26-8697_Exhibit_J_Technical_Specifications.pdf
PDF 384 KB Posted
- Solicitation number
- 26-8697
- Issued by
- Collier County, Florida
About this file
This is a technical specifications document for Collier County's Wiggins Pass and Doctors Pass Maintenance Dredging Project, prepared by the Engineer Humiston & Moore Engineers, P.A. The project encompasses navigation maintenance dredging at two separate inlet locations in Collier County, Florida to restore safe and navigable boating conditions impacted by hurricane-induced shoaling in 2023 and 2024. For Wiggins Pass, approximately 81,000 cubic yards (cy) of material will be dredged from the main channel and interior channels, with estimated quantities increased to 85,000 cy to account for potential additional shoaling; for Doctors Pass, approximately 34,400 cy will be dredged from four segments including the west settling basin, entrance channel, turning basin, and interior west channel, with estimated quantities increased to 37,000 cy. Dredged material will be placed on beaches and in nearshore areas at designated disposal sites. The bid solicitation (No. 26-8697) was advertised on July 21, 2026, with sealed bids due by August 10, 2026 at 3:00 p.m. local time through the OpenGov procurement portal. The selected contractor must achieve substantial completion of both projects within 90 calendar days from the Notice to Proceed and be fully mobilized within 5 calendar days. Work will be conducted 24 hours per day, seven days per week, with operations permitted during sea turtle nesting season (May 1 through October 31, 2026) and shorebird monitoring periods (February 15 through August 31) subject to daily clearance requirements.
The contractor must furnish a minimum 14-inch hydraulic dredge capable of pumping 6,000 feet and handling coarse sand with shell material, with documented experience on similar Gulf or ocean-exposed dredging projects of equal or greater size completed prior to bid opening. Contractor responsibilities include obtaining all local permits and U.S. Coast Guard authorization, providing pre-construction surveys within 14 days of Notice to Proceed, submitting comprehensive operations plans addressing equipment, methodology, scheduling, quality control, environmental protection, safety, and severe weather protocols, and maintaining daily reporting and as-built records. Environmental compliance is stringent, requiring adherence to Florida Department of Environmental Protection and U.S. Army Corps of Engineers permits, third-party turbidity monitoring with specific calibration and reporting standards, strict manatee protection protocols including 50-foot equipment exclusion zones and immediate reporting of any incidents, avoidance of hardbottom and seagrass communities, and compliance with sea turtle and shorebird protection measures including beach fill advancement limitations and required daily clearances. Payment is based on quantities computed from pre-dredge and post-dredge surveys conducted by a registered Professional Surveyor and Mapper, with 60 percent of mobilization costs payable upon demonstrating 1,000 cubic yards excavation and placement in 24 hours, and remaining 40 percent payable upon final completion and site restoration; non-beach-compatible material encountered during dredging becomes the contractor's responsibility for removal and disposal.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Specifications Page 1 of 42
TECHNICAL SPECIFICATIONS
COLLIER COUNTY
Wiggins Pass and Doctors Pass Maintenance Dredging Project July 17, 2026
Introduction. Collier County will conduct navigation maintenance dredging of Wiggins Pass and Doctors Pass to provide safe and navigable boating conditions within each inlet. Collier County completed maintenance dredging of Wiggins Pass in March 2022 and Doctors Pass in April 2022.
Since that time, Collier County has been impacted by hurricanes in 2023 and 2024 resulting in shoaling within the navigation channels for both inlets.
Collier County completed surveys of Wiggins Pass and Doctors Pass in January 2026, and the Contract Drawings are based on those surveys. Pay quantities are estimated at approximately 81,000 cy of material for Wiggins Pass and 34,500 cy for Doctors Pass. Pay quantities for both inlets will be based on updated pre-construction surveys. CONTRACTOR shall provide an updated pre-construction survey of Wiggins Pass and beach disposal area by a registered surveyor approved by the COUNTY within 14 days from the commencement date stipulated in the written Notice to Proceed from the COUNTY, and COUNTY shall conduct a pre-construction survey of Doctors Pass. To account for potential additional shoaling since January 2026, these quantities are increased to 85,000 cy and 37,000 cy, respectively, for Wiggins Pass and Doctors Pass should additional dredge quantities be documented by surveys.
Time is of the essence, and per the Acceptance and acknowledgement of Form 1 – Bid Response Form, the CONTRACTOR shall be fully mobilized to commence Work within 5 calendar days from the commencement date stipulated in the written Notice to Proceed from the COUNTY. Maintenance dredging of Wiggins Pass shall be completed first, followed immediately by maintenance dredging of Doctors Pass. Upon issuance of contract Notice to Proceed from the COUNTY, for dredging at Wiggins Pass, CONTRACTOR shall achieve Substantial Completion of both Wiggins and Doctors Pass maintenance dredging projects within 90 calendar days.
Selected CONTRACTOR must use a minimum 14-inch hydraulic dredge or larger capable of pumping at least 6000 feet from the larger cuts within the ebb shoals of each inlet. The dredge must be capable of moving coarse sand with shell. If the CONTRACTOR elects to use a larger dredge, the CONTRACTOR shall consider existing depths in the areas to be dredged when selecting the physical plant used to execute the Project. The dredge shall be suitable for the open Gulf site shown in the Contract Drawings. The CONTRACTOR and CONTRACTOR’s employees shall have company experience with the 14-inch or larger dredge used for dredging in exposed areas similar to an ebb shoal channel in the Gulf of America. The size of dredge shall be determined by its inside diameter at the discharge flange on the dredge pump. CONTRACTOR shall verify the equipment to be used and the specific completed project experience for similar work as called for in the Notice to Bidders. Projects listed as references must be of similar size (CY), or larger; must be at least partially Gulf or ocean exposed open water dredging and must be successfully completed prior to the bid opening of this project. Construction is allowed and work shall be planned to be conducted 24 hours per day, seven days a week. CONTRACTOR is advised that dredging will occur during sea turtle nesting season, and strict adherence to construction protocol as specified under the regulatory permits is required.
