26_05 HVAC Replacement at the Locust Grove Re.pdf
PDF 529 KB Posted
- Solicitation number
- PE-67500-NONST-2026-000000124
- Issued by
- Henry County, Georgia
About this file
Henry County, Georgia is soliciting competitive sealed bids for Bid #26-05, an HVAC Replacement project at the Locust Grove Recreation Center located at 10 Cleveland Street. The project involves removing and replacing multiple HVAC systems, including specific units such as a 7.5 Ton dual stage outdoor unit, multiple 5 Ton and 4 Ton condensers, and various furnaces. A mandatory pre-bid conference and site visit is scheduled for September 16, 2025, at 10:00 AM, and bids are due on October 7, 2025, at 3:00 PM. Bidders must have an unrestricted Georgia Warm Air License and propose HVAC equipment with a minimum 14.3 SEER2 rating, using only ICP equipment. The project requires compliance with current building/fire codes, proper refrigerant reclamation, and completion during normal business hours (Monday - Friday, 8:00 AM – 5:00 PM).
The bid includes specific requirements for line set sizing, flushing, and vacuum procedures, with a minimum one-year warranty on equipment and workmanship. Bidders must provide insurance coverage including workers' compensation, commercial general liability, automobile liability, and umbrella liability, with specific monetary limits outlined in the document. A 5% bid bond is required, and successful bidders will need to provide 100% performance and payment bonds. The county encourages participation from small, local, veteran-owned, Disadvantaged Business Enterprise (DBE), and female-owned businesses. Additional compliance requirements include E-Verify participation, Georgia Security and Immigration Compliance Act adherence, and a non-conflict of interest certification.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 1 of 26
*The posting of additional addenda may be required and it is the responsibility of the bidder to ensure that they review the
County’s website for any additional addenda, and that they submit acknowledgement of all applicable addenda (on the included form) with their solicitation. Bidders should not expect to be individually notified by Henry County.
Henry County
Purchasing Department 140 Henry Parkway, McDonough, GA 30253
Phone: 770-288-6027 Fax: 770-288-6047
Website: https://henrycountyga.gov
INVITATION TO BID
Sealed Envelope shall be marked with the following information:
Bid # 26-05
HVAC Replacement at the Locust Grove Recreation Center
Due Date and Time: October 7, 2025, 3:00 PM
SCHEDULE OF EVENTS FOR
BID # 26-05
A Mandatory Pre-Bid Conference and site visit has been scheduled 10:00 AM on September 16, 2025, at 10 Cleveland Street, Locust Grove, GA.
Attendance at the Pre-Bid Conference is mandatory for bidders responding to this proposal; bidders must attend.
10:00 AM
September 16, 2025
Deadline for requests for clarifications and questions. Any possible exceptions to the bid specifications and/or terms and conditions should be addressed during this phase. These requests will be answered in an addendum and must be submitted through the County’s eProcurement Portal at:
https://procurement.opengov.com/portal/henryga
3:00 PM
September 23, 2025
*Deadline for first addendum, if required, posted on Henry County’s eProcurement Portal at: https://procurement.opengov.com/portal/henryga
3:00 PM
September 30, 2025
Sealed bids will be accepted until the due date and time. Any late submittals will not be considered. Bids may be submitted by mail, common carrier or delivered in person. Electronic bids are to be submitted through the County’s eProcurement Portal at (https://procurement.opengov.com/portal/henryga)
3:00 PM
October 7, 2025
THIS FORM MUST BE SIGNED AND SUBMITTED TO BE CONSIDERED FOR AWARD
COMPANY NAME: DATE:
MAILING ADDRESS: PHONE:
CITY: FAX:
STATE: ZIP: SSN OR FEDERAL TAX ID:
EMAIL: TITLE OF AUTHORIZED REPRESENTATIVE:
PRINTED NAME: AUTHORIZED SIGNATURE:
https://procurement.opengov.com/portal/henryga https://procurement.opengov.com/portal/henryga
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 2 of 26
Bid # 26-05
TABLE OF CONTENTS Page
SECTION I – GENERAL OVERVIEW
A - PURPOSE 3
B - GENERAL INSTRUCTIONS, TERMS, AND CONDITIONS 4 - 12
SECTION II – SPECIFICATIONS
A – SCOPE OF WORK 13
B - INSURANCE REQUIREMENTS 14-15
C – BOND REQUIREMENTS 16
SECTION III - FORMS
STANDARD CONTRACT (SAMPLE) 17
BID BOND 18
BID AUTHORIZATION AFFIDAVIT 19
NON-CONFLICT OF INTEREST 20
REFERENCES 21
GA SECURITY & IMMIGRATION COMPLIANCE AFFIDAVIT & AGREEMENT 22
SUPPLIER INCLUSION PROGRAM 23
BID PRICE SHEET(S) 24
CHECKLIST FOR BID DOCUMENTS 25
SECTION IV – SEALED BID LABEL 26
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 3 of 26
SECTION I - GENERAL OVERVIEW
A. PURPOSE
The intent of this invitation is to obtain competitive sealed bids from qualified vendors for the removal and replacement of HVAC systems located at the Locust Grove Recreation Center. The Contractor shall furnish all labor, materials, equipment, and services required to fulfill the terms and conditions of this bid.
