This is a functional space requirements worksheet for Project Number 260282, the National Guard Readiness Center Addition/Alteration in Michigan, prepared by the Army National Guard (ARNG). The project involves both expansion and alteration of an existing readiness center facility with a project date of April 29, 2026. The scope encompasses 91,959 square feet of authorized space, with 43,681 square feet requested and 44,247 square feet existing. The addition will total 36,531 square feet with 13,976 square feet designated for alteration. The facility design includes common use areas such as an assembly hall (6,300 square feet), classrooms (7,080 square feet), learning center (700 square feet), and multi-purpose training area (1,500 square feet), along with administrative office space (15,020 square feet), unit storage space including arms vaults (18,802 square feet), and locker room space (8,624 square feet). Supporting facilities include a detached general purpose training bay (5,253 gross square feet) and a controlled waste handling facility. The project also incorporates an unheated vehicle storage shed (7,150 square feet), organizational vehicle parking (4,158 square yards), rigid pavement improvements (3,475 square yards), flexible pavement (15,450 square yards), sidewalks, curbs, and security fencing totaling 2,310 linear feet.
The project requires significant infrastructure improvements including utilities, storm water drainage, exterior fire protection, and outside security lighting. Information systems requirements specify 237 single-line phones, 10 multi-line phones, 237 LAN ports, and one SIPRNET connection across a facility designed for 468 maximum occupants. Air conditioning requirements total 307 tons with 270 tons authorized and 122 tons for the addition. Construction costs are estimated at $254,000 for primary funded construction and $119,000 for construction support, with Information Systems and Communications Equipment (ISCE) costs of $367,000 in operations and personnel allocation and $469,000 in Other Maintenance and Non-Gross Operations funding. The facility must accommodate 4 arms vaults, with 1 authorized in the existing space and 3 in the addition.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Number: 260282 Project Title: NATIONAL GUARD READINESS CENTER Addition/Alteration Date: April 29, 2026
Functional Space Details � Actual/English 171R: ARNG � Readiness Center
Authorized Requested Existing Addition Alteration Memo
ARNG - Readiness Center 91,959 43,681 44,247 36,531 13,976
Readiness Center: Yes Yes 0 Yes Yes
Joint Forces Headquarters: No No 0 No No
Civil Support Team Ready Building: No No 0 No No
RAPIDS Office Assigned: No No 0 No No
Existing Physical Fitness Facility: No No 0 No No
Detached General Purpose Training Bay: Yes No 5,104 No No
Detached Controlled Waste Handling: Yes No 491 No No
Detached Unit Unheated Storage: Yes No 0 No No
Detached Flammable Materials Storage: Yes No 0 No No
No. of Firefinder Radar Facilities: 0 0 0 0 0
No. of Controlled Waste Barrels: 0 0 0 0 0
No. of Arms Vaults: 4 1 3 0 0
No. of Fed Reimbursed Admin State Employees: 0 0 0 0 0
