This is a Clarification Notice issued by Elite Companies for the Springport Public Schools' High School and Elementary School Addition and Renovation project (26-029) located in Springport, Michigan. The clarification addresses multiple bid packages for the comprehensive renovation and addition project, with sealed bids due on September 29, 2026, at 3:30 p.m. local time at the Springport Public Schools District Administration Office, located at 300 West Main Street, Springport, Michigan 49284. Bids will be publicly opened and read aloud immediately following the deadline at Springport High School. The document includes post-bid interviews scheduled for September 30 through October 2, 2026, with specific time slots assigned to 15 different bid packages. Board approval is scheduled for October 19, 2026, with contract execution to trades occurring between October 20 and November 4, 2026. The overall project timeline extends from August 28, 2026, through January 31, 2028, encompassing bidding, construction, and closeout phases.
The clarification specifies work scope revisions and responsibility assignments across multiple bid packages, including air monitoring during demolition (BP 2.5), fiberglass column wrap installation (BP 6.1), laminated plywood and molding installation (BP 6.1), roofing cutting and patching (BP 7.5), metal panel preparation and painting (BP 9.9), existing cooler removal and reinstallation (BP 11.4), mechanical brake metal covers and electrical line concealment (BP 22.2), dome camera installation (BP 27.9), and sanitary and storm sewer hydro-jetting and camera inspection (BP 31.1). All staking, layout, and material testing will be provided by Elite Companies, with trade contractors required to coordinate timing and specifications during construction. Contractors are responsible for providing their own lift equipment for overhead work, with Elite Companies constructing ramps and installing handrail barriers at specified elevations to facilitate lift access and safety at the new Cafetorium slab levels.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ELITE COMPANIES | KALAMAZOO | BATTLE CREEK
269-910-1347 | elite-companies.com
Clarification #: 01
Springport BP 2 – Elementary and HS
Date: 09-16-26 Bids Due: 09-29-26 @ 3:30 Local Time
From: ELITE COMPANIES Email: mark.rimes@elite-companies.com
Clarification Details
All Bid Packages: Bid Proposals Sealed bids due 09/29/26 @ 3:30 pm local time, will be received at
Springport Public Schools, located at 300 W Main St, Springport, MI 49284 Attn: Superintendent. Bids to be dropped off at the District Administration Office. No faxed or email bids will be accepted. Envelopes are to be clearly marked as SEALED BID with Project name and number and Bid Package name and number. Bid Opening Bids will be publicly opened immediately after and read aloud at the Springport High
School, located at 300 W Main St, Springport, MI 49284. Bids received after specified date and time will not be accepted and will be returned unopened. Bids will be accepted as determined to be in the Owner's best interest.
All Bid Packages: Review Addendum #1 issued 09-15-26 by Tower Pinkster All items changed are to be carried by the applicable scope of work Bid Package base bid. Only the listed below Bid Package Scope of
Works have been revised with this Clarification attached for bidders use. The additional / clarified scope in the attached Addendum 01 is to be included but did not warrant reissue of Scopes of Work.
General: All trades, refer to the attached preliminary construction schedules.
General: All staking, layout and material testing will be by ELITE Companies. Trades will need to coordinate with ELITE Companies during construction on when and what needs to be staked and laid out.
General: Trades will need to provide their owner lift for all overhead work. ELITE will construct a ramp at each level in the middle for lift access at the new Cafetorium slab levels. Additionally ELITE will install handrail barriers at elevation 100' and 99' with toe kicks so lift wheels won't be able to run off the slab
Bid Package 02.5: Not-Reissued, Clarification; This bid package to furnish and provide air monitoring during major demolition at the Gymnasium and Cafetorium
Bid Package 06.1: Not-Reissued, Clarification; This bid package to furnish and install fiberglass column wrap as shown on sheet A 352
Bid Package 06.1: Not-Reissued, Clarification; This bid package to furnish and install laminated FRT plywood, reglet molding and corners as shown on sheet A 352
Bid Package 07.5: Not-Reissued, Clarification; This bid package will be responsible for all cutting and patching required per new mechanical penetrations and curb installation in new and existing roofing areas.