B. GENERAL INSTRUCTIONS, TERMS, AND CONDITIONS
1. Bids Submission
a. These instructions will bind bidders to terms and conditions herein set forth, except as specifically stated otherwise in special contract terms with any individual bid. These instructions are to be considered an integral part of the bid.
b. Electronic bids are to be submitted through the County’s eProcurement Portal at
(https://procurement.opengov.com/portal/henryga). Bids may also be submitted by mail, common carrier or delivered in person. If an electronic bid is submitted, a physical paper submittal in not necessary. Emailed or faxed bids will not be considered. It shall be the duty of each Bidder to ensure that their bid is delivered within the time and at the place prescribed in this document. Bids received prior to the time fixed in this bid document will be securely kept unopened. A date/time stamp will be affixed to the envelope/package immediately upon its arrival to the Purchasing
Department. Any bid received at the office designated in this document after the exact time and date specified, will not be considered. If a late bid is received via carrier, it will be marked “late bid” and will not be opened. If a late bid is hand delivered, it will be returned unopened to the presenter.
c. At the date and time specified for the opening of the bid, the bid shall be publicly opened and read aloud for the information of Bidders and others present.
d. The bid must be submitted in a sealed envelope/parcel on or before the date and time stated in this document and is to be mailed or delivered to:
Henry County Purchasing Department
140 Henry Parkway
McDonough, GA 30253
Bid #26-05
HVAC Replacement at the Locust Grove Recreation Center
e. The Submittal Checklist must be reviewed and the bidder is to comply with the order of the submittal of documents. This document along with the cover page (page 1) is to be included with the bid.
f. The following items are to be included if the bid is submitted by mail, common carrier or delivered in person:
• One (1) unbound clearly marked “Original,” of the bid documents,
• One (1) bound copy identical to the original bid documents, and
• One (1) digital version in PDF format on a USB flash drive identical to the original bid documents. The USB flash drive should be labeled with the bid number and bidder’s name.
g. All bids must be manually signed and filled out legibly (typewritten or printed in ink) with all changes or corrections initialed by the person signing the bid.
h. If descriptive literature is attached to the bid, your firm’s name must be on all sheets submitted.
i. Each bid submitted shall be deemed to have been made with full knowledge of all terms, conditions, and requirements contained in this Bid request. The failure or omission of any Bidder to examine any form, instrument or document shall in no way relieve any Bidder from obligations in respect to the bid submittal or the compliance of the terms, conditions and requirements of the
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 4 of 26 bid.
j. Individual contractors shall provide their Social Security number and proprietorships; partnerships and corporations shall provide their Federal Employer Identification number on page one of this bid documents and provide a completed W9 form to be submitted with the bid.
k. The authorized representative whose signature will appear on the bid submitted certifies that the
Bidder has carefully examined the instructions of this bid and the terms and specifications applicable to and made a part of this bid. The Bidder further certifies that the prices shown on the
Bid Price Submittal Form is in accordance with the conditions, terms and specifications of the bid and that any exception taken thereto may disqualify the bid.
l. Any documentation submitted with or in support of a bid or bid shall become subject to public inspection under the Georgia Open Records Act. Labeling such information “Confidential”, “Proprietary”, or in any other manner shall not protect this material from public inspection upon request. All records become subject to public inspection only after award of the contract or purchase order.
2. Preparation of Bids
a. Negligence on the part of the Bidder in preparing the bid confers no right for withdrawal or modification in any way after the deadline for the bid opening.
b. Unit price must be shown on the Bid Cost Submittal Form in this document. All bids should be tabulated, totaled and checked for accuracy. The unit price will prevail in case of errors.
c. All product, equipment, article or material must be new and unused or current production. No reconditioned or used item(s) will be accepted except as specifically requested herein. Units that are classified as prototype or discontinued models are not acceptable.
d. Samples of items, when required, must be submitted within the time specified and unless otherwise specified by the County, at no expense to the County. Unless otherwise specified, samples will be returned at the Bidder’s request and expense if items are not destroyed by testing.
e. Full identification of each item bid upon, including brand name, model, catalog number, etc., must be furnished to identify exactly what the Bidder is offering. Whenever an article or material is defined by describing a proprietary product or by using the name of a manufacturer, the term “or equal” if not inserted shall be implied. The specified article or material shall be understood as indicating the type, function, minimum standard of design, efficiency and quality desired and shall not be construed as to exclude other manufactured products of comparable quality, design and efficiency. In the event that any equivalent version is proposed, prospective Bidders are herewith advised that precise, adequate, and documented evidence of equivalency in performance, stability, and operational efficiency should be submitted with the bid for further consideration. Final determination of equivalency will be determined by Henry County.
3. Clarification and Communication to County Concerning Bid
a. From time to time, the Purchasing Department may have to release written changes to a solicitation. These formal written changes are called addendum or if multiple, Addenda. It is the ultimate responsibility of the Bidder to ensure that they have all applicable addenda prior to the bid submission. Therefore, we encourage all Bidders to frequently review the
County’s eProcurement portal at (https://procurement.opengov.com/portal/henryga). All addenda forms must be signed and submitted with the bid. Failure to respond and acknowledge any addenda or requests for clarification, even after the bid opening, shall result in a non-responsive bid.
b. The successful firm’s bid and all addenda will become a part of the agreement resulting from this document.
c. Bidders seeking an award of a Henry County contract shall not initiate or continue any verbal or written communication regarding a solicitation with any County officer, elected official, employee or other County representative without permission of the Purchasing Department between the date of the issuance of the solicitation and the date of the final contract award by the Board of
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 5 of 26
Commissioners. Violations will be reviewed by the Purchasing Director. If determined that such communication has compromised the competitive process, the offer submitted by the individual, firm or business shall be disqualified from consideration for award. EXCEPTION to the above would be emailing request for clarification and/or questions to the County’s eProcurement portal at https://procurement.opengov.com/portal/henryga. (These requests will be answered in an addendum. Please see schedule of events.)