Technical Specifications Page 2 of 42
COLLIER COUNTY
Wiggins Pass and Doctors Pass Maintenance Dredging Project
July 2026
Introduction Wiggins Pass Maintenance Dredging
Section Page TS-1.0 Definitions TS-2.0 Scope of Work TS-3.0 Permits TS-4.0 Pre-construction Submittals and Meetings TS-5.0 Order of Work TS-6.0 Layout of the Work TS-7.0 Record Drawings and Daily Reports TS-8.0 Site Conditions TS-9.0 General Notes TS-10.0 Dredging TS-11.0 Beach Fill Disposal TS-12.0 Surveys and Payment TS-13.0 Project Completion TS-14.0 Environmental Protection
Appendix A Regulatory Permits and Associated DEP QA/QC Plan and FWC Lighting
Requirements for Wiggins Pass Appendix B Contract Drawings
Doctors Pass Maintenance Dredging Starts on Page 23
Technical Specifications Page 3 of 42
WIGGINS PASS MAINTENANCE DREDGING
TS-1.0 Definitions.
TS-1.1 The following terms and abbreviations used in these Technical Specifications shall be defined as:
Contract Drawings Construction Plans prepared by ENGINEER.
CONTRACTOR Those parties selected and duly authorized by the OWNER to conduct the work contained herein.
COUNTY Collier County, its employees or designees as appropriate.
CY Cubic yard.
DEP State of Florida Department of Environmental Protection.
ENGINEER Humiston & Moore Engineers, P.A., its employees or designees as appropriate.
NTP Notice to Proceed
OWNER Collier County, its employees or designees as appropriate.
PARK Delnor-Wiggins Pass State Park, its employees or designees.
PROJECT Wiggins Pass Maintenance Dredging Project
Sand Beach compatible dredge and fill material as specified in Rule 62B-
41.007(2)(j) of the Florida Administrative Code (F.A.C.)
USACE United States Army Corps of Engineers
USCG United States Coast Guard
TS-2.0 Scope of Work.
TS-2.1 The Work consists of furnishing all labor, materials, and equipment, and performing all tasks necessary for the construction of the following project:
The Wiggins Pass Maintenance Dredge Project is located near the inlet portion of the main channel for Wiggins Pass in Collier County, Florida. The Contract Drawings were developed based on a survey from 01/2026 and show dredging of a total of approximately 81,000 CY of sand from the Wiggins Pass channels. This includes approximately 76,400 from a portion of the authorized main channel template from Station 11+00 east to Station C-12, approximately 1,500 CY from east
Technical Specifications Page 4 of 42 channel located from station C-20 east to C-23, and another approximately 3,100 CY from the south channel ranging from the main channel south to Station C-32, and placement of the sand on the beach and in the nearshore south of Wiggins Pass along Delnor-Wiggins State Park from DEP reference monument R-18 to R-20. The main channel includes a relatively small area to avoid dredging along Stations 2+00 to -1+00 within the north side slope of the channel due to rock being encountered in this area in the past. The final determination of the quantity of sand to be dredged and/or placed on the beach will be based on the Contract Drawings dated 04/20/2026 which will be updated with the new pre-construction survey to be provided by the CONTRACTOR within two weeks from the commencement date stipulated in the written Notice to Proceed from the COUNTY. The Bid Schedule for this Work references an estimated quantity of 85,000 CY which is a higher quantity of dredging to account for potential shoaling and increase in the dredge quantity if documented by an updated acceptable survey conducted by the CONTRACTOR’s registered professional surveying subcontractor.
TS-2.2 The Work must be completed according to the Contract Drawings and these Technical Specifications within the time specified in these specifications and contract and in compliance with the conditions of all federal, state, and local permits, including permits from Collier County, DEP, USACE, and USCG. Work conducted during the 2026 sea turtle nesting season which begins May 1, 2026 and extends through October 31, 2026, will require daily clearance from the marine turtle monitor for Collier County. CONTRACTOR must comply with the state and federal permits for specific protocol during sea turtle season, which also includes a limit of 500 feet of beach fill advancement at night and limited lighting with shielding for sea turtle protection. For any sea turtle nest encountered in the disposal areas, the marine turtle monitor for Collier County will mark a 25-foot permitter from the center of the nest for protection. Work conducted on the beach between February 15th and August 31st requires daily clearance from the County’s shorebird monitor.
TS-2.3 The CONTRACTOR is solely responsible for all construction means, methods, techniques, and procedures including construction layout and staking, monitoring and recording of dredge depths, maintaining as-built drawings, monitoring turbidity by a third party, maintaining water quality, and the sequence of the Work as specified in Section TS-5.0.
TS-3.0 Permits.
TS-3.1 CONTRACTOR is responsible for obtaining any and all local permits, including any application fees associated with any required local permit and authorization from USCG. The CONTACTOR is required to contact USCG a minimum of two weeks prior to project commencement. A copy of these permits must be submitted to the OWNER and ENGINEER prior to construction. The COUNTY will remain responsible for obtaining all state and federal authorizations.
TS-3.2 CONTRACTOR shall comply with all conditions of federal, state and local permits that have been obtained by OWNER, including those listed below and provided in Appendix A.
1. Florida Department of Environmental Protection JCP Permit 0142538-019-JM
2. U.S. Army Corps of Engineers SAJ-2004-07621(MOD-SJF), 3rd Modification
Technical Specifications Page 5 of 42
TS-4.0 Pre-Construction Submittals and Meetings.