No. of Statewide Media Outlets for JFHQ Media Rm: 0 0 0 0 0
A. Schedule 1 -- Common Use Areas 22,930 6,805 14,494 6,805 7,476
1. Assembly Hall 6,300 0 6,741 0 3,000
2a. Auditorium 0 0 0 0 0
2b. Classrooms 7,080 3,810 2,919 3,810 2,000
3. Learning Center 700 151 493 151 549
4. Multi-Purpose Training Area 1,500 1,500 0 1,500 0
5. Kitchen 800 0 564 0 600
Date: April 29, 2026
Functional Space Details � Actual/English 171R: ARNG � Readiness Center
Authorized Requested Existing Addition Alteration Memo
6. Break / Vending 400 0 362 0 400
7. Toilets/Shower 3,030 1,344 1,515 1,344 0
a. Toilets 1,782 1,025 680 1,025 0
b. Showers 1,248 319 835 319 0
8. Flammable Materials Storage 200 0 0 0 0
9. Lactation Area 80 0 67 0 0
10. Family Readiness Office 400 0 355 0 395
11. RAPIDS Office 150 0 0 0 0
12. Retention Office 440 0 184 0 205
13. Table/Chair Storage 550 0 394 0 139
14. Physical Fitness 1,000 0 899 0 188
15. Controlled Waste Handling Facility (CWHF) 300 0 0 0 0
B. Schedule II -- Unit and Special Space Allowances 42,846 18,168 17,595 18,168 4,677
1. Administrative Office Space 15,020 9,727 4,758 9,727 4,677
a. Basic Space 3,200 28 2,851 28 1,000
b. Office Allowance 10,320 8,199 1,906 8,199 3,000
c. Special Administrative Allowances 1,500 1,500 0 1,500 677
(1) Division Headquarters 0 0 0 0 0
(2) Brigade and Division Artillery Headquarters 0 0 0 0 0
(3) Echelons above Brigade Units 0 0 0 0 0
(4) Special Operations Groups 0 0 0 0 0
(5) Battalion Headquarters and Headquarters (HHC or HHD) 1,500 1,500 0 1,500 677
Date: April 29, 2026
Functional Space Details � Actual/English 171R: ARNG � Readiness Center
Authorized Requested Existing Addition Alteration Memo
(6) State Headquarters (ARNG) 0 0 0 0 0
(7) Troop Command 0 0 0 0 0
(8) Army Advisors Office 0 0 0 0 0
(9) Personnel Services Companies/Sections 0 0 0 0 0
(10) State Headquarters military record archive 0 0 0 0 0
(11) Training Support Brigade (TSB) 0 0 0 0 0
2. Unit Storage Space (Including Arms Vault) 18,802 6,841 9,598 6,841 0
a. Arms Vaults 2,400 588 1,629 588 0
b. Battalion Headquarters with Organic Subunits (per TOE) 1,000 1,000 0 1,000 0
c. Supply and Transportation Battalion (Division) 0 0 0 0 0
d. Support Battalion (Separate Brigade) 0 0 0 0 0
e. Heated Storage Space 10,800 1,934 7,969 1,934 0
(1) Units with Required Strength >= 55 4 1 3 1 0
(2) Units with Required Strength 10 � 55 0 0 0 0 0
f. Unheated storage space 4,602 3,319 0 3,319 0
3. Locker Room Space 8,624 1,200 3,239 1,200 0
a. Basic Space (One per readiness center) 200 200 0 200 0
b. Space per Authorized Position 8,424 1,000 3,239 1,000 0
4. Special Functions 400 400 0 400 0
a. JFHQ Joint Operations Center (JOC) 0 0 0 0 0
b. JFHQ Secure Conference Center 0 0 0 0 0
c. JFHQ Secure Commo Vehicle Ready Bay 0 0 0 0 0
Date: April 29, 2026
Functional Space Details � Actual/English 171R: ARNG � Readiness Center
Authorized Requested Existing Addition Alteration Memo
d. Public Affairs Detachment 0 0 0 0 0
e. JFHQ Photographic Studio 0 0 0 0 0
f. JFHQ Media Room 0 0 0 0 0
g. Medical Section within a Headquarters Unit 400 400 0 400 0
h. Physical Exam Space. 0 0 0 0 0
i. Flight Eye Physical Exam Space 0 0 0 0 0
