26-051 Landing Blvd LIft Station Rehab ITB WW1901F Manual to post.pdf

PDF 9 MB Posted

Attached to
Landing Blvd Lift Station Rehab WW1901F
Solicitation number
26-051
Issued by
Williamson County, San Antonio City, Texas

About this file

Landing Blvd. Lift Station Rehabilitation ITB Summary

This is an Invitation to Bid (ITB) document issued by the City of League City, Texas for the rehabilitation of the Landing Blvd. Lift Station (Project WW1901F, Bid No. 26-051). The project encompasses comprehensive rehabilitation of an existing lift station wet well, including replacement of duplex submersible Flygt NP-3102 7.5 HP pumps, discharge piping, installation of a new access hatch with safety grate, relocation and improvement of electrical components, installation of a SCADA panel with pump control panel and auto-sensory controls, filling of the existing dry well with cement-stabilized sand, improvements to driveway access, site fencing replacement, and concrete paving work. The project also requires implementation of Storm Water Pollution Prevention Measures (SWPPP) throughout construction and coordination with a SCADA consultant (Badger Meter). An optional pre-bid conference is scheduled for October 14, 2026 at 2:00 pm at the City Civic Center. The question cut-off date is 5:00 pm on October 21, 2026. Sealed bids must be received by 2:00 pm on November 3, 2026, with public opening at the Civic Center. The bid documents are available electronically at http://leaguecitytx.gov/bids.aspx and www.CivcastUSA.com at no charge. Contractors must indicate the number of calendar days required for substantial completion, with final completion to occur within 30 days thereafter.

The City will use $240 as the monetary value per calendar day for evaluation purposes under an "A+B" bidding structure, meaning the number of days bid will be multiplied by this amount and added to the base bid for award consideration. Liquidated damages of $240 per calendar day will apply for project delays beyond the contracted completion date. A bid bond equal to 5% of the maximum bid price, payable to the City of League City, must accompany each proposal. The successful bidder must furnish Performance, Payment, and One-Year Maintenance Bonds in the amount of 100% of the total contract price from a surety company with a minimum Best Key Rating of "B" or equivalent SBA eligibility and listing in U.S. Department of Treasury Circular 570. The contractor must perform a minimum of 40% of the overall contract value. Bid items include lump sum provisions for mobilization/demobilization (not to exceed 4% of contract), SWPPP implementation, traffic control, bypass pumping operations, wet well coating with Warren Environmental 301-14 High Performance Epoxy, and electrical improvements. Extra unit price items with minimum bid amounts are provided for excavation, skilled and unskilled labor, cement-stabilized sand backfill, bank sand, ductile iron fittings, and concrete work. The bid also includes a $25,871.00 fixed cost for SCADA programming by Badger Meter and a $50,000.00 cash allowance for miscellaneous items as directed by the City and Engineer of Record. All bidders must submit financial statements current within twelve months, a statement of qualifications with minimum ten references of similar projects, proof of insurance, and a completed HB 89 Verification Form and Conflict of Interest Questionnaire.

View the file

Other files

File Type Posted
1774449343583-e77a9fc9-800685_1765998048.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specifications and Contract Documents for

Landing Blvd. Lift Station Rehabilitation

WW1901F

Invitation to Bid (ITB) Bid No. 26-051

Oller Engineering, Inc.

TEXAS BOARD OF PROFESSIONAL ENGINEERS FIRM NO. F-2145

2600 South Shore Boulevard, Ste. 300A, Office 394 League City, TX 77573

10/1/2026

SPECIFICATIONS AND CONTRACT DOCUMENTS

for

Landing Blvd. Lift Station Rehabilitation

WW1901F

in

CITY OF LEAGUE CITY, TEXAS

Invitation to Bid (ITB) Bid No. 26-051

Oller Engineering, Inc.

TEXAS BOARD OF PROFESSIONAL ENGINEERS FIRM NO. F-2145

2600 South Shore Boulevard, Ste. 300A, Office 394 League City, TX 77573

City of League City

TC-1

TABLE OF CONTENTS

NO. OF

BIDDING REQUIREMENTS PAGES

Notice to Bidders

General Instructions to Bidders

Subcontractors and Major Suppliers Form

Bid Proposal

Bidders Certification and Addenda Acknowledgement………………………………………………1

Bid Bond

HB 89 Verification Form……………………………………………………………………………..1

Public Information Request Act Form………………………………………………………………..1

CONTRACT FORMS

Performance Bond

Payment Bond

Standard Form of Agreement

Conflict of Interest Questionnaire

One-Year Maintenance Bond

Contractor’s Insurance Certificate......................................................................Provided by Contractor

CONDITIONS OF THE CONTRACT

General Conditions of Agreement

Attachment No. 1 to General Conditions - Worker’s Compensation Insurance

Attachment No. 2 to General Conditions

Agreement for Final Payment and Contractor’s Sworn Release

Subcontractor/Materialman’s Full and Final Release and Waiver of Claims and Liens

Consent of Surety Company to Final Payment

TC-2

Attachment No. 3 - Wage Rates (Not Used)

Special Conditions

Badger Meter Quote No. 260406-0-RD-R2 Dated September 15, 2026

Rohn 25 G Antenna Tower Manufactures Specifications

00 00 00

TABLE OF CONTENTS

CITY OF LEAGUE CITY

Standard Construction Specification Documents December 2024

Landing Blvd. Lift Station Rehabilitation

WW1901F

SECTION 00 00 00

Division 00 - General Conditions

To be provided by Engineer of Record.

