This is a technical specifications document prepared by Carollo Engineers for Collier County, Florida's South County Regional Water Treatment Plant (SCRWTP) Lime Softening Improvements - Blend Tank project (Bid No. 26-8683). The work consists of demolishing the existing chemical blend tank with all associated internal components and appurtenances, and providing and installing a new chemical blend tank with yard piping and related equipment. The project is located at SCRWTP, 3851 City Gate Dr, Naples, FL 34117. Sealed bids are due by July 1, 2026 at 3:00 PM local time, with a non-mandatory pre-bid meeting scheduled for June 9, 2026 at 11:00 AM at the project site. The County will furnish four ductile iron pipe items including a 36" MJ Class 153 DIP sleeve, one 36" standard length pipe segment, two 36" MJ Class 153 DIP tees, and two 36" diameter spools. Prospective bidders must register through the County's procurement portal at https://procurement.opengov.com/portal/collier-county-fl to access complete bid documents.
General contractor qualification requirements include completion of at least three projects within the past ten years with minimum contract values of $1,000,000 each, involving water or wastewater treatment plant work with chemical systems and reinforced concrete structures of similar size and complexity. All work must be performed while the SCRWTP continues normal operations as the County's sole source of drinking water, with strict adherence to the County's "Five N's" policy prohibiting offsite odors, light emissions, spills, fugitive dust emissions, and offsite noise. The contract includes significant operational constraints, including shutdowns limited to night work from 6:00 PM to 6:00 AM with a maximum duration of eight hours, and mandatory Maintenance of Plant Operations (MOPO) documentation and approval processes. All surfaces contacting potable water or treatment chemicals must be disinfected, and the contractor bears responsibility for any penalties imposed on the County for water quality violations caused by contractor actions. The specifications comprehensively detail work across multiple divisions including general requirements, concrete, metals, electrical, earthwork, utilities, process integration, and water equipment.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
301 NORTH CATTLEMEN ROAD, SUITE 302 SARASOTA, FLORIDA 34232 P 941-371-9832
pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/00_01_02
COLLIER COUNTY
SOUTH COUNTY REGIONAL WATER TREATMENT PLANT
LIME SOFTENING IMPROVEMENTS - BLEND TANK
CLIENT PROJECT NO. 70283.2
TECHNICAL SPECIFICATIONS
BID DOCUMENTS
MAY 2026
This item has been digitally signed and sealed by Anthony Ryan Horvat on the date adjacent to the seal.
Printed copies of this document are not considered signed and sealed and the signature must be verified on any electronic copies.
Carollo Engineers, Inc.
301 North Cattlemen Road Suite 302 Sarasota, Florida 941-371-9832 (Ph)
Vanessa Negron-Vieira on the date adjacent to the seal.
Printed copies of this document are not considered signed and sealed and the signature must be verified on any electronic copies.
Carollo Engineers, Inc.
301 North Cattlemen Road Suite 302 Sarasota, Florida 941-371-9832 (Ph)
Aleksandar D. Stojanovic on the date adjacent to the seal.
Printed copies of this document are not considered signed and sealed and the signature must be verified on any electronic copies.
ADS Engineering PLLC 4701 North Federal Hwy 390 Pompano Beach, FL 33064 954-471-2016 (Ph)
Table of Contents 00_01_10-1 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/00_01_10 (Bid Set)
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION
NO.
TITLE RESPONSIBLE
ENGINEER
01_11_00 SUMMARY OF WORK ANTHONY R.
HORVAT
01_14_00 WORK RESTRICTIONS ANTHONY R.
HORVAT
01_21_00 ALLOWANCES ANTHONY R.
HORVAT
01_26_00 CONTRACT MODIFICATION PROCEDURES ANTHONY R.
HORVAT
01_29_73 SCHEDULE OF VALUES ANTHONY R.
HORVAT
01_29_77 APPLICATIONS FOR PAYMENT ANTHONY R.
HORVAT
01_31_19 PROJECT MEETINGS ANTHONY R.
HORVAT
01_32_21 SCHEDULES AND REPORTS ANTHONY R.
HORVAT
01_32_34 PHOTOGRAPHIC AND VIDEOGRAPHIC
DOCUMENTATION
ANTHONY R.
HORVAT
01_33_00 SUBMITTAL PROCEDURES ANTHONY R.
HORVAT
01_35_21 SELECTIVE ALTERATIONS AND DEMOLITION ANTHONY R.
HORVAT
01_35_73 DELEGATED DESIGN PROCEDURES ANTHONY R.
HORVAT
01_41_00 REGULATORY REQUIREMENTS ANTHONY R.
HORVAT
01_45_00 QUALITY CONTROL ANTHONY R.
HORVAT
01_56_17 EROSION AND SEDIMENT CONTROL ANTHONY R.
HORVAT
01_60_00 PRODUCT REQUIREMENTS ANTHONY R.
HORVAT
01_71_23 FIELD ENGINEERING ANTHONY R.
HORVAT
01_75_17 COMMISSIONING ANTHONY R.
HORVAT
01_75_18 DISINFECTION ANTHONY R.
HORVAT
01_75_19 WATER LEAKAGE TEST FOR CONCRETE
STRUCTURES
ANTHONY R.
HORVAT
00_01_10-2 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/00_01_10 (Bid Set)
01_77_00 CLOSEOUT PROCEDURES ANTHONY R.
01_78_24 OPERATION AND MAINTENANCE MANUALS ANTHONY R.
HORVAT
01_78_36 WARRANTIES AND BONDS ANTHONY R.
HORVAT
01_81_50 DESIGN CRITERIA ANTHONY R.
DIVISION 03 - CONCRETE
NO.
