This is a Site Assessment and Conceptual Design report prepared by LPA Design Studios and MWL Architects for the City of Hayward's proposed Public Safety Center, a facility intended to address critical deficiencies in the existing police department and animal services infrastructure. The project is supported by a budget of $200–$250 million and encompasses comprehensive programming for both the Hayward Police Department and Animal Services, with two potential sites evaluated: the former California Air National Guard (CANG) site adjacent to Hayward Executive Airport and the City Center site at the former City Hall location in downtown Hayward. The study process included full programming, site analysis, concept massing studies, and detailed cost estimations, ultimately resulting in programmatic reductions to align with available funding. The CANG site was selected as the preferred option, with Phase 1 addressing essential police operations in a 79,176-gross-square-foot Essential Services Building, a 19,537-gross-square-foot Non-Essential Services Building, and supporting site infrastructure across 9.87 acres. Phase 2 is planned to accommodate future programmatic needs under separate funding, while Animal Services was removed from the initial phase scope due to budget constraints.
The final cost estimate for the CANG site is $246,652,888, compared to $259,253,787 for the City Center site, with construction projected to begin in January 2027 and escalation calculated to the project midpoint. The report indicates that the CANG site provides superior advantages including adequate space for all-at-grade parking, reduced seismic design complexity (Seismic Design Category D versus F), minimal construction timeline impacts due to remote location from residential areas, and flexibility for site expansion and future phasing. Site hazards including seismic liquefaction zones and Federal Aviation Administration height clearance reviews for structures exceeding 40 feet were evaluated for both locations. The delivery method evaluation recommends a Public-Private Partnership (P3) structure to provide cost certainty through guaranteed maximum price provisions, contractual schedule commitments, liquidated damages for late delivery, and transparent open-book cost accounting with competitive trade package bidding. The project incorporates a three-story Essential Services Building with parking, outdoor firearms ranges (100-yard and 50-yard configurations), tactical simulation facilities, and secure perimeter design to meet police operational requirements for decades of service.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PUBLIC SAFETY CENTER
SITE ASSESSMENT &
CONCEPTUAL DESIGN
February 10, 2026February 17, 2026
PUBLIC SAFETY CENTER SITE ASSESSMENT & CONCEPTUAL DESIGN
CONTENTS
• Executive Summary
• Program Summary
• Site Assessment & Massing Studies
• Cost Estimate Summary
• Site Selection
• Delivery Method Evaluation
• Summation of Recommendations
• Conceptual Rendering
• Appendix
EXECUTIVE SUMMARY
The City of Hayward is planning a new Public Safety Center to address critical deficiencies in the existing police facility, which no longer meets the department’s space, operational, staffing, and security needs. With growing service demands and aging infrastructure, a modern, resilient facility is essential to support effective public safety operations for decades to come.
Supported by a project budget of $200-250 million, the study began with full programming for both the Hayward Police Department and Animal Services. Two potential sites were evaluated:
| 1. | The former California Air National Guard (CANG) site, adjacent to the Hayward Executive Airport, and |
| 2. | The City Center site, located at the former City Hall site in downtown Hayward. |
Initial programming, site analysis, and concept massing were followed by a comprehensive cost estimate, which significantly exceeded the available budget. This required a strategic reassessment of the overall project scope. Through subsequent rounds of programming refinement, it was determined that the Animal Services program could not be accommodated within the current budget. Additional reductions to the police program were also necessary to align the project with available funding.
Further site analysis showed that increasing the buildable area at the CANG site would allow the project to eliminate the need for a costly parking structure and instead provide all at-grade parking, yielding substantial savings. This adjustment positioned the CANG site as the preferred option for meeting the project’s financial, operational, and phasing requirements.
To maintain long-term functionality while staying within budget, a portion of the police program is planned for Phase 2, which will be delivered under separate and future funding. This phased approach preserves the core operational improvements needed today while creating a pathway for future expansion as resources allow.