Division 01 - General Requirements

01 11 00 Summary of Work Revised 01 25 00 Substitution Procedures 01 29 76 Stored Materials (Materials on Hand) Revised 01 31 19 Preconstruction Meeting 01 31 20 Project Meetings 01 32 16 Construction Progress Schedule 01 32 33 Preconstruction Video 01 33 00 Submittal Procedures 01 35 13 Special Project Procedures 01 45 23 Testing and Inspection Services 01 50 00 Temporary Facilities and Controls 01 57 13 Storm Water Pollution Prevention 01 58 13 Temporary Project Signage 01 60 00 Product Requirements 01 66 00 Product Storage and Handling Requirements 01 70 00 Mobilization and Remobilization 01 71 23 Construction Staking and Survey 01 74 23 Cleaning 01 77 00 Warranty of Work 01 77 19 Closeout Requirements 01 78 23 Operation and Maintenance Data 01 78 39 Project Record Documents

CITY OF LEAGUE CITY

Standard Construction Specification Documents December 2024

TECHNICAL SPECIFICATIONS

Division 02 – Existing Conditions

02 41 12 Selective Site Demolition 02 41 13 Material Disposal 02 41 14 Utility Removal and Abandonment 02 41 15 Paving Removal

Division 03 – Concrete

03 00 00 Concrete and Concrete Reinforcing

03 30 00 Cast-in-Place Concrete 03 30 53 Concrete 03 34 13 Controlled Low Strength Material (CLSM) 03 80 00 Modifications to Existing Concrete Structures

Division 26 – Electrical (16010-16510) 16010 16110 16120 16130 16140 16170 16195 16441 16470 16477 16510

Basic Electrical Requirements Raceways Wires and Cables Boxes Wiring Devices Grounding and Bonding Electrical Identification Safety Switches Panelboards Fuses Lighting

Division 31 – Earthwork 31 10 00 Clearing and Grubbing 31 23 16 Unclassified Excavation 31 23 22 Cement Stabilized Sand 31 24 00 Embankment 31 25 14 Erosion and Sediment Control 31 34 19 Geosynthetic Soil Reinforcement 31 36 00 Gabions 31 37 00 Riprap

Division 32 – Exterior Improvements

32 01 17 Flexible Paving Repair

32 01 29 Concrete Repair 32 05 16 Aggregate for Exterior Improvements 32 11 23 Flexible Base Courses 32 11 29 Lime Treated Base Courses 32 11 33 Cement Treated Base Courses 32 12 16 Asphalt Paving 32 12 73 Asphalt Paving Crack Sealants 32 13 13 Concrete Paving 32 13 16 Decorative Concrete Paving 32 13 73 Concrete Paving Joint Sealants 32 16 00 Curbs, Gutters, Sidewalks, and Driveways

CITY OF LEAGUE CITY

Standard Construction Specification Documents December 2024

32 17 23 Pavement Markings 32 31 00 Fences and Gates 32 32 00 Retaining Walls

CITY OF LEAGUE CITY

Standard Construction Specification Documents December 2024

Division 33 – Utilities 33 01 12 Hydrostatic Testing and Disinfection 33 01 13 Cleaning and Approval 33 01 14 Sewer and Manhole Testing 33 01 15 Closed Circuit Television (CCTV) Inspection 33 01 16 Bypass Pumping of Existing Sewer Systems 33 04 10 Joint Bonding and Electrical Isolation 33 05 01 Location of Existing Utilities 33 05 06 Pipe Bedding and Backfill Material 33 05 19 Ductile Iron Pipe and Fittings 33 05 22 Nuts, Bolts, and Gaskets 33 05 24 Steel Pipe and Fittings 33 05 31 Polyvinyl Chloride (PVC) Pressure Pipe 33 05 32 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe 33 05 33 High Density Polyethylene (HDPE) Pipe and Fittings 33 05 36 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers 33 05 38 High Density Polyethylene (HDPE) Pipe 33 05 41 Cured in Place Pipe (CIPP) 33 05 50 Auger Boring 33 05 51 Metal Liner Plate 33 05 52 Jacking and Steel Casing Pipe 33 05 53 Hand Tunneling 33 05 54 Installation of Carrier Pipe in Casing or Metal Liner Plate 33 05 57 Water Line Lowering 33 05 60 Pre-Cast Concrete Manholes and Bases 33 05 62 Fiberglass Manholes 33 05 64 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to Grade 33 05 67 Frames, Rings, Covers, and Inflow Protection Devices 33 05 84 Gate Plug Valves (Revised) 33 05 85 Butterfly Valves 33 05 86 Combination Air Valve Assemblies for Sewer Force Mains (Revised) 33 05 91 Utility Markers, Locators, and Tracer Wire 33 14 12 Water Services and Service Connections 33 14 19 Fire Hydrants 33 14 25 Connections to Existing System (Revised) 33 14 30 Combination Air Valve Assemblies for Potable Water Systems (Revised) 33 31 16 Sanitary Sewer Service Connections and Service Line 33 31 30 33 32 13

Liners for Sanitary Sewer Structures (Revised) Lift Station

33 42 11 Stormwater Pipe and Boxes 33 42 23 Stormwater Headwalls, Wingwalls, and End Treatments 33 42 30 Stormwater Junction Boxes 33 42 31 Stormwater Drop Inlets 33 42 33 Stormwater Curb Inlets

CITY OF LEAGUE CITY

Standard Construction Specification Documents December 2024

Division 34 – Transportation

Division 41 – Bulk Material Processing Equipment

41 14 00 Batching Equipment

Appendix

END OF SECTION

NTB-1

NOTICE TO BIDDERS

Sealed bids must be submitted with, one marked original, and one marked copy, properly labeled and clearly marked with the Bid number and description, directed to City of League City, Office of the Purchasing Manager, 300 W. Walker St., League City, Texas 77573. Bids will be received until 2:00 pm, November 3, 2026, and then publicly opened and read aloud at the Civic Center, 400 W.

