26-06_Job_Walk_Handout.pptx
PPTX presentation 18 MB Posted
- Attached to
- Specification No. 26-06, C56195 2026 Levee Repairs - Colusa Basin Drain and Sacramento River
- Solicitation number
- 0000039533
- Issued by
- California
About this file
This is a Job Walk Handout presentation for Specification No. 26-06, Contract No. C51695, prepared by the California Department of Water Resources for the 2026 Levee Repairs project in the Colusa Basin Drain and Sacramento River areas spanning Colusa and Yolo Counties. The project encompasses two primary sites: Site 97, addressing waterside erosion along approximately 310 feet of riverbank, and Site 23-078, addressing landside erosion along approximately 450 feet of levee. Work activities include excavation and removal of failed embankment soils, installation of geotextile fabric, placement of launch rock and soil-filled rockfill, earthfill placement in benched lifts, surface treatments with native and agricultural topsoil, seeding and erosion control fabric installation, willow pole cuttings installation, tree protection and removal by certified arborists, Giant Garter Snake exclusion fencing, turbidity curtain installation for in-water work, and levee crown road resurfacing with aggregate base. The site inspection trip occurred on June 18, 2026. Written questions regarding plans and specifications must be submitted by June 26, 2026, which is five days prior to the bid opening date of July 1, 2026. The bid opening will occur from 12:00 p.m. to 2:00 p.m. at the California Natural Resources Headquarters, 715 P Street, Sacramento, California. The contract contains 36 bid items, and the contractor must begin work within 7 days of receiving the Notice to Begin Work, with completion of primary work required by November 30, 2026, and plant and seed establishment work completion required by May 31, 2027.
The estimated cost range is $1,800,000 to $2,500,000, with contract award based on the lowest responsive bid considering all incentives and bid preferences. Bid security of 10 percent of the bid amount is required in the form of a certified check, cash, or bidder's bond. The Department offers three incentive and preference options: a 3 percent Disabled Veteran Business Enterprise incentive (maximum $100,000) for bids meeting or exceeding 3 percent DVBE participation; a 5 percent small business preference (maximum $50,000) for certified small business bidders; and a 5 percent non-small business preference (maximum $50,000) for bidders committing to use at least 25 percent California-certified small business subcontractors or suppliers, with the combined amount of all incentives and preferences not exceeding $100,000. Bidders must be registered with the Department of Industrial Relations as contractors and subcontractors at time of bid submission and throughout construction, and safety prequalification forms must be received at least five days prior to the bid due date. Liquidated damages are assessed at $2,400 per day for failure to complete primary work by the specified deadline and $1,000 per day for failure to complete plant and seed establishment work by May 31, 2027. A Department Safety Engineer will be on-site during construction, and all personnel must complete Worker Environmental Awareness Program training. Environmental compliance requirements include adherence to permit conditions outlined in Appendix III, with in-water work restricted to August 1 through October 31 and terrestrial work restricted to May 1 through October 1.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Safety_Prequal_Package.pdf | ||
| 26-06_Information_Copy.pdf | ||
| 26-06_Notice_of_Inspection_Trip.pdf | ||
| 26-06_Notice_to_Contractors.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Specification No. 26-06 Contract No. C51695 2026 Levee Repairs - Colusa Basin Drain and Sacramento River Colusa and Yolo Counties Site Inspection Trip Presentation June 18, 2026
NEGATIVE SPACE
GOOD
CALIFORNIA DEPARTMENT OF WATER RESOURCES
Disclaimer Site inspection trip presentation and discussion are for information only.
The files shall not be used to prepare bids or for construction purposes. Location and extents of project features shall be based on the contract drawings and specifications.
The intent of the presentation is to help guide potential bidders through the drawings and specifications and spatially identify project components.
Discussion during the inspection trip doesn’t change the plans or specifications or is binding on the Department.