The resulting Public Safety Center concept provides a modern, efficient, and flexible solution—responsive to today’s constraints and tomorrow’s needs—ensuring the Hayward Police Department can continue to provide high-quality service to the community.
PRIMARY PARTICIPANTS
City of Hayward
| Alex Ameri | Director of Public Works |
| Dave Hung | Acting Deputy Director of Public Works |
Hayward Police Department
| Bryan Matthews | Chief of Police | |
| Dan Olsen | Captain | |
| Jennie Comstock | Animal Services Administrator |
LPA Design Studios
| Jeremy Hart | Director of Civic + Cultural | |
| Patrick McClintock | San Jose Studio Director | |
| Helen Pierce | Design Director |
MWL Architects (Public Safety)
| Jim McClaren | Principal, Public Safety |
| Pete Seiter | Project Architect |
RFA Architects (Animal Services)
| Warren Freedenfeld | Principal | |
| Eric Nelson | Associate |
In addition, over 50 participants within the Police and Animal Services were interviewed as part of the programming process.
PROGRAM
The following program is a summary of the overall program and includes both building and site programs.
The full program can be found in the Appendix.
Police
| Phase 1 | Essential Services Building | 79,176 gsf | ||
| Phase 1 | Non-Essential Services Building | 19,537gsf | ||
| Phase 1 | Site / Parking | 9.57 acres |
Phase 2 Site / Parking .3 acres
Total
| Essential Building | 79,176 gsf | |||
| Non-Essential Building | 19,537 gsf | |||
| Total Building | 98,712 gsf | |||
| Site | ` | 9.87 acres |
Program Summary
SITE ASSESSMENT
Two sites were accessed as part of this study:
Site A is the former California Air National Guard (CANG) site adjacent to the Hayward Executive Airport.
Site B is the City Center site and former site of the Hayward City Hall in downtown Hayward.
The two sites were examined for their suitability to support a new Public Safety Facility.
Site Option A
CANG
Site Option B City Center
Site Options A&B Locations
Current Location of HPD
Site Options A&B Data
Site B - City Center
| • | 3 Parcels @ 5.79 +/- Acres |
| • | Zoning: UC |
| • | Within Downtown Specific Plan |
| • | Retail and Office Commercial (ROC) Zone |
| • | Designated as Future Housing Element |
| • | Council; District 1 |
| • | Borders Seismic Liquefaction Zone |
| • | Adjacent to Hayward Fault |
| • | Elevation: Approx 131’ - 140’ Above Sea Level |
Site A - CANG
| • | 1 Proposed Site @ 8.1 +/- Acres |
| • | Zoning: At-Ac & At-C per Hayward Zoning Map |
| c.Air Terminal—Aviation Commercial (AT-AC). | |
| d.Air Terminal—Commercial (AT-C). |
| • | Within Airport Boundary |
| • | Public/Quasi-Public (PQP) Zone |
| • | Council; District 4 |
| • | Within Seismic Liquefaction Zone |
| • | Elevation: Approx 31’ - 36’ Above Sea Level |
Existing Hanger Existing Parking Garage
SEC. 10-1.1942 - AT-AC USES PERMITTED.
a.Primary Uses. The following uses, or uses determined to be similar by the Planning Director, are permitted in the AT-AC District, as primary uses.(1)Aviation Commercial Uses.(a)Air photography, survey, and map-making services.(b)Air charter service.(c) Aircraft repair.(d)Aircraft storage (inside or outside).(e)Aviation clubs.(f)Aviation schools.
(g)Passenger transportation terminal.(h) Retail sales within passenger transportation terminals.(i)Retail sales of aviation equipment, aircraft, fuel and lubricants.(2)Administrative and Professional Offices/Services.
None.
(3)Automobile Related Uses.
Parking lot.
(4)Personal Services.
None.
(5)Residential Uses.
None.
(6)Retail Commercial Uses.
None.
(7)Service Commercial Uses.
None.
(8)Other Uses.
None.
b.[Reserved.] (Amended by Ordinance 19-10, adopted June 4, 2019)
SEC. 10-1.1943 - AT-AC CONDITIONALLY
PERMITTED USES.
a.Administrative Uses. The following uses or uses determined to be similar by the Planning Director, are permitted in the AT-AC Subdistrict, subject to approval of an administrative use permit:(1)Aviation Commercial Uses.
None.
(2)Administrative and Professional Offices/ Services.
None.
(3)Automobile Related Uses.
Automobile rental.
(4)Personal Services.
None.
(5)Residential Uses.
None.
(6)Retail Commercial Uses.
Restaurant. (No drive-through.)
(7)Service Commercial Uses.
None.
(8)Other Uses.
None.
b. Conditional Uses. The following uses or uses determined to be similar by the Planning Director, are permitted in the AT-AC Subdistrict, subject to approval of a conditional use permit:(1)Aviation Commercial Uses.
None.
(2)Administrative and Professional Offices/ Services.
None.
(3)Automobile Related Uses.
None.
(4)Personal Services.
None.
(5)Residential Uses.
None.
(6)Retail Commercial Uses.
Sales, rental, and service of non-aviation equipment, when compatible with aviation uses, for a period not to exceed one day less than
Site Option A - CANG Zoning
Site Option B - City Zoning & Specific Plan
Site Options A&B Data
Site A - CANG
| • | 1 Proposed Site @ 8.1 +/- Acres |
| • | Zoning: At-Ac & At-C per Hayward Zoning Map |
| c. | Air Terminal—Aviation Commercial (AT-AC). |
| d. Air Terminal— | Commercial (AT-C). |
| • | Within Airport Boundary |
| • | Public/Quasi-Public (PQP) Zone |
| • | Council; District 4 |
| • | Within Seismic Liquefaction Zone |
| • | Elevation: Approx 31’ - 36’ Above Sea Level |
Site B - City Center
| • | 3 Parcels @ 5.79 +/- Acres |
| • | Zoning: UC |
| • | Within Downtown Specific Plan |
| • | Retail and Office Commercial (ROC) Zone |
| • | Designated as Future Housing Element |
| • | Council; District 1 |
| • | Borders Seismic Liquefaction Zone |
| • | Adjacent to Hayward Fault |
| • | Elevation: Approx 131’ - 140’ Above Sea Level |
N
S E
W
C I
T Y
O
F
H A
Y W
A
R D
PROPOSED
PUBLIC SAFETY CENTER SITE
FORMER
CITY CENTER/CENTENNIAL HALL SITE
5/22/25 1"=60'
N S
E W
CITY
O F
H A
Y W
A
RD
B.D.S.
1" = 100'
CLAWITER RD.
W
IN
TO
N
A
VE
TUSKEGEE AIRMAN DR.
BACK OF CURB
EXISTING LEASE LINE
APPROXIMATE EXISTING FENCE LINE
NOTE:
THE SITE AREA HAS BEEN DETERMINED BY RECORD
LEASE AGREEMENTS, STREET IMPROVEMENT PLANS,
RECORD RIGHT OF WAY AND FENCE LINES DEPICTED
OFF AERIAL PHOTOGRAPHY. THE AREAS SHOWN MY BE
ADJUSTED AFTER A FIELD SURVEY IS PERFORMED.
6/4/2025
PROPOSED
PUBLIC SAFETY CENTER SITE
PORTION OF FORMER
CALIFORNIA AIR NATIONAL GUARD LEASE AREA
W. Winton Ave
Claw iter Rd
Tuskegee Airmen Dr.
Hesperian Blvd
Union Pacific Rail Road
Hayward Executive Airport
Hayward Fire Station 6 & Regional Training Center
North
Site Option A - CANG Site Access
Site Option A - CANG Airport Runway Height Clearances
+52’ MSL Elevation
+148’ MSL Height Limitation
Seismic Risk
• Hayward Fault relative to Airport Site
| • | Risk Category IV |
| • | Essential Facility |
| • | Seismic Design |
Cat D
• SDS= 1.45
Flood Risk
• Area Of Minimal Flooding Hazard (land outside the 0.2% annual chance (500-year) floodplain)
Site Option A - CANG
SITE
SITE
Site Hazards
Site Option A - CANG Preliminary Massing Studies
The following preliminary site and massing studies for the CANG site were based on the initial, full Police and Animal Services programs as well as the initial smaller (8.1 acre) site area. Due to the size of the Police and Animal Services program and the initial site area all secured parking is shown in a 3-story garage.
Definition: Massing Studies - Early stage architectural analysis used to show only overall size, shape and form.
Site Option A - CANG
Three Story 91,151 gsf Essential Services First Floor 50% Second & Third 50%
One Story 30,234 gsf Non-Essential Services
Three Story Parking 70,000 sf / flr 210,000 sf total
Visitor Parking
Entry / Public Plaza
Service / Secure Garage Access
100 Yard Outdoor rangeTwo Story Animal
Services 29,180 gsf
Tactical Simulation Building
Outdoor / Expansion Space for Ess Serv
Outdoor Training / Expansion Space for Non-Ess Serv
Jail Release / Evidence Pick-Up Parking
Preliminary Massing Studies
W. Winton Ave.
Tu sk eg ee
A irm en D r.
*Reflects original programmatic square footages*
Three-Story 91,151 gsf Essential Services First Floor 50% Second & Third 50%
One Story 30,234 gsf Non-Essential Services
Three Story Parking 70,000 sf / flr 210,000 sf total
*Reflects original programmatic square footages*
Visitor Parking
Entry / Public Plaza
Service / Secure Garage Access
100 Yard Outdoor rangeTwo Story Animal
Services 29,180 gsf
Tactical Simulation Building
Outdoor / Expansion Space for Ess Serv
Outdoor Training / Expansion Space for Non-Ess Serv
Jail Release / Evidence Pick-Up Parking
Preliminary Massing Studies
W. Winton Ave.
Tu sk eg ee
A irm en D r.
Site Option A - CANG Final Massing Study
Further review of the Police and Animal Services program and related cost estimates dictated a reduction in project scope and enlargement of site from 8.1 acres to 9.87 acres to support all at-grade parking. The following diagrams indicate a reduced program and 2-phase approach to meet Police needs and current available funds.
One Story 19,537 gsf Non-Essential Services
All At-grade Parking
Visitor Parking
Entry / Public Plaza
Secure Access
Expansion Space for Ess Serv
Storm Water Area
Jail Release / Evidence Pick-Up Parking
Final Massing Study - Phase 1
9.87 Acre Site
100 & 50 Yard Shooting Range
Secure Perimeter
Three-Story 79,176 gsf Essential Services First Floor 50% Second & Third 50%W. Winton Ave.
Tu sk eg ee
A irm en
Tactical Simulation Building
Future Non Essential Service
Outdoor K9 Training
Final Massing Study - Phase 2
W. Winton Ave.
Tu sk eg ee
A irm en
Animal Services
Expand Visitor Parking
Parking Garage Required when Animal Services Added
Final Massing Study - Future Phase
W. Winton Ave.
Tu sk eg ee
A irm en
Site Option B - City Center
B.A.R.T.
City Center Dr, Foothill Blvd
A St.
2nd St., M ain St.Mission Blvd.
Site Access to 880 in xx miles
Seismic Risk
• Hayward Fault relative to City Center Site
| • | Risk Category IV |
| • | Essential Facility |
| • | Seismic Design |
Cat F
• SDS= 1.67
Flood Risk
• Area Of Minimal Flood Zone (land outside the 0.2% annual chance (500-year) floodplain)
Site Option B - City Center
SITE
SITE
Site Hazards
Site Option B - City Center Massing Studies
Five Story (two