign panels for single column ground mounted signs shall utilize aluminum plate with a minimum thickness of 0.08 inches. All panels shall have rounded corners.
98-2.4 Sheeting: Use Type XI sheeting that meet the material and process requirements of Section 994.
98-2.5 Project Sign Content: Sign template to be provided by the Engineer.
Update the template with project specific information and submit as a shop drawing. Relationship of lettering size will be similar to that depicted. The background shall be white. Seasons are defined as:
Winter = December, January, February Spring = March, April, May Summer = June, July, August Fall = September, October, November
98-2.6 Surtax Sign Content: When a project is funded with County surtax funds, additional signage will be required. The signage is designated as a “Surtax Sign” and is in addition to the project sign. The Surtax Sign template will be provided by the Engineer. Relationship of lettering size will be similar to that depicted on the Surtax Sign Template.
98-2.7 Wage Determination Sign: The contractor shall post the applicable Wage Determination on the project signboard, along with all required U.S. Department of Labor posters outlining worker rights and protections under the Davis-Bacon Act and other applicable federal labor requirements. The cost of providing and maintaining this signage shall be considered incidental to the Contract and included in the applicable pay item.
98-3 Construction Requirements.
98-3.1 General: Project signs remain the property of the Contractor for the duration of the project and shall be maintained by the Contractor to the satisfaction of the Engineer. Project signs may need to be relocated due to conflicts during construction, at no additional cost to the County.
Upon completion of the project, and with the permission of the Engineer, remove and dispose of the sign and supports, and restore the site to the satisfaction of the Engineer. Surtax Sign(s) are to be removed and returned upon completion of the project.
98-3.2 Installation: Install project signposts as depicted in FDOT Standard Plans 700-010.
98-4 Method of Measurement: The quantities to be paid for will be the number of project signs, furnished and installed.
98-5 Basis of Payment: Price and payment will be full compensation for furnishing and installing all materials necessary to complete the signs in accordance with the details shown in the plans, including sign panels complete with sheeting, painting, and message, signposts and supports, footings, excavation, etc., and all other work specified in this Section, including all incidentals necessary for the complete item.
Payment will be made under:
Item No. 98-1 Project Sign, Furnish and Install – per each.
Item No. 98-2 Project Surtax Sign, Furnish and Install – per each.
Item No. 98-2-1 Project Surtax Sign, Install – per each.
MAINTENANCE OF TRAFFIC (COUNTY SPECIFIC REQUIREMENTS).
(REV 09-30-21) (7-22)
SUBARTICLE 102-3.3 is expanded with the following:
Requests for lane closures shall include a site-specific traffic control plan signed and sealed by the Contractor’s Engineer of Record who possesses a valid Advance Temporary Traffic Control certification when no other lane closure plans have been included in the Plans.
SUBARTICLE 102-6.2 is deleted and the following substituted:
102-6.2 Construction: Plan, construct, and maintain detours for the safe passage of traffic in all conditions of weather. Provide the detour with all facilities necessary to meet this requirement.
Where pedestrian facilities are detoured, blocked or closed during the work, provide safe alternate accessible routes through or around the work zone meeting the requirements of the ADA Standards for Transportation Facilities. When temporary walkway surfaces and ramps are required to be constructed, ensure surfaces are stable, firm, slip resistant, and kept free of any obstructions and hazards such as holes, debris, mud, construction equipment and stored materials. Install detectable warnings on temporary ramps in accordance with Section 522.
SUBARTICLE 102-6.5 is expanded with the following:
When closing a roadway in both directions, provide a detour plan signed and sealed by a Florida Professional Engineer with Advanced Traffic Control Certification and the request for road closure form - filled out with the specific dates of closure – for review by the County Engineer. When a detour plan is provided with the plans, the Contractor is still responsible for application to the County Engineer for approval. Do not close any roadways without advanced approval by the County Engineer. Allot a minimum of 14 calendar days for the review and approval process.
When the County specifies that traffic be detoured over roads or streets outside the project area, do not maintain such roads or streets. However, maintain all signs and other devices placed for the purpose of the detour.
102-9.11 Portable Changeable Message Sign (PCMS): Use PCMSs or truck mounted changeable message signs that meet the requirements of Section 990 as required by the Plans and Standard Plans to supplement other temporary traffic control devices used in work zones. Ensure that the PCMS display panel is raised to a fully upright position and is fully visible to motorists from ½ mile, or a distance approved by the Engineer, under both day and night conditions. Reduce the intensity of the flashers when using PCMS at night. Use PCMS with a minimum letter height of 18 inches. For facilities with posted speed limits of 45 mph or less, PCMS with a minimum letter height of 12 inches may be used.
Messages must have no more than two phases. The display time for each phase must be at least two seconds but no more than three seconds. The sum of the display time must be a maximum of six seconds.
Install PCMSs a minimum of 14 calendar days prior to construction activities.
Immediately update messages as directed by the Engineer within 2 hours of notification.