Bid Package 09.9: Not-Reissued, Clarification; This bid package to prep and paint existing metal panels and fascia as noted on sheet A301
Bid Package 11.4: Not-Reissued, Clarification; This bid package is responsible for removing, salvage and reinstall existing owner cooler in new location as noted on the construction drawings
Bid Package 22.2: Not-Reissued, Clarification; This bid package to furnish and install brake metal cover at classrooms to cover electrical and refrigerant lines. Paint brake metal to match unit ventilator. It is assumed these covers can be installed next to each unit ventilator to go straight up to above the ceiling
Bid Package 22.2: Not-Reissued, Clarification; Bid package 7.5 will be responsible for all cutting and patching required per new mechanical penetrations and curb installation in new and existing roofing areas.
Bid Package 22.2: Not-Reissued, Clarification; Part 2 and 3 of the work scopes in this bid package contradicts demolition requirements. Demolition will be by the demolition contractor 2.5. This bid package to follow part III in the Unique Scopes to drain the mechanical systems down and remove any existing refrigerant in line sets prior to completed demolition of system Bid Package 2.5
Bid Package 27.9: Not-Reissued, Clarification; Specification section 28.2113.02 – Dome Cameras will be the responsibility of this bid package
Bid Package 31.1: Not-Reissued, Clarification; This bid package to hydro jet and camera existing sanitary sewer and storm sewer. Provide video to ELITE Companies and A/E for review prior to construction
Post Bid Schedule:
September 30
• 10am – BP 2.5
• 11am – BP 3.1
• 1pm – BP 4.2
• 2PM – BP 5.1
• 3PM – BP 6.1
• 4pm – BP 7.5
October 1
• 10am – BP 8.8
• 11am – BP 9.2
• 1pm – BP 9.6
• 2PM – BP 9.9
• 3PM – BP 11.4
• 4pm – BP 21.1
October 2
• 8am – BP 22.2
• 19am – BP 26.1
• 10am – BP 27.9
• 11am – BP 31.1
Attachments:
• Pre-Bid Sign-In Sheet
• Preliminary Construction Schedules
End of Clarification
ID Task
Mode
Task Name Duration Start Finish Predecessors
1 Springport High School and Elementary School Renovations 372 days? Fri 8/28/26 Mon 1/31/28
2 Bidding Phase 90 days Fri 8/28/26 Thu 12/31/26
3 Construction Documents to ELITE 1 day Fri 8/28/26 Fri 8/28/26
4 Plan Review 40 days Mon 8/31/26Fri 10/23/26 3
5 Construction Bidding 16 days Tue 9/8/26 Tue 9/29/26 3FS+6 days
6 Post Bid Interviews 3 days Wed 9/30/26Fri 10/2/26 5
7 Board Approval 1 day Mon 10/19/26Mon 10/19/266FS+10 days
8 Contract to Trades 12 days Tue 10/20/26Wed 11/4/267
9 Submittals, Approvals, and Material Procurement 90 days Fri 8/28/26 Thu 12/31/26
10 Construction Gym Addition 372 days? Fri 8/28/26 Mon 1/31/28