Walker St., League City, TX 77573. Bids received after that time will not be accepted. Bids sent via courier must be sealed in a separate envelope inside of the mailer. The Bidder shall furnish all labor, materials, and equipment and perform all work for the construction of the following project:

Landing Blvd. Lift Station Rehabilitation

CIP WW1901F

Bid #26-051

This project consists of the rehabilitation of an existing lift station wet well, including the replacement of pumps and discharge piping; new access hatch with safety grate; electrical components relocation and improvements; installation of SCADA panel, pump control panel, auto-sensory controls, floats and terminal boxes; filling in the existing dry well; improvements to driveway access to the lift station site; site fencing and paving; along with all related subsidiary and incidental components as shown in the Project Plan Set and contract documents. Storm Water Pollution Prevention Measures (SWPPP) shall be implemented throughout the construction to maintain compliance with applicable environmental and permit requirements. This project consists of temporarily taking Landing Blvd. Lift Station out of service and installing a by-pass pump around to enable the lift station to be rehabilitated. A new epoxy coating on the wet well along with filling in the dry pump valve box and placing aboveground valves and quick connect for vacuum truck. Existing concrete paving will be demolished and replaced with new concrete, new concrete drive approach, and new sidewalk to connect existing sidewalk from the north to the existing sidewalk to the south.

Bid documents may be obtained from http://leaguecitytx.gov/bids.aspx as well as www.CivcastUSA.com, search League City, Galveston County. Bidders must register on this website in order to view and/or download specifications, plans, and bid documents for this project. There is NO charge to view or download documents.

All inquiries about this bid or specifications must be made in writing to the League City Purchasing Department, at purchasing@leaguecitytx.gov. The City shall not be responsible for any verbal communication between any employee of the City and any potential bidder.

Only written requirements and qualifications will be addressed.

An optional pre-bid conference will be held October 14, 2026, at 2:00 pm, at the City of League City, Civic Center, 400 W. Walker St., League City, Texas 77573. Prospective Bidders are invited to attend. Failure to attend will not bar Bidders. The cutoff for questions will be 5:00 pm on Tuesday, October 21, 2026.

A cashier’s check or Certified Check from a Texas Bank, or acceptable Bid Bond from a reliable surety company authorized to do business in Texas, payable to the City of League City, in an amount not less than 5% of the maximum Bid price submitted, must accompany each Bid as a guarantee that, if awarded the contract, the bidder will, within 10 calendar days of Award of Contract, enter into a Contract and execute Bonds on the forms provided in the Contract Documents.

The Bidder’s deposit http://leaguecitytx.gov/bids.aspx http://www.civcastusa.com/ mailto:purchasing@leaguecitytx.gov

NTB-2

shall be forfeited and become the property of the OWNER in the event the Bidder neglects or refuses to enter into a contract and to furnish bonds acceptable to the OWNER within 10 calendar days after receipt of Notice to Award from the OWNER. The Bid Deposit of all except the three lowest Bidders will be returned within 10 calendar days after the opening of the bids. The Bid Deposit of the three lowest bidders will be returned within 7 working days after the executed contract and required Bonds have been fully approved by the OWNER.

The successful Bidder must furnish PERFORMANCE, PAYMENT, and MAINTENANCE BONDS on the forms furnished with the PROPOSAL, in the amount of 100% of the total contract price, from a surety company holding a permit from the State of Texas to act as surety. The surety company must have a minimum Best Key Rating of “B”, or if the surety company does not have such a rating due to the length of time it has existed, the surety company must be eligible to participate in the surety bond guarantee program of the Small Business Administration and must be an approved surety listed in the current U.S. Department of Treasury Circular 570, and must meet all of the related rules and regulations of the Treasury Department. The surety company and the agency or agent issuing the PAYMENT, PERFORMANCE, and MAINTENANCE BONDS must be authorized to issue and sign PAYMENT, PERFORMANCE, and MAINTENANCE BONDS in Texas in an amount equal to, or greater than, the total Contract price.

Upon consideration of the proposals the City Council plans to award a Contract; however, the City reserves the right to reject any and all bids, to waive any and all irregularities and technicalities, and to accept any bid which it deems advantageous to it. Each bidder agrees to waive any claim it has or may have against the Owner, the Engineer, and their respective employees, arising out of or in connection, with the administration, evaluation, or recommendation of any bid.

First Publication: October 2, 2026 Second Publication: October 9, 2026

GIB-1

GENERAL INSTRUCTION TO BIDDERS

1. SCOPE OF WORK

The work to be done under the contract documents is included in the bid proposal.

Landing Blvd. Lift Station Rehabilitation

(CIP PROJECT WW1901F)

Bid # (26-051)

The Contractor shall furnish all labor, superintendence, machinery, equipment and all materials necessary to complete this project in accordance with the contract documents.

2. COMPLIANCE WITH CONTRACT DOCUMENTS

All work covered by this Contract shall be done in accordance with the contract documents as described in the General Conditions.

All bidders shall be thoroughly familiar with all of the requirements set forth in the contract documents for the construction of this project and shall be responsible for the satisfactory completion of all work contemplated by said contract documents.

3. PLANS FOR USE BY BIDDERS

It is the intent of the Owner that all parties interested in submitting a bid on the project covered by the contract documents be given a reasonable opportunity to examine the documents and prepare a bid. The contract documents may be examined without charge as noted in the Notice to Bidders. Any party wishing to purchase a hard copy of the contract documents, including all plans and specifications, may do so with a request and payment of printing cost.

4. INTERPRETATION OF TECHNICAL SPECIFICATIONS, PLANS AND OTHER

DOCUMENTS

Bidders desiring additional information or clarification of technical specifications, plans or other documents must make written requests for such information to the Engineer as the Owner's representative by the cut-off date, and time, as indicated in the Notice to Bidders.