TS-4.1 Prior to commencement of construction, CONTRACTOR shall attend a Pre-construction Meeting with the OWNER, ENGINEER and state and federal agencies. CONTRACTOR'S designated superintendent shall be present at the pre-construction meeting. A separate meeting will be held with the OWNER and ENGINEER to address any outstanding issues with the COUNTY.
TS-4.2 REQUIRED SUBMISSION: OPERATIONS PLAN
No less than ten (10) days prior to the Pre-construction Meeting, the CONTRACTOR shall submit an Operations Plan including the following items in completed form for review and acceptance by the ENGINEER and the COUNTY, as appropriate:
4.2.1 Letter of Understanding. The CONTRACTOR shall confirm that they have read, understand, and will abide by all terms and conditions of this contract and all of the permits, easements and any applicable ordinances, statutes, laws, rules or regulations which may affect this project and that they shall take responsibility for ensuring that their subcontractors have the same understanding and agree to abide by the same terms and conditions. A copy of the state and federal permits and state approved QA/QC plan is provided in Appendix A of these Technical Specifications.
4.2.2 Appointment of the Superintendent(s). Subject to the approval of the ENGINEER and OWNER, the CONTRACTOR shall provide, in writing, the name and qualifications of the appointed superintendent(s) who has/have authority to act for the CONTRACTOR and shall directly supervise all work through to completion of the Project. CONTRACTOR shall provide a summary of the number and qualifications of personnel to be used to complete the Work.
4.2.3 List of Subcontractors. The CONTRACTOR shall provide a list of all subcontractors that will or may be used for this work and a list of their qualifications and experience. CONTRACTOR’s surveyor must be registered in the State of Florida and must be approved by ENGINEER and OWNER.
4.2.4 Water Quality Monitoring Personnel. The CONTRACTOR shall provide a list of all third-party personnel responsible for collection and analysis of water quality samples and provide their qualifications and experience sufficient to satisfy NTP requirements of the DEP. A 24-hour/day contact number shall be provided for these personnel. A detailed map identifying the turbidity monitoring protocol shall be provided by the firm conducting the water quality monitoring using the latest forms provided by DEP as part of this submittal for filing with the DEP. This information shall be provided prior to the submittal of the Operations Plan to facilitate the processing of the state
NTP.
4.2.5 Construction Methodology. This Section shall describe the proposed equipment to be used including the dredge, size and dredging capacity of the dredge, and any tugs, Technical Specifications Page 6 of 42 barges or small vessels; the specific construction sequence; and methodology including specification of the number and type of bulldozers and loaders proposed for this Work. CONTRACTOR shall provide water transportation for OWNER and ENGINEER for access to construction activities as necessary.
4.2.5.1 Positioning. CONTRACTOR shall provide written details concerning the positioning system to be used on this project. Information to be submitted shall include written description of the equipment including applicable manufacturers' specifications and data, and documentation concerning previous jobs on which the equipment was used. Additionally, CONTRACTOR shall provide specific methods to be used in establishing horizontal and vertical control for both the dredging and the beach fill and for staking out the Work. This includes specific methods for accounting for all grade stakes and control markers to ensure their removal prior to completion of the project, including the use of a log and numbering system for all grade stakes so removal of all grade stakes can be documented prior to completion of the Project. All grade stakes shall be metal durable stakes and not made of wood. The log shall contain the location of each grade stake in a format such as x, y state plane coordinates or station number and range. Specifics of site grade stakes and their use for disposal site management shall be determined during the pre-construction meeting between the CONTRACTOR, OWNER, and ENGINEER.
4.2.5.2 Turbidity and Positioning Control. The CONTRACTOR shall provide specific methods for monitoring the positioning and depth of dredging in the navigation channel areas. The CONTRACTOR shall provide the ENGINEER with a certification, attesting to the accuracy of his turbidity testing equipment and procedure prior to the Pre-construction meeting. The CONTRACTOR will follow the calibration guidelines in the state DEP permit. Whenever there is doubt as to the adequacy of the turbidity testing or validity of the results, the ENGINEER may direct that additional tests be performed at no additional cost to the OWNER.
4.2.5.3 Staging and Dredge Area Management. The specific area of staging, mobilization, material and equipment storage, pipeline assembly or fusion, and pipeline route within authorized areas of use shall be clearly described by the CONTRACTOR. This includes specific reference to management of debris and filings of the pipeline that may be generated from the fusion process. The Operations Plan shall specifically identify measures of management of the upland area and any land-based equipment to be used in coordination with the dredging. This Operations Plan will also include procedural details of how the beach fill will be placed and graded to achieve the design grades to ensure the sand disposal is placed within the authorized template.
4.2.5.4 Project Schedule. The CONTRACTOR shall provide an outline of the
Technical Specifications Page 7 of 42 sequence of Work and project schedule to the ENGINEER and OWNER for acceptance and approval. The project schedule shall also be submitted as part of the Operations Plan. The project schedule shall be based on calendar days and indicate, at a minimum, timing and completion of the pre-construction survey, start of Work, construction period, fill placement completion date, beach tilling, final grading, and completion of all Work. The CONTRACTOR shall propose the order the Work will be performed. The CONTRACTOR shall submit revised progress schedules as appropriate during construction at construction progress meetings. CONTRACTOR shall be fully mobilized to commence Work within 5 calendar days from the commencement date stipulated in the written Notice to Proceed from the COUNTY.