11 Site Mobilization 2 days Thu 11/5/26 Fri 11/6/26 8SS+12 days
12 Existing Site Elements Protection 5 days Thu 11/5/26 Wed 11/11/268SS+12 days
13 Hazardous Material Removal 15 days Mon 11/9/26Fri 11/27/26 11
14 Hydrojet Storm and Sanitary Sewer 5 days Mon 11/9/26Fri 11/13/26 11
15 Utility Disconnects 3 days Mon 11/30/26Wed 12/2/2613
16 Move District Office and UofM Health Out of Offices 3 days Mon 11/30/26Wed 12/2/2613
17 Remodel District Office 90 days Thu 12/3/26 Wed 4/7/27 16
18 Miss-Dig/GPR Utility Finding 5 days Mon 11/30/26Fri 12/4/26 13
19 Utility Relocation 30 days Mon 11/9/26Fri 12/18/26 11
20 Demolition 15 days Mon 12/21/26Fri 1/8/27 19
21 New Under Ground Utilities 15 days Mon 1/11/27Fri 1/29/27 20
22 Staking and Layout 5 days Mon 1/25/27Fri 1/29/27 21SS+10 days
23 Excavation of Footings and Foundations 7 days Mon 2/1/27 Tue 2/9/27 22
24 Compaction of Footings 3 days Wed 2/10/27Fri 2/12/27 23
25 Form Footings 8 days Mon 2/15/27Wed 2/24/2724
26 Footing Rebar 4 days Thu 2/25/27 Tue 3/2/27 25
27 Footing Rebar Inspection 2 days Wed 3/3/27 Thu 3/4/27 26
28 Pour Footings 2 days Fri 3/5/27 Mon 3/8/27 27
29 Strip Footings 2 days Tue 3/9/27 Wed 3/10/2728
30 Form Foundations 7 days Thu 3/11/27 Fri 3/19/27 29
31 Foundation Rebar 4 days Mon 3/22/27Thu 3/25/27 30
32 Foundation Rebar Inspection 1 day? Fri 3/26/27 Fri 3/26/27 31
33 Pour Foundations 2 days Mon 3/29/27Tue 3/30/27 32
34 Strip Foundations 2 days Wed 3/31/27Thu 4/1/27 33
35 Foundation Drainage 10 days Fri 4/2/27 Thu 4/15/27 34
36 Foundation Backfill 3 days Fri 4/16/27 Tue 4/20/27 35
37 Concrete Slab Prep 4 days Wed 4/21/27Mon 4/26/2736
38 Underground Electrical and Plumbing Rough-In 15 days Tue 4/27/27 Mon 5/17/2737
39 Underground Electrical and Plumbing Inspections 15 days Tue 4/27/27 Mon 5/17/2737
40 Final Concrete Slab Prep 3 days Tue 5/18/27 Thu 5/20/27 39
41 Concrete Slab Compaction Test 2 days Fri 5/21/27 Mon 5/24/2740
42 Pour Concrete Slab 3 days Tue 5/25/27 Thu 5/27/27 41
43 Block Walls, Lintels, Base Plates and Hollow Metal Frame
Installation
25 days Fri 6/4/27 Thu 7/8/27 42FS+5 days
44 In-Wall Electrical and Plumbing 25 days Fri 6/4/27 Thu 7/8/27 42FS+5 days
45 Roof Joists 10 days Fri 7/9/27 Thu 7/22/27 43
46 Reinstall Wood Arches 5 days Fri 7/9/27 Thu 7/15/27 43
47 Roof Decking 5 days Fri 7/23/27 Thu 7/29/27 45
48 Roof Blocking 10 days Fri 7/30/27 Thu 8/12/27 47
49 Roofing Insulation and Membrane 15 days Fri 8/13/27 Thu 9/2/27 48
50 Move District Office and UofM Health back into Offices 5 days Fri 7/30/27 Thu 8/5/27 47
51 Temp Interior Lighting 5 days Fri 7/30/27 Thu 8/5/27 47
52 Cavity Insulation 20 days Fri 7/9/27 Thu 8/5/27 43