j. COMSEC Material Direct Support Activities (CMDSA) 0 0 0 0 0
k. Information Technology (IT) Support Activities 0 0 0 0 0
l. General Purpose Training Bay (GPTB) 3,978 0 0 0 0
(1) Work bays 3,168 0 0 0 0
(2) Office Space 810 0 0 0 0
m. Air/Army National Guard Weather Flight 0 0 0 0 0
n. Band 0 0 0 0 0
5. Fire finder Radar Readiness Bay 0 0 0 0 0
6. Secure Area 0 0 0 0 0
7. Civil Support Team Ready Building 0 0 0 0 0
a. Classrooms/Library 0 0 0 0 0
b. Training Aid Storage 0 0 0 0 0
c. Break Room (Area) 0 0 0 0 0
d. Vending Area 0 0 0 0 0
e. Toilets/Shower 0 0 0 0 0
f. Flammable Materials Storage 0 0 0 0 0
Date: April 29, 2026
Functional Space Details � Actual/English 171R: ARNG � Readiness Center
Authorized Requested Existing Addition Alteration Memo
g. Table/Chair Storage 0 0 0 0 0
h. Physical Fitness 0 0 0 0 0
i. Ready Bays 0 0 0 0 0
j. Operations Center 0 0 0 0 0
k. Admin Space General 0 0 0 0 0
l. Admin Space Special 0 0 0 0 0
m. COMSEC 0 0 0 0 0
n. Storage 0 0 0 0 0
o. Lockers 0 0 0 0 0
p. Laundry 0 0 0 0 0
q. Medical Support/Storage 0 0 0 0 0
r. Equipment Maintenance 0 0 0 0 0
s. DECON Room 0 0 0 0 0
8. Other Special Facilities 0 0 0 0 0
a. 0 0 0 0 0
b. 0 0 0 0 0
c. 0 0 0 0 0
d. 0 0 0 0 0
e. 0 0 0 0 0
Date: April 29, 2026
Functional Space Details � Actual/English 171R: ARNG � Readiness Center
Authorized Requested Existing Addition Alteration Memo
Total Net Readiness Center Space 65,776 24,973 32,089 24,973 12,153
Maintenance and Storage (3% of Total Net Area) 1,973 749 963 749 0
Mechanical/Electrical Room (5% of Total Net Area) 3,289 1,249 1,604 1,249 0
Telecom/IT (1% of Total Net Area) 658 250 321 250 0
Circulation Allowance (15% or 22% of Total Net Area) 15,773 5,989 5,248 5,989 1,823
Structural Allowance (10% of Total Net Area) 8,747 3,321 4,022 3,321 0
Total Gross Readiness Center Space 96,216 36,531 44,247 36,531 13,976
Adjusted Gross Alteration Area 0 0 0 0 0
- Other Gross Readiness Center Space 0 0 0 0 0
Total Readiness Center Space 96,216 36,531 44,247 36,531 13,976
Detached General Purpose Training Bay (GPTB)
1. Work bays 3,168 0 3,079 0 0
2. Office Space 810 0 787 0 0
Total Net GPTB Space 3,978 0 3,866 0 0
Maintenance and Storage (3% of Total Net Area) 119 0 116 0 0
Mechanical/Electrical Room (5% of Total Net Area) 199 0 193 0 0
Telecom/IT (1% of Total Net Area) 40 0 39 0 0
Office Space Circulation (15% of Office Totals) 122 0 118 0 0
Work Bay Circulation (10% of Work Bay Totals) 317 0 308 0 0
Structural Allowance (10% of Total Net Area) 478 0 464 0 0
Total Gross GPTB Space 5,253 0 5,104 0 0
Adjusted Gross Alteration Area 0 0 0 0 0
Date: April 29, 2026
Functional Space Details � Actual/English 171R: ARNG � Readiness Center
Authorized Requested Existing Addition Alteration Memo
Detached Controlled Waste Handling 300 0 277 0 0
Structural Allowance (10% of Net Space) 9 0 8 0 0
Total Gross Controlled Waste Handling Space 309 0 285 0 0
Detached Flammable Materials Storage 200 0 200 0 0
Structural Allowance (10% of Net Space) 6 0 6 0 0
Total Gross Unheated Storage Space 206 0 206 0 0
Detached Unheated Storage Space 0 0 0 0 0
Circulation Allowance (15% of Net) 0 0 0 0 0