4. Pre-Bid Conference The Pre-Bid Conference or any other information session (if indicated in the schedule of events) will be held at the offices referred to in the “Schedule of Events” of this bid. Unless indicated otherwise, attendance is not mandatory; although suppliers are strongly encouraged to attend. However, in the event the conference has been identified as mandatory, then a representative of the supplier must attend the conference in its entirety to be considered eligible for contract award.
5. Rejection and Withdrawal of Bids
a. Withdrawal of bid due to errors, the supplier has up to forty-eight (48) hours to notify the
Purchasing Department of an obvious clerical error made in calculation of bid in order to withdraw a bid after bid opening. Withdrawal of bid for this reason must be done in writing within the forty-eight hour period.
b. The County will make a recommendation of the bid to the Board of Commissioners within 60 days from date of the opening, unless the successful Bidder agrees in writing to a longer period for the award.
c. The County may reject all or part of the bid within 60 days of bid opening.
6. Bid and Contract Documents
a. A bid executed by an attorney or agent on behalf of the Bidder shall be accompanied by an authenticated copy of the Power of Attorney or other evidence of authority to act on behalf of the
Bidder.
Corporation: If the Bidder is a corporation, the bid must be submitted in the name of the corporation, not simply the corporation’s trade name. In addition, the bid shall be signed by an officer of the corporation.
Partnership: If the Bidder is a partnership, all partners must sign the bid. If all the partners do not sign the bid, then the names of all those except limited partners must be furnished on the bid and evidence of the authority of the signer(s) to execute the bid on behalf of the partnership.
Limited Liability Company (LLC): If the Bidder is a limited liability company, the authorized agent having authority to bind the limited liability company must sign the bid documents.
Sole Proprietorship or Individual: If the Bidder is a sole proprietor or individual, a signature is required on all bid documents by that individual.
b. The contract documents consist of this Agreement, Specifications and Addenda issued prior to execution of this Agreement, other documents listed in this Agreement and Modifications issued after execution of this Agreement. These form the Contract and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated Agreement between the parties hereto and supersedes prior negotiations, representation or agreements, either written or oral.
c. Contract Term – The time period of the agreement, if any is formed from this bid, will be determined after the review and evaluation of the Time Line Schedules submitted by the successful Consultant.
7. Exceptions and Omissions Any exceptions to the specifications and/or terms and conditions must be addressed during the question/clarification and addendum phases.
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 6 of 26
8. Alterations of Solicitation and Associated Documents Alterations of County documents are strictly prohibited and will result in automatic disqualification of the Bidder’s solicitation response
9. Cost Incurred by Vendors All expenses involved with the preparation and submission of the bid to the Henry County Board of
Commissioners, or any work performed in connection therewith is the responsibility of the vendor(s).
10. Codes, Permits, Fees, Licenses and Law
a. All permits, fees, arrangements for inspections, licenses, and costs incurred for the same shall be the sole responsibility of the successful Bidder. All materials, labor and construction must comply with all applicable rules and regulations of local, state and/or national codes, laws and ordinances of all authorities having jurisdiction over the project, shall apply to the contract throughout and will be deemed to be included in the contract the same as though herein written out in full.
b. Effective July 1, 2008: All General Contractors must have a current valid license from the
State Licensing Board for Residential and General Contractors, unless specifically exempted from holding such license pursuant to Georgia law, O.C.G.A. Section 43-41-17.
c. State Law regarding Worker Verification requires that all who enter into a contract for the physical performance of services with the County must satisfy O.C.G.A. §13-10-91 and Rule 300-10-1-.02, in all manner, and such are conditions of the contract. By submitting a bid to the County contractor agrees that in the event the contractor employs or contracts with any subcontractor(s) in connection with the covered contract, the contractor will secure from the subcontractor(s) such subcontractor(s) indication of the employee-number category applicable to the subcontractor, as well as attestation(s) from such subcontractor(s) that they are in compliance. Such attestation(s) shall be maintained and may be inspected by the County at any time. An affidavit of such compliance included with the bid, must be signed by the contractor, and will become part of the contract.
11. Safety All vendors and subcontractors performing services are required and shall comply with all Occupational
Safety and Health Administration (OSHA), State and County Safety and Occupational Health Standards and any other applicable rules and regulations. Also, all contractors and subcontractors shall be held responsible for the safety of their employees and any unsafe acts or conditions that may cause injury or damage to any persons or property within and around the work site area under this Contract.
12. Design, Standards and Practices Design, strength, quality of materials and workmanship must conform to the industry acceptable standards of engineering practices and/or professional services.