Activate portable regulatory signs only during active work activities and deactivate when no work is being performed.
PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER
POLLUTION (COUNTY SPECIFIC REQUIREMENTS).
(REV 05-30-18) (7-22)
The following new SUBARTICLE is added after SUBARTICLE 104-6.4.10:
104-6.4.11 Dust Abatement: Dust abatement shall consist of applying, when ordered by the Engineer, water or dust palliative for abatement of dust nuisance originating within the project limits. The methods, materials, and procedures for dust abatement shall be subject to approval by the Engineer. Perform dust abatement operations at the time, location, and in the amount ordered by the Engineer. Dust abatement operations shall be on-call for operations on a 24-hour per day, seven-day per week basis.
Water used for dust abatement shall be furnished and applied by means of vehicle-mounted tanks equipped with sprinkling devices. The water used for dust abatement may be obtained from any approved pond, lake, stream, or municipal water system. The water shall be free of excessive silt, excess/harmful chemicals, acids, alkalis, or any substance which might be obnoxious to traffic or harmful to plant growth. Saltwater shall not be used.
All work associated with dust abatement is considered incidental to the prevention, control, and abatement of erosion and water pollution.
CLEARING AND GRUBBING (COUNTY SPECIFIC REQUIREMENTS).
(REV 05-01-20) (7-22)
ARTICLE 110-1 is expanded by the following:
Note that certain utility companies may have been permitted to execute their relocation work in County right-of-way prior to this project. The Contractor is responsible for removal of debris resulting from these clearing operations as it may exist at the site at the time of bid opening.
The following new SUBARTICLE is added after SUBARTICLE 110-2.4:
110-2.5 Trees to Remain: As directed by the Engineer, trim, protect, and leave standing desirable trees within the project limits, at no additional compensation.
Trim branches of trees extending over the area occupied by the roadway as directed, to give a clear height of 16 feet above the roadway. Trimming of any tree and root pruning requires the utilization of an ISA certified Arborist.
The following new SUBARTICLE is added after SUBARTICLE 110-3.5:
110-3.6 Exotic/Nuisance Species Eradication: All exotic and nuisance plants within the areas described above shall be burned or removed and disposed of off-site. Following initial clearing and grubbing, be responsible for maintaining cleared and grubbed areas free of exotic and nuisance species for the duration of the construction periods. This maintenance shall consist of species-appropriate herbicide treatment utilizing products listed in the approved herbicides/pesticides products available at https://www.scgov.net/government/health-and-human-services/mosquito-management-services, by a licensed applicator in combination with manual removal of new seedlings, to be performed semi-monthly at the Engineer’s direction. Exotic and nuisance species are listed under Florida Exotic Pest Plant Council at http://fleppc.org/list/list.htm, and is expanded by Brazilian Pepper, Carrotwood, Chinese Tallow, Melaleuca, Potato Vine, Tropical Soda Apple, and Australian Pine. Two copies of the Pesticide Application Record shall be submitted to the Engineer following each treatment.
Plants located adjacent to the exotic/nuisance control areas, which have been judged by the Engineer to be damaged by eradication methods and/or any breach of or failure to comply with professional standards as set forth in ANSI and/or International Society of Arboriculture guidelines shall be replaced at no additional cost to the County.
SUBARTICLE 110-8 is expanded by the following:
Material not incorporated in the work in a manner acceptable to the
Engineer shall be removed from the project area at no additional cost to the County.
SUBARTICLE 110-9.2 is expanded by the following:
County.
Obtain all necessary permits prior to burning at no additional cost to the
The following new SUBARTICLE is added after SUBARTICLE 110-11.1:
110-11.1.1 Exotic/Nuisance Species Eradication: The quantity to be paid for will be per each or by the lump sum, or per acre quantity as further described below.
The following new SUBARTICLE is added after SUBARTICLE 110-12.1.2:
110-12.1.3 Exotic/Nuisance Species Eradication: Price and payment will be full compensation for all exotic/nuisance species eradication. The work of removing such species shall be paid for at the contract lump sum or per acre price for initial removal of exotic/nuisance species, and such lump sum or per acre payment shall be full compensation for all work of initial removal and disposal as http://www.scgov.net/government/health-and-human-http://fleppc.org/list/list.htm specified and described herein. Each maintenance event consisting of herbicide treatment of cleared and grubbed areas or areas of exotic/nuisance removal shall be paid for at the contract per each price.
SUBARTICLE 110-12.6 is deleted and the following substituted:
110-12.6 Mailboxes: Price and payment will be full compensation for all work and materials required, including supports, numbers and any temporary relocations necessary for the continuous use of the mailbox.
SUBARTICLE 110-12.8 is expanded by the following:
Item No. 110-9-1 Exotic/Nuisance Species Eradication – lump sum.
Item No. 110-9-2 Exotic/Nuisance Species Eradication – acre.
Item No. 110-9-3 Exotic/Nuisance Species Eradication – each occurrence.