Answers to all such requests will be given in writing, in addendum form, to all bidders, and all addenda will be bound with and become a part of the contract documents. No written or oral explanation or interpretation except that which is provided by the addenda prepared by the Engineer will be considered official or binding. If the bidder should find discrepancies in or omissions from the technical specifications or plans, or should some doubt exist as to their meaning, the bidder shall notify the Engineer in writing so that a written addendum may be sent to all bidders. It is the responsibility of the bidders to know if they have received all such addenda. A complete file on all addenda issued will be maintained at the Engineer's office. In the event a bidder shall fail to seek clarification or interpretation of any part or

GIB-2

portions of the technical specifications, plans or other documents, such bidder shall be presumed to have full knowledge of the interpretation by the Engineer.

5. CONDITIONS OF WORK

Each bidder shall fully inform himself of the construction and working conditions under which the work will be performed. Bidders shall inspect the site and thoroughly familiarize themselves with the full bid documents including technical specifications and plans. Failure to do so will not relieve a successful bidder of his obligation to perform the work in accordance with contractual requirements. It is understood that the bid prices shall include the furnishing of all superintendence, labor, material, machinery, equipment, tools, transportation, services and other means of construction, including parts, incidentals and appurtenances, as necessary to complete the work in accordance with the contract documents, technical specifications and plans.

Bidder should carefully examine the bidding documents and the site to determine the actual conditions under which work will be done. Data in the bidding documents pertaining to existing conditions is for convenience only and does not supplant obtaining firsthand information at the site. Submission of a bid constitutes acceptance by the bidder of existing site conditions as part of the requirements of this work.

6. SUBSURFACE INFORMATION

Any information provided in regard to subsurface data, test borings, etc., is to be considered approximate. Soil reports, if any, that the Engineer has obtained for this project will be provided to the bidders for their use. The interpretation of soil information, results of soil borings, etc., is in no way guaranteed.

7. OPEN SPECIFICATIONS

Where equipment or materials are specified by a trade or brand name, it is not the intention of the Owner to discriminate against an equal product of another manufacturer but rather to set a definite standard of quality and/or performance and to establish an equal basis for the evaluation of bids. Where the words "equivalent" or "equal to" are used, they shall be understood to mean that the thing referred to shall be, in the opinion or judgment of the Engineer, the equivalent of or equal to the product or item specified by name. Unless otherwise specified, all materials shall be the best of their respective kinds and shall be, in all cases, fully equivalent to approved samples. Notwithstanding that the words "equivalent", "equal to" or other such expressions may be used in the specifications in connection with a material, manufactured article or process, the material, article or process specifically designated shall be used unless a substitute shall be approved in writing by the Engineer.

The Engineer has the right to require the use of such specifically designated materials, articles or processes.

GIB-3

8. PREPARATION OF BID PROPOSAL

Unless otherwise directed in the Notice to Bidders, bids shall be submitted in duplicate upon forms furnished by the Owner or copies thereof. All bids shall be prepared in compliance with the requirements of the Notice to Bidders, these instructions and any instructions printed on the prescribed forms. All blank spaces in the form shall be correctly filled in, and the bidder shall state the price(s) both in words and in numerals, for which he proposes to do the work contemplated or to furnish the materials required. Such prices shall be written in ink, distinctly and legibly, or typewritten. Amounts shall be extended and totaled, and no change shall be made in the phraseology of the form or of the bid items thereon. In case of discrepancy between the price written in words and the price written in figures, the price written in words shall govern. If optional items are shown on the bid form and the bidder elects not to bid on such optional items, then "No Bid" must be entered in the blank spaces provided. If a space is left blank on the bid form, the Owner will interpret such blank as a "No Bid".

The bidder must sign the bid proposal in ink in the space provided on the bid form; unsigned bids will not be accepted. If the proposal is submitted by an individual, his name must be signed by him or his duly authorized agent. A bid submitted by a sole proprietorship must be signed by the proprietor and must clearly set out the name under which the proprietor is conducting business. If the proposal is submitted by a firm, association or partnership, then the name and address of the firm, association or partnership must be shown together with the name and address of each member, and the proposal must be signed by a member of the firm, association or partnership or other person duly authorized.

If the proposal is submitted by a company or corporation, the company or corporate name and business address, the name of the registered agent, the address of the registered office, and the names, addresses and offices of each corporate officer, must be given. Bids submitted by a corporation must be signed by an officer of the corporation having the authority to execute such documents for the corporation, which authority is granted either by the corporate charter, the by-laws of the corporation or a resolution of the board of directors of the corporation, and shall specify under what authority the proposal is signed; the proposal shall be attested to by the secretary or an assistant secretary of the corporation, and the corporate seal shall be affixed thereto.

Powers of attorney authorizing agents or others to sign proposals must be properly certified and must be in writing and submitted with the proposal.

Each bid proposal shall be enclosed in a sealed envelope and submitted in duplicate, addressed as specified in the Notice to Bidders and bearing the bidder's name and the notation "Bid Enclosed”

GIB-4

9. BID BOND REQUIRED

Each bidder is required to submit with each bid a cashier’s check or Certified Check from a Texas Bank, or acceptable Bid Bond from a reliable surety company authorized to do business in Texas, payable to the City of League City, in an amount not less than 5% of the maximum Bid price submitted, as a guarantee that, if awarded the contract, the bidder will, within 10 calendar days of Award of Contract, enter into a Contract and execute Bonds on the forms provided in the Contract Documents. The Bidder’s deposit shall be forfeited and become the property of the OWNER in the event the Bidder neglects or refuses to enter into a contract and to furnish bonds acceptable to the OWNER within 10 calendar days after receipt of Notice to Award from the OWNER. The Bid Deposit of all except the three lowest Bidders will be returned within 10 calendar days after the opening of the bids. The Bid Deposit of the three lowest bidders will be returned within 7 working days after the executed contract and required Bonds have been fully approved by the OWNER.

