About this file

This is a Public Construction Bond exhibit for the Bay County Board of County Commissioners, Florida, related to contract 26-55 for the Ira Hutchinson Seawall Replacement project. The bond document establishes the surety requirements for the selected contractor to perform construction work at Ira Hutchinson Park, which includes installing vinyl sheet piles with a concrete cap and constructing two new sets of stairs for water access. Electronic or sealed paper submissions must be received by 2:30 pm on Thursday, September 3, 2026, with public opening immediately following the deadline. Any submissions received after the specified deadline will not be considered.

The bond document outlines the contractor's obligations to perform work according to contract specifications, promptly pay all claimants supplying labor, materials, or supplies, and guarantee all work and materials for the time specified in the contract. The bond includes standard provisions for payment bond claims governed by Florida Statutes Section 255.05, with a 60-day limitation period for claimants to file suit. The document provides templates for notice of contest of claims, progress payment waivers, final payment waivers, and final lien releases that vendors must execute upon receiving payments. All vendors receiving final payment must agree to hold harmless and indemnification agreements and duty to pay defense costs as specified in the contract.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT 5

PUBLIC CONSTRUCTION BOND

Bond No. (enter bond number)

BY THIS BOND, We , as Principal and , a corporation, as Surety, are bound to the Bay County Board of County Commissioner, Bay County, FL, herein called Owner, in the sum of $ , for payment of which we bind ourselves, our heirs, personal representatives, successors, and assigns, jointly and severally.

THE CONDITION OF THIS BOND is that if Principal:

1. Performs the contract dated , , between Principal and Owner for construction of , the contract being made a part of this bond by reference, at the times and in the manner prescribed in the contract; and

2. Promptly makes payments to all claimants, as defined in Section 255.05(1), Florida Statutes, supplying Principal with labor, materials, or supplies, used directly or indirectly by Principal in the prosecution of the work provided for in the contract; and

3. Pays Owner all losses, damages, expenses, costs, and attorney’s fees, including appellate proceedings, that Owner sustains because of a default by Principal under the contract; and

4. Performs the guarantee of all work and materials furnished under the contract for the time specified in the contract, then this bond is void; otherwise it remains in full force.

Any action instituted by a claimant under this bond for payment must be in accordance with the notice and time limitation provisions in Section 255.05(2), Florida Statutes.

Any changes in or under the contract documents and compliance or noncompliance with any formalities connected with the contract or the changes does not affect Surety’s obligation under this bond.

DATED ON ,

(Name of Principal)

By (As Attorney in Fact)

(Name of Surety)

26-55 Ira Hutchinson Seawall Replacement 59 of 69 http://www.leg.state.fl.us/STATUTES/index.cfm?App_mode=Display_Statute&Search_String=&URL=0200-0299/0255/Sections/0255.05.html http://www.leg.state.fl.us/STATUTES/index.cfm?App_mode=Display_Statute&Search_String=&URL=0200-0299/0255/Sections/0255.05.html

NOTICE OF CONTEST OF CLAIM

AGAINST PAYMENT BOND

To: (Name and address of claimant)

You are notified that the undersigned contests your notice of nonpayment, dated , , and served on the undersigned on , , and that the time within which you may file suit to enforce your claim is limited to 60 days after the date of service of this notice.

Vendor:

By:

Printed Name:

Title:

Date:

26-55 Ira Hutchinson Seawall Replacement 60 of 69

WAIVER OF RIGHT TO CLAIM

AGAINST THE PAYMENT BOND

(PROGRESS PAYMENT)

The undersigned, in consideration of the sum of $ , hereby waives its right to claim against the payment bond for labor, services, or materials furnished through (insert date) to (insert the name of Vendor) on the job of Bay County Board of County Commissioners, for improvements to the following described project:

(Project Name)

This waiver does not cover any retention or any labor, services, or materials furnished after the date specified.

26-55 Ira Hutchinson Seawall Replacement 61 of 69

WAIVER OF RIGHT TO CLAIM

AGAINST THE PAYMENT BOND

(FINAL PAYMENT)

The undersigned, in consideration of the final payment in the amount of $ , hereby waives its right to claim against the payment bond for labor, services, or materials furnished to (insert the name of Vendor) on the job of Bay County Board of County Commissioners for improvements to the following described project:

(Project Name)

26-55 Ira Hutchinson Seawall Replacement 62 of 69

FINAL LIEN RELEASE

FINAL WAIVER OF CLAIMS AND LIENS AND RELEASE OF RIGHTS

Project Name:

Date: Contract Price:

Purchase Order Number:

The undersigned hereby acknowledges that the above Balance Due when paid represents payment in full for all labor, materials, etc., furnished by the below named Contractor or Vendor in connection with its work on the above Project in accordance with the Contract.

The Vendors warrants that they have already paid or will use final funds received from Final payment to promptly pay in full all laborers, materials, suppliers, subcontractors and etc., for all work to the above referenced project.

By signing and accepting Final payment the Vendor agrees to the Hold harmless and Indemnification Agreement and Duty to Pay Defense Costs and Expenses as per the contract.

VENDOR

By: ______________________________ (Authorized Representative)

Its: ______________________________

State of County of

This Contract was acknowledged and subscribed before me the undersigned notary this day of , , by , as of and with proper authority, and who is personally known by me or produced identification of

Notary Public

26-55 Ira Hutchinson Seawall Replacement 63 of 69

File details come from the government source that posted it. Updated .