Any questions will need to be submitted in writing to doe_specs@water.ca.gov
CALIFORNIA DEPARTMENT OF WATER RESOURCES
Safety (Document 00701)
JHA for the Site Inspection Trip Inspection Injury & Illness Prevention Plan & Code of Safe Practices Pre-work Safety Plan Site Specific Emergency Response Plan Emergency Action Plan Fire Prevention and Control Plan Public Safety Job Hazard Analysis Environmental Hazards Trenching & Excavation Hazardous Material Others as referenced in the Specification.
Some submittals required 15 days prior to mobilization.
Plans & Specification Plans and Specifications available at the Department website:
https://cosmos.water.ca.gov/
Contact doe_specs@water.ca.gov for login information.
Cal-eProcure https://caleprocure.ca.gov/
Questions on Plans &Specification Email doe_specs@water.ca.gov
Only written responses to the questions submitted are contractually binding.
Per Document 00002 – Notice to Contractors, Paragraph 2, Questions or requests for clarification of the drawings or specifications shall be made in writing at least 5 days (June 26, 2026) before the bid opening date (July 1, 2026).
Responses is provided with either an Addendum – modifying the contract; or Information Letter to all Plan Holders.
All Addenda must be acknowledged with the bid form.
Prequalification – Document 00040 Department of Industrial Relations (DIR) Registered Contractors and Subcontractors at time of bid submission and throughout construction.
Safety: Required to receive bid documents for the contract.
Safety Prequalification forms, must be received by the Department at least 5 days prior (June 26, 2026) to the bid due date .
Joint Venture: Contact doe_specs@water.ca.gov bidding requirements.
Bid Opening Sealed bids:
Bidders/Visitors shall allow sufficient time for checking in with Security upon entering the building. Bids will be accepted and timestamped in the main lobby of the California Natural Resources Headquarters.
| Bid Due Date: | July 1, 2026 |
| Time: | 12:00 pm – 2:00 pm |
| Location: | California Natural Resources Headquarters, 715 P Street, Sacramento, California, 95814 |
Bid Schedule – Document 00410
Complete all bid items
Write legibly and within the boxes/spaces provided.
Currently contains (36) Bid Items.
Initial to any changes to your bid.
Do not leave blank items.
Do not condition your bids or change the specification requirements.
Contracting Requirements Use Bidder’s Bond form – Document 00430.
Bid Security in the form of Certified Check, Cash, or Bidder’s Bond (10% of bid amount).
Do Not Use Bonding companies Bidder Bond form (will not conform to the State Contract Act requirements).
The Estimated Cost Range :
$1,800,000 - $2,500,000
Preferences & Incentives – Bid Comparison only Disabled Veteran Business Enterprise (DVBE) Incentive – Zero Percent Goal, however the Department has a 3% DVBE Incentive to bids that meet or exceed the 3% DVBE Participation. (Max. $100K)
Small Business Preference – 5% reduction in the bid amount, to the Certified Small Business bidder. (Max. $50K)
Non-Small Business Preference – 5% reduction in the bid amount, to bidders committing to use at least 25% CA Certified Small Business subcontractors or suppliers. (Max. $50K)
Combined amount of all incentives and preferences cannot exceed $100,000.
Contract Award is based on the Lowest Responsive Bid, considering all incentives and bid preferences.
Information Available – Document 00300
Department of Industrial Relations General Prevailing Wage Determinations.
Site Inspection Reports for both sites 23-078 and 97.
Historical Documents: https://ferix.water.ca.gov/lep/ Environmental Documents, Permits and References related to this project.
Geotechnical Investigation Report.
Specification 26-06, Job Walk Handout.
Time of Completion Pursuant to Document 00705 – Prosecution of Work, Paragraph 1.A, the Contractor shall begin Work, within
7 DAYS
from the date of receipt of Notice to Begin Work.
The Contractor shall complete all work, excluding the work specified in Section 32 90 20 – Plant and Seed Establishment before the expiration of November 30, 2026.
The Contractor shall complete the balance of the work specified in Section 32 90 20 – Plant and Seed Establishment, before the expiration of May 31, 2027.
Liquidated Damages – Section 01110
Liquidated damages for failure to complete the work specified in Paragraph 1.04 B within the time specified will be $2,400 per day.