TITLE RESPONSIBLE
ENGINEER
03_11_07 CONCRETE FORMWORK VANESSA NEGRON-
VIEIRA
03_15_00 CONCRETE ACCESSORIES VANESSA NEGRON-
VIEIRA
03_15_14 HYDROPHILIC RUBBER WATERSTOP VANESSA NEGRON-
VIEIRA
03_20_00 CONCRETE REINFORCING VANESSA NEGRON-
VIEIRA
03_21_17 ADHESIVE-BONDED REINFORCING BARS AND
ALL THREAD RODS IN CONCRETE
VANESSA NEGRON-
VIEIRA
03_30_00 CAST-IN-PLACE CONCRETE VANESSA NEGRON-
VIEIRA
03_35_29 CONCRETE FINISHES VANESSA NEGRON-
VIEIRA
03_60_00 GROUTING VANESSA NEGRON-
VIEIRA
03_63_01 EPOXIES VANESSA NEGRON-
VIEIRA
DIVISION 05 - METALS
NO.
TITLE RESPONSIBLE
ENGINEER
05_05_24 MECHANICAL ANCHORING AND FASTENING TO
CONCRETE AND MASONRY
VANESSA NEGRON-
VIEIRA
05_50_00 METAL FABRICATIONS VANESSA NEGRON-
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
NO.
TITLE RESPONSIBLE
ENGINEER
07_11_00 DAMPPROOFING VANESSA NEGRON-
VIEIRA
07_16_17 CEMENTITIOUS CRYSTALLINE CONCRETE
WATERPROOFING
VANESSA NEGRON-
VIEIRA
07_92_00 JOINT SEALANTS VANESSA NEGRON-
00_01_10-3 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/00_01_10 (Bid Set)
DIVISION 08 - OPENINGS
NO.
TITLE RESPONSIBLE
ENGINEER
08_31_14 FLOOR ACCESS DOORS VANESSA NEGRON-
DIVISION 09 - FINISHES
NO.
TITLE RESPONSIBLE
ENGINEER
09_91_00 PAINTING VANESSA NEGRON-
VIEIRA
09_96_01 HIGH-PERFORMANCE COATINGS VANESSA NEGRON-
DIVISION 26 - ELECTRICAL
NO.
TITLE RESPONSIBLE
ENGINEER
26_05_02 BASIC ELECTRICAL REQUIREMENTS ALEKSANDAR D.
STOJANOVIC
26_05_04 BASIC ELECTRICAL MATERIALS AND METHODS ALEKSANDAR D.
STOJANOVIC
26_05_05 CONDUCTORS ALEKSANDAR D.
STOJANOVIC
26_05_26 GROUNDING ALEKSANDAR D.
STOJANOVIC
26_05_33 RACEWAYS ALEKSANDAR D.
STOJANOVIC
26_08_00 ELECTRICAL TESTING ALEKSANDAR D.
STOJANOVIC
26_20_00 ELECTRICAL MOTORS ALEKSANDAR D.
STOJANOVIC
DIVISION 31 - EARTHWORK
NO.
TITLE RESPONSIBLE
ENGINEER
31_00_00 EARTHWORK ANTHONY R.
HORVAT
31_05_15 SOILS AND AGGREGATES FOR EARTHWORK ANTHONY R.
HORVAT
31_10_00 SITE CLEARING ANTHONY R.
HORVAT
31_23_19 DEWATERING ANTHONY R.
HORVAT
31_23_35 TRENCHING ANTHONY R.
HORVAT
31_50_00 EXCAVATION SUPPORT AND PROTECTION ANTHONY R.
00_01_10-4 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/00_01_10 (Bid Set)
DIVISION 32 - EXTERIOR IMPROVEMENTS
NO.
TITLE RESPONSIBLE
ENGINEER
32_92_23 SODDING ANTHONY R.
DIVISION 33 - UTILITIES
NO.
TITLE RESPONSIBLE
ENGINEER
33_05_12 TEMPORARY BYPASS PUMPING ANTHONY R.
DIVISION 40 - PROCESS INTEGRATION
NO.
TITLE RESPONSIBLE
ENGINEER
40_05_00.01 COMMON WORK RESULTS FOR GENERAL
PIPING
ANTHONY R.
HORVAT
40_05_00.03 PIPE IDENTIFICATION ANTHONY R.
HORVAT
40_05_00.09 PIPING SYSTEMS TESTING ANTHONY R.
HORVAT
40_05_06.01 PIPING SPECIALTIES ANTHONY R.
HORVAT
40_05_06.03 PIPE COUPLINGS ANTHONY R.
HORVAT
40_05_07.01 PIPE SUPPORTS ANTHONY R.
HORVAT
40_05_07.03 PREFORMED CHANNEL PIPE SUPPORT
SYSTEM
ANTHONY R.
HORVAT
40_05_07.05 NON-METALLIC PIPE SUPPORT SYSTEM ANTHONY R.
HORVAT
40_05_19.01 DUCTILE IRON PIPE: AWWA C151 ANTHONY R.
HORVAT
40_05_31.01 PLASTIC PIPING AND TUBING ANTHONY R.
HORVAT
40_05_51.01 COMMON WORK RESULTS FOR VALVES ANTHONY R.
HORVAT
40_05_57.13 MANUAL ACTUATORS ANTHONY R.
HORVAT
40_05_59.20 LOW-HEAD FABRICATED STAINLESS STEEL
SLIDE GATES
ANTHONY R.
HORVAT
40_05_63 BALL VALVES ANTHONY R.
HORVAT
40_05_65.01 GATE VALVES ANTHONY R.
HORVAT
40_90_00 INSTRUMENTATION AND CONTROL ALEKSANDAR D.
STOJANOVIC
40_91_00 INSTRUMENTATION AND CONTROL
COMPONENTS
ALEKSANDAR D.
STOJANOVIC
00_01_10-5 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/00_01_10 (Bid Set)
DIVISION 43 - PROCESS GAS AND LIQUID HANDLING, PURIFICATION, AND STORAGE
EQUIPMENT
SECTION
NO.
TITLE RESPONSIBLE
ENGINEER
43_23_13.45 HORIZONTAL SELF-PRIMING SAMPLE
CENTRIFUGAL PUMPS
ANTHONY R.
DIVISION 46 - WATER AND WASTEWATER EQUIPMENT
NO.
TITLE RESPONSIBLE
ENGINEER
46_05_10 COMMON WORK RESULTS FOR MECHANICAL
EQUIPMENT
ANTHONY R.