53 Decorative Block 20 days Fri 7/9/27 Thu 8/5/27 43
54 Block Washing 4 days Fri 8/6/27 Wed 8/11/2753
55 Exterior Framing and Sheathing for Metal Panels and Soffits 20 days Fri 7/9/27 Thu 8/5/27 43
56 Metal Panels and Soffits 20 days Fri 8/6/27 Thu 9/2/27 55
57 Aluminum Windows, Storefronts, and Curtain Walls 20 days Fri 9/3/27 Thu 9/30/27 56
58 Interior Framing 15 days Fri 7/30/27 Thu 8/19/27 47
59 Electrical Rough-In 20 days Fri 7/30/27 Thu 8/26/27 47
60 Mechanical Rough-in 20 days Fri 7/30/27 Thu 8/26/27 47
61 Plumbing Rough-In 20 days Fri 7/30/27 Thu 8/26/27 47
62 Rough-In Inspections 2 days Fri 8/27/27 Mon 8/30/2761
63 Gymsum Board Bulkheads and Ceilings 15 days Tue 8/31/27 Mon 9/20/2762
64 Interior Painting 30 days Tue 9/21/27 Mon 11/1/2763
65 Millwork Installation 1 day? Tue 10/19/27Tue 10/19/2764SS+20 days
66 Acoustical and Metal Ceilings 30 days Tue 11/2/27 Mon 12/13/2764
67 Ceramic Floor and Wall Tiling 20 days Tue 11/2/27 Mon 11/29/2764
68 Concrete Seal Floors and Base 10 days Tue 11/2/27 Mon 11/15/2764
69 Concrete Polish and Seal Floors and Base 1 day? Fri 8/28/26 Fri 8/28/26
70 Gym Equipment (Backboards, Climbing Wall, Divider, Scoreboard, Wall Pads)
40 days Tue 11/2/27 Mon
12/27/27
71 Acoustical Sound Panels 15 days Tue 11/30/27Mon 12/20/2764FS+20 days
72 Resilient Gym Floor 10 days Tue 12/28/27Mon 1/10/2870
73 Gym Bleachers 8 days Tue 1/11/28 Thu 1/20/28 72
74 Electrical Trim 45 days Tue 11/2/27 Mon 1/3/28 64
75 Mechanical Trim 45 days Tue 11/2/27 Mon 1/3/28 64
76 Plumbing Trim 45 days Tue 11/2/27 Mon 1/3/28 64
77 Toilet Paritions and Accessories 5 days Tue 1/4/28 Mon 1/10/2876
78 Exterior Site Work (Sidewalks, Pads, Restoration) 25 days Fri 9/3/27 Thu 10/7/27 56
79 Final Cleaning 7 days Tue 1/11/28 Wed 1/19/2877
80 Final Inspections 3 days Tue 1/11/28 Thu 1/13/28 77
81 Punch List Walk with Architect/Owner 2 days Tue 1/11/28 Wed 1/12/2877
82 Punch List Work 12 days Thu 1/13/28 Fri 1/28/28 81
83 Owner Training 1 day Mon 1/31/28Mon 1/31/2882
TWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSM
Aug 23, '26Aug 30, '26Sep 6, '26Sep 13, '26Sep 20, '26Sep 27, '26Oct 4, '26Oct 11, '26Oct 18, '26Oct 25, '26Nov 1, '26Nov 8, '26Nov 15, '26Nov 22, '26Nov 29, '26Dec 6, '26Dec 13, '26Dec 20, '26Dec 27, '26Jan 3, '27Jan 10, '27Jan 17, '27Jan 24, '27Jan 31, '27Feb 7, '27Feb 14, '27Feb 21, '27Feb 28, '27Mar 7, '27Mar 14, '27Mar 21, '27Mar 28, '27Apr 4, '27Apr 11, '27Apr 18, '27Apr 25, '27May 2, '27May 9, '27May 16, '27May 23, '27May 30, '27Jun 6, '27Jun 13, '27Jun 20, '27Jun 27, '27Jul 4, '27Jul 11, '27Jul 18, '27Jul 25, '27Aug 1, '27Aug 8, '27Aug 15, '27Aug 22, '27Aug 29, '27Sep 5, '27Sep 12, '27Sep 19, '27Sep 26, '27Oct 3, '27Oct 10, '27Oct 17, '27Oct 24, '27Oct 31, '27Nov 7, '27Nov 14, '27Nov 21, '27Nov 28, '27Dec 5, '27Dec 12, '27Dec 19, '27Dec 26, '27Jan 2, '28Jan 9, '28Jan 16, '28Jan 23, '28Jan 30, '28Feb 6, '28Feb 13, '28Feb 20, '28Feb 27, '28Mar 5, '28Mar 12, '28Mar 19, '28Mar 26, '28Apr 2, '28Apr 9, '28Apr 16, '28Apr 23, '28Apr 30, '28
