This is a bid schedule document for Collier County, Florida, related to Bid No. 26-8678 for the Immokalee Road (C.R. 846) Shoulder Improvements project (SCOP 3), a grant-funded construction project. The project involves shoulder improvements along Immokalee Road and includes multiple construction line items with associated quantities. Key bid schedule items include mobilization, maintenance of traffic, sediment barrier installation (8,236 linear feet), standard clearing and grubbing, mailbox relocation (2 units), excavation (2,060 cubic yards), embankment work (3,184 cubic yards), type B stabilization (7,176 square yards), optional base groups totaling 6,528 square yards, asphalt milling (922 square yards), superpave asphalt concrete installation (245 tons), friction course asphalt (410 tons), mitered end sections (2 units), performance turf/sod (9,151 square yards), sign relocation, and pavement markings. Sealed bids must be received no later than December 14, 2026, at 3:00 p.m. local time. A non-mandatory pre-bid meeting is scheduled for November 16, 2026, at 9:00 a.m. at 3295 Tamiami Trail East Building C-2, Conference Room B, Naples, Florida. Prospective bidders must register through the Collier County procurement portal at https://procurement.opengov.com/portal/collier-county-fl.
The bid schedule contains 21 line items with all unit prices currently shown as $0.00, resulting in a total bid amount of $0.00, indicating this is a blank bid form requiring vendor completion. The project includes a Roadway Allowance of $50,000.00 that the owner has reserved for unforeseen conditions or work as directed by the owner; this allowance is not guaranteed as payment to the contractor and will only be expended through formal change order with supporting documentation of time and materials. The project is grant-funded, and vendors submitting incomplete bid schedules may be deemed non-responsive or non-responsible.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Immokalee SCOP 3
| Vendor Name: | |||||
| 26-8676 BID SCHEDULE | |||||
| Immokalee Road (C.R. 846) SCOP 3 Shoulder Improvements - Grant Funded | |||||
| FPID: 454028-1-54-01 | |||||
| *Vendor may be deemed non-responsive/non-responsible if an incomplete bid schedule is submitted. | |||||
| ITEM No. | DESCRIPTION | QUANTITY | UNIT | UNIT PRICE | TOTAL COST |
| 101-1 | MOBILIZATION | 1 | LS | $0.00 |
| 102-1 | MAINTENANCE OF TRAFFIC | 1 | LS | $0.00 |
| 104-10-3 | SEDIMENT BARRIER (TYPE III SILT FENCE) | 8,236 | LF | $0.00 |
| 110-1-1 | STANDARD CLEARING & GRUBBING | 1 | LS | $0.00 |
| 110-7-1 | MAILBOX (RELOCATE) | 2 | EA | $0.00 |
| 120-1 | EXCAVATION | 2,060 | CY | $0.00 |
| 120-6 | EMBANKMENT | 3,184 | CY | $0.00 |
| 160-4 | TYPE B STABILIZATION (3-FOOT SHOULDERS) | 7,176 | SY | $0.00 |
| 285-701 | OPTIONAL BASE GROUP 1 (4" THICK, BLACK BASE ONLY) | 4,500 | SY | $0.00 |
| 285-715 | OPTIONAL BASE GROUP 15 (9" THICK, BLACK BASE ONLY) | 2,028 | SY | $0.00 |
| 327-70-1 | MILLING EXISTING ASPHALT PAVEMENT (1" AVG. DEPTH) | 922 | SY | $0.00 |
| 334-1-12 | SUPERPAVE ASPH. CONC. TYPE SP-12.5 (TRAF. B)(2" THICK) | 245 | TN | $0.00 |
| 337-7-81 | ASPH. CONC. FRICTION COURSE TYPE FC-9.5 (TRAFFIC B) | 410 | TN | $0.00 |
| 430-982-129 | MITERED END SECTION, OPTIONAL ROUND, 24" CD | 2 | EA | $0.00 |
| 570-1-2 | PERFORMANCE TURF (SOD) | 9,151 | SY | $0.00 |
| 700-1-500 | SIGNS, SINGLE POLE (RELOCATE) | 1 | EA | $0.00 |
| 701-18-101 | PROFILED THERMO., STD.-ASPH. SURF., 6" WHITE SOLID | 2.00 | GM | $0.00 |
| 701-18-206 | PROFILED THERMO., STD.-ASPH. SURF., 6" YELLOW SOLID | 0.39 | GM | $0.00 |
| 701-18-221 | PROFILED THERMO., STD.-ASPH. SURF., 6" YELLOW SKIP (10'-30') | 0.78 | GM | $0.00 |
| 706-1-3 | PAVEMENT MARKERS, RETRO-REFLECTIVE | 159 | EA | $0.00 |
| 711-17 | REMOVE EXIST. PAVEMENT MARKINGS | 1 | LS | $0.00 |
| TOTAL BID: | $0.00 | |||
| Roadway Allowance - The owner has set aside an amount of $50,000.00 for their use. This Allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of the Owner's Allowance will be made through Change Order with proper documentation of Time and Materials that support the change. |