HORVAT
46_05_94 MECHANICAL EQUIPMENT TESTING ANTHONY R.
Summary of Work 01_11_00-1 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_11_00 (Bid Set)
SECTION 01_11_00
SUMMARY OF WORK
PART 1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Detailed description of the Work.
1.02 THE WORK
A. The Work consists of demolition and construction of the following items. All of which shall be constructed in accordance with the Drawings and Specifications:
1. Demolish and dispose of existing chemical blend tank including access hatches, internal baffles, weirs, stairway, ladders, handrails, coatings, liners, drains, penetrations, sample tabs, analyzers, chemical piping to the points of termination as indicated on the Drawings.
2. Provide and install new chemical blend tank, including yard piping and appurtenances.
B. The work to be performed under this Contract shall consist of furnishing all tools, equipment, materials, supplies, and manufactured articles and for furnishing all transportation and services, including fuel, power, water, and essential communications, and for the performance of all labor, work, or other operations required for the fulfillment of the Contract in strict accordance with the Contract Documents.
C. Implied and Normally Required Work: It is the intent of these Specifications to provide the County with complete operable systems, subsystems, and other items of Work. Any part or item of Work, which is reasonably implied or normally required to make each installation satisfactorily and completely operable, is deemed to be included in the Work and the Contract Amount. All miscellaneous appurtenances and other items of Work incidental to meeting the intent of these Specifications are included in the Work and the Contract Amount even though these appurtenances may not be specifically called for in these Specifications.
D. Quality of Work: Regard the apparent silence of the Contract Documents as to any detail, or the apparent omission from them of a detailed description concerning any Work to be done and materials to be furnished as meaning that only the best general practice is to prevail and that only materials and workmanship of the best quality are to be used. Interpretation of these specifications will be made upon this basis.
E. Except as specifically noted otherwise, provide and pay for:
1. Insurance and bonds.
2. Labor, materials, and equipment.
3. Tools, equipment, and machinery required for construction.
01_11_00-2 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_11_00 (Bid Set)
4. Utilities required for construction.
5. Temporary facilities including sheeting and shoring.
6. Traffic control and dust control measures.
7. Other facilities and services necessary for proper execution and completion of the Work.
1.03 LOCATION OF PROJECT
A. The Work is located at South County Regional Water Treatment Plant (SCRWTP) located at 3851 City Gate Dr, Naples, FL 34117.
1.04 COUNTY ASSIGNED SUBCONTRACTORS
A. There are no County-assigned Subcontractors.
1.05 COUNTY FURNISHED EQUIPMENT
A. The County will furnish the following items for incorporation into the work. These items shall be utilized to the maximum extent possible prior to procuring new piping or materials. Any item that is not included in this list, that is needed to complete construction, shall be provided by Contractor.
1. 36” MJ Class 153 DIP sleeve.
2. 36” standard length pipe segment (nominal 20-ft), Class 250 DIP, fastite joint.
3. Two 36" MJ Class 153 DIP tees.
4. Two 36” diameter by 1’-6” long flange by plain end DIP spools.
1.06 ACTIVITIES BY OTHERS
A. Activities by others which may affect performance of work include:
1. County will continuously operate the SCRWTP as a public water supply. As such, there will be ongoing operations and maintenance activities by either County forces or outside contracted firms. Contractor shall not interfere with the work of others in or near the work area.
2. The County will occupy premises during the entire period of construction in order to maintain normal operations. Cooperate with the County's Manager or designee in all construction operations to minimize conflict, and to facilitate County usage.
1.07 QUALIFICATION OF BIDDERS
A. A. Minimum qualification requirements for General Contractors shall include completion of at least 3 projects in the past ten (10) years, which meet the following criteria:
1. Minimum contract value of $1,000,000.
2. Water or wastewater treatment plant projects. The scope of work for these reference projects shall include either water and/or wastewater chemical systems including sampling and delivery, and reinforced concrete water, wastewater and/or infrastructure retaining structures of at least the size indicated on the drawings.
01_11_00-3 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_11_00 (Bid Set)
3. Retrofit, rehabilitation, or improvements completed to an operating water or wastewater facility without unreasonable disruptions to service due to Contractor’s actions or failure to act.
4. Work including water retaining structures, piping systems, site work, mechanical, and work of similar type, size, and complexity.
5. Projects completed and operating to the satisfaction of County (to be verified by calling references).
6. Projects completed on time.
7. Projects completed within budget without unreasonable claims or excessive change orders.
B. Any sub-contractors selected by Contractor shall have equivalent experience for the trade in which the work will be performed (exclusive of dollar value noted).
1.08 COORDINATION OF WORK
A. Contractor shall have a preconstruction video made that records the project sites (with the Engineer and County present) including all concrete and asphalt pavements, curb and gutter, fencing to remain, structures to be demolished, and existing structures and facilities that are to be modified.
1. The original and 2 copies of the DVD shall be turned over to Engineer and
County prior to beginning construction activities.
2. The format of the video file on the DVD shall be 1 file that can be played on a desktop in the windows media player.
3. The video shall clearly identify existing site and structural conditions prior to construction.
1.09 CONTRACTOR'S USE OF SITE
A. Limit use of site and premises for work and storage to allow for the following:
1. Coordination of the Work under this Contract with the work of the other
Contractors where Work under this Contract encroaches on the Work of other Contractors.
2. County occupancy and access to operate existing facilities.
3. Coordination of site use with Engineer.
4. Responsibility for protection and safekeeping of products under this Contract.
5. Providing additional off-site storage at no additional cost to the County as needed.
1.10 COUNTY OCCUPANCY
A. The County will occupy premises during the entire period of construction in order to maintain normal operations. Cooperate with the County’s Manager or designee in all construction operations and minimize conflict, and to facilitate County’s usage.
B. Conduct operations with the least inconvenience to the general public.
PART 2 PRODUCTS (NOT USED)
01_11_00-4 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_11_00 (Bid Set)
PART 3 EXECUTION (NOT USED)
END OF SECTION
Work Restrictions 01_14_00-1 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
SECTION 01_14_00
WORK RESTRICTIONS
PART 1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Requirements for sequencing and scheduling the Work affected by existing site and facility, work restrictions, and coordination between construction operations and plant operations.