Structural Allowance (10% of Net Space) 0 0 0 0 0
Total Gross Unheated Storage Space 0 0 0 0 0
Date: April 29, 2026
Functional Space Details � Actual/English ARNG � Common Supporting Items
Authorized Requested Existing Addition Alteration Memo
ARNG - Common Supporting Items
Unheated Vehicle Storage Shed Needed: Yes Yes 0 7,150 0
Wash Platform Required: No No 0 0 0
Loading Ramp Required: No No 0 0 0
MCOFT Type Simulator Required: No No 0 0 0
Rigid Paving for Access Road: No No 0 0 0
Access Road Length (LF) No No 0 0 0
No. of Controlled Waste Access Facilities: 0 0 0 0 0
No. of Fuel Trucks/Trailer to be Parked with Fuel: 0 0 0 0 0
No. of Trucks Simultaneously at Loading Dock: 0 0 0 0 0
No. of Turning Pads: 0 0 0 0 0
No. of Refuse Collection/Dumpster Sites: 0 0 0 0 0
No. of Other Access Apron Service Sites: 0 0 0 0 0
No. of Generator Pads 1 1 0 0 0
Fuel Storage and Dispensing Systems (EA)
A. Total Vehicles Requiring Support 0 0 0 0 0
1. Vehicles Requiring MOGAS (EA) 0 0 0 0 0
2. Vehicles Requiring Diesel Fuel (EA) 0 0 0 0 0
3. Vehicles Requiring AVGAS (EA) 0 0 0 0 0
4. Vehicles Requiring Other Fuel (EA) 0 0 0 0 0
Date: April 29, 2026
Functional Space Details � Actual/English ARNG � Common Supporting Items
Authorized Requested Existing Addition Alteration Memo
B. Organizational Vehicle Parking 0 0 0 0 0
1. Other Functional Activities 0 0 0 0 0
a. Authorized based on Vehicle Inventory 21,225 4,158 6,897 4,158 0
1) Wheeled vehicle and trailer/towed equip (SY) 17,100 33 6,897 33
2) Tracked/engineer vehicle, and equip > 30 (SY) 2,550 2,550 0 2,550 0
3) Fuel Truck (SY) 1,575 1,575 0 1,575 0
4) HET vehicle (SY) 0 0 0 0 0
2. Unheated Enclosed Vehicle Storage Shed (SF) 114,615 7,150 0 7,150 0
3. Total Exterior Organizational Vehicle Parking (SY) 21,225 4,158 6,897 4,158 0
C. Loading Docks
1. Readiness Center Loading Dock (LS) 0 0 0 0 0
D. Wash Platform (EA) 0 0 0 0 0
E. Military Vehicle Loading Ramp (EA) 0 0 0 0 0
F. Rigid Pavement Other Than Parking (SY) 3,564 3,475 0 3,475 0
1. Structures and Pads Supporting Operations (SY) 0 0 0 0 0
a. Fuel Truck Containment Area (SY) 400 400 0 400 0
b. Military Vehicle Loading Ramp Support (SY) 400 311 0 311 0
c. Turn Pads (SY) 0 0 0 0 0
d. Helipads (SY) 0 0 0 0 0
e. Parking Pad for MCOFT Type Simulators (SY) 0 0 0 0 0
f. Generator Pad with Electrical Hookup (SY) 150 150 0 150 0
g. Mobile Kitchen Trailer (MKT) Parking Pad (SY) 150 150 0 150 0
Date: April 29, 2026
Functional Space Details � Actual/English ARNG � Common Supporting Items
Authorized Requested Existing Addition Alteration Memo
2. Service and Access Aprons (SY) 0 0 0 0 0
a. Military Vehicle Loading Ramp (SY) 0 0 0 0 0
b. Wash Platform Pad (SY) 0 0 0 0 0
c. Wash Platform Access (SY) 0 0 0 0 0
d. Refuse Collection/Dumpster Pad (SY) 150 150 0 150 0
e. Controlled Waste Handling (SY) 100 100 0 100 0
f. Fuel Pump Island (SY) 0 0 0 0 0
g. Fuel Pump Access (SY) 0 0 0 0 0
h. Loading Dock Access (SY) 0 0 0 0 0
i. Fire-finder Radar Readiness Bay Access 0 0 0 0 0
j. Other Service Area (SY) 0 0 0 0 0
k. Readiness Center Work Bay Access Apron (SY) 214 214 0 214 0
l. Vehicle Storage Shed Apron (SY) 1500 1500 0 1,500 0
