26-8683_Exhibit_P_–_Pipe_Schedule.pdf

PDF 476 KB Posted

Attached to
SCRWTP Lime Softening Improvements - Blend Tank
Solicitation number
26-8683
Issued by
Collier County, Florida

About this file

This is a Pipe Schedule exhibit prepared by Carollo Engineers, Inc. for Collier County's South County Regional Water Treatment Plant (SCRWTP) Lime Softening Improvements - Blend Tank project (Bid No. 26-8683). The document specifies materials, dimensions, pressure ratings, testing methods, and installation requirements for all piping systems associated with the blend tank construction. Piping materials include polyvinyl chloride (PVC) for drain lines ranging from 0.5 to 12 inches, chlorinated polyvinyl chloride (CPVC) Schedule 80 for chemical injection systems (chlorine solution, ammonia, sodium hydroxide, and corrosion inhibitor) in sizes from 0.5 to 4 inches, and ductile iron pipe (DIP) rated at 150 pounds per square inch for process water lines including 42-inch blended finished water and 36-inch filter effluent lines. All chemical injection piping requires double-wall containment with leak detection. Joints and fittings specifications vary by application, with solvent-welded connections for plastic piping and restrained mechanical joints for ductile iron piping. Test pressures range from gravity method testing for drain systems to high-head testing at 125 pounds per square inch for pressurized water lines. The schedule includes coating and lining requirements, with cement mortar lining and polyethylene encasement specified for ductile iron piping carrying blended finished water and filter effluent to ensure water quality protection and corrosion resistance.

The document was digitally signed and sealed on June 29, 2026, by Anthony Ryan Horvat, P.E., and serves as Addendum 4 to the specification set for the blend tank construction. This pipe schedule is referenced in Section 40_05_00.01 (Common Work Results for General Piping) and cross-references detailed specifications in Section 40_05_31.01 for plastic piping and Section 40_05_19.01 for ductile iron piping. The schedule establishes standards for underground and aboveground piping installations, differentiating between process water, chemical injection, and drain systems to ensure compliance with applicable codes and the project's operational requirements while maintaining the facility's function as the county's sole drinking water source during construction.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

301 NORTH CATTLEMEN ROAD, SUITE 302 SARASOTA, FLORIDA 34232 P 941-371-9832

pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/00_01_02_Addendum4.docx

COLLIER COUNTY

SOUTH COUNTY REGIONAL WATER TREATMENT PLANT

LIME SOFTENING IMPROVEMENTS - BLEND TANK

CLIENT PROJECT NO. 70283.2

ADDENDUM 4 ATTACHMENT

JUNE 2026

This item has been digitally signed and sealed by Anthony Ryan Horvat on the date adjacent to the seal.

The signature must be verified on any electronic copies.

Carollo Engineers, Inc.

301 North Cattlemen Road Suite 302 Sarasota, Florida 941-371-9832 (Ph)

Common Work Results for General Piping 40_05_00.01-13 204170-10 June 2026 – Addendum No. 4 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/40_05_00.01 (Bid Set)

ATTACHMENT A - PIPE SCHEDULE

40_05_00.01-14 204170-10 June 2026 – Addendum No. 4 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/40_05_00.01 (Bid Set)

PIPE SCHEDULE

Process Abbrev. Service

Nominal Diameter (inches) Material

Pressure Class Special

Thickness Class

Schedule Wall Thickness

Pipe Spec.

Section

Joints/ Fittings

Test Pressure/ Method Lining Coating

Service Conditions Comments

D Drain

Underground 1 - 12 PVC SCH 80 40_05_31.01 - Plastic Piping and Tubing

SW 15 feet/GR None None

Aboveground 0.5 - 6 PVC SCH 80 40_05_31.01 - Plastic Piping and Tubing

SW 15 feet/GR None None

Groundwater Dewatering

6 - 8 PVC SCH 40

40_05_31.01 - Plastic Piping and Tubing

SW 20 feet/GR None None

BFW

Blended

Finished Water

Post Blend

Tank (Underground)

42 DIP 150

40_05_19.01 - Ductile Iron

Pipe:

AWWA C151

RSMJ

125 psig/H

H

CM PEE

BTV

Blend Tank Vent Piping

Vent

12 DIP 150

40_05_19.01 - Ductile Iron

Pipe:

AWWA C151

FL N/A CM

EPP (EPU-

M-1;

Exposed)

Vent

12 DIP 150

40_05_19.01 - Ductile Iron

Pipe:

AWWA C151

FL N/A CM

EPP (EPX-

M-1-PWS;

Submerged)

LS

Lime Softened

Water

40_05_00.01-15 204170-10 June 2026 – Addendum No. 4 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/40_05_00.01 (Bid Set)

Abbrev. Service

Nominal Diameter (inches) Material

Pressure Class Special

Thickness Class

Schedule Wall Thickness

Pipe Spec.