10. FINANCIAL STATEMENT

Each bid must be accompanied by a financial statement of the bidder as reflected by his most recently prepared statement; the financial statement submitted must be current and shall not have been prepared prior to twelve (12) months immediately preceding the date specified for receipt of bids. The financial statement shall be submitted in a sealed envelope, properly identified as to contents and project description. The bidder's financial statement will be examined only if the bid submitted is actively considered for award; otherwise, it will be returned unopened after the execution of the Contract.

11. DELIVERY OF BIDS

It is the bidder's responsibility to deliver his bid in accordance with the instructions contained in the Notice to Bidders. Bids dispatched but not received by the date and time specified will be returned unopened upon receipt.

The City will receive bids electronically through www.publicpurchase.com or hard copies delivered to Purchasing Department. Instructions for Public Purchase can be found on Attachment B. Hard copies must be submitted with one (1) marked original, one (1) marked copy properly labeled and clearly marked with the Bid Number, CIP Number, and description, directed to:

City of League City Purchasing Department

300 W. Walker St.

League City, Texas 77573

Monday – Thursday: 7:30 am to 5:30 pm Friday: 7:30 am to 12:00 pm

If the bid is submitted electronically through Public Purchase, a hard copy of the bid bond must be received to the Purchasing Department prior to the bid opening.

http://www.publicpurchase.com/

GIB-5

Bids sent via courier must be sealed in a separate envelope inside of the mailer. Mark envelope/package with Bid Number and name. The Bidder shall furnish all labor, materials, and equipment and perform all work for the construction of the following project:

Landing Blvd. Lift Station Rehabilitation

(CIP PROJECT WW1901F)

Bid # (26-051)

12. BID MODIFICATIONS

At any time prior to the deadline set for receipt of bids, a bid may be withdrawn and resubmitted by submitting a written request to do so to the person who holds the bid, but no proposal may be altered after the closing time set for receipt of bids. In addition, any bidder may modify his bid by telegraphic communication or by any available means of written or mechanically printed communication at any time prior to the scheduled closing time, provided such communication is received by the Owner at the City of League City’s Purchasing Office prior to the deadline set for receipt of bids and provided further that if written confirmation of the modification, over the actual signature of the bidder, has not been delivered into the hands of the Owner prior to the closing time, the Owner is satisfied that such written confirmation, over the actual signature of the bidder, was mailed prior to the closing time as determined from an examination of the postmark. If signed written confirmation is not received within two (2) days from the closing time, no consideration shall be given to such modification. Receipt of a bid modification by any other employee, office or division of the Owner shall not constitute receipt by the Owner, and it shall be the sole responsibility of the bidder to verify or confirm that any such modification has in fact been received by the City of League City’s Purchasing Office prior to the deadline.

13. WITHDRAWAL OF BID

At any time prior to the time set for opening of the bids, a bid proposal may be withdrawn by submitting a written request to do so to the person who holds the bid.

14. REJECTION OF IRREGULAR OR IMPROPER BID

Any bid which contains any omission, alteration, erasure, addition or change of any nature, or which does not include prices for each and every bid item (excluding optional items) may, at the option of Owner, be deemed irregular. In order for any such bid to be considered, any alteration, erasure or other change must be initialed by the bidder prior to submission of the bid. In addition, any bid in which the prices are obviously unbalanced or which fails in any manner to conform to the bidding procedures as set forth may be considered irregular. Any bid proposal which is deemed irregular may be rejected and returned to the bidder without being considered.

Further, any proposal containing any conditions which provide for changes in the stated bid price due to increases or decreases in the cost of materials, labor or other items required for the project will be rejected and returned to the bidder without being considered.

GIB-6

Failure to provide the required number of calendar days for project completion will result in disqualification of the bid.

15. OWNER’S RIGHT TO REQUIRE ADDITIONAL INFORMATION

The Owner reserves the right, after the bids have been opened and before the contract has been awarded, to conduct such investigations as the Owner deems necessary to assist in the evaluation of the bids and to establish the responsibility, qualifications and financial ability of bidders, proposed subcontractors, suppliers and other persons and organizations to perform the work in accordance with the Contract Documents; and to require of a bidder additional information to aid in the evaluation of the bid and the bidders qualifications including but not limited to the following information:

(a) The experience record of the bidder and key subcontractors, suppliers and other persons showing completed jobs of similar scope and work requirements to the one covered by the proposed Contract and all work in progress with bond amounts and percentage completed.

(b) A sworn statement of the current financial condition of the bidder, key subcontractors and suppliers,

(c) An equipment schedule.

16. AWARD OF CONTRACT

(a) Unless all bids are rejected, the Owner will award the Contract as promptly as possible, consistent with the time required for a thorough analysis of the bids submitted. However, the Owner reserves the right to delay award for ninety (90) days after receipt of bids. If no award is made within ninety (90) days after receipt of bids, a bidder may withdraw his bid without prejudice to himself by submitting a written request for its withdrawal to the person who holds the bid. The contract will be awarded to the lowest responsible, responsive bidder whose evaluation by Owner indicates to Owner that the award will be in the best interest of the project. The Contract will be awarded on the basis of all factors that are available to be judged by the Owner and deemed by the Owner to be of the greatest advantage to it, considering the type of work involved, the length of duration thereof, the elements of the bid, history and performance of bidders in previous jobs and other factors as shall be determined by the Owner. Each bidder agrees to waive any claim it has or may have against the Owner, the Engineer, and their respective employees, arising out of or in connection with the administration, evaluation, or recommendation of any bid. The Owner reserves the right to reject any or all bids and to waive bid irregularities as the interest of the Owner may require. Also, the Owner reserves the right to reject the bid of any bidder if the Owner believes that it would not be in the best interest of the Project to make an award to that bidder, whether because the bid is not responsive, or the bidder is unqualified or of doubtful financial ability or fails to meet any other pertinent standard or criteria established by the Owner. Discrepancies in the multiplication of units of Work and unit prices will be resolved in favor of the unit prices.