m. Drill Hall Door Access Apron (SY) 500 500 0 500 0
3. Access Road and Entrance Throat (SY) 0 0 0 0 0
G. Flexible Pavement (SY) 20,450 15,450 10,483 4,967 10,483
1. Privately owned vehicle (POV) parking (SY) 14,770 12,970 8,003 4,967 8,003
2. Visitor/Customer Parking (SY) 680 680 680 0 680
3. Access Road and Entrance Throat (SY) 5,000 1,800 1,800 0 1,800
4. Helipad Clearance Area (SY) 0 0 0 0 0
Date: April 29, 2026
Functional Space Details � Actual/English ARNG � Common Supporting Items
Authorized Requested Existing Addition Alteration Memo
H. Sidewalks (SY) 1,533 609 0 500 109
I. Curbs (LF) 4,076 2,798 0 2,798 0
J. Security Fencing (LF) 2,150 2,310 2,235 75 2,235
K. Flagpole(s) (EA) Yes No Yes No No
L. Exterior Fire Protection (LS) Yes Yes No No Yes
M. Detached Facilities Sign/Static Display (EA) Yes Yes No Yes No
N. Outside Security Lighting (LS) Yes Yes Yes Yes Yes
O. Utilities (LS) Yes Yes Yes Yes Yes
1. Gas (LS) Yes Yes No Yes No
2. Electric (LS) Yes Yes Yes No Yes
3. Chilled/Heated Water Dist Systm (LS) Yes No No No No
4. Water (LS) Yes Yes Yes No Yes
5. Wastewater/Sewer (LS) Yes Yes No Yes No
P. Storm Water Drainage (LS) Yes Yes Yes Yes No
Q. Installed Equipment (EA) 0 0 0 0 0
1. Stand-by Generator (prioritize for top 35% of load) Yes Yes No Yes No
2. Refuse Collection Facilities Yes No Yes No Yes
3. Other Installed Equipment (LS) 0 0 0 0 0
a. 0 0 0 0 0
b. 0 0 0 0 0
c. 0 0 0 0 0
d. 0 0 0 0 0
Date: April 29, 2026
Functional Space Details � Actual/English ARNG � Common Supporting Items
Authorized Requested Existing Addition Alteration Memo
R. Fuel Storage and Dispensing Systems (EA) 0 0 0 0 0
1. 3000 Gallons 0 0 0 0 0
2. 5000 Gallons 0 0 0 0 0
3. 7000 Gallons 0 0 0 0 0
4. 10000 Gallons 0 0 0 0 0
5. 20000 Gallons 0 0 0 0 0
S. AC Tonnage (Total) 0 0 0 0 0
1. AC Tonnage (Readiness Center) 307 270 148 122 148
Date: April 29, 2026
Functional Space Details � Actual/English INFO: ARNG � Information Systems Worksheet
Authorized Requested Memo
I ISCE Inputs:
A. Square Footage Tab 24,973 24,973
1 Admin 11,471 11,471
2 Intermediate 0 0
3 Barracks 0 0
4 Warehouse/Storage 6,841 6,841
5 Clinic/Medical 0 0
6 Classrooms 5,461 5,461
7 Others 1,200 1,200
B. New Services Tab
1 Single Line Phone 237 237
2 ISDN Sets 0 0
3 Multi-Line Phones 10 10
4 Weatherproof Phones 1 1
5 Explosive Environment Phones 2 2
6 LAN Ports 237 237
7 Wall/Payphone Outlet w/telephone set (additional) 0 0
8 Fiber Optic Outlets (2RJ-45 w/ Dual SC) 0 0
9 SIPRNET 0 1
10 TV Outlets -- All Services 8 8
Date: April 29, 2026
Functional Space Details � Actual/English INFO: ARNG � Information Systems Worksheet
Authorized Requested Memo
C. Cabling, Switching, and Building Tab
1 No. Persons to Use Facility Initially 200 200
2 No. Ducts into Building: 2, 4, 6, 9, 12-way 9 9
3 Maximum Occupant Capacity 468 468
4 Proposed Building Entry Duct/Sys Length � Underground 0 0
5 Type of Building 6 6
II ISCE Results:
A. Construction Primary Funded ($000) 254 254
B. Construction Support Funded ($000) 119 119
C. ISC Equipment (OPA $000) 367 367
D. ISCE Proponent (OMNG $000) 469 469
File details come from the government source that posted it. Updated .