1.02 SUBMITTALS
A. Baseline Schedule with MOPO tasks.
B. Maintenance of Plant Operations (MOPO) Form.
C. Maintenance of Plant Operations (MOPO) Log.
D. Progress Schedule with MOPO tasks.
1.03 MAINTENANCE OF PLANT OPERATIONS (MOPO)
A. Comply with MOPO instructions as specified in Attachment A - Maintenance of Plant Operations (MOPO).
B. Prepare a MOPO for the following conditions:
1. Shutdowns, diversions, and tie-ins to the existing facility.
2. Process start-up activities.
3. Power interruption and tie-ins.
4. Switch over between temporary and permanent facilities, equipment, piping, and electrical and instrumentation systems.
5. Process constraints requiring interruption of operating processes or utilities.
C. Other Work not specifically listed may require MOPOs as determined necessary by the Contractor, Owner, or Engineer.
D. Submit Baseline Schedule as specified in Section 01_32_21 - Schedules and Reports with proposed MOPOs.
E. Submit MOPO Log at construction progress meetings as specified in Attachment E - Maintenance of Plant Operations (MOPO) Log.
F. No consideration will be given to claims of additional time and cost associated to preparing MOPOs required by the Owner and Engineer to complete this work in a manner that facilitates proper operation of the facility and compliance with effluent discharge criteria.
01_14_00-2 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
G. Where required to minimize treatment process interruptions while complying with specified constraints, provide temporary pumping, power, lighting, controls, instrumentation, and safety devices.
1.04 GENERAL CONSTRAINTS ON WORK AND SCHEDULING OF WORK
A. Plant access for the Contractor will be provided at the security gate located at the entrance of SCRWTP.
B. Perform abandoned pipe work as specified in Section 01_35_21 -Selective Alterations and Demolition.
C. Water projects:
1. The South County Regional Water Treatment Plant is the Owner’s sole source of drinking water.
2. Conduct Work and commissioning activities, as specified in Section 01_75_17
- Commissioning, such that the Owner’s ability to meet its customer’s demands for treated drinking water shall not be impaired or reduced in terms of the required quantity or quality of treated water.
a. Do not impair the operational capabilities of essential elements of the treatment process or reduce treatment capacity below levels sufficient to meet demands for water throughout the contract time.
b. The quantities of and quality of treated water required are described in this Section.
3. PCIS optimization and fine-tuning as specified in Section 01_75_17 - Commissioning.
4. The status of the treatment plant shall be defined as operational when the plant is capable of meeting the Owner’s customer’s demands for treated drinking water in terms of the required quantity or quality of treated water as defined in this Section.
D. Contractor shall adhere to the County’s “Five N’s,” which consist of:
1. No offsite odors,
2. No offsite light emissions,
3. No onsite or offsite spills (SSOs), and,
4. No fugitive-dust emissions.
5. No offsite noise.
1.05 COMPLIANCE WITH DRINKING WATER PERMIT
A. The existing facility is operating under the terms of a drinking water permit issued by the Florida Department of Environmental Protection.
1. This permit specifies the water quality limits that the plant must meet prior to conveyance of finished water.
2. A copy of the existing permit is on file for review at the SCRWTP.
B. Perform work in a manner that will not prevent the existing facility from achieving the finished water quality requirements established by regulations.
C. Bear the cost of penalties imposed on the Owner for water quality violations caused by actions of the Contractor.
01_14_00-3 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
D. Conduct the Work and provide temporary facilities required to keep the existing plant continuously operational.
E. Do not remove or demolish existing facilities required to keep the existing plant operational at the capacities specified until the existing facilities are replaced by temporary, new, or upgraded facilities or equipment.
1. Test replacement facilities to demonstrate operational success prior to removing or demolishing existing facilities.
F. Bear the cost of penalties imposed on the County for water quality violations caused by actions of the Contractor.
1.06 UTILITIES
A. Provide advance notice to and utilize services for location and marking of underground utilities operated by utility agencies other than the Owner.
1. Sunshine State One Call, at 1-800-432-4770.
2. Other locating service retained and paid by Contractor as required for the performance of the work.
B. Maintain electrical, telephone, water, gas, sanitary facilities, and other utilities within existing facilities in service. Provide temporary utilities when necessary.
C. New yard utilities were designed using existing facility drawings.
1. Field verification of utilities locations was not performed during design.
2. Services crossed or located nearby by new yard utilities may require relocation and possible shutdowns.
3. Pipe alignments as indicated on the Drawings.
1.07 WORK BY OTHERS
A. Where proper execution of the Work depends upon work by others, inspect and promptly report discrepancies and defects.
1.08 SHUTDOWN CONSTRAINTS
A. General shutdown constraints:
1. Execute the Work while the existing facility is in operation.
2. Some activities may be accomplished without a shutdown.
3. Apply to activities of construction regardless of process or work area.
4. Activities that disrupt plant or utilities operations must comply with these shutdown constraints.
5. Organize work to be completed in a minimum number of shutdowns.
6. Provide thorough advanced planning, including having required equipment, materials, and labor on hand at time of shutdown.
7. Shutdown MOPOs:
a. Advise the Engineer a minimum of 3 weeks prior to need for any complete or partial plant shutdown for tie-ins.
b. Prepare and submit MOPO to the Engineer for any complete or partial plant shutdown required a minimum of 2 weeks prior to the shutdown.
c. Shutdown restrictions are limited to night work from 6pm to 6am.
01_14_00-4 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
d. Owner’s written approval of MOPO is required prior to beginning Work.
8. Where required to minimize treatment process interruptions while complying with specified constraints, provide temporary pumping, power, lighting, controls, instrumentation, and safety devices.
9. Final determination of the permitting of shutdowns will be the sole judgment of the Owner.
10. Owner maintains the ability to abort on the day of the scheduled shutdown.
11. Unplanned shutdowns due to emergencies are not specified in this Section.
B. Unit process availability work limitations:
1. Shutdowns and tie-ins or other activities that disrupt plant operations are prohibited unless the following unit process availability conditions exist and unless otherwise approved in writing by the Owner and Engineer.