Discrepancies between the indicated sum of any column of figures and the correct sum there of will be resolved in favor of the correct sums.

GIB-7

The amount of experience on projects similar in type, size and complexity as this project which the bidders and key subcontractors have and the degree of success on such projects may affect the award.

It is the Owner’s desire that the successful bidder and his key subcontractors be qualified and experienced in providing successful projects; that such successful bidder and key subcontractors have recent successful experience on several projects of similar size and nature as this project.

(b) The City may not execute the contract until it has received from the Bidder a completed, signed, TEC Form 1295 complete with a certificate number assigned by the Texas Ethics Commission (“TEC”), pursuant to Texas Government Code § 2252.908 and the rules promulgated thereunder by the TEC. The Bidder understands that failure to provide said form complete with a certificate number assigned by the TEC will prohibit the City from executing the final contract.

17. CONTRACT SECURITY

When the Successful Bidder delivers the executed Standard Form of Agreement to Owner, it must be accompanied by the PERFORMANCE, PAYMENT, and MAINTENANCE BONDS required by the Contract Documents. Bonds may be on the forms provided herein or an equal form containing no substantive changes, as determined by Owner. Bonds must be in the amount of 100% of the total contract price, from a surety company holding a permit from the State of Texas to act as surety. The surety company must have a minimum Best Key Rating of “B”, or if the surety company does not have such a rating due to the length of time it has existed, the surety company must be eligible to participate in the surety bond guarantee program of the Small Business Administration and must be an approved surety listed in the current U.S. Department of Treasury Circular 570, and must meet all of the related rules and regulations of the Treasury Department. The surety company and the agency or agent issuing the PAYMENT, PERFORMANCE, and MAINTENANCE BONDS must be authorized to issue and sign PAYMENT, PERFORMANCE, and MAINTENANCE BONDS in Texas in an amount equal to, or greater than, the total Contract price.

18. BOUND COPIES OF CONTRACT DOCUMENTS

The Agreement, Bonds and all related contract documents will be prepared and signed in not less than five (5) multiple original counterparts. Each set of contract documents shall be bound (with binder bolts) and shall include the following:

(a) Notice to Bidders;

(b) General Instructions to Bidders.

(c) Subcontractors and Major Suppliers Form

(d) Bid Proposal.

(e) House Bill 89 Verification Document

(f) Public Information Act Form

(g) Performance, Payment and One Year Maintenance Bonds.

(h) Standard Form of Agreement.

GIB-8

(i) General Conditions of Agreements.

(j) Special Conditions.

(k) Technical Specifications (including plans and drawings),

(l) Insurance Certificates.

(m) All other documents made available to bidder for his inspection in accordance with the Notice to Bidders.

The Owner will furnish the Contractor with three (3) sets of conforming contract documents, technical specifications and plans free of charge. Additional sets, if needed, can be obtained from the ENGINEER at the amount indicated in the Notice to Bidders. Plans and specifications for use during construction will only be furnished directly to the Contractor.

The Contractor shall then distribute copies of plans and specifications to suppliers, subcontractors or others as required for proper prosecution of the work contemplated by the Contractor.

19. TEXAS STATE SALES TAX

This Contract is issued by an organization which qualifies for exemption provisions pursuant to provisions of Tex. Tax Code §§ 151.301, 151.307, 151.309 and 151.311.

The Contractor must obtain a limited sales, excise and use tax permit or exemption certificate which shall enable him to buy the materials to be incorporated into the work without paying the tax at the time of purchase.

20. INSURANCE

The Contractor shall not commence work under this Contract until he has obtained all insurance as required in the General Conditions of Agreement, set forth in the contract documents, from an underwriter authorized to do business in the State of Texas and satisfactory to the Owner. Proof of coverage shall be furnished to the Owner and written notice of cancellation or any material change shall be provided to the Owner not less than thirty (30) days in advance of cancellation or change. All policies shall contain an agreement on the part of the insurer waiving the right to subrogation.

The insurance certificates furnished shall name the Owner, the Engineer, their agents and employees, as an additional insured and shall further state that all subcontractors are named as additional insured or, in the alternative, shall be accompanied by a statement from the Contractor to the effect that no work on this particular project shall be subcontracted.

21. CONTRACTOR'S REPRESENTATIVE

The successful bidder shall be required to have a responsible local representative available at all times while the work is in progress under this Contract. The successful bidder shall be required to furnish the name, address and telephone number where such local representative may be reached during the time that the work contemplated by this Contract is in progress.

22. TIME AND ORDER FOR COMPLETION

GIB-9

The CONTRACTOR will determine the number of calendar days to achieve Substantial Completion of the Work and will indicate this in the Bid Proposal, including application of topsoil and seed mix, after the date when the Contract Time began, and 30 calendar days to achieve Final Completion and meet all requirements for final payment.

For projects with a requirement of CALENDAR DAYS TO COMPLETE PROJECT and/or TOTAL BID AMOUNT, the City will use the sum of $240 as the monetary value of a calendar day.

Bidders should be aware that the evaluation for the award may consider the number of days bid. The difference in the number of calendar days bid will be multiplied by the above stipulated calendar day value and added to each bidder’s base bid. This is also sometimes referred to as ‘A+B’ bidding.

Bidders should be aware that the OWNER expects timely completion of the contract within the timeframe indicated by the bidder in their bid. Consequently, bidders should be aware that the above stipulated value of a calendar day will be applied by the OWNER as liquidated damages for each calendar day the project is delayed in completion.

The CONTRACTOR will be permitted to prosecute the work in the order of his own choosing unless stated otherwise in the Contract Documents, provided, however, the OWNER reserves the right to require the CONTRACTOR to submit a progress schedule of the work contemplated by the contract documents. In the event the OWNER requires a progress schedule to be submitted and it is determined by the OWNER that the progress of the work is not in accordance with such schedule, the OWNER may direct the CONTRACTOR to take such action as the OWNER deems necessary to insure completion of the project within the time specified.