4.2.5.5 Daily Reporting. Construction may be conducted 24 hours per day, seven days a week. CONTRACTOR shall submit a Daily Report Form acceptable to ENGINEER and OWNER, to be used for reporting daily operations. This form shall include; dredge progress including the location of the dredge at the beginning and end of the day, average before and after dredging depth, width of dredge cut, and estimated dredged quantity during the reporting period; the location of the discharge end of the pipeline within the beach fill, depending on the project at the beginning and end of the reporting period; a place to record the number of personnel on the job, equipment at the site, materials delivered to the site and materials incorporated in the Work completed during the reporting period, weather and sea conditions, the extent of and reason for any delays, and any instructions received from the ENGINEER, OWNER, Park, or regulatory agency personnel. Daily reports from CONTRACTOR to ENGINEER and OWNER shall also include dredge tracking data (position and depth) and turbidity monitoring data.
4.2.5.6 Quality Control Plan. The CONTRACTOR will designate a Quality
Assurance Officer who will be responsible for implementing all aspects of the Plan. This Plan shall describe the quality control measures that will be specified to achieve compliance with the terms and conditions of this contract and all regulatory permit conditions, including the DEP approved QA/QC plan.
4.2.5.7 Beach Quality Sand. CONTRACTOR shall indicate measures to be taken at either the suction end or discharge end of dredge pipeline to screen material with openings no larger than 2” x 2” to avoid placement of rock and debris on the beach larger than 2 inches. CONTRACTOR is also responsible to oversee that sand placed on the beach is beach compatible sand in accordance with the State DEP approved QA/QC Plan.
4.2.5.8 Environmental Protection Plan. The CONTRACTOR will prepare a plan to comply with the requirements specified in this document, including all permit requirements, and will designate a person(s) responsible for implementing this plan, adequately training all personnel who will be implementing
Technical Specifications Page 8 of 42 elements of the plan, compliance with all permit conditions, terms and conditions of this contract, and adherence to conditions of all of the easements and any applicable ordinances, statutes, laws, rules and permits.
4.2.5.9 Accident Prevention Plan and Appointment of Safety Officer. The
CONTRACTOR shall provide the name and contact information for the Safety Officer(s) responsible for this project, including functional descriptions of duties. CONTRACTOR shall provide a plan for maintaining pedestrian safety, navigation safety, and pedestrian control in the vicinity of the Work, including both the dredging and beach fill placement.
4.2.5.10 Severe Weather Plan. The CONTRACTOR shall monitor NOAA or other weather broadcasts during all dredging operations and notify the ENGINEER and OWNER at the time of any decision to move equipment in preparation for potential storms. Progress surveys are encouraged to be completed prior to any forecasted severe weather event. The CONTRACTOR shall provide a prioritized list of actions to be taken in the event of a severe storm and assign personnel to each action. Safety shall remain a priority at all times and any weather data used in making decisions which will delay Work shall be duly documented on the daily report forms required for each calendar day during the Contract period. The CONTRACTOR shall specify emergency operating procedures to be implemented in the event of mooring equipment failures, loss of a spud, swing wires, anchor wires, or other mooring equipment.
TS-4.3 CONTRACTOR shall designate a competent superintendent who will attend the pre-construction conference as well as be on site during construction activities and be responsible for seeing the Work is in compliance with the Contract Documents, including the Contract Drawings, Technical Specifications and regulatory permits. This person must remain as the superintendent during the entire duration of the project, unless a written request is made by the CONTRACTOR for a change and is approved by the OWNER. The OWNER can temporarily cease Work if no superintendent, approved by the OWNER, is working on the project, and such delays will not be an acceptable reason to justify contract time extension.
TS-4.4 CONTRACTOR’s superintendent is responsible for ensuring safety protocols are followed for the protection of the public, pedestrians, and all personnel of the CONTRACTOR, COUNTY and ENGINEER when recreating or working within the Project Work area in compliance with these Contract Documents. The COUNTY has the authority to require that the CONTRACTOR assign a new superintendent acceptable to the COUNTY, should site and job safety be compromised at any time.
TS-4.5 CONTRACTOR’s superintendent shall attend a weekly progress meeting to be held on site with the OWNER and the ENGINEER to review progress of the Work, work schedule, and submittals. Initially, progress meetings will be held weekly and will be subject to change based on instructions from the OWNER or ENGINEER.
TS-4.6 CONTRACTOR shall provide a cell phone number by which the Superintendent may be
Technical Specifications Page 9 of 42 reached at any time during construction as well as a backup contact if needed.
TS-4.7 The Contract Drawings are based on a January 2026 pre-construction survey conducted by Collier County. The CONTRACTOR may conduct an additional pre-construction survey, and if one is conducted, CONTRACTOR shall submit the updated pre-construction survey to OWNER and ENGINEER for the project within 14 days of receipt of NTP from OWNER. If an updated survey is completed, it may be used for pay quantity determination subject to acceptance by the COUNTY and ENGINEER.
TS-4.8 CONTRACTOR shall submit third party turbidity monitor qualifications, monitoring plan and report form, prior to the Preconstruction meeting with OWNER, ENGINEER and regulatory agencies, for ENGINEER to file with DEP for acceptance and approval.
TS-5.0 Order of Work.
TS-5.1 The order of Work shall generally be:
The CONTRACTOR shall review site conditions and Contract Drawings and have an updated survey completed of the dredge and sand disposal areas. The updated survey shall be conducted by a registered Professional Surveyor and Mapper registered in the State of Florida. Construction shall commence prior to completion of the updated survey since the design depth of dredging will not change. The stationing and extent of the surveys shall match the plan included as part of these Technical Specifications. The data shall be provided to the ENGINEER for generation of updated construction plans showing beach disposal and beach fill limits, dredging limits, and tolerances. Pre and post construction beach profiles, and profiles for the inlet channels to be dredged, shall extend at least 15 feet beyond the point of profile closure.