2. At a minimum, the following facilities must be in service in order to proceed with a scheduled shutdown.
a. The reverse osmosis treatment system.
b. Finished water storage tanks.
c. All associated chemical storage and feed systems necessary to operate the reverse osmosis treatment system including subsequential disinfection.
C. Process, electrical and instrumentation - tie-in shutdowns:
1. Maximum shutdown duration: 8 hours.
1.09 WORK RESTRICTIONS
A. Provide safe, continuous access to process control equipment for plant operations and maintenance personnel.
B. Piping:
1. Provide temporary piping during construction for existing and new equipment to maintain plant operation in service during construction.
1.10 WORK SEQUENCE
A. Contractor shall sequence the work to minimize disruption to the existing operation of facilities, keep plant drives accessible for personnel and fire access and chemical deliveries, and coordinate the following tasks along with all other activities required to complete the work indicated on the Drawings and Specifications:
1. It is necessary to keep both the lime softening treatment system and reverse osmosis systems in service throughout the duration of the project except for shutdown as requested to make tie-ins.
a. The 36” lime softening effluent piping shall be installed near the tie-point at the filter building to the temporary piping and including the isolation valve.
b. The 42” reverse osmosis permeate piping shall be installed from the temporary piping, including gate valve, up to the tee location at the identified tie-in.
c. All features shall be constructed up to the point of connection, but not making the connection, to existing process features.
01_14_00-5 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
d. Conduct pressure testing of each line as indicated in the pipe schedule.
Disinfect each respective line following successful pressure testing. If the segments for closure pieces exceed the limits for swab disinfection per AWWA C651, then portions of the piping shall be constructed and disinfected above grade for bacteriological testing and then installed.
e. A partial request for clearance will be prepared by the Engineer to submit to FDEP. Upon receipt of authorization to place components into service by FDEP, the shutdown to make the tie-in may be scheduled.
f. Conduct shutdown lasting no longer than 8 hours to make tie-in at filter building and reverse osmosis permeate piping. The tie-in work shall be completed within this period and have adequate on-site personnel to accommodate this (i.e. multiple crews if necessary). Contractor shall install a temporary restrained plug on the branch of the tee connection near the blend tank. Visual leakage testing will be performed prior to backfilling.
g. The piping, including temporary segment, will be placed into service.
2. Begin installation of the new blend tank, 42-inch effluent ductile iron piping
(blend tank finished water) and all chemical injection lines entering the blend tank or installed for injection on the below grading ductile iron piping as indicated on the drawings.
a. Complete leak testing and disinfection prior to Commissioning. This include leakage testing of the blend tank and all related piping. Leaks shall be repaired, as specified prior to the submission of the request for clearance to FDEP. The work will not be deemed complete if leaks remain.
b. Perform installation testing, functional testing and clean water facility testing. All work shall be deemed substantially complete such that the request for clearance to place components into service may be requested from FDEP by the Engineer.
c. Upon receipt of authorization to place components into service, perform process startup.
1) Initiate a shutdown not exceeding 8-hours to make final tie-in connection of the following. The tie-in work shall be completed within this period and have adequate on-site personnel to accommodate this (i.e. multiple crews if necessary):
a) Connect 42-inch ductile iron piping (blend tank finished water) to the tee connection at the transfer pumps suction piping.
Disconnect the existing blend tank effluent piping and install a plug in the branch of the new tee.
b) Install a cap or plug at the existing 42-inch ductile iron piping west of the tee connection of the reverse osmosis permeate line entering the existing blend tank.
c) Cap or plug the temporary bypassing line at the tee connections of the new 36-inch ductile iron piping and new 42-inch ductile iron piping (previously connecting the filter effluent line to the reverse osmosis line) and remove and dispose the temporary piping.
2) The new blend tank will be placed into service.
3. For any other item indicated in the Contract Documents, but not listed above, Contractor shall sequence construction to minimize impacts to the existing water treatment plant processes.
01_14_00-6 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
4. All surfaces that come into contact with potable water, or water being treated to become potable water, or chemicals used to treat the water, shall be disinfected.
5. Install the concrete sidewalk as indicated on the drawings.
6. Demolish the existing concrete blend tank.
PART 2 PRODUCTS (NOT USED)
01_14_00-7 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
ATTACHMENT A - MAINTENANCE OF PLANT OPERATIONS (MOPO)
01_14_00-8 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
MAINTENANCE OF PLANT OPERATIONS (MOPO)
Instructions and Forms
Definition and Purpose
Maintenance of Plant Operations (MOPO) is a detailed document submitted by the Contractor to request process shutdown(s), utility tie-in(s), work in areas that may risk unanticipated outages, or flow diversions to accommodate site construction activities during a project. Such activities may include (but are not limited to) new tie-ins to utilities or structures, mechanical modifications to process piping or equipment, demolition, bulkhead installation, and cleaning processes.
The MOPO provides a detailed plan to the Owner and Engineer that describes specific aspects of the work, including purpose, time of execution, and anticipated impacts on treatment processes. The MOPO also includes contingency measures and provisions for rapid closure in the event that shutdown or work progress difficulties are encountered. Information from relevant trades associated with the requested shutdown, diversion, or tie-in is also included.
The Owner should use the information within the MOPO to define operational procedures and methods to safely and successfully assist the Contractor.
MOPO Process Summary
WHO STEP TIMING
Contractor 1. Identify MOPOs needed on MOPO Log and Baseline Schedule
No later than 7 days prior to Preconstruction Scheduling Meeting
Contractor, Owner, Engineer
2. Pre-MOPO Meeting More than 28 days prior to work
Contractor 3. Submits MOPO No later than 28 days prior to work Owner 4. Reviews MOPO Owner 5. MOPO finalized No later than 7 days prior to work Contractor 6. Complete Readiness Checklist No later than 5 days prior to work Contractor 7. Complete Safety Checklist Immediately prior to commencing work Contractor 8. Complete Work Contractor 9. Update MOPO Log and Progress
Schedules Monthly
MOPO Process Detail
STEP 1. Identifies MOPOs needed on MOPO Log and Baseline Schedule.
