26012-HMA_Pavement-_County_Projects_Attachment_updated_260223.xlsx

XLSX spreadsheet 63 KB Posted

Attached to
HMA Pavement- County Projects (2026)
Solicitation number
2026-RFB-012
Issued by
Dane County, Mattoon Village, Wisconsin

About this file

This is a cost proposal spreadsheet for Dane County, Wisconsin's Request for Bid 2026-RFB-012 for Hot Mix Asphalt (HMA) pavement services on county highway projects scheduled for 2026. The procurement encompasses three project areas: County Highway G (Britt Valley Road to State Highway 19, approximately 1.55 miles), County Highway CV (State Highway 19 to Vinburn Road, approximately 2.96 miles), and milling of transverse rumble strips at various Dane County locations. The scope of work includes removing asphaltic surface butt joints, installing HMA pavement in multiple mix designs (3 LT 58-28 S, 4 LT 58-28 S, 3 MT 58-28 S, and 4 MT 58-28 H), pulverizing and relaying pavement (72,650 square yards on CTH CV), installing concrete curb and gutter, concrete sidewalk and driveway work, applying tack coat, installing temporary marking lines, performing asphalt sawing, and providing traffic control. Total HMA pavement quantities range from 850 to 4,850 tons for CTH G and 13,500 to 7,400 tons for CTH CV, with rumble strip milling at 71 square yards. The bid deadline is February 26, 2026, at 2:00 p.m. via the County's eProcurement Portal, with vendor questions due by February 19, 2026, and all asphaltic paving operations must be completed by November 18, 2026. The contract term is one year from purchase order or contract execution.

Vendors must submit pricing using the provided Excel spreadsheet with all labor, materials, equipment, shipping, and associated costs included, with pricing remaining fixed throughout the contract term. Contractors must be prequalified with the Wisconsin Department of Transportation and possess equipment capable of producing 200 tons of asphaltic material per hour. Required bonds include a certified check or bid bond equal to 5 percent of the total bid amount and a performance bond equal to 100 percent of the contracted amount. Insurance requirements include Commercial General Liability of not less than $1,000,000 per occurrence with the County named as additional insured, Commercial/Business Automobile Liability of $1,000,000 per occurrence, Environmental Impairment Liability of $1,000,000 per occurrence, and Workers' Compensation at Wisconsin statutory limits. Invoices will be paid within thirty days of receipt of goods or services. The County reserves the right to accept partial bids, reject any or all bids, negotiate terms, and award to the lowest responsible responsive bidder. The documentation does not identify specific set-aside designations or incumbent vendors. Contractors are subject to liquidated damages of $200 per weekday for delays and must begin work within ten calendar days of official notice.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cost Proposal

Cost Proposal (Updated 2/23/2026)
HMA Pavement - County Projects (2026)
2026-RFB-012
Instructions:

1. Pricing shall be inclusive of all labor, delivery costs and other expenses necessary to provide product and services in accordance with the specifications and terms and conditions of this bid document and your proposal.

2. Vendor to fill in cells highlighted in in orange.

3. Enter "no bid" in No Bid column if not bidding on a project, cells are yellow.

4. Changes made via addendum 1 are highlighted in purple and changes made via addendum 2 are highlighted in pink.

Vendor Name
CTH G (Britt Valley Rd. to STH 19)

Project No. 61011-2400

Line ItemItem NumberDescriptionQuantityUOM0
Unit CostTotal CostNo Bid
1204.0115REMOVING ASPHALTIC SURFACE BUTT JOINTS2000SY$ - 0$ - 0
2465.0120ASPHALTIC SURFACE DRIVEWAYS AND FIELD ENTRANCES60TON$ - 0$ - 0
3465.0315ASPHALTIC FLUMES8SY$ - 0$ - 0
4460.5223HMA PAVEMENT 3 LT 58-28 S850TON$ - 0$ - 0
5460.5224HMA PAVEMENT 4 LT 58-28 S4850TON$ - 0$ - 0
6601.0411CONCRETE CURB & GUTTER 30-INCH TYPE D435LF$ - 0$ - 0
7602.0405CONCRETE SIDEWALK 4-INCH330SY$ - 0$ - 0
8602.0415CONCRETE SIDEWALK 6-INCH655SY$ - 0$ - 0
9455.0605TACK COAT2100GAL$ - 0$ - 0
10649.0150TEMPORARY MARKING LINE REMOVABLE TAPE, 4-INCH300LF$ - 0$ - 0
11690.0150SAWING ASPHALT200LF$ - 0$ - 0
12TRAFFIC CONTROL1EA$ - 0$ - 0
Total$ - 0

CTH CV (STH 19 to Vinbrun Road) Project No. 69232-2300

Line ItemItem NumberDescriptionQuantityUOM0
Unit CostTotal CostNo Bid
13204.0115REMOVING ASPHALTIC SURFACE BUTT JOINTS4700SY$ - 0$ - 0
14325.0100PULVERIZE AND RELAY72650SY$ - 0$ - 0
15455.0605TACK COAT5100GAL$ - 0$ - 0
16460.6223HMA PAVEMENT 3 MT 58-28 S13500TON$ - 0$ - 0
17460.6424HMA PAVEMENT 4 MT 58-28 H7400TON$ - 0$ - 0
18465.0315ASPHALTIC FLUMES10SY$ - 0$ - 0
19465.0120ASPHALTIC SURFACE DRIVEWAYS AND FIELD ENTRANCES570TON$ - 0$ - 0
20601.0411CONCRETE CURB & GUTTER 30-INCH TYPE D6975LF$ - 0$ - 0
21601.0576CONCRETE CURB & GUTTER 4-INCH SLOPED TYPE J0LF$ - 0
22602.0515CURB RAMP DETECTABLE WARNING FIELD NATURAL PATINA90SF$ - 0$ - 0
23602.0810CONCRETE DRIVEWAY 6-INCH483SY$ - 0$ - 0
24SPV.0001ADJUSTING MANHOLE COVERS29EA$ - 0$ - 0
25SPV.0002ADJUSTING WATER VALVE BOXES55EA$ - 0$ - 0
26SPV.0003VALLEY GUTTER180LF$ - 0$ - 0
27649.0150TEMPORARY MARKING LINE REMOVABLE TAPE, 4-INCH300LF$ - 0$ - 0
28TRAFFIC CONTROL1EA$ - 0$ - 0
Total$ - 0

Milling in transverse rumble strips at various Dane Co. locations Various Locations

Line ItemItem NumberDescriptionQuantityUOM0
Unit CostTotal CostNo Bid
29465.045ASPHALTIC RUMBLE STRIPS TRANSVERSE (LOCATIONS TBD)71SY$ - 0$ - 0
Total$ - 0