EXCAVATION AND EMBANKMENT (COUNTY SPECIFIC REQUIREMENTS).
(REV 06-06-18) (7-22)
SUBARTICLE 120-1.2 is deleted and the following substituted:
120-1.2 Unidentified Areas of Contamination: When encountering or exposing any abnormal condition indicating the presence of contaminated materials, cease operations immediately in the vicinity and notify the Engineer. The presence of tanks or barrels; discolored earth, metal, wood, ground water, etc.; visible fumes;
abnormal odors; excessively hot earth; smoke; or other conditions that appear abnormal may indicate the presence of contaminated materials and must be treated with extreme caution.
Make every effort to minimize the spread of contamination into uncontaminated areas. Immediately provide for the health and safety of all workers at the job site and make provisions necessary for the health and safety of the public that may be exposed to any potentially hazardous conditions. Ensure provisions adhere to all applicable laws, rules or regulations covering potentially hazardous conditions and will be in a manner commensurate with the gravity of the conditions.
The Engineer will notify the County’s Contamination Assessment Firm for assessment of the site. Provide access to the potentially contaminated area.
Preliminary investigation by the Contamination Assessment Firm will determine the course of action necessary for site security and the steps necessary under applicable laws, rules, and regulations for additional assessment and/or remediation work to resolve the contamination issue.
The Contamination Assessment Firm will delineate the contamination area(s). The Engineer will then notify the Prime Contractor of the findings. If remediation work is necessary, one of the following courses of actions will occur:
(1) The Engineer will offer the Prime Contractor the remediation work as extra work on the contract, provided the Prime Contractor can provide documentation of authorization/certification to perform such work, or
(2) The Engineer will solicit a separate contract with an independent
Contractor to perform such remediation work.
If an outside Contractor is selected to perform any necessary remediation work, that Contractor will delineate any staging or holding area required, and, in cooperation with the Prime Contractor and Engineer, develop a work plan that will provide the outside Contractor’s operations schedule with projected completion dates for the final resolution of the contamination issue. The outside Contractor will maintain jurisdiction over activities inside any outlined contaminated areas and any associated staging holding areas. The outside Contractor will be responsible for the health and safety of workers within the delineated areas. Provide continuous access to these areas for the outside Contractor and representatives of regulatory or enforcement agencies having jurisdiction. Both Contractors will use the schedule as a basis for planning the completion of both work efforts. The Engineer may grant the Contract Time extensions according to the provisions of 8-7.3.2. Cooperate with the outside Contractor to expedite integration of the outside Contractor’s operations into the construction project.
The Prime Contractor is not expected to engage in routine construction activities, such as excavating, grading, or any type of soil manipulation, or any construction processes required if handling of contaminated soil, surface water or ground water is involved. All routine construction activities requiring the handling of contaminated soil, surface water or groundwater will be by the outside Contractor. Adjustments to quantities or to Contract unit prices will be made according to work additions or reductions on the part of the Prime Contractor in accordance with 4-3.
If the Prime Contractor performs any necessary remediation work, the Engineer may grant the Contract Time extensions according to the provisions of 8-
7.3.2 and may make adjustments to quantities or to Contract unit prices according to work additions or reductions on the part of the Prime Contractor in accordance with 4- 3.
The Engineer will direct the Prime Contractor when operations may resume in the affected area.
SUBARTICLE 120-5.4 is deleted and the following substituted:
120-5.4 Disposal Areas: Where the Contract Documents require disposal of excavated materials outside the right-of-way, and the disposal area is not indicated in the Contract Documents, furnish the disposal area without additional compensation.
Provide areas for disposal of dredged materials out of sight of the project and at least 300 feet from the nearest roadway right-of-way line of any State-, County- , or City-maintained Road. If the materials are buried, disregard the 300-foot limitation.
TECHNICAL
SPECIAL
PROVISIONS
1 General Conditions
1.1 Definitions
PROJECT: Maintenance dredging of a portion of Phillippi Creek, Sarasota County, FL to improve stormwater conveyance and mitigate the potential for flooding.
FDEP: State of Florida Department of Environmental Protection.
USACE: United States Army Corps of Engineers.
USCG: United States Coast Guard.
FWS: U.S. Fish and Wildlife Service.
NMFS: National Marine Fisheries Service.
FWC: Florida Fish and Wildlife Conservation Commission.
DMMA: Dredge Material Management Area, the designated upland site(s) for managing dredged material.
BD Survey: Before Dredge Survey (i.e., pre-construction survey) AD Survey: After Dredge Survey (i.e., post-construction survey) Acceptance Section: The portion of the dredge area between two adjacent approved profile lines used for measurement and payment.
MLW: Mean Low Water datum NAVD88: North Atlantic Vertical Datum of 1988
1.2 Scope of Work
The intent and purpose of this Project is to provide dredging of the channel, generally maintaining a minimum 10-foot offset from shorelines and structures, and to -4 feet MLW in accordance with the approved Plans and Specifications and all requirements of the Contract Documents.