13. Statement of Warranty A Statement of Warranty should include all applicable manufacturers’ warranty and the Contractor’s warranty in regards to equipment, materials and workmanship. This statement shall include the terms, conditions and the period of warranty coverage. Any exclusion(s) must be clearly stated.
14. Non-collusion By submitting a bid in response to this solicitation, the Bidder represents that in the preparation and submission of this bid, said Bidder did not either directly or indirectly, enter into any combination or arrangement with any person, Bidder, Corporation or enter into any agreement, participate in any collusion, or otherwise take any action in the restraint of free, competitive bidding in violation of the
Sherman Act (15 U.S.C. Section I or Section 59.1-9.1 through 59.1-9.17 or Sections 59.1 – 68.6 through 59.68.8). Collusion and fraud in bid preparation shall be reported to the State of Georgia
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 7 of 26
Attorney General and the United States Justice Department.
15. Nondiscrimination Notwithstanding any other provision of this Agreement, during the performance of this Agreement
Contractor, for itself, its heirs, personal representatives, successors in interest and assigns, as part of the consideration of this Agreement does hereby covenant and agree, as a covenant running with the land, that:
a. No person on the grounds of race, color, religion, sex or national origin shall be excluded from participation in, denied the benefits of, or otherwise be subjected to discrimination;
b. In the production of the vehicle(s), and the furnishing of services therein or thereon, no person on the grounds of race, color, religion, sex or national origin shall be excluded from participation in, or denied the benefits of, such activities, or otherwise be subjected to discrimination.
16. Drug Free Workplace Certification By signing the Supply Service Contract form, the Contractor certifies that the provisions of Code
Sections 50-24-1 through 50-24-6 of the Official Code of Georgia Annotated, relating to the “Drug-free
Workplace Act”, have been complied with in full. The undersigned further certifies that:
a. A drug-free workplace will be provided for the Contractor’s employees during performance of the contract; and
b. Each Contractor who hires a subcontractor to work in a drug-free workplace shall secure from that subcontractor the following written certification:
“As part of the subcontracting agreement with (Contractor’s name), (Subcontractor’s name) certifies to the Contractor that a drug-free workplace will be provided for the subcontractor’s employees during the performance of this Contract pursuant to Paragraph (7) of Sub-section (b) of
Code Section 50-24-3”.
c. The Contractor further certifies that he will not engage in the unlawful manufacture, sale, distribution, dispensation, possession, or use of a controlled substance or marijuana during the performance of the Contract.
d. Contractor may be suspended, terminated, or debarred if it is determined that:
(1) The Contractor has made false certification hereinabove; or
(2) The Contractor has violated such certification by failure to carry out the requirements of the
Official Code of Georgia Section 50-24-3.
17. Georgia Security and Immigration Compliance Act Pursuant to the Georgia Security and Immigration Compliance Act of 2006, the successful Contractor understands and agrees that compliance with the requirements of O.C.G.A.13-10-91 and Georgia
Department of Labor Rule 300-10-02 are conditions of this bid and contract document. The Contractor further agrees that such compliance shall be attested by the Contractor and any of his Subcontractors by execution of the appropriate Affidavit and Agreement which will be included and become a part of the
Agreement between Henry County and the successful Contractor.
18. Supplier Inclusion Program Small, local, veteran-owned, Disadvantaged Business Enterprise (DBE), and female-owned business enterprises are encouraged to participate in the solicitation process. Please see the Supplier Inclusion
Program form for a description of each of these type businesses.
19. Delivery and F.O.B. Destination
a. All prices shall include shipping and delivery cost to our destination; F.O.B., Henry County, Georgia, unless otherwise requested. The Bidder shall handle all material procurement, storage and delivery to project site. Unless otherwise specified in this specification, Bidder shall supply all materials required. The County will grant no allowance for boxing, crating or delivery unless
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 8 of 26 specifically provided for in this bid. The Bidder shall retain title for the risk of transportation, including the filing for loss or damages.
b. The County desires delivery of the product(s) or service(s) as specified at the earliest possible time after the date of award. Unreasonable delivery may be cause for disqualifying a bid. Each firm shall state a definite delivery time and avoid using general terms such as "ASAP" or approximately so many days.
20. Discounts Cash discounts for early payment (i.e. 2%-10) or Net 30 terms should be shown separately, even if terms are Net.
21. County’s Tax Exemption Henry County is exempt from Federal Excise Tax or Georgia Sales Tax with regard to goods and services purchased directly by Henry County. Exemption certificates furnished upon request.
22. Award of Contract
a. Henry County desires to complete the award process in a timely manner. Henry County reserves the right to reject or accept any or all bids, whole or any parts hereof, by item or group of items, by section or geographic area, or make multiple awards and be the final approval of bid(s) selection which would be the most advantageous to the County with price and other factors considered.
Henry County may elect to waive any technicalities. The bid will be awarded to the lowest responsive, responsible Bidder(s), if awarded. The bid specifications and results will be available on the County’s eProcurement Portal at (https://procurement.opengov.com/portal/henryga).
b. Henry County reserves the right to reject any bid if the evidence submitted by or investigation of, the Bidder fails to satisfy the County that the Bidder is properly qualified to carry out the obligations of the Contract. If the successful Bidder defaults on their bid, an award may be made to the next low responsive and responsible Bidder.