Pre- and post- construction survey scope is as follows:
o Wiggins Pass Dredge Stations 12+00 east to -2+00 and C-3 east to C-12 (25 Stations). Including the upland portion of the profile for the stations containing upland in or near the boundaries of the dredge template.
o Wiggins Pass Dredge Stations C-17 east to C-24 and C-29 south to C-32 (12 Stations).
o Wiggins Pass Disposal Monuments R17.5, R18, R18.5, R19, R19.5, R20 and R20.5 (7 Profiles). Offshore to -13.0 NAVD and extending upland to DEP monuments or stationing position control to ensure profile closure.
o The vegetation line from R17.5 south to R20.5 o Record the type, number, and location (x,y coordinate, NAD83 Florida East Zone) of all daymarks with the potential to be removed, displaced or destroyed during construction. Elevation of the bottom of the sign on the daymark shall be documented so that installation of replacement daymarks or reinstallation of the displaced daymark is reestablished at the same elevation with a 6-inch tolerance.
CONTRACTOR shall coordinate with the OWNER and position pedestrian fencing for the beach disposal operations, including beach fill placement, staging area which includes Parking Lot 5, and appropriate USCG markings for navigation safety for channel dredging in Wiggins Pass. Once accepted and following preconstruction meetings with the DEP, Technical Specifications Page 10 of 42
USACE, OWNER and ENGINEER, CONTRACTOR shall begin construction in accordance with all regulatory requirements of the local, state and federal authorizations within 5 calendar days from the commencement date stipulated in the written Notice to Proceed from the COUNTY.
CONTRACTOR shall commence with dredging and beach fill placement upon:
o Acceptance of the pedestrian control and navigation protection by OWNER, o Completion of all necessary pre-construction requirements as confirmed by
ENGINEER, and receipt of the Notice to Proceed (NTP) from the state DEP and from the OWNER.
TS-5.2 Work is permissible 24 hours per day, seven days a week. WORK must comply with all local, state and federal requirements including endangered species protection and lighting requirements. A copy of the lighting requirements is included in Appendix A.
TS-5.3 Beach disposal will commence at the north end of disposal area and proceed to the south unless an alternate plan is provided and detailed by CONTRACTOR to support an alternative. If there exists a sea turtle nest within the beach fill area, CONTRACTOR will follow a mark and avoid procedure for protection of the nest and place a suitable amount of sand fill to fill the depressed area following the hatching of the nest and clearance from the Marine Turtle Permit Holder with the COUNTY.
TS-5.4 Upon completion and acceptance of the beach fill, CONTRACTOR shall complete necessary tilling and final site grading in the upland beach fill area in accordance with these Technical Specifications and referenced state regulatory permit for acceptance by OWNER and ENGINEER. Project tilling will also follow the state permit conditions and avoid and stay clear of any marked sea turtle nests.
TS-6.0 Layout of the Work.
TS-6.1 The CONTRACTOR shall use R-monuments, coordinates and the Construction Stations provided on the Contract Drawings to layout the work. It is the CONTRACTOR’s responsibility to layout the work using the horizontal and vertical positioning information shown on the plans.
Additional benchmarks may be established based on existing DEP reference monuments, and identified stationing, and CONTRACTOR shall provide ENGINEER with a copy of field notes prepared during the establishment of any additional benchmarks. The CONTRACTOR shall furnish such stakes, equipment, tools, and qualified personnel as may be required in laying out any part of the Work, and for maintaining such staking as necessary for completion of the Work.
Upland stakes may be used for station reference of sight lines for the beach disposal, and upland beach fill shall be staked on 100-foot stations as deemed necessary by OWNER and ENGINEER for visual checking and guidance of Work. It is understood that CONTRACTOR may be using a HYPACK system, or similar, for guidance of the dredging and fill placement. All grade stakes used to establish positioning and beach fill elevations must be accounted for and removed from the beach by the CONTRACTOR prior to final completion. A log of all grade stakes shall be maintained by the CONTRACTOR as described in Section TS 4.2.5.1 throughout the project.
Grade stakes shall be made of steel pipe or other material and not wood for safety and
Technical Specifications Page 11 of 42 sustainability, such that each grade stake can be accounted for and be removed intact after construction. The ENGINEER may request that Work be suspended if grade stake layout is not adequate to permit visual checking of work. Any delays to Work progress as a result of mismanagement of the grade stakes shall not be a justified delay relative to Contract timelines and performance. Grade stake colored ribbon markings shall be established at the onset of construction, and the same color scheme shall be maintained throughout the project to allow visual checking of work.
TS-6.2 Since a portion of the dredging may be attached to the upland, grade stakes shall also be used in a similar manner to provide a visual guide and check for the area of dredging and disposal.
TS-7.0 Record Drawings and Daily Reports.
TS-7.1 During the course of construction, the CONTRACTOR shall record all information required to complete a set of As-Built Record Drawings. Information to be included on the Record Drawings shall be recorded on one working set of construction drawings during the course of the Work and shall include actual dimensions and elevations. If field changes are made to modify the Work in any way, such field changes shall be documented on the Record Drawings by dimension, detail and date and in the corresponding daily report. The working set of construction drawings shall be kept at the project site and be available for review by OWNER, ENGINEER, and regulatory agencies during the progress of the Work. Prior to Substantial Completion of the Work, the CONTRACTOR shall provide the documented information to the ENGINEER for generation of a final Project Record set of drawings, and such drawings will be signed by CONTRACTOR and OWNER to verify extent and agreement of any changes in the plans. Prior to final payment, the Record Drawings shall be revised by the CONTRACTOR and provided to ENGINEER and OWNER to reflect any changes which have occurred since the submittal for substantial completion.