Liquidated damages for failure to complete the work specified in Paragraph 1.04 C within the time specified will be $1,000 per day.
Project Safety
The Department will have a Safety Engineer on-site during construction efforts.
ALL staff on the job site, both Department and Contractor, have stop work authority.
The Contractor is expected adhere to all laws and regulations (CAL/OSHA, etc.).
The Department Safety Engineer and staff will assist with the ensuring all safety expectations are met, including CAL/OSHA standards, industry standards and Contractor’s safety procedures and policies.
Environmental Protection – Section 01 57 19 Environmental Speciation Overview
Former Environmental Spec 01570 (Environmental Protection) DWR now uses 6-digit spec numbers
Current Applicable Environmental sections 01 57 19: Temporary Environmental Controls 01 57 23: Temporary Storm Water Pollution Control 01 57 26: Temporary Fencing 01 57 39: Temporary Tree and Plant Protection 32 90 20: Plant and Seed Establishment
Site Specific Environmental Requirements
Sites 78 and 97 operate under different CEQA documents
Each Site has unique permit requirements
Refer to Permit tables (Appendix III) for complete permit obligations
Vegetation and Seeding Requirements
All disturbed areas must be seeded
At time of final landscape inspection, vegetation must meet:
80% minimum vegetative cover If cover is not met, the contractor is responsible for re-seeding at no cost to the Department
Site 97 requires willow pole cuttings to be installed
Site 97 has many mature trees and shrubs require protection (2 types of protection measures) All trimming, cutting, and removal must be preformed by a certified arborist
Environmental Compliance and Training
All personnel onsite must complete Worker Environmental Awareness Program (WEAP) training given by DWR prior to preforming work
Environmental monitors will be onsite throughout project activities to ensure compliance with:
Permit conditions Environmental protection measures Resource avoidance requirements
Environmental Measures
Work Windows In-Water work (August 1- October 31st) Terrestrial work (May 1st- October 1st)
GGS Exclusion Fencing is required
Turbidity Curtain is required for in water work
Site 97 Project Features
Waterside bank repair with launch rock and soil-filled rockfill.
Surface treatment including aggregate chinking, native topsoil, agricultural soil, erosion control fabric, seeding, and fiber rolls.
Willow pole cuttings.
Site 97 Cross Section
Site 23-078 Project Features
Site 23-078
Landside slope earthfill repair.
Surface treatment including native topsoil, agricultural soil, erosion control fabric, seeding, and fiber rolls.
Site 23-078 Cross Section
Project Locations – Area Map
Project Site Locations
Site 23-078 Site 97
Site 97 Summary of Work
The proposed repair addresses waterside erosion along approximately 310 feet of riverbank. The repair includes the following construction activities:
Tree protection and removal.
Installing a turbidity curtain for in-water work.
Excavating and removing failed embankment soils on the waterside slope.
Installing geotextile fabric along the excavated slope.
Placing launch rock from the base to the height in accordance with the lines and grades shown in the plans. Placing soil-filled rockfill above the launch rock to the top of the repair.
Applying surface treatment, including aggregate chinking on the launch rock; native and agricultural topsoil, seeding, and erosion control fabric on the soil-filled rockfill.
Installing willow cuttings.
Resurfacing the levee crown road with aggregate base.
Site 23-078 Summary of Work
The proposed repair addresses landside erosion along approximately 450 feet of levee. The repair includes the following construction activities:
Installing Giant Garter Snake fencing.
Excavating eroded and unstable soil material from the landside slope. The backslope will be regraded to the proposed design geometry.
Placing earthfill on top of the shaped backslope in benched lifts.
Applying surface treatment, including native and agricultural topsoil, seeding, and erosion control fabric.
Resurfacing the levee crown road with aggregate base.
Conclusion Thank you for participating in the Site Inspection trip.
Please submit any questions to doe_specs@water.ca.gov @water.ca.gov image1.png image2.png image3.png image4.jpeg image5.jpg image6.jpeg