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Project: Springport BP 2 Schedu
Date: Sat 9/12/26
Task Name Duration Start Finish Predecessors Resource Names
1 Springport High School and Elementary School Renovations 278 days? Fri 8/28/26 Tue 9/21/27
2 Bidding Phase 90 days Fri 8/28/26 Thu 12/31/26
3 Construction Documents to ELITE 1 day Fri 8/28/26 Fri 8/28/26
4 Plan Review 40 days Mon 8/31/26Fri 10/23/26 3
5 Construction Bidding 16 days Tue 9/8/26 Tue 9/29/26 3FS+6 days
6 Post Bid Interviews 3 days Wed 9/30/26Fri 10/2/26 5
7 Board Approval 1 day Mon 10/19/26Mon 10/19/266FS+10 days
8 Contract to Trades 12 days Tue 10/20/26Wed 11/4/267
9 Submittals, Approvals, and Material Procurement 90 days Fri 8/28/26 Thu 12/31/26
10 Construction Cafetorium 229 days? Thu 11/5/26 Tue 9/21/27
11 Site Mobilization 3 days Thu 11/5/26 Mon 11/9/268SS+12 days
12 Construct Temporary Fire Walls 10 days Tue 11/10/26Mon 11/23/2611
13 Hazardous Material Removal 10 days Tue 11/24/26Mon 12/7/2612
14 Demolition 15 days Tue 12/8/26 Mon 12/28/2613
15 Slab Removal 5 days Tue 12/29/26Mon 1/4/27 14
16 Excavation of Footings and Foundations 5 days Tue 1/5/27 Mon 1/11/2715
17 Compaction of Footings 2 days Tue 1/12/27 Wed 1/13/2716
18 Form Footings 4 days Thu 1/14/27 Tue 1/19/27 17
19 Footing Rebar 2 days Wed 1/20/27Thu 1/21/27 18
20 Footing Rebar Inspection 2 days Fri 1/22/27 Mon 1/25/2719
21 Pour Footings 1 day Tue 1/26/27 Tue 1/26/27 20
22 Strip Footings 1 day Wed 1/27/27Wed 1/27/2721
23 Form Foundations 5 days Thu 1/28/27 Wed 2/3/27 22
24 Foundation Rebar 3 days Thu 2/4/27 Mon 2/8/27 23
25 Foundation Rebar Inspection 2 days Tue 2/9/27 Wed 2/10/2724
26 Pour Foundations 2 days Thu 2/11/27 Fri 2/12/27 25
27 Strip Foundations 2 days Mon 2/15/27Tue 2/16/27 26
28 Underground Electrical and Plumbing Rough-In 25 days Tue 1/5/27 Mon 2/8/27 15
29 Underground Electrical and Plumbing Inspections 2 days Tue 2/9/27 Wed 2/10/2728
30 Final Concrete Slab Prep 3 days Wed 2/17/27Fri 2/19/27 27
31 Concrete Slab Compaction Test 2 days Mon 2/22/27Tue 2/23/27 30
32 Pour Concrete Slab 3 days Wed 2/24/27Fri 2/26/27 31
33 Block Walls, Lintels, Base Plates and Hollow Metal Frame Installation25 days Mon 3/8/27 Fri 4/9/27 32FS+5 days
34 In-Wall Electrical and Plumbing 25 days Mon 3/8/27 Fri 4/9/27 32FS+5 days