TS-7.2 During the course of construction, CONTRACTOR shall submit a Daily Report of Operations to include the information listed under TS-4.2. The report shall be submitted on a form to be approved by the ENGINEER and OWNER and shall be submitted electronically by 5:00 pm on the day following the day covered by the report. All surveys conducted by CONTRACTOR for verification of pay quantity and regulatory compliance shall be conducted under the supervision and direction of a registered Professional Surveyor and Mapper (PSM) in the State of Florida and the CONTRACTOR shall ensure that the OWNER or ENGINEER may be present during data collection by the surveyor. All copies of final surveys shall be signed and sealed by the registered surveyor, and the final survey shall be accompanied by the surveyor certification satisfying the State DEP reporting requirements.
TS-7.3 All surveys (pre, post, and interim) shall include a signed and sealed survey report, field notes, control information, metadata and submitted in both x,y,z and DEP formats in compliance with state DEP Monitoring Standards for Beach Erosion Control Projects May 2014 Edited:
October 2014.
TS-8.0 Site Conditions.
Technical Specifications Page 12 of 42
TS-8.1 The beach fill construction site is in the nearshore and on the beach, at the water’s edge of the Gulf. The CONTRACTOR shall document conditions of the upland staging areas and areas used for access prior to construction and shall submit site photos and drone photography of those areas in advance of commencement of construction. CONTRACTOR shall take every precaution to avoid damage to the existing facilities and environmental habitat and shall be responsible for restoring facilities and environmental habitat damaged during construction to their preconstruction condition. This includes but is not limited to, daymarks, beach access points, fencing, parking areas, and vegetation.
TS-8.2 The dredge channels are located in or adjacent to Wiggins Pass. These areas of work are adjacent to and within a tidal inlet and may be subject to strong tidal currents as well as wakes generated by vessels going in and out of the respective inlet. The CONTRACTOR is responsible for being familiar with these conditions and to take them under consideration in the cost of the Work, and to take appropriate precautions to ensure that partially completed work is not subject to displacement or damage due to natural site conditions or boat wakes. Should any such damage or displacement of partially completed Work occur prior to the Work being surveyed and accepted, the CONTRACTOR is responsible for repairing any such damage or displacement of partially completed Work at no additional cost to the OWNER.
TS-8.3 The inlet was first dredged in 1984. Since 1990, the inlet has been dredged on approximately 2-year intervals. The most recent maintenance dredging events were completed in 2020 and 2022, and the area has been impacted by hurricane events in 2022, 2023 and 2024.
CONTRACTOR is advised that there may be storm debris encountered when dredging. Any debris encountered shall be stockpiled and disposed of properly.
TS-8.4 Information and data furnished or referred to herein are for the CONTRACTOR’S information; however, it is expressly understood that the OWNER and ENGINEER shall not be responsible for any interpretation or conclusion drawn there from by the CONTRACTOR. It is the CONTRACTOR'S responsibility, in accordance with the Instructions to Bidders, to visit the project site and to take whatever other measures necessary to be familiar with local conditions and review project mapping and technical data that may in any manner affect the cost and performance of the Work.
TS-8.5 It is the CONTRACTOR’S responsibility to determine the suitability of the CONTRACTOR’S equipment for working under the site conditions and that the capacity of the CONTRACTOR’S equipment is sufficient for completion of the work within the construction window.
TS-8.6 The CONTRACTOR shall be solely responsible for all informational (manatee) signage markers in the waterways that may be removed, destroyed or otherwise displaced during construction. The informational signage markers shall be restored by the CONTRACTOR at previous location or a location approved by the OWNER. Replaced markers shall be constructed of new material, as approved by the OWNER and in compliance with FFWCC and FWS Guidelines for Posting Uniform Waterway Markers in Florida’s Waterways, March 2008. Pilings shall be wrapped with high density polyethylene pile wrap (.030 thick min.) from 18” above the MHW elevation to 18” below the mudline. Alternative designs by CONTRACTOR may be
Technical Specifications Page 13 of 42 submittal for value engineering for acceptance by OWNER and ENGINEER. Warranty for marker pilings to be provided pre-construction for approval by OWNER.
https://myfwc.com/media/13268/boat_waterwaymarkerguidelines.pdf
Navigational channel markers may be replaced and new markers installed at the direction of the OWNER. Markers to include one capped fiberglass piling and a sign provided by the OWNER.
Warranty for channel marker installation to be provided pre-construction for approval by OWNER.
TS-9.0 General Notes.
TS-9.1 The Work is to be completed within two areas:
Wiggins Pass is located in Collier County, Sections 17 and 20, Township 48 South, Range 25 East, and in the Gulf of America, Class III Waters. Portions of the project are within Outstanding Florida Waters (OFW) associated with Delnor-Wiggins Pass State Park and Wiggins Pass Estuarine Area and Cocohatchee River System.
TS-9.2 Upland staging areas for the PROJECT will be designated by the OWNER and include parking lot #5. CONTRACTOR shall be responsible for restoring these areas to their documented pre-project condition, including native vegetation and parking areas, before the project will be considered to be Substantially Complete. If additional storage is required for construction equipment and materials, arrangements for such storage facilities shall be the responsibility of the CONTRACTOR and must be coordinated with the OWNER and the Park.
TS-9.3 Special measures shall be taken to prevent bilge pumpage or effluent, chemicals, fuels, oils, greases, and bituminous materials from entering the water.
TS-9.4 Disposal of any materials, waste, effluent, trash, garbage, oil, grease, chemicals, etc., in and adjacent to the project site shall not be permitted. If any waste materials are dumped in unauthorized areas, the CONTRACTOR shall remove the material and restore the area to the original condition as it existed before being disturbed. If necessary, contaminated ground shall be excavated, disposed of as directed by the COUNTY, OWNER, or ENGINEER, and replaced with suitable fill material.
TS-9.5 The CONTRACTOR is responsible for maintaining a safe work environment. The CONTRACTOR is referred to the USACE COE EM 385-1-1 USACE Safety and Health Requirements Manual. Hard hats, long pants, and steel-toed boots are required to be worn on the beach and on the dredge. Life vests are required when working on, in, or near the water.
