26-6023_Schedule STEM Demolition.pdf

PDF 95 KB Posted

Attached to
Bid for Demolition of Old STEM Bldg
Solicitation number
RFP CPS 260000002484 1
Issued by
Kalamazoo County, Michigan

About this file

This is a project schedule for the demolition of the STEM facility at Comstock Public Schools in Michigan, prepared by Miller Davis. The bid phase runs from August 3, 2026 through October 9, 2026, with key milestones including the posting of announcement on August 10-24, 2026, a pre-bid walk-through scheduled for August 20, 2026, the last date for requesting information on August 27, 2026, and the issuance of a final addendum on September 2, 2026. Bids are due on September 8, 2026, followed by post-bid interviews scheduled for September 9-14, 2026. The recommendation of award and board approval are expected September 15-18, 2026, with award and contracting activities concluding by October 9, 2026.

The actual demolition work is scheduled to commence on October 12, 2026 and continue through January 29, 2027, spanning 80 days. The demolition scope includes abatement (October 12-November 6, 2026), cut cap/utilities work (November 2-6, 2026), structural demolition and removal (November 9-December 11, 2026), excavation of footings and foundations (December 14, 2026-January 1, 2027), asphalt and parking removal (January 4-8, 2027), site fill and balancing (January 11-15, 2027), topsoil and seeding (January 18-22, 2027), and demobilization (January 25-29, 2027). The schedule reflects a comprehensive 114-day project timeline from bid phase through project completion.

View the file

Other files

File Type Posted
26-6023 STEM Demo - Advertisement to Bid 8.4.2026.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task

Mode

Name Duration Start Finish Predecessors

1 Bid Phase 50 days Mon 8/3/26 Fri 10/9/26

2 Prepare Front Ends Draft 10 days Mon 8/3/26 Fri 8/14/26

3 Review Documents 5 days Mon 8/3/26 Fri 8/7/26

4 Posting of Announcement (over two weekends before bid opening)

11 days Mon 8/10/26 Mon 8/24/26 3

5 Issue to Building Connected 0 days Fri 8/14/26 Fri 8/14/26 2

6 PreBid Walk Thru 0 days Thu 8/20/26 Thu 8/20/26 5FS+4 days

7 Last Date for RFI 0 days Thu 8/27/26 Thu 8/27/26 6FS+5 days

8 Issue Final Addendum 0 days Wed 9/2/26 Wed 9/2/26 7FS+4 days

9 Bids Due Date 0 days Tue 9/8/26 Tue 9/8/26 8FS+4 days

10 Post Bid Interviews 4 days Wed 9/9/26 Mon 9/14/26 9

11 Recommendation of Award and Board Approval4 days Tue 9/15/26 Fri 9/18/26 10

12 Award and Contracting 15 days Mon 9/21/26 Fri 10/9/26 11

14 Demolition of STEM Facility 80 days Mon 10/12/26 Fri 1/29/27

15 Abatement 20 days Mon 10/12/26 Fri 11/6/26 12

16 Cut Cap/Utilities 5 days Mon 11/2/26 Fri 11/6/26 15FS-5 days

17 Demo/remove the structure 25 days Mon 11/9/26 Fri 12/11/26 16

18 Excavate footings and foundations for removal15 days Mon 12/14/26 Fri 1/1/27 17

19 Asphalt/Parking Removal 5 days Mon 1/4/27 Fri 1/8/27 18

20 Fill/Balance Site 5 days Mon 1/11/27 Fri 1/15/27 19

21 Topsoil & Seed 5 days Mon 1/18/27 Fri 1/22/27 20

22 Demobilize 5 days Mon 1/25/27 Fri 1/29/27 21

114 days

S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Aug 2, '26 Aug 9, '26 Aug 16, '26 Aug 23, '26 Aug 30, '26 Sep 6, '26 Sep 13, '26 Sep 20, '26 Sep 27, '26 Oct 4, '26 Oct 11, '26 Oct 18, '26 Oct 25, '26 Nov 1, '26 Nov 8, '26 Nov 15, '26 Nov 22, '26 Nov 29, '26 Dec 6, '26 Dec 13, '26 Dec 20, '26 Dec 27, '26 Jan 3, '27 Jan 10, '27 Jan 17, '27 Jan 24, '27 Jan 31, '27

Critical

Critical Split

Task

Split

Milestone

Slack

Slippage

Summary

Project Summary

Rolled Up Critical

Rolled Up Critical Split

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Comstock Public Schools STEM Academy Demolition Schedule

Tue 8/4/26

Miller Davis 26-6015

File details come from the government source that posted it. Updated .