35 Roof Joist Reinforcement 10 days Mon 3/8/27 Fri 3/19/27 32FS+5 days
36 Roof Decking 5 days Mon 3/22/27Fri 3/26/27 35
37 Roofing Insulation and Membrane 10 days Mon 3/29/27Fri 4/9/27 36
38 Temp Interior Lighting 1 day? Tue 12/29/26Tue 12/29/2614
39 Interior Framing 15 days Mon 4/12/27Fri 4/30/27 33
40 Electrical Rough-In 20 days Mon 4/12/27Fri 5/7/27 34
41 A/V Rough-In 20 days Mon 4/12/27Fri 5/7/27 34
42 Mechanical Rough-in 20 days Mon 4/12/27Fri 5/7/27 34
43 Plumbing Rough-In 20 days Mon 4/12/27Fri 5/7/27 34
44 Rough-In Inspections 2 days Mon 5/10/27Tue 5/11/27 43
45 Gymsum Board Bulkheads 15 days Wed 5/12/27Tue 6/1/27 44
46 Interior Painting 15 days Wed 6/2/27 Tue 6/22/27 45
47 Millwork Installation 15 days Wed 6/16/27Tue 7/6/27 46SS+10 days
48 Acoustical Ceilings 20 days Wed 6/23/27Tue 7/20/27 46
49 Sound Reflectors 15 days Wed 6/30/27Tue 7/20/27 48SS+5 days
50 Stage Flooring 15 days Wed 6/23/27Tue 7/13/27 46
51 Cafetorium Flooring and Base 20 days Wed 7/21/27Tue 8/17/27 48
52 Theater Equipment (Rigging, Lights, Curtains) 20 days Wed 6/23/27Tue 7/20/27 46
53 Cooler and Freezer Installation 20 days Mon 7/19/27Fri 8/13/27 32FS+100 days
54 Electrical Trim 30 days Wed 6/23/27Tue 8/3/27 46
55 A/V Trim 30 days Wed 6/23/27Tue 8/3/27 46
56 Mechanical Trim 30 days Wed 6/23/27Tue 8/3/27 46
57 Plumbing Trim 30 days Wed 6/23/27Tue 8/3/27 46
58 Final Cleaning 5 days Wed 8/18/27Tue 8/24/27 51
59 Final Inspections 5 days Wed 8/18/27Tue 8/24/27 51
60 Punch List Walk with Architect/Owner 2 days Wed 8/18/27Thu 8/19/27 51
61 Punch List Work 10 days Fri 8/20/27 Thu 9/2/27 60
62 Owner Training 20 days Wed 8/25/27Tue 9/21/27 59
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Aug 23, '26 Aug 30, '26 Sep 6, '26 Sep 13, '26 Sep 20, '26 Sep 27, '26 Oct 4, '26 Oct 11, '26 Oct 18, '26 Oct 25, '26 Nov 1, '26 Nov 8, '26 Nov 15, '26 Nov 22, '26 Nov 29, '26 Dec 6, '26 Dec 13, '26 Dec 20, '26 Dec 27, '26 Jan 3, '27 Jan 10, '27 Jan 17, '27 Jan 24, '27 Jan 31, '27 Feb 7, '27 Feb 14, '27 Feb 21, '27 Feb 28, '27 Mar 7, '27 Mar 14, '27 Mar 21, '27 Mar 28, '27 Apr 4, '27 Apr 11, '27 Apr 18, '27 Apr 25, '27 May 2, '27 May 9, '27 May 16, '27 May 23, '27 May 30, '27 Jun 6, '27 Jun 13, '27 Jun 20, '27 Jun 27, '27 Jul 4, '27 Jul 11, '27 Jul 18, '27 Jul 25, '27 Aug 1, '27 Aug 8, '27 Aug 15, '27 Aug 22, '27 Aug 29, '27 Sep 5, '27 Sep 12, '27 Sep 19, '27
Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress
Task Name Duration Start Finish
1 Springport High School and Elementary School Renovations 219 days? Fri 8/28/26 Wed 6/30/27
2 Bidding Phase 90 days Fri 8/28/26 Thu 12/31/26
3 Construction Documents to ELITE 1 day Fri 8/28/26 Fri 8/28/26
4 Plan Review 40 days Mon 8/31/26Fri 10/23/26