TS-10.0 Dredging.
TS-10.1 The scope of the dredging includes excavation of all material from the designated areas within the Wiggins Pass main channel and interior channels as shown on the Contract Drawings and discharge of the material in the nearshore and on the beach within the fill template in accordance with the Contract Drawings.
Technical Specifications Page 14 of 42
Rock substrate was removed from the Wiggins Pass dredge template in 2013, and the pass was dredged again in 2018. With the exception of the relatively small areas identified in Stations 2+00 to -1+00, no rock is anticipated within the dredge template. However, if rock is encountered, the CONTRACTOR is to notify the OWNER and ENGINEER. Refer to Section TS-4.2.5.7. of these Technical Specifications for material screening.
TS-10.2 The dredging depths are shown on the Contract Drawings. The Contract Drawings show the design dredge depth includes an overdepth allowance. The design dredge depth is the minimum depth of required dredging, and the overdepth allowance is provided for the CONTRACTOR to ensure the design depth is achieved. The overdepth allowance establishes a not to exceed depth.
The volume of any material dredged from below the overdepth elevation will be computed from post dredge surveys and deducted from the pay quantity, unless determined acceptable by the OWNER and ENGINEER prior to the dredging.
TS-10.3 The side slopes along the design dredge template may be dredged as a box cut so that material not dredged above the elevation of the dredge cut along the side slope will match the amount of material dredged laterally beyond the side slope, below the elevation of the cut along the side slope, and above the maximum depth of cut for that template.
TS-10.4 The CONTRACTOR is required to use a submerged pipeline. The pipeline shall rest on the bottom, and CONTRACTOR shall make every effort to locate the pipeline such that the top of the submerged pipeline shall be no higher than -6 feet NAVD when located within 25 feet of Wiggins Pass Main & South Channel. Should this condition not be achievable due to shoaling, CONTRACTOR shall submit a pipeline location for acceptance by OWNER and ENGINEER.
TS-10.5 The CONTRACTOR shall clearly mark the entire length of submerged pipeline as necessary to conform to USCG regulations and COUNTY requirements.
TS-10.6 The dredge cuts are near navigable channels, and the CONTRACTOR shall maintain navigability of the channels at all times. Should CONTRACTOR’s pipeline, barges, or other floating equipment temporarily obstruct the channel for passage of boat traffic, CONTRACTOR shall take immediate steps to allow boat traffic to pass.
TS-10.7 The pipeline joints shall be constructed as to preclude spillage and leakage. Regular daily pipeline inspections a minimum of twice a day shall be made during operation and any leaks that develop shall be promptly repaired and the dredge shall be shut down until repairs are completed.
Confirmation of daily pipeline inspections and the location of any leak shall be documented by GPS coordinates in the daily report.
TS-10.8 Should the CONTRACTOR during the progress of the Work, lose, dump, throw overboard, sink, or misplace any material, dredged material, plant, machinery, equipment, or pipe, the CONTRACTOR shall recover and remove same immediately upon instructions from the ENGINEER. The CONTRACTOR shall give immediate notice, with description and location of such obstructions, to the ENGINEER, and when required, shall mark with buoy such misplaced material until same are removed.
Technical Specifications Page 15 of 42
In the event of refusal, neglect, or delay in compliance with the above requirements, such misplaced materials may be removed by the COUNTY, and the cost of such removal may be deducted from any money due or to become due to the CONTRACTOR or may be recovered under the CONTRACTOR’s bond.
TS-10.9 The CONTRACTOR shall contact the U.S. Coast Guard regarding issuance of a Notice to Mariners, in accordance with U.S. Coast Guard regulations, regarding the dredging and disposal operation immediately after the Notice to Proceed has been received from the OWNER. A copy of the Notice to Mariners shall be provided to the OWNER and ENGINEER.
TS-10.10 Should the CONTRACTOR, during dredging operations, encounter any objects on the Gulf or inlet channel bottom that could be a hazard to navigation, he will notify the OWNER and ENGINEER immediately as to the location of said object and any other pertinent information necessary for the CONTRACTOR to contact the U.S. Coast Guard regarding issuance of a Notice to Mariners.
TS-11.0 Beach Fill Disposal.
TS-11.1 The CONTRACTOR is required to place only beach fill from the area of excavation complying with the criteria established in the State approved Sediment Quality Assurance/Quality Control (QA/QC) Plan approved for this project. CONTRACTOR shall use the Primary Beach Disposal Area on the Contract Drawings, or as directed otherwise by the OWNER and
ENGINEER.
TS-11.2 All fill material shall be compatible with the existing native beach sand and meet the requirements of the DEP and USACE permits. Should clay, clay balls, rock, rubble, or any other debris larger than two (2) inches in diameter or shell hash (visually more than 5%) be encountered during excavation, which exceed the allowance in the State approved QA/QC Plan, the CONTRACTOR will immediately relocate or reduce the excavation depth to avoid placing such material on the beach or nearshore. CONTRACTOR shall document all areas where clay, rock, or other non-beach compatible materials is encountered and include the time, date and location and depth of the non-compatible material on the Daily Report Form.
CONTRACTOR shall be responsible for removing any such non-beach compatible material including clay balls, rock or shell hash which is placed on the beach or in the nearshore.
CONTRACTOR shall remove from the site of the Work, all snags, driftwood and similar debris lying within the limits of the beach fill section, as directed by OWNER or ENGINEER, before placement of the fill. All materials removed shall be disposed of in an area provided by and at the expense of the CONTRACTOR and approved by the OWNER or ENGINEER. Grading and other construction equipment will not be permitted outside the construction limits except for ingress or egress to and from the site by way of construction access approved by the OWNER. The CONTRACTOR shall grade all areas used by the CONTRACTOR on the beach including those areas used for access to and from the Work area.
