This is a bid schedule for Collier County, Florida's Wiggins Pass and Doctors Pass Maintenance Dredging Project (ITB 26-8697), a grant-funded construction initiative advertised on July 21, 2026. The project comprises two distinct dredging operations: Wiggins Pass maintenance dredging involving 85,000 cubic yards of material with beach disposal, and Doctors Pass maintenance dredging involving 37,000 cubic yards from the settling basin, turning basin, and west channel, also with beach disposal. Ancillary work for both passes includes mobilization and demobilization, navigational and manatee marker installation or relocation, environmental control with turbidity testing, construction surveys, final tilling and grading, debris removal, and restoration of construction access. Sealed bids were required by August 10, 2026, at 3:00 p.m. local time, with prospective bidders required to register on the Collier County procurement portal at https://procurement.opengov.com/portal/collier-county-fl to access complete bid documents.

The bid schedule presents all line items with estimated quantities and unit costs, though specific pricing has been redacted from this document. Quantities for the primary dredging work are estimates, with final quantities to be determined following pre-construction surveys. The contractor is responsible for providing manatee marker materials at Wiggins Pass and implementing screening measures to ensure sand placed on beaches does not exceed five percent material greater than 0.5 inches in diameter. The county will provide navigational marker materials for Wiggins Pass. Debris removal accounts for potential storm-generated material, and all work includes provisions for environmental compliance and construction-phase surveying documentation.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Schedule

2026 COLLIER COUNTY MAINTENANCE WIGGINS PASS AND DOCTORS PASS DREDGING PROJECT
CONSTRUCTION ITB: 26-8697
BID SCHEDULE

A. Wiggins Pass Maintenance Dredging

Item Item Description Estimated Quantity Unit Unit Cost Total Cost

1 Mobilization and Demobilization 1 Lump Sum $ - 0

2 Dredge Wiggins Pass Channel with Beach Disposal (See Note I & V) 85,000 CY $ - 0 $ - 0

3a Navigational Channel Marker Install (See Note II) 15 Each $ - 0 $ - 0

3b Manatee Marker Installation (See Note III) 1 Each $ - 0 $ - 0

4 Environmental Control including Turbidity Testing 1 Lump Sum $ - 0 $ - 0

5 Construction Surveys (Pre, Interim, and Post) 1 Lump Sum $ - 0 $ - 0

6 Final Tilling and Grading 1 Lump Sum $ - 0 $ - 0

7 Debris Removal (See Note VI) 1 20 cy container $ - 0 $ - 0

8 Restoration of Construction Access 1 Lump Sum $ - 0 $ - 0

Subtotal Bid Item A. Wiggins Pass $ - 0

B. Doctors Pass Maintenance Dredging

Item Item Description Estimated Quantity Unit Unit Cost Total Cost

1 Mobilization and Demobilization 1 Lump Sum $ - 0 $ - 0

2 Dredge Doctors Pass Settling Basin, Turning Basin, and West Channel with Beach Disposal (See Note I & V) 37,000 CY $ - 0 $ - 0

3 Temporary Removal and Re-Install Navigational Channel Marker Install (See Note IV) 5 Each $ - 0 $ - 0

4 Environmental Control including Turbidity Testing 1 Lump Sum $ - 0 $ - 0

5 Construction Surveys (Interim & Post-Construction. 1 Lump Sum $ - 0 $ - 0

6 Final Tilling and Grading 1 Lump Sum $ - 0 $ - 0

7 Debris Removal (See Note VI) 1 20 cy container $ - 0 $ - 0

8 Restoration of Construction Access 1 Lump Sum $ - 0 $ - 0

Subtotal Bid Item B. Doctors Pass$ - 0
Total Bid A + B$ - 0
Notes:
I. Quantity is estimated; final quantity based on results of a pre-construction survey.
II. Includes replacement of removed markers or installation of new makers at Wiggins Pass (OWNER to provide materials).
III. Includes replacement of removed manatee markers or installation of new makers at Wiggins Pass (CONTRACTOR to provide materials).
IV. Includes removal and re-installation of markers temporarily removed for construction purposes at Doctors Pass
V. Includes measures to ensure sand placed on the beach greater than 0.5" diameter does not exceed 5% through the use of

screen boxes, raking, and/or other means as determined by the contractor. (Ref. Technical Spec. 11.4)

VI. Potential debris from storms. (Re. Technical Spec. 8.3)

File details come from the government source that posted it. Updated .