Contractor submits a preliminary list of anticipated project MOPOs on MOPO Log. MOPOs identified but not limited to those shutdowns, diversions, or tie-ins described in the Contract Documents. Incorporate MOPOs as tasks in Baseline Schedule. Date scheduled MOPOs to coincide with the appropriate construction activities.
01_14_00-9 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
STEP 2. Pre-MOPO Meeting.
Contractor requests a Pre-MOPO Meeting with the Owner and Engineer to discuss the nature of the shutdown, diversion, or tie-in, and to gather the information necessary to complete the MOPO Form. The pre-MOPO meeting may be waived by the Owner or Engineer if the work is deemed to be minor.
STEP 3. Submits MOPO.
Contractor completes the MOPO Form and submits 3 copies for approval to the Owner’s Project Manager (OPM).
STEP 4. Reviews MOPO.
OPM distributes MOPO Form for review by the Owner’s Construction Coordinator, O&M Representative, and Engineer’s Project Representative. Review MOPO Form for completeness, accuracy, compliance with both the construction schedule, constraints defined in Contract Documents, and to ensure that the requested work does not negatively impact plant operations or other concurrent project activities. Additional information may be requested to better understand the nature of and method for completing the Work.
STEP 5. MOPO finalized.
Once the MOPO is agreed to by all parties, the MOPO will be finalized by signature. Copies are distributed to the Owner, Engineer, and Contractor.
STEP 6. Complete Readiness Checklist as specified in Attachment C - Readiness Checklist.
Contractor verifies everything is ready for the Work.
STEP 7. Complete Safety Checklist as specified in Attachment D - Safety Checklist.
Contractor ensures safety.
STEP 8. Complete Work.
Contractor completes Work.
STEP 9. Update MOPO Log and Progress Schedules.
Contractor updates MOPO Log weekly and distributes at the regularly scheduled construction progress meetings.
01_14_00-10 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
ATTACHMENT B - MAINTENANCE OF PLANT OPERATIONS (MOPO) FORM
01_14_00-11 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
MAINTENANCE OF
PLANT OPERATIONS (MOPO) FORM
Owner: Date:
Contractor: Carollo Project No.:
Project Name: Submittal No.:
Submittal Title: Spec/Drawing. Ref.:
MOPO #: TASK TITLE:
(Provide <10 word title)
SUBMITTAL DATE:
(No later than 28 days prior to work)
SCHEDULE OF WORK ACTIVITY:
START: (Date/Time) END: (Date/Time)
REQUESTOR:
PRIMARY POINT OF CONTACT: PHONE/PAGER:
SECONDARY POINT OF CONTACT: PHONE/PAGER:
NOTIFY: Control Room, Phone: Security, Phone:
BUILDING: LOCATION OF WORK FLOOR/LEVEL:
DESCRIPTION OF WORK: (Provide sufficient details on process isolation, work sequencing, and safety (i.e. control of significant hazards unique to the work) to demonstrate an understanding of the work and how it will be completed within the constraints, and its impact on the processes and facility.)
Task Summary:
Processes Affected:
Trades Affected:
WORK PLAN:
Work Sequencing:
Process Isolation:
Spill Prevention Plan:
Contingency Plans:
CRITICAL EQUIPMENT/TOOLS: (Pumps and discharge hoses with correct fittings, blind flanges and pipe plugs, no-hub fittings, properly sized electrical service components, generators, portable lighting, chlorine for potable water pipe breaks, etc.)
Acoustic Ceiling/or Walls Access Excavation Permit Lock Out/Tag Out Chemical Use Approval Fire Sprinkler Impairment Life Safety Systems Confined Space Permit Flammable Materials Roof Protocol Critical Lift Plan Flush/Discharge Work After Dark Energized Electrical Work High Pressure Test Elect. Panel Schedules Hot Work/Open Flame
01_14_00-12 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
EXISTING SERVICE(S) AT RISK:
Breathing Air Elect Normal Process Access Telephones Chemical Distribution Fire Protection Safety Showers UPS City Water HVAC SCADA VAX/DATA Communication Inert Gas Security Domestic Drain Instrument - Air Solvent Drain Elect-Bus Duct Life Safety System Specialty Gases Elect. Emergency Natural Gas Storm Drain
REVIEWER’S INSTRUCTIONS/COMMENTS:
PREJOB BRIEFING MUST BE COMPLETED PRIOR TO COMMENCING WORK:
Full Name (printed) Signature Phone Date
Submitted By
System Owner
Reviewer (if needed)
Reviewer (if needed)
Reviewer (if needed)
Reviewer (if needed)
01_14_00-13 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
ATTACHMENT C - READINESS CHECKLIST
01_14_00-14 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
READINESS CHECKLIST
(5 days prior to work)
Checklist provided as a guide but is not all inclusive.
1. Confirm all parts and materials are onsite:
2. Review work plan:
3. Review contingency plan:
01_14_00-15 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
ATTACHMENT D - SAFETY CHECKLIST
01_14_00-16 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
SAFETY CHECKLIST
(Just prior to commencing work)
Checklist provided as a guide but is not all inclusive.
1. Location awareness:
a. Emergency exits: _____________________________________________________
b. Emergency shower and eyewash: ________________________________________
c. Telephones and phone numbers: _________________________________________
d. Shut-off valve: ________________________________________________________
e. Electrical disconnects: _________________________________________________
2. Inspect work area:
a. Take time to survey the area you are working in. Ensure that what you want to do will work. Do you have enough clearance? Is your footing secure? Do you have adequate lighting and ventilation? Are surrounding utilities out of the way for you to perform your work?
3. SDS (Safety Data Sheets):
a. Understand the chemicals and substances in the area you are working in by reading the SDS.
4. Lockout/tagout procedure:
a. Lockout/tagout energy sources before beginning work.
b. Make sure all valves associated with the work are locked out and tagged out on each side of the penetration.
c. Make sure the lines are depressurized.