TS-11.3 The CONTRACTOR shall continuously visually monitor the sediment being excavated and placed in the nearshore or on the beach. If noncompliant sediment is encountered, the
Technical Specifications Page 16 of 42
CONTRACTOR will immediately cease dredging, adjust dredging operations accordingly into compliant sediment, and verbally notify the OWNER and ENGINEER, providing the time, location, and description of the noncompliant sediment. The CONTRACTOR will also report any encounters with noncompliant sediment in the CONTRACTOR’s Daily Report, providing depth and location in State Plane Coordinates of said materials. The CONTRACTOR will take the appropriate remediation actions as directed by the OWNER or ENGINEER.
TS-11.4 As part of the Project, CONTRACTOR shall plan to utilize appropriate measures as necessary to ensure sand placed on the beach meets the Quality Assurance and Quality Control (QA/QC) Plan for gravel-size in excess of 0.5-inch diameter material does not exceed 5% through use of screen boxes, raking, or other means as determined by the CONTRACTOR. Such means and methods shall be presented to OWNER and ENGINEER for acceptance and employed as necessary for sediment quality compliance with the state permit and approved QA/QC Plan. The collection of non-compatible material exceeding the QA/QC allowance shall be removed and transported to a designated area within the Park. The CONTRACTOR will be required to temporarily dispose of the material in a pile at the designated location within the Park and then remove it to a location meeting County, State and Federal requirements.
TS-11.5 CONTRACTOR shall adhere to all requirements of the Quality Assurance and Quality Control Plans. The Quality Assurance and Quality Control Plan for the Project is included in Appendix A and will become part of the contract upon execution. During beach disposal, the COUNTY shall collect a pint-sized sand sample daily from the beach disposal area, save in Ziplock bags, mark with date and location of discharge, review and archive. The quality of the sand placed on the beach shall be visually analyzed and discussed at the weekly progress meetings, or daily if requested by ENGINEER. The sampling time and frequency will comply with the State approved QA/QC plan.
TS-11.6 CONTRACTOR shall use all practicable means to minimize turbidity levels during fill placement. This includes the use of shore parallel sand dikes during beach placement of beach fill.
TS-11.7 The dredge and fill quantities shown on the Contract Drawings are estimated based on recent survey data collected in January 2026. The elevations shown in the Contract Drawings are subject to change and CONTRACTOR shall be responsible for verifying depths as needed for construction activities. An additional pre-construction survey shall be completed by the CONTRACTOR’s surveyor through the dredge channels and beach fill areas and will be used for pay quantity verification. All updated survey information will be provided by CONTRACTOR to OWNER and ENGINEER within 14 calendar days from the commencement date stipulated in the written Notice to Proceed from the COUNTY. ENGINEER shall update the Contract Drawings accordingly and provide to CONTRACTOR in CAD format. The survey for the Wiggins Pass dredge areas will be conducted to allow for ENGINEER to prepare updated construction plans and dredge quantities. The design depth of dredging does not change, and therefore dredging will occur while the updated survey and preparation of updated Contract Drawings are being conducted.
TS-11.8 Payment for the dredge quantity on this Project will be based on quantities computed from a pre-dredge survey and a post-dredge survey or progress survey as appropriate, and the unit price
Technical Specifications Page 17 of 42 on the bid schedule, up to the maximum quantity agreed to as part of the Contract between CONTRACTOR and OWNER. Pay quantity verification shall be based on the construction template shown on the Contract Drawings unless amended by OWNER prior to dredging.
TS-11.9 The CONTRACTOR shall grade the upland beach above the waterline to the grades shown on the plans.
TS-11.10 CONTRACTOR shall stake the lines and grades of the beach fill as the work progresses and maintain such stakes and grades as necessary to ensure accurate placement of the fill. All grade stakes shall be accounted for and removed by the CONTRACTOR prior to final acceptance.
TS-11.11 CONTRACTOR shall set barricades, fences, and signs to prevent public access to the construction area. CONTRACTOR shall provide a minimum of two safety personnel at all times during daylight hours on the beach to ensure beach pedestrians and nearshore recreational kayakers and paddleboarders remain outside fenced and designated Work areas.
TS-11.12 CONTRACTOR shall construct temporary ramps over the shore pipeline lying on the beach at the request of the OWNER or ENGINEER, in order to accommodate pedestrian traffic, if deemed necessary by the Park.
TS-11.13 The upland beach fill shall be tilled to a depth of 24 inches following completion of the beach fill placement in accordance with the limitations provided in the DEP permit.
TS-11.14 CONTRACTOR shall not allow runoff from the dredge discharge to flow landward of the upland beach fill section. The upland beach fill shall be graded to eliminate low spots where ponding could occur. Upon completion of all upland filling operations, the beach fill shall be graded and dressed so as to eliminate any undrained pockets, depressions or high spots on the beach fill and to grade the fill to within a tolerance of plus or minus five-tenths of a foot of the design grade above the waterline. As part of the final dressing of the beach, CONTRACTOR shall grade the seaward slope above mean high water to have a 1 vertical to 15 horizontal slope.
TS-11.15 Construction and grading equipment shall not be permitted outside the staging and construction limits except for ingress or egress to and from the site by way of construction access locations agreed to during the pre-construction conference.
TS-11.16 CONTRACTOR shall clean up the construction site upon completion of the Work removing all surplus and debris materials, and other equipment, regrade the beach to eliminate any mounds or low spots created during the construction activity.
TS-12.0 Surveys and Payment.
TS-12.1 Payment for the Project will be based upon quantities of material removed from the dredge template as shown on the construction plans as documented by the CONTRACTOR’s progress surveys, conducted by a PSM registered in the State of…