26-8683_Bid_Schedule.xlsx
XLSX spreadsheet 15 KB Posted
- Attached to
- SCRWTP Lime Softening Improvements - Blend Tank
- Solicitation number
- 26-8683
- Issued by
- Collier County, Florida
About this file
This is a bid schedule form for Collier County, Florida's South County Regional Water Treatment Plant (SCRWTP) Lime Softening Improvements project, identified as Bid No. 26-8683. The project involves the construction of a blend tank system with eight primary work items: general conditions and mobilization/demobilization, demolition and disposal of the existing blend tank, demolition and disposal of chemical piping and analyzers, demolition and disposal of ductile iron piping, provision and installation of the new blend tank with piping and appurtenances, disinfection, commissioning, and record drawings. All items are listed as lump sum (LS) units with quantities of one each. Sealed bids are due by July 1, 2026 at 3:00 PM local time. A non-mandatory pre-bid meeting is scheduled for June 9, 2026 at 11:00 AM at the SCRWTP facility located at 3851 City Gate Drive, Naples, Florida 34117. Prospective bidders must register on the Collier County procurement portal at https://procurement.opengov.com/portal/collier-county-fl to access complete project documents.
Collier County has allocated a $300,000 Owner's Allowance to address unforeseen conditions and work directed by the County at its discretion. This allowance is not guaranteed as payment to the contractor and will only be expended through formal change orders with supporting documentation of time and materials. General conditions and mobilization costs are capped at 10 percent of the total bid amount. The bid schedule does not specify a maximum contract value or award timeline.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Form
| Vendor Name: | |||||
| 26-8683 Bid Schedule | |||||
| South County Regional Water Treatment Plant - Blend Tank Project | |||||
| Item No. | DESCRIPTION | UNIT | QTY | Unit Price | TOTAL AMOUNT |
| 1 | General Conditions, Mobilization & Demobilization (10% Max of the Total Bid Amount) | LS | 1 | $ - 0 | |
| 2 | Demolish and Dispose of Existing Blend Tank | LS | 1 | $ - 0 | |
| 3 | Demolish and Dispose of Chemical Piping, Analyzers, and Appurtenances | LS | 1 | $ - 0 | |
| 4 | Demolish and Dispose of Ductile Iron Piping and Appurtenances | LS | 1 | $ - 0 | |
| 5 | Provide and Install Blend Tank, Including Chemical and Conveyance Yard Piping and Appurtenances | LS | 1 | $ - 0 | |
| 6 | Disinfection | LS | 1 | $ - 0 | |
| 7 | Commissioning | LS | 1 | $ - 0 | |
| 8 | Record Drawings | LS | 1 | $ - 0 | |
| TOTAL BID AMOUNT | $ - 0 | ||||
| Staff has allocated $300,000 in Owner's Allowance - for Owners Use as Directed. This Allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of Owners Allowance will be made through Change Order with proper documentation of Time and Materials supporting the change. |