Section

Joints/ Fittings

Test Pressure/ Method Lining Coating

Service Conditions Comments

Filter Effluent

(Underground)

36 DIP 150

40_05_19.01 - Ductile Iron

Pipe:

AWWA C151

RSMJ

125 psig/H

H

CM PEE

ROP

Reverse Osmosis Permeate

RO Permeate from Degasifiers

42 DIP 150

40_05_19.01 - Ductile Iron

Pipe:

AWWA C151

RSMJ

125 psig/H

H

CM PEE

SHC

Chlorine Solution

(Chemical Piping)

SHC-1

& 2

Underground 2- 4 CPVC SCH 80 40_05_31.01 - Plastic Piping and Tubing

SW

1.5x Working

Pressure /

HH

None None Double

Containme nt

Provide 2”

– 4” carrier piping

SHC-1

& 2

Aboveground 2 - 4 CPVC SCH 80 40_05_31.01 - Plastic Piping and Tubing

SW

1.5x Working

Pressure /

HH

None None

Drain- To-

Waste Piping

Drain-To- Waste Piping

Underground 1/2 - 2 CPVC SCH 80 40_05_31.01 - Plastic Piping and Tubing

SW GR None None

40_05_00.01-16 204170-10 June 2026 – Addendum No. 4 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/40_05_00.01 (Bid Set)

Nominal Diameter (inches) Material

Pressure Class Special

Thickness Class

Schedule Wall Thickness

Pipe Spec.

Section

Joints/ Fittings

Test Pressure/ Method Lining Coating

Service Conditions Comments

Aboveground 1/2 - 2 CPVC SCH 80 40_05_31.01 - Plastic Piping and Tubing

SW GR None None

AMS

Ammonia System

Underground 1 - 2 CPVC SCH 80

Plastic Piping and Tubing

SW

1.5x Working

Pressure /

HH

None None Double

Containme nt

Provide 2” carrier piping

Aboveground 1 CPVC SCH 80 40_05_31.01 - Plastic Piping and Tubing

SW

1.5x Working

Pressure /

HH

None None

CS

Sodium Hydroxide

Underground 1/2 - 2 CPVC SCH 80

Plastic Piping and Tubing

SW

1.5x Working

Pressure /

HH

None None Double

Containme nt

Provide 2” carrier piping

Aboveground 1/2 CPVC SCH 80 40_05_31.01 - Plastic Piping and Tubing

SW

1.5x Working

Pressure /

HH

None None

CRI

Corrosion Inhibitor

40_05_00.01-17 204170-10 June 2026 – Addendum No. 4 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/40_05_00.01 (Bid Set)

Nominal Diameter (inches) Material

Pressure Class Special

Thickness Class

Schedule Wall Thickness

Pipe Spec.

Section

Joints/ Fittings

Test Pressure/ Method Lining Coating

Service Conditions Comments

Underground 1.5 - 4 CPVC SCH 80 40_05_31.01 - Plastic Piping and Tubing

SW

1.5x Working

Pressure /

HH

None None Double

Containme nt

Provide 4” carrier piping

Aboveground 1.5 CPVC SCH 80 40_05_31.01 - Plastic Piping and Tubing

SW

1.5x Working

Pressure /

HH

None None

Abbreviations:

1. The following abbreviations used in the column of test method refer to the respective methods as specified in Section 40_05_00.09 - Piping Systems Testing.

AM Air method GR Gravity method HH High head method LH Low head method SC Special case

2. Abbreviations to designate piping include the following:

AMS Ammonium Solution B&SP Bell and spigot BSP Black Steel Pipe CS Caustic Soda – Sodium Hydroxide CE Ceramic epoxy lining CI Cast iron CISP Cast iron soil pipe CL Class, followed by the designation CM Cement mortar CRI Corrosion Inhibitor CTP Coal tar pitch DIP Ductile iron piping EPP Epoxy polyurethane coating FL Flange

GA Gauge, preceded by the designation GE Grooved end joint GL Glass lined GSP Galvanized steel pipe MJ Mechanical joint MWA Mechanical wedge action NPS Nominal pipe size, followed by the number in inches psi pounds per square inch psig pounds per square inch gauge PE Polyethylene PEE Polyethylene encasement PTW Polyethylene tape wrap PVC Polyvinyl Chloride RPO Restrained push-on RSMJ Restrained Mechanical Joint SCH Schedule, followed by the designation SCRD Screwed-on SHC Sodium Hypochlorite SST Stainless steel SW Solvent welded VCP Vitrified clay piping WLD Weld

40_05_00.01-18 204170-10 June 2026 – Addendum No. 4 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/40_05_00.01 (Bid Set)

Carollo Engineers, Inc.
2026-06-29T18:32:13-0400
Anthony Ryan Horvat