Responsibility - The determination of the Bidder’s responsibility will be made by the County based on whether the Bidder meets the following minimum standard requirements:
• Maintains a physical location presence and permanent place of business.
• Has the appropriate and adequate technical experience required.
• Has adequate personnel and equipment to perform the work expeditiously
• Able to comply with the required or proposed delivery and installation schedule.
• Has a satisfactory record of performance.
• The ability of Bidder to provide future maintenance and service for the use of the contract under consideration.
• Has adequate financial means to meet obligations incidental to the work.
• Such other factors as appear to be pertinent to either the bid or the contract.
Responsiveness - The determination of the Bidder’s responsiveness will be made by the County based on a consideration of whether the Bidder has submitted complete bid documents meeting bid requirements without irregularities, excisions, special conditions, or alternatives bids for any item unless specifically requested in the bid solicitation.
c. Henry County is subject to making records available for disclosure after the Board of
Commissioners approval of the recommendation. The award shall be made by the Board of
Commissioners of Henry County unless the lowest, qualified bid is less than the Board of
Commissioners’ approval limit. No claim shall be made by the selected Consultant for loss of profit if the contract is not awarded or awarded for less work than is indicated and for less than the amount of the bid. The total of the awarded contract shall not exceed the available funds allocated for the bid project.
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 9 of 26
23. Local Vendor Privilege
a. There is established in Henry County, a local vendor privilege. Bids or bids awarded to local vendors contribute to the local tax base and will therefore be given special consideration when bidding against out-of-jurisdiction (out-of-county) vendors. Bids or bids received from local vendors will be given preference if such bid or bid is responsive and within five (5) percent of the low bid submitted by any out-of-county bidder. In such instance, the local vendor will be given the opportunity to match the low bid offered by the out-of-county vendor. If such local vendor agrees to match the low bid received from the out-of-county vendor within the time specified by the county, the bid shall be awarded to the local vendor.
b. A local vendor shall only be eligible to receive the benefit of this privilege if it meets each of the following requirements prior to any award of a contract or purchase:
1. The business or supplier must operate and maintain a regular place of business within the geographical boundaries of Henry County; and
2. The business or supplier must have a current occupational tax certificate; and
3. The business or supplier must have paid all real and personal taxes owed the county; and
4. The business or supplier must certify its compliance with the Georgia Security and
Immigration Act.
c. This policy shall not apply to any bid or bid for material, equipment or services in excess of one hundred thousand dollars ($100,000.00). In such cases, the bid award shall be subject to the competitive bidding requirements as otherwise provided herein or general law.
24. County Direction of Project Site and Monitoring of Work
a. The Contractor may have a Project Coordinator, but the project site shall remain under the control of Henry County. The Contractor shall provide and make available an appointee to Henry County for project coordination and supervision of Bidder installation personnel. Coordination consist of meeting with the Henry County representatives to review the project; on site walk throughout of installation area(s) before the installation begins; review installation procedures; review installation progress and to handle any problems during installation until project completion.
b. The successful Bidder will promptly correct all work rejected by the County as faulty, defective, or failing to conform to the Minimum Specifications and/or to consensus standards adopted by both government and industry governing the repairs, whether observed before or after substantial completion of the work, and whether or not fabricated, installed, or completed. The successful
Bidder will bear all costs of correcting such rejected work.
c. The Contractor shall insure all trash generated by work performed shall be removed from the site and properly disposed as each work operation is completed in a given area. Additionally, the
Contractor shall ensure all disturbances to the area where the Contractor performed work are restored to the same condition prior to start of the project. If an inspection reveals that the
Contractor fails to clean up after work has been performed. The County will notify the Contractor of the discrepancy and the Contractor will have twenty-four (24) hours to make the correction.
Should the Contractor still fails to clean the area, the County reserves the right to make other arrangements to have the area cleaned and the County shall deduct the cost from the Contractor’s invoice.
d. No one except authorized employees of the Contractor is allowed on the premises of Henry County facilities. Contractor employees are not to be accompanied in their work area by acquaintances, family members, assistants, or any other person unless said person is an authorized employee of the Contractor.
e. All information disclosed by Henry County to the successful Contractor for the purpose of the work to be done or information that comes to the attention of the successful Contractor during the course of performing such work is to be kept strictly confidential.
25. Indemnification
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 10 of 26
a. The vendor that is selected as the contractor shall, at its own expense, protect, defend (but only to the extent not prohibited by O.C.G.A. §13-8-2(c)), indemnify, save and hold harmless Henry
County and its elected and appointed officers, employees, servants and agents from all claims, damages, lawsuits, costs and expenses including, but not limited to, all costs from administrative proceedings, court costs and attorney fees that Henry County and its elected and appointed officers, employees, servants and agents may incur as a result of the negligence, recklessness, or intentionally wrongful conduct of the Contractor or other persons employed or utilized by the
Contractor in the performance of the contract.
b. The contractor’s indemnification responsibility under this section shall include the sum of damages, costs and expenses which are in excess of the sum of damages, costs and expenses which are paid out in behalf of or reimbursed to the County, its officers, employees, servants and agents by the insurance coverage obtained and/or maintained by the contractor, but only to the extent and for such claims as are permitted under O.C.G.A. §13-8-2(c).