5. Overhead work:
a. Use appropriate personal protective equipment; i.e., safety harness, lifeline, etc.
b. Select appropriate tie-off points; i.e., structurally adequate, not a pipe or conduit, etc.
c. Spotter assigned and in position.
d. Pipe rack access; i.e., check design capacity, protective decking or scaffolding in place, exposed valves or electrical switches identified and protected.
6. Safety equipment:
a. Shepherd’s hook.
b. ARC flash protection.
c. Fire extinguisher.
d. Other: ______________________________________________________________
7. Accidents:
a. Should accidents occur, do not shut off and do not attempt to correct the situation unless you are absolutely positive that your action will correct the problem and not adversely affect other people or equipment.
8. Review process start-up documents:
a. In the event the system is shutdown, the Control Center should have a working knowledge of the process start-up procedures in order to deal effectively with unforeseen events.
9. Evacuation procedures:
a. Do not obstruct evacuation routes.
b. Take time to survey the area for evacuation routes.
01_14_00-17 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
ATTACHMENT E - MAINTENANCE OF PLANT OPERATIONS (MOPO) LOG
01_14_00-18 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_14_00 (Bid Set)
MAINTENANCE OF PLANT OPERATIONS (MOPO) LOG
Sample
MOPO
Number Task Title
Date Requested
Date Approved
Date Work Planned
Work Completed (Yes/No)
Allowances 01_21_00-1 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_21_00 (Bid Set)
SECTION 01_21_00
ALLOWANCES
PART 1 GENERAL
1.01 SUMMARY
A. Section includes:
1. Listing of allowance items:
a. Related responsibilities of Contractor and procedures.
1.02 ALLOWANCE AMOUNTS
A. Contract Allowance - dollar value as indicated on the schedule of bid prices.
1.03 COSTS INCLUDED AND EXCLUDED IN ALLOWANCES
A. Costs included in allowances for furnishing products only:
1. Net cost of product.
2. Delivery and unloading at site.
3. Applicable taxes and fees.
B. Costs included in Contract Price, but not included in allowances for furnishing products only:
1. Handling at site, including uncrating and storage.
2. Protection from elements, theft, and damage.
3. Labor, installation, testing, and finishing.
4. Other expenses required to complete installation.
5. Overhead and profit.
C. Costs included in allowances for furnishing and installing products:
1. Net cost of product.
2. Delivery and unloading at site.
3. Applicable taxes.
4. Handling at site, including uncrating and storage.
5. Protection from elements and from damage.
6. Labor, installation, testing, and finishing.
7. Other expenses required to complete installation.
1.04 DUTIES OF CONTRACTOR IN PROVIDING PRODUCTS BY ALLOWANCE
A. Advise Engineer at least 60 days in advance of purchase date necessary to avoid impacts to Progress Schedule.
B. Obtain proposals from suppliers, including:
1. Quantity.
2. Complete description of product and services provided under allowance.
3. Unit cost.
Allowances 01_21_00-2 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_21_00 (Bid Set)
4. Total amount of purchase.
5. Taxes and delivery charges.
C. On notification of selection, enter into purchase agreement with designated supplier.
D. Arrange for delivery and unloading.
E. Install products in accordance with Contract Documents.
1.05 ADJUSTMENT OF COSTS
A. When actual cost is more or less than amount of allowance, Contract Price will be adjusted by Change Order.
1.06 ALLOWANCES
A. Owner’s Allowance:
1. The County has allocated $300,000 in Owner’s Allowance – for Owner’s Use as Directed. This Allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of Owner's Allowance will be made through Change Order with proper documentation of Time and Materials supporting the change.
Contract Modification Procedures 01_26_00-1 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_26_00 (Bid Set)
SECTION 01_26_00
CONTRACT MODIFICATION PROCEDURES
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Administrative and procedural requirements for executing a change in the
Work.
1.02 PRELIMINARY REQUIREMENTS
A. Change Order Cost Basis Summary Form:
1. Submit a sample to Engineer for review within 15 calendar days following
Notice to Proceed.
a. Items will be reviewed and their value, percentage, or calculation method mutually agreed to by the Contractor and County prior to executing a Change Order on the Project.
2. Used by the Contractor for pricing each Change Order required for additions, deletions, or revisions in the Work.
3. Include the following information:
a. Agreed upon markups, percentages, and procedures for calculating all surcharges, etc. associated with the Cost of the Change Order Work.
b. References for unit price information and special unit price information.
c. Attachments with the following information:
1) Certified labor rates breakdown.
2) Equipment rates.
3) Bond and insurance rates (PI&I).
1.03 REQUEST FOR INFORMATION OR INTERPRETATION (RFI)
A. Contractor may issue RFIs to request interpretation of the documents or to request for information that may be missing.
B. General Instructions:
1. Number RFIs consecutively.
a. Add a consecutive letter to the RFI number on modified submittals of the same RFI (i.e., RFI 4B).
2. Provide RFI for 1 item.
a. There may be exceptions when multiple items are so functionally related that expediency indicates review of the group of items as a whole.
b. RFIs with multiple items will be rejected without review.
3. Contractor sign and date RFIs indicating review and approval.
a. Contractor’s signature indicates that they have satisfied RFI review responsibilities and constitutes Contractor's written approval of RFI.
01_26_00-2 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_26_00 (Bid Set)
b. RFIs without Contractor's signature will be returned to the Contractor unreviewed. Subsequent submittal of this information will be counted as the first resubmittal.
C. Engineer will render a written clarification, interpretation, or decision on the issue submitted or initiate an amendment or supplement to the Contract within 21 days.
1. In the event the Contractor identifies an RFI as critical to the progress of the project, Engineer will make every effort to reduce the RFI response time.
1.04 PRELIMINARY PROCEDURES
A. County or Engineer may initiate changes by submitting a Request for Proposal (RFP) to Contractor including the following information:
1. Detailed description of the Change, Products, and location of the change in the
Project.
2. Supplementary or revised drawings or specifications.
3. Projected time span for making the change, and a specific statement if overtime work is authorized.
4. A specific period of time during which the requested price will be considered valid.
5. Such request is for information only, and is not an instruction to execute the changes, or to stop work in progress.
B. Contractor may initiate changes by submitting a Change Proposal to Engineer containing the following:
1. Description of proposed changes.
2. Reason for making changes.
3. Specific period of time during which requested price will be considered valid.
4. Effect on Total Contract Cost and/or Contract Time.
5. Documentation supporting any change in Total Contract Cost and/or Contract
Time, as appropriate.
1.05 WORK CHANGE DIRECTIVE AUTHORIZATION
A. In lieu of a Request for Proposal (RFP), Engineer may issue a Work Change Directive Authorization for Contractor to proceed with a change for subsequent inclusion in a Change Order.
B. Authorization will describe changes in the Work, both additions and deletions, with attachments of revised Contract Documents to define details of the change and will designate method of determining any change in the Contract Sum and/or the Contract Time, as appropriate.
C. County and Engineer will sign and date the Work Change Directive Authorization as authorization for the Contractor to proceed with the changes.
D. Contractor may sign and date the Work Change Directive Authorization to indicate agreement with the terms.
01_26_00-3 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_26_00 (Bid Set)
1.06 DOCUMENTATION OF CHANGE PROPOSALS
A. Change proposal:
1. Support with sufficient substantiating data to allow Engineer to evaluate the quotation.
a. Lump sum.
b. Unit prices: Use previously established unit prices.
c. Time-and-material/force account basis:
1) Name of the County’s authorized agent who ordered the work, and date of the order.
2) Dates and times work was performed, and by whom.
3) Time record, summary of hours worked, and hourly rates paid.
4) Receipts and invoices for:
a) Equipment used, listing dates and times of use.
b) Products used, listing of quantities.
c) Subcontracts.
2. Provide additional data to support time and cost computations:
a. Labor required.
b. Equipment required.
c. Products required:
1) Recommended source of purchase and unit cost.
2) Quantities required.
d. Taxes, insurance, and bonds.
e. Credit for work deleted from Contract, similarly documented.
f. Overhead and profit.
g. Justification for change to Contract Time.
1.07 PREPARATION OF CHANGE ORDERS AND FIELD ORDERS
A. Engineer will prepare each Change Order and Field Order.
B. Change Orders:
1. Will describe changes in the Work, both additions and deletions, with attachments of revised Contract Documents to define details of the change.
2. Will provide an accounting of the adjustment in the Contract Sum and in the
Contract Time.
3. Recommendation of Change Proposal is indicated by Engineer's signature.
4. Upon signature and execution by County, the Change Proposal becomes a
Change Order altering the Contract Time and Total Contract Cost, as indicated.
a. County’s Representative will transmit one signed copy each to Contractor and Engineer.
5. Contractor may only request payment for changes in the Work against an approved Change Order.
6. If either Engineer or County’s Representative disapproves the Change
Proposal, the reason for disapproval will be stated.
a. A request for a revised proposal or cancellation of the proposal will be shown.
01_26_00-4 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_26_00 (Bid Set)
C. Field Orders:
1. Order minor changes in the Work without changes in Contract Price or
Contract Times.
1.08 LUMP-SUM/FIXED PRICE CHANGE ORDER
A. Content of Change Orders will be based on, either:
1. Engineer’s Proposal Request and Contractor’s responsive Change Proposal as mutually agreed between County and Contractor.
2. Contractor’s Change Proposal for a change, as recommended by Engineer.
B. County and Engineer will sign and date the Change Order to establish the change in Contract Sum and in Contract Time and serve as authorization for the Contractor to proceed with the changes.
C. Contractor will sign and date the Change Order to indicate agreement with the terms.
1.09 UNIT PRICE CHANGE ORDER
A. Content of Change Orders will be based on, either:
1. Engineer’s definition of the scope of the required changes.
2. Contractor’s Change Proposal for a change, recommended by Engineer.
3. Survey of completed work.
B. The amounts of the unit prices to be:
1. Those stated in the Contract.
2. Those mutually agreed upon between County and Contractor.
C. When quantities of each of the items affected by the Change Order can be determined prior to start of the work:
1. County and Engineer will sign and date the Change Order as authorization for
Contractor to proceed with the changes.
2. Contractor will sign and date the Change Order to indicate agreement with the terms.
D. When quantities of the items cannot be determined prior to start of the work:
1. Engineer or County will issue a Work Change Directive authorization directing
Contractor to proceed with the change on the basis of unit prices, and will cite the applicable unit prices.
2. At completion of the change, Engineer will determine the cost of such work based on the unit prices and quantities used.
3. Contractor shall submit documentation to establish the number of units of each item and any claims for a change in Contract Time.
E. County and Engineer will sign and date the Change Order to establish the change in Contract Sum and in Contract Time and serve as authorization for the Contractor to proceed with the changes.
F. Contractor will sign and date the Change Order to indicate their agreement with the terms.
01_26_00-5 204170-10 April 2026 pw://Carollo/Documents/FL/Collier County/204170-100000/04 Design/04 Specs/Carollo/Blend Tank/01_26_00 (Bid Set)
1.10 TIME AND MATERIAL/FORCE ACCOUNT CHANGE ORDER/WORK CHANGE
DIRECTIVE AUTHORIZATION
A. Engineer will issue a Work Change Directive for the County’s signature authorizing Contractor to proceed with the changes.
B. At completion of the change, Contractor shall submit itemized accounting and supporting data as specified in this Section.
C. Engineer will determine the allowable cost of such work, as provided in the Contract Documents.
D. County and Engineer will sign and date the Change Order to establish the change in Contract Sum and in Contract Time and serve as authorization for the Contractor to proceed with the changes.
E. Contractor will sign and date the Change Order to indicate their agreement.
1.11 CORRELATION WITH CONTRACTOR’S SUBMITTALS
A. Periodically revise Schedule of Values and Applications for Payment forms to record each Change Order as a separate item of Work, and to record the adjusted Contract Sum.
B. Periodically revise the Construction Schedule to reflect each change…