5 Construction Bidding 16 days Tue 9/8/26 Tue 9/29/26
6 Post Bid Interviews 3 days Wed 9/30/26Fri 10/2/26
7 Board Approval 1 day Mon 10/19/26Mon 10/19/26
8 Contract to Trades 12 days Tue 10/20/26Wed 11/4/26
9 Submittals, Approvals, and Material Procurement 90 days Fri 8/28/26 Thu 12/31/26
10 Construction Courtyard Playground 170 days? Thu 11/5/26 Wed 6/30/27
11 Site Mobilization 2 days Thu 11/5/26 Fri 11/6/26
12 Miss-Dig/GPR Utility Finding 5 days Mon 11/9/26Fri 11/13/26
13 Courtyard Demolition 5 days Mon 11/16/26Fri 11/20/26
14 Undergound Utility Install and Connections 15 days Mon 11/23/26Fri 12/11/26
15 Concrete Paving and Curbs 15 days Mon 12/14/26Fri 1/1/27
16 Playground Footings and Equipment Installation 15 days Mon 12/14/26Fri 1/1/27
17 Playgound Equipment Installation 15 days Mon 4/12/27Fri 4/30/27
18 Poured Rubber Surfacing 10 days Mon 5/10/27Fri 5/21/27
19 Planting Beds and Landscaping 15 days Mon 5/24/27Fri 6/11/27
20 Exterior Furniture 5 days Mon 5/24/27Fri 5/28/27
21 Final Cleaning 5 days Mon 6/14/27Fri 6/18/27
22 Final Inspections 5 days Mon 6/14/27Fri 6/18/27
23 Punch List Walk with Architect and Owner 2 days Mon 6/21/27Tue 6/22/27
24 Punch List Work 5 days Wed 6/23/27Tue 6/29/27
25 Turn Over to Owner 1 day? Wed 6/30/27Wed 6/30/27
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
Aug 23, '26 Aug 30, '26 Sep 6, '26 Sep 13, '26 Sep 20, '26 Sep 27, '26 Oct 4, '26 Oct 11, '26 Oct 18, '26 Oct 25, '26 Nov 1, '26 Nov 8, '26 Nov 15, '26 Nov 22, '26 Nov 29, '26 Dec 6, '26 Dec 13, '26 Dec 20, '26 Dec 27, '26 Jan 3, '27 Jan 10, '27 Jan 17, '27 Jan 24, '27 Jan 31, '27 Feb 7, '27 Feb 14, '27 Feb 21, '27 Feb 28, '27 Mar 7, '27 Mar 14, '27 Mar 21, '27 Mar 28, '27 Apr 4, '27 Apr 11, '27 Apr 18, '27 Apr 25, '27 May 2, '27 May 9, '27 May 16, '27 May 23, '27 May 30, '27 Jun 6, '27 Jun 13, '27 Jun 20, '27 Jun 27, '27
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Task Name Duration Start Finish Predecessors Resource Names
1 Springport High School and Elementary School Renovations 271 days? Fri 8/28/26 Fri 9/10/27
2 Bidding Phase 90 days Fri 8/28/26 Thu 12/31/26
3 Construction Documents to ELITE 1 day Fri 8/28/26 Fri 8/28/26
4 Plan Review 40 days Mon 8/31/26Fri 10/23/26 3
5 Construction Bidding 16 days Tue 9/8/26 Tue 9/29/26 3FS+6 days
6 Post Bid Interviews 3 days Wed 9/30/26Fri 10/2/26 5
7 Board Approval 1 day Mon 10/19/26Mon 10/19/266FS+10 days
8 Contract to Trades 12 days Tue 10/20/26Wed 11/4/267
9 Submittals, Approvals, and Material Procurement 90 days Fri 8/28/26 Thu 12/31/26
10 Construction Elementary Remodel 190 days Mon 12/21/26Fri 9/10/27
11 Pre Tab for Elementary School 10 days Mon 12/21/26Fri 1/1/27 8FS+32 days