26. Controlling Law, Venue Any dispute arising as a result of this bid and/or an Agreement which was created from the terms, conditions and specifications of this document or their interpretation, litigation shall only be entered into and shall be performed in Henry County, Georgia. This Agreement shall be governed by the applicable laws of the County of Henry and the State of Georgia. Any dispute arising out of the agreement, this bid solicitation, its interpretations, or its performance shall be litigated only in the County of Henry Judicial
Courts.
27. Contractor as Independent Contractor In conducting its business hereunder, Contractor acts as an independent contractor and not as an employee or agent of County. The selection, retention, assignment, direction and payment of Contractor’s employees shall be the sole responsibility of Contractor.
28. Assignment The Agreement, in whole or any part hereof, created by the award to the successful contractor shall not be sold, not be assigned or transferred by Contractor by process or operation of law or in any other manner whatsoever, including intra-corporate transfers or reorganizations between or among a subsidiary of
Contractor, or with a business entity which is merged or consolidated with Contractor or which purchases a majority or controlling interest in the ownership or assets of Contractor without the prior written consent of Henry County.
29. Owner and Ownership of Documents The Henry County Board of Commissioners, 140 Henry Parkway, McDonough, Georgia 30253 is the owner of the proposed work. Reports and all relevant data such as maps, diagrams, plans, designs, electronic data, statistics, specifications, and other supporting records or drawings compiled or prepared in the course of performance of the services required by this contract shall be the absolute property of the County and shall not be used by the Contractor for purposes unrelated to this contract without the prior written approval of the County. Such original documents shall be turned over to the County upon completion of the project except that Contractor shall have the right to retain copies of the same.
30. Performance of Contract
a. Henry County reserves the right to enforce the Contractor’s performance of this Agreement in any manner prescribed by law or deemed to be in the best interest of the County in the event of breach or default or resulting contract award. It will be understood that time is of the essence in the Bidder’s performance.
b. The successful Contractor shall execute the entire work described in the Contract Documents, except to the extent specifically indicated in the Contract documents to be the responsibility of
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 11 of 26 others.
c. The Contractor accepts the relationship of trust and confidence established by the award of this bid solicitation. The Contractor covenants with the County to utilize the Contractor’s best skill, efforts and judgment in furthering the interest of the County; to furnish efficient business administration and supervision; to make best efforts to furnish at all times an adequate supply of workers and materials; and to perform the work in the best way and most expeditious and economical manner consistent with the interest of the County,
d. All purchases for goods or services are subject to the availability of funds for this particular purpose.
31. Default and Termination
a. Termination by Contractor
The agreement resulting from this bid shall be subject to termination by Contractor in the event of any one or more of the following events: The default by County in the performance of any of the terms, covenants or conditions of this Agreement, and the failure of County to remedy, or undertake to remedy such default, for a period of thirty (30) days after receipt of notice from
Contractor to remedy the same.
b. Termination by County
The agreement resulting from this bid shall be subject to termination by the County at any time in the opinion of the County; the contractor fails to carry out the contract provisions of any one or more of the following events:
(1) The default by Contractor in the performance of any of the terms, covenants or conditions of the Agreement, and the failure of Contractor to remedy, or undertake to remedy with sufficient forces and to the County’s reasonable satisfaction, the County shall provide the vendor with notice of any conditions which violate or endanger the performance of the
Agreement. If after such notice the Contractor fails to remedy such conditions within thirty
(30) days to the satisfaction of the County, the County may exercise their option in writing to terminate the Agreement without further notice to the Contractor and order the
Contractor to stop work immediately and vacate the premises, to cancel ordered products and/or services with no expense to the County.
(2) Contractor files a voluntary petition in bankruptcy, including a reorganization plan, makes a general or other assignment for the benefit of creditors, is adjudicated as bankrupt or if a receiver is appointed for the benefit of creditors, is adjudicated as bankrupt or if a receiver is appointed for the property or affairs of Contractor and such receivership is not vacated within thirty (30) days after the appointment of such receiver.
(3) Contractors’ failure to conduct services according to the approved bid specifications.
(4) Contractors’ failure to keep, perform, or observe any other term or condition of this
Agreement.
(5) Contractor’s performance of the contract is unreasonably delayed.
(6) Should the successful Bidder fail to provide the commodities or services when ordered, and in accordance with the General Terms and Conditions, specifications and any other requirements contained herein are not met, the County reserves the right to purchase commodities or services covered by this contract elsewhere if available from an alternate source.
(7) The Contractor agrees by its bid submission that the County’s decision is final and valid.
c. Termination for Convenience
This Agreement may be terminated by Henry County for its own convenience by providing vendor (30) thirty days’ written notice. All fees and costs incurred by vendor up until the date of termination shall be paid to vendor.
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 12 of 26
d. Force Majeure
Neither party shall be held to be in breach of the Agreement resulting from this bid, because of any failure to perform any of its obligations hereunder if said failure is due to any act of God, fire, flood, accident, strike, riot, insurrection, war, or any other cause over which that party has no control. Such party shall give notice and full particulars of such Force Majeure in writing to the other party within a reasonable time after occurrence of the event and the obligation of the party giving such notice shall endeavor to remove or overcome such inability with all reasonable dispatch.
e. Waiver
The waiver of any breach, violation or default in or with respect to the performance or observance of the covenants and conditions contained herein shall not be taken to constitute a waiver any subsequent breach, violation or default in or with respect to the same or any other covenant or condition hereof.
32. Invoices Invoices and/or statements should not be faxed but originals must be mailed directly to:
Henry County Board of Commissioners
Finance Department
140 Henry Parkway
McDonough, GA 30253
The following information must appear on all invoices submitted:
• Name and address of successful Bidder;
• Detailed breakdown of all charges for the services or products delivered stating any applicable period of time;
• Henry County’s Purchase Order Number and Bid Package number;
• Invoices shall be based upon actual services rendered, actual work performance and/or products delivered.
33. Payment Payment shall be tendered to the successful Bidder upon acceptance and approval by the County for satisfactory compliance with the general terms, conditions and specifications of the bid; by completed services; verification of delivery of products; assurance that the product/service performs as specified and warranted; and receipt of a valid invoice.
34. Required Documents If submitting an electronic bid through the County’s eProcurement Portal at
(https://procurement.opengov.com/portal/henryga), the required documents and/or forms mentioned in this solicitation must be uploaded to our eProcurement Portal once they are executed.
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 13 of 26
SECTION II - SPECIFICATIONS
A. SCOPE OF WORK
Henry County is looking for a licensed contractor to provide all equipment, materials and labor required to remove and replace the HVAC systems located at the Locust Grove Recreation Center. The contractor must properly dispose of the old equipment and reclaim refrigerant according to EPA guidelines.
Location:
Locust Grove Recreation Center (Church Side): 10 Cleveland Street, Locust Grove, GA 30248
Units:
• Unit 14: 7.5 Ton 230-volt 3 phase dual stage outdoor unit, (2) 92% 100k BTU furnaces, (2) 4 Ton evaporator coils, Twinning kit.
• Units 11, 12, & 13: 5 Ton 230-volt 3 phase condenser, 5 Ton air handler.
• Unit 16: (2) 92% 120k BTU furnaces, Twinning kit. (Heat only)
• Unit 10: 4 Ton 230-volt single phase condenser, 92% 100k BTU furnace, 4 Ton coil.
• Units 9 & 15: 5 Ton 230-volt single phase condenser, 92% 100k BTU furnace, 5 Ton coil.
Narrative:
• Unrestricted GA Warm Air License required.
• HVAC equipment must have minimum standard SEER rating (14.3 SEER2)
• Only ICP equipment will be considered.
• All line sets must be sized to manufactured specifications.
• All line sets must be flushed and vacuumed to 500 microns.
• All current building/fire codes must be followed.
• All duct work that needs reworked or repaired is to be included.
• All penetration must be sealed.
• Any new penetration must be approved by Henry County Facility Maintenance.
• All flue pipe, drain lines and gas line connections are to be completed and sealed by vendor.
• Vendor is responsible for all required utility connections and terminations (i.e. gas, electrical, etc.).
• Upon completion of the project, equipment and materials must be promptly removed from the facility.
• Job site must be cleaned, and unused material, stored daily.
• All material and equipment must be stored in a secure location overnight.
• All work must be completed during normal business hours of Monday - Friday 8:00am – 5:00pm.
Warranty:
Minimum (1) one-year Warranty on equipment and workmanship.
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 14 of 26
B. INSURANCE REQUIREMENTS
General insurance requirements shall be applicable to the Contractor and any authorized subcontractor.
Insurance requirements shall be based on conditions in place as of the date of the Contract's execution.
Insurance companies must be licensed by the Georgia Department of Insurance and the Georgia Secretary of State to do business in the State of Georgia. The County reserves the right to require adjustments in the level of coverage or waive any or all requirements based on information pertinent to this Contract.
The following requirements shall also be applicable to the Contractor:
a. Evidence of insurance must be provided to the Purchasing Department, 140 Henry Parkway, McDonough, Ga. 30253, within five days of execution of this contract and prior to commencing operations under this Contract;
The certificate holder is to be issued to:
Henry County Board of Commissioners
Henry County, Georgia but delivered to:
Henry County Purchasing Department
McDonough, Georgia 30253
The Bid Package number and project name should be referenced in the description of operations. The certificates may be faxed to the Purchasing Department at 770-288-6027.
b. The insurance policy required herein shall include a Project-specific endorsement incorporating the indemnification obligations assumed by the Contractor under the terms of this Agreement.
c. Any change in coverage or insurance carrier must be reported to the County’s Purchasing Office in writing within five business days of the change.
d. Failure of any Contractor to procure and maintain the required insurance shall not relieve the
Contractor of any liability under the Contract, nor shall these requirements be construed to conflict with the obligation of the Contractor concerning indemnification;
e. Any and all insurance required by this Contract shall be maintained during the entire term of this
Contract;
f. The County shall, without exception, be given no less than thirty (30) days notice prior to cancellation for any and all reasons other than non-payment of premium; and
g. The County shall, without exception, be given immediate notification in the event of cancellation for reasons of non-payment of premium.
h. The Contractor shall procure and maintain insurance coverage in the following particulars:
Workers Compensation Insurance
In the amounts of the statutory limits established by the General Assembly of the State of Georgia (A self-insurer must submit a certificate from the Georgia Board of Workers compensation stating that the
Contractor qualifies to pay its own workers compensation claims.) In addition, the Contractor shall require that all subcontractors occupying the premises or performing the work under the contract to obtain an insurance certificate showing proof of Worker Compensation Coverage with the following minimum coverage:
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 15 of 26
Georgia Statutory including Employers Liability
Bodily injury by Accident – each employee $100,000
Bodily injury by Disease - each Employee $100,000
Bodily injury by Disease – policy limit $500,000
Commercial General Liability
Each Occurrence Limit $1,000,000
Personal and Advertising Injury Limit $1,000,000
General Aggregate Limit $2,000,000
Products/Completed Operations Aggregate Limit $2,000,000
Automobile Liability
Combined Single Limit $1,000,000
Umbrella Liability $2,000,000
Property Coverage or Builders’ Risk Policy For new construction: In an amount of one hundred percent (100%) of the contract amount (minimum).
For renovations of existing facilities:
Existing Facilities value (Owner provided)
Plus (+) the renovation contract amount
(minimum).
If hazardous substances are involved:
Contractor’s Pollution Liability (with 1-year extended reporting period)
Each Occurrence $ 1,000,000
Aggregate $ 2,000,000
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 16 of 26
C. BOND REQUIREMENTS
a. All Bids shall be accompanied by a Bid Bond in an amount of not less than five percent (5%) of the bid for the complete work. The Bid Bond shall be forfeited to Henry County, Georgia as liquidated damages if the Bidder fails to execute the Contract and provide Performance and
Payment Bonds within fifteen (15) calendar days after being notified that he has been awarded the
Contract. The Bid Bond shall be in the form of a surety issued bond made payable to the Henry
County Board of Commissioners. The Surety Company shall be licensed to do business in the
State of Georgia and listed in the Department of the Treasury Circular 570, latest edition. The
Surety Company shall have an A.M. Best Company minimum rating of “A” with a financial size of VI “6” or better.
b. The Owner will require 100% Performance and Payment Bonds. If awarded the Contract, the bidder will execute the Contract and provide the bond(s) as required by the Specifications. The successful bidder, upon his failure or refusal to execute and deliver the Contract and bonds required within fifteen (15) calendar days after he has received notice of the acceptance of the bid, shall forfeit to the Owner, as liquidated damages for such failure or refusal, the security deposited with his bid.
c. All Proposal Guaranties may be retained until the Contract and the Contract Bonds have been signed and approved. Early release of Proposal Guaranties will be considered if a request is made in writing. The Department reserves the right to return all Proposal Guaranties by registered or certified mail, and its responsibility pertaining to them will end when they are mailed.
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 17 of 26
Henry County
Standard Contract Form
Solicitation Title Solicitation Number Contract Number
1. This Contract is entered into between Henry County and the Contractor named below:
Henry County (hereafter called County)
Contractor’s Name (hereafter called Contractor)
2. Contract to Begin: Date of Completion: Renewals:
3. Lump Sum Amount of this Contract
(if applicable)
Fee Represented as a Percentage Of Designated Cost
Revenue Represented as a Percentage of a Designated Lump Sum or Income Stream (if applicable):
Annual Contract Price Agreement
4. The parties agree to comply with the terms and conditions of the following documents which are by this reference made a part of the Contract:
1: All Terms, Conditions and Statements of Work Included in Solicitation and Addendum (referenced above)
2: Bid or Proposal Submitted by Contractor along with Contractor’s Final Response
3: Fee/Cost Submitted by Contractor
4: All Other Documentation Required in Solicitation
IN WITNESS WHEREOF, this Contract has been executed by the parties hereto.
5.
Contractor
Contractor’s Name (If other than an individual, state whether a corporation, partnership, etc.) Federal Identification No.
By (Authorized Signature)
Date Signed
Printed Name and Title of Person Signing
Address
Telephone Number E-mail Address
6.
Henry County
Chair or Designee
By (Authorized Signature)
Date Signed
Printed Name and Title of Person Signing
140 Henry Parkway, McDonough, Georgia 30253
Bid #26-05, HVAC Replacement at the Locust Grove Recreation Center Page 18 of 26
BID BOND
KNOW ALL MEN BY THESE PRESENTS, THAT WE
(hereinafter called the Principal) and (hereinafter called the Surety), a Corporation chartered and existing under the laws of the State of with its principal offices in the City of and authorized to do business in the State of Georgia, are held and firmly bound unto Henry County, Georgia, in the full and just sum of Dollars ($ ) good and lawful money of the United States of America, to be paid upon demand to Henry County, Georgia, to which payment will and truly to be made, we bind ourselves, our heirs, executors, administrators and assigns jointly and severally and firmly by these presents.
WHEREAS, the Principal is about to submit, or has submitted to Henry County, Georgia, a proposal for furnishing materials, labor and equipment for:
BID NUMBER: 26-05
HENRY COUNTY PROJECT NUMBER: HVAC Replacement at the Locust Grove Recreation Center
WHEREAS, the Principal desires to file this Bond in accordance with law in lieu of a certified Bidder's check otherwise required to accompany this Proposal.
NOW, THEREFORE, the conditions of this obligation are such that if the proposal be accepted, the Principal shall within fifteen (15) days after receipt of notification of the acceptance, execute a Contract in accordance with the Proposal and upon the terms, conditions, and prices set forth in the form and manner required by Henry
County, Georgia, and execute a sufficient and satisfactory Performance Bond and Payment Bond payable to
Henry…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .