26_52 REQUEST FOR QUOTE _CHILLER REPLACEMENT.pdf
PDF 270 KB Posted
- Attached to
- CHILLER REPLACEMENT
- Solicitation number
- PE-66061-NONST-2026-000000087
- Issued by
- Fulton County, Colquitt City, Georgia
About this file
This is a Request for Quote issued by the City of College Park, Georgia, Contracts and Procurement Department, for turnkey chiller replacement installation services. The solicitation seeks qualified contractors to furnish and install a complete chiller plant system, including two new centrifugal chillers (Trane or approved equivalent), associated mechanical equipment such as condenser and chilled water pumps, cooling tower components, piping and hydronic systems, electrical integration with variable frequency drives, a Trane Tracer-based Building Automation System, and a dual-zone refrigerant monitoring system with alarms. The project scope encompasses demolition and removal of existing chiller plant equipment, equipment installation and alignment, system pressure testing and flushing, control integration, refrigerant handling in compliance with EPA regulations, startup and commissioning with factory-authorized assistance, and comprehensive documentation including O&M manuals and owner training. Quotations must be submitted electronically through BidNet Direct no later than 3:00 p.m. on Thursday, May 14th, 2026. No pre-proposal conference has been scheduled.
Respondents must demonstrate experience with commercial HVAC and chiller installation projects of similar size and scope and possess all required licenses and insurance coverage. Insurance requirements include Workers' Compensation, Business Auto Policy ($500,000 minimum), Commercial General Liability ($1,000,000 per claim/$2,000,000 per occurrence), and Professional Liability ($1,000,000 minimum), with the City of College Park named as an additional insured on all applicable policies. Certificates of Insurance must be provided within ten days of Notice of Award and maintained throughout contract execution with thirty-day cancellation notice provisions. All work must comply with manufacturer specifications, applicable mechanical, electrical, and building codes, industry best practices, and OSHA safety standards. The City reserves the right to reject any or all quotations, eliminate non-qualified respondents, cancel the solicitation at any time without cause or prior notification, and incur no liability to contractors as a result of cancellation.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF COLLEGE PARK Contracts and Procurement Department Attention: Carl Hall, Purchasing Department
3667 Main Street. City Hall College Park, Georgia 30337
Email: Carlton.Hall@collegeparkga.gov Phone: (404)-767-1537ext. 1500
RE: REQUEST FOR QUOTE NO. 26-52
CHILLER REPLACEMENT
OBJECTIVE
PURPOSE
The purpose of this solicitation is to obtain qualified contractors to provide turnkey chiller installation services, including equipment, labor, materials, and all related work necessary for complete installation and operational functionality.
MINIMUM QUALIFICATIONS & GENERAL REQUIREMENTS
Respondents must demonstrate experience with commercial HVAC and chiller installation projects of similar size and scope and possess all required licenses and insurance coverage. The selected contractor shall provide all labor, materials, equipment, supervision, permits, and related services necessary for a complete turnkey chiller installation in accordance with applicable codes, manufacturer specifications, safety standards, and City requirements.
SCOPE of SERVICE
1. General Scope
Provide all labor, materials, equipment, supervision, engineering coordination, and incidentals necessary to furnish and install a complete, operational chiller plant system.
Work shall be executed as a fully coordinated turnkey installation, including demolition, replacement, integration, testing, and commissioning.
All work shall comply with:
• Manufacturer requirements (including Trane installation standards where applicable)
• Applicable mechanical, electrical, and building codes
• Industry best practices
2. Demolition, Removal & Disposal
Remove and properly dispose of existing chiller plant equipment, including:
• Existing chillers (2)
• Condenser water pumps and chilled water pumps
• Associated starters, VFDs, actuators, and controls
• Existing chiller plant control system
• Existing air compressor (if present)
• Chiller isolation and head pressure control devices
Contractor shall:
• Recover refrigerant per EPA regulations
• Disconnect and safely remove mechanical and electrical systems
• Provide rigging, cranes, and lifting operations
• Dispose of all equipment and refrigerants legally and responsibly
3. New Mechanical Equipment Installation
Furnish and install:
• (2) new centrifugal chillers (Trane or approved equal)
• Condenser water pumps (qty per design basis)
• Chilled water pumps (qty per design basis)
• Cooling tower fan motors and belts (as required)
• Heat exchanger cleaning and recommissioning (existing plate frame HX)
Include:
• Setting, alignment, and securing of equipment on existing or new pads
• Verification of service clearances
• Equipment pad modifications as required
• Minimum flow bypass provisions
4. Piping, Valves & Hydronic Systems
Provide complete chilled water and condenser water system modifications including:
• New and modified piping for chillers, pumps, cooling towers, and heat exchanger
• Condenser head pressure control valves
• Isolation valves for:
o Chillers o Cooling towers o Heat exchanger o Pumping systems
• Minimum flow bypass piping
• Pressure testing of all new and modified piping systems
• System flushing and preparation for startup
• Insulation replacement where removed or modified
5. Electrical Scope
Provide complete electrical integration including:
• New power feeds to all mechanical equipment
• Disconnect/reconnect of existing electrical services as required
• New or reused breakers as applicable
• Installation of:
o VFDs for chilled water pumps o VFDs for cooling tower fans (if applicable)
• Control wiring between equipment and BAS
• All conduit, wire, fusing, relays, and terminations required for a complete system
6. Controls / Building Automation System (BAS)
Provide a fully functional control system including integration of all chiller plant components.
System shall include a Trane Tracer-based BAS or approved equivalent:
• Central system controller with web interface
• Integration of:
o Chillers o Pumps o Cooling towers o Heat exchanger
• Control valves and end devices as required
• Monitoring of temperatures, pressures, and equipment status
• Alarms and safeties for system protection
• Outside air temperature/humidity monitoring
• Minimum flow bypass control logic
7. Refrigerant Monitoring & Safety Systems
Provide a dual-zone refrigerant monitoring system including:
• Sensors at each chiller
• Audible/visual alarms inside mechanical room
• Audible/visual alarms outside mechanical room
• Integration with BAS or standalone alarm system
• Testing and commissioning of all alarm functions
8. Start-Up, Testing & Commissioning
Provide complete system startup including:
• Factory-authorized startup assistance (Trane or equivalent)
• Functional performance testing
• Pressure testing of piping systems
• Verification of controls and interlocks
• Load testing under normal operating conditions
• Final system balancing and verification
9. Documentation & Closeout
Provide:
• Equipment submittals
• O&M manuals
• Startup reports
• Warranty documentation
• As-built documentation (if available)
• Owner training session
• Final site cleanup
10. Environmental & Regulatory Compliance
• EPA-compliant refrigerant handling and disposal
• Proper disposal of removed mechanical/electrical equipment
• Compliance with all federal, state, and local environmental requirements
11. Safety Requirements
All work shall comply with OSHA and site safety standards including:
• PPE requirements (hard hats, gloves, safety glasses, etc.)
• Lockout/Tagout procedures
• Rigging and lifting safety protocols
INSURANCE REQUIREMENTS
Within ten (10) days of Notice of Award, and at all times that this contract is in force, the contractor shall obtain, maintain, and furnish the City of College Park, Certificates of Insurance from licensed companies doing business in the State of Georgia and acceptable to the City of College Park covering:
1. Worker’s Compensation
In accordance with O.C.G.A. Title 34, Chapter 9, as amended
2. Business Auto Policy
- Not less than $500,000.00
3. Commercial General Liability -
Minimum $1,000,000.00/claim $2,000,000.00/occurrence for Personal Injury, Bodily Injury, and Property Damage Liability
4. Professional Liability
- Not less than $1,000,000.00/occurrence
Copies of these Certificates of Insurance shall be furnished to the City of College Park prior to execution of the contract. Such policies shall be non-cancellable except on a thirty-day (30) written notice to the City of College Park.
1. The CITY OF COLLEGE PARK (and any applicable Authority) will be shown as an additional insured on General Liability, Auto Liability, and Professional Liability policies and noted accordingly on the Certificate of Insurance.
2. The cancellation provision should provide 30 days’ notice of cancellation.
3. Certificate Holder shall read:
City of College Park, Ga.
3667 Main Street
College Park, Ga. 30337
Pre-Proposal Conference Not scheduled at this time
Submittal Instructions Bidders are required to submit all responses to this solicitation electronically through the designated procurement platform-BidNet Direct
If assistance is needed with registration, account access, or submission of documents, please contact BidNet Direct’s Support Team at 800-835-4603, ext. 2.
Bidders are responsible for ensuring that all required documents are fully uploaded and submitted prior to the solicitation deadline. Late or incomplete submissions may not be accepted. It is recommended that bidders allow sufficient time to complete the electronic submission process to avoid technical delays.
Right to Reject Quotations
The City reserves the right to accept or reject any or all written quotations received under this Request for Quotations, or to eliminate any or all Contractors Selected Provider responding to this Request for Quotations from further consideration for award, and to duly notify any such Selected Provider of the City’s determination in the manner deemed most convenient by the City.
The City reserves the right to reject any written quotations that are submitted by a Contractor Selected Provider using a form and/or format other than the form and/or format stipulated in the Scope of Work Scope of Services and/or provided by the City, or an application that is in any way or manner incomplete, illegible, irregular or non-compliant, and to duly notify any such Contractors Selected Provider of the City’s determination in the manner deemed most convenient by the City.
Right to Eliminate Non-Qualified Selected Provider from Award Consideration
The City reserves the right to eliminate from award consideration any or all Contractors Selected Provider who submit an incomplete and/or inadequate written quotation response or who are not responsive to any and/or all of the requirements stipulated in the attached Scope of Work, Scope of Services and to duly notify any such Contractors Selected Provider of the City’s determination in the manner the City deems most convenient.
Right to Cancel Request for Quotations
This Request for Quotations does not obligate the City to select a Contractor or Selected Provider and/or to procure and/or contract the Selected Provider for any goods and/or services whatsoever.
The City reserves the right to cancel this Request for Quotations, with or without substituting another Request for Quotations, and, if so desired, terminate the process at any time. Cancellation of this Request for Quotations may occur with or without cause or prior notification. Cancellation of this Request for Quotations, with or without substitution, shall not result in any liability to any Contractor Selected Provider for any reason whatsoever.
Event Time/Date Thursday, May 14th, 2026, no later than 3:00 p.m. Request for Quotes Due
| OBJECTIVE |
| MINIMUM QUALIFICATIONS & GENERAL REQUIREMENTS |
| Respondents must demonstrate experience with commercial HVAC and chiller installation projects of similar size and scope and possess all required licenses and insurance coverage. The selected contractor shall provide all labor, materials, equipment, s... |
| Submittal Instructions |
File details come from the government source that posted it. Updated .