12 Site Mobilization 2 days Thu 6/10/27 Fri 6/11/27 8FS+155 days
13 Hazardous Material Removal 5 days Mon 6/14/27Fri 6/18/27 12
14 Demolition 10 days Mon 6/21/27Fri 7/2/27 13
15 Roofing Reinforcement 10 days Mon 6/21/27Fri 7/2/27 13
16 Roofing Insulation and Membrane 7 days Mon 7/5/27 Tue 7/13/27 15
17 Wall Framing 5 days Mon 7/5/27 Fri 7/9/27 14
18 Electrical Rough-In 15 days Mon 6/21/27Fri 7/9/27 13
19 Fire Alarm Rough-In 70 days Fri 3/26/27 Thu 7/1/27 8FS+101 days
20 Plumbing Rough-In 15 days Mon 6/21/27Fri 7/9/27 13
21 Mechanical Rough-In 15 days Mon 6/21/27Fri 7/9/27 13
22 Rough-In Inspections 3 days Mon 7/12/27Wed 7/14/2721
23 Gypsum Board Hang and Finish 7 days Thu 7/15/27 Fri 7/23/27 22
24 Toilet Room Finishes 15 days Mon 7/5/27 Fri 7/23/27 14
25 Duct and Pipe Insulation 10 days Thu 7/15/27 Wed 7/28/2722
26 Electrical Trim 25 days Thu 7/15/27 Wed 8/18/2722
27 Fire Alarm Trim 20 days Fri 7/2/27 Thu 7/29/27 19
28 Mechanical Trim 25 days Thu 7/15/27 Wed 8/18/2722
29 Plumbing Trim 25 days Thu 7/15/27 Wed 8/18/2722
30 Exterior Louver Re-Work and Installation 15 days Mon 6/21/27Fri 7/9/27 13
31 Unit Ventilator Installation 15 days Mon 7/12/27Fri 7/30/27 30
32 Mechanical Controls 30 days Mon 7/12/27Fri 8/20/27 31SS
33 Exterior Site Work (Sidewalks, Pads, Restoration) 20 days Mon 6/21/27Fri 7/16/27 13
34 Acoustical Ceiling Re-work and New Install 15 days Thu 7/29/27 Wed 8/18/2725
35 Painting 10 days Mon 7/26/27Fri 8/6/27 24
36 Roller shades 25 days Mon 6/21/27Fri 7/23/27 13
37 Toilet Partitions 10 days Mon 8/2/27 Fri 8/13/27 35SS+5 days
38 Final Cleaning 5 days Thu 8/19/27 Wed 8/25/2734
39 Final Inspections 5 days Thu 8/12/27 Wed 8/18/2734SS+10 days
40 Punch List Walk with Architect/Owner 2 days Thu 8/12/27 Fri 8/13/27 34SS+10 days
41 Punch List Work 10 days Mon 8/16/27Fri 8/27/27 40
42 Owner Training 10 days Mon 8/30/27Fri 9/10/27 41
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Aug 23, '26 Aug 30, '26 Sep 6, '26 Sep 13, '26 Sep 20, '26 Sep 27, '26 Oct 4, '26 Oct 11, '26 Oct 18, '26 Oct 25, '26 Nov 1, '26 Nov 8, '26 Nov 15, '26 Nov 22, '26 Nov 29, '26 Dec 6, '26 Dec 13, '26 Dec 20, '26 Dec 27, '26 Jan 3, '27 Jan 10, '27 Jan 17, '27 Jan 24, '27 Jan 31, '27 Feb 7, '27 Feb 14, '27 Feb 21, '27 Feb 28, '27 Mar 7, '27 Mar 14, '27 Mar 21, '27 Mar 28, '27 Apr 4, '27 Apr 11, '27 Apr 18, '27 Apr 25, '27 May 2, '27 May 9, '27 May 16, '27 May 23, '27 May 30, '27 Jun 6, '27 Jun 13, '27 Jun 20, '27 Jun 27, '27 Jul 4, '27 Jul 11, '27 Jul 18, '27 Jul 25, '27 Aug 1, '27 Aug 8, '27 Aug 15, '27 Aug 22, '27 Aug 29, '27 Sep 5, '27 Sep 12, '27
Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress
Date: Tue 9/15/26