23. WORKING HOURS

All construction work under this contract shall be performed between the hours of 7:00 a.m.

and 6:00 p.m., Monday through Friday unless specific authorization is granted by the project representative after obtaining Owner’s concurrence, or unless extension of working hours is necessary either to avoid lengthy interruption of utility service to the Owner’s customers, or due to an emergency situation.

Construction work under this Contract requiring an on-site project representative will not be performed on weekends or holidays unless the following conditions exist:

(a) The project being constructed is essential to the Owner's ability to provide the necessary service to its citizens; or

(b) Delays in construction are due to factors outside the control of the Contractor. The Contractor is approaching the penalty provisions of the Contract and can show that he has made a diligent effort to complete the Contract within the allotted time.

GIB-10

Before construction work requiring an on-site project representative is to be performed on weekends or holidays, the Contractor must notify the Owner's representative not less than three (3) full working days prior to the weekend or holiday he desires to do work and obtain written permission from the Owner's representative to do such work. The final decision on whether to allow construction work requiring an on-site project representative on weekends or holidays will be made by the Owner's representative in coordination with the Owner.

When such work is permitted, Contractor shall credit the Owner $50.00/hour by change order for site representation services for work on weekends or Legal Holidays.

The Contractor will not be permitted to work on any Holidays observed by the City. The Contractor may request a list of the official City holidays at the pre-construction conference.

Construction work requiring an on-site project representative will be any work where excavation, installation of pipes, materials, backfill or paving surface material installation is occurring and any work where investigation processes or testing processes are occurring or are required.

In any event, if a condition should occur or arise at the site of this project or from the work being done under this Contract which is hazardous or dangerous to property or life, the Contractor shall immediately commence work, regardless of the day of the week or the time of day, to correct or alleviate such condition so that it is no longer dangerous to property or life.

24. MATERIALS AND WORKMANSHIP

The intent of these contract documents is that only materials and workmanship of the best quality and grade will be furnished. The fact that the specifications may fail to be sufficiently complete in some detail will not relieve the Contractor of full responsibility for providing materials of high quality and for protecting them adequately until completion of the project and acceptance by the Owner. The presence or absence of a representative of the Owner on the construction site will not relieve the Contractor of full responsibility for complying with this provision. The specifications for materials and methods set forth in the contract documents provide minimum standards of quality which the Owner believes necessary to procure a satisfactory project.

25. GUARANTEES

All equipment and materials incorporated in the project and all construction shall be guaranteed against defective materials and workmanship. Prior to final acceptance, the Contractor shall furnish the Owner with a Maintenance Bond which shall provide that the Contractor shall remedy any defects in the work, at no cost to the Owner, and pay for any and all damages of any nature whatsoever resulting from such defects when such defects appear as a result of defective materials or workmanship within one (1) year from the date of final acceptance of the work.

26. PROTECTION OF THE WORK

GIB-11

The Contractor shall be responsible for the care, preservation, conservation and protection of all materials, supplies, machinery, equipment, tools, apparatus, accessories, facilities and all means of construction, and any and all parts of the work, whether the Contractor has been paid, partially paid or not paid for such work until the date the Owner issues its certificate of completion to the Contractor.

27. PROTECTION OF SUBSURFACE LINES AND STRUCTURES

It shall be the Contractor's responsibility to prosecute the work contemplated by the contract documents in such a way as to exercise due care to locate and prevent damage to all underground pipelines, utility lines, conduits or other underground structures which might or could be damaged by Contractor during the construction of the project contemplated by these contract documents. The Owner will furnish Contractor with the approximate information of City owned utility lines of which it has knowledge. However, such fact shall not relieve the Contractor of his responsibilities aforementioned; the location and depth of utilities shown on any drawings must be regarded as approximate, and it shall be the responsibility of the Contractor to determine for himself the exact location and depth of any utilities which exist in the project site. All such underground lines or structures cut or damaged by Contractor during the prosecution of the work contemplated by this Contract shall be repaired immediately by Contractor, at Contractor's expense, to the satisfaction of the Owner.

28. BARRICADES AND SAFETY MEASURES

The Contractor shall, at his own expense, furnish and erect such barricades, fences, lights and danger signals, and shall take such other precautionary measures for the protection of persons, property and the work as may be necessary.

The Contractor will be held responsible for all damage to the work due to failure of barricades, signs and lights to protect it; and when damage is incurred, the damaged portion shall be immediately removed and replaced by Contractor at his own cost and expense. The Contractor's responsibility for maintenance of barricades, signs and lights shall not cease until the date of issuance to Contractor of the Owner's certificate of acceptance of the project.

The Contractor will be held responsible for all damage to the work which may occur prior to final acceptance by the Owner regardless of the adequacy of protective barricades and lighting, and when damage is incurred, the damaged portion shall be immediately removed and replaced by Contractor at his own cost and expense.

29. EXPLOSIVES

The use of explosives shall not be permitted.

30. PAYMENT OF EMPLOYEES

The Contractor and each of his subcontractors agree to pay all employees engaged in work on the project under this Contract in full (less mandatory legal deductions), and further agree

GIB-12

that no such employees shall look to the Owner for payment of wages or compensation earned by reason of such work.

31. PAYMENT TO CONTRACTOR

All payments due to Contractor shall be made in accordance with the provisions of the General Conditions of Agreement of the contract documents.

32. AFFIDAVITS OF BILLS PAID

The Owner reserves the right, prior to final acceptance of this project or with the project’s pay estimate submitted each month, to require the Contractor to execute an affidavit certifying that all bills for labor, materials and incidentals incurred in the construction of the improvements contemplated by the contract documents have been paid in full and that there are no claims pending of which the Contractor has been notified.

33. QUESTIONS

Submit questions about bidding documents to the Engineer. Inquiries are permitted until the cut-off date, and time, as indicated in the Notice to Bidders. Necessary replies will be issued to bidders of record as addenda, which become a part of the bidding documents. Oral instructions do not form a part of the bidding documents. Bidders should contact the Engineer not less than 48 hours before bid opening to secure any addenda that may affect bidding.

34. LIST OF SUBCONTRACTORS AND MAJOR SUPPLIERS

With the bid, submit a list of subcontractors for major portions of the work and major suppliers. Give the names and addresses of the selected subcontractors and major suppliers listed in the bid proposal. Include on the list all “local” subcontractors and major suppliers.

“Local” shall be defined as those subcontractors and major suppliers whose principal business location is in Galveston County. The “Subcontractors and Major Suppliers Form” is provided at the conclusion of the “General Instructions to Bidders” section and shall be attached to Bid.

35. STATEMENT OF QUALIFICATIONS

Each bid must be accompanied by a statement of the qualifications of the Bidder to properly execute the work. No bid will be considered unless such a statement is submitted. Include in the statement of qualifications a list of ten (10) references minimum. The references shall consist of projects of similar nature, cost of the project, Owner's name, Engineer or prime contact and telephone number. The statement of qualifications shall also include the following:

• Organization available for the work contemplated on this project:

- Available Manpower Description

- Available Equipment Description

GIB-13

• Equipment Resources

- Provide total list of firm’s equipment

The amount of experience on projects similar in type, size and complexity as this project which the bidders and key subcontractors have and the degree of success on such projects may affect the award.

It is the Owner’s desire that the successful bidder and his key subcontractors be qualified and experienced in providing successful projects; that such successful bidder and key subcontractors have recent successful experience on several projects of similar size and nature as this project.

36. SUPPLEMENTAL PAY ITEMS AND MINIMUM UNIT PRICE BID ITEMS

Approximate quantity and a minimum unit price have been established for certain supplemental items and for certain base bid items shown in the bid proposal section. The Contractor may not bid a unit price less than the minimum value; however, he may increase the minimum unit price. If no entry is made in the spaces provided, the minimum unit prices shown shall apply. The supplemental pay items are included to facilitate payment for changes and alterations that may be required to complete work. The actual work as provided by the General and Special Conditions of the Agreement and Technical Specifications and as shown on Plans is described in Proposal items other than supplemental pay items. When work covered by supplemental items is requested by the Contractor and approved by Owner, payment will be based on the quantity actually constructed and unit prices bid in Proposal.

37. PRE BID CONFERENCE

The pre-bid conference is not mandatory.

38. All Bidders are required to submit the following with their bid:

a) Completed Bid Cover Sheet

b) Bid Sheet

c) Bidder Certification and Addenda Acknowledgment, Addendum(s) if applicable

d) Financial Statements, last 12 months

e) Statement of Qualifications, to include references

f) Bid Bond

g) House Bill 89 Verification Document

h) Conflict of Interest Questionnaire

i) Public Information Act Form

j) List of Subcontractors and Major Suppliers Form

BIDS MAY BE SUBMITTED IN ONE OF THE FOLLOWING TWO FORMATS:

a.) Hard copy submission (include one original and one copy) b.) Electronic submission via Public Purchase

39. General Contractor must perform a minimum of 40 percent of the overall contract value.

40. DISCLOSURE OF INTERESTED PARTIES AFTER AWARD OF BID

GIB-14

In compliance with Texas Government Code § 2252.908, the winning bidder must submit a Disclosure of Interested Parties (Texas Ethics Commission Form 1295) to the City at the time of contract execution. Pursuant to the rules prescribed by the Texas Ethics Commission (TEC), Form 1295 must be completed online through the TEC’s website, where it will be assigned a certificate number. The winning bidder must print, sign, and provide to the City.

For purposes of completing the TEC Form 1295, the governmental entity’s name is City of League City; the contract ID number and description will be provided at award. Neither the City nor its consultants have the ability to verify the information included in Form 1295, and neither have an obligation nor undertake responsibility for advising any bidder with respect to the proper completion of the TEC Form 1295.

SUBCONTRACTORS AND MAJOR SUPPLIERS FORM

LIST OF SUBCONTRACTORS AND TYPE OF WORK TO BE PERFORMED:

1.

2.

3.

4.

LIST OF LOCAL SUBCONTRACTORS:

(PRINCIPAL BUSINESS LOCATION IN GALVESTON COUNTY)

1.

2.

3.

4.

LIST OF MAJOR SUPPLIERS:

1.

2.

3.

4.

LIST OF LOCAL MAJOR SUPPLIERS:

(PRINCIPAL BUSINESS LOCATION IN GALVESTON COUNTY)

1.

2.

3.

4.

Bid Coversheet Bid # 26-051

Name of Firm/Company

Agent’s Name (Please Print) Agent’s Title

Mailing Address City State Zip

Telephone Number Email Address

Authorized Signature Date

Bidder Submission Checklist

Bid submission package shall consist of the following:

� Bid Cover Sheet

� Proposal & Cost Sheet (If hard copy submitted: one marked original, one marked copy and two flash drives)

� List of Subcontractors and Major Suppliers

� Bidder Certification and Addendum Acknowledgment (If applicable)

� Bid Bond (If bid submitted electronically, hard copy delivered to Purchasing before bid deadline.)

� Financial Statements

� Statement of Qualifications

� House Bill 89

� Public Information Act Form � Conflict of Interest Questionnaire

� Federally Required Clauses (If applicable)

BP-1

BID PROPOSAL

BID FOR UNIT PRICE CONTRACT

DATE:_________________ __

Proposal of

(Hereinafter called "Bidder")

TO: THE HONORABLE MAYOR AND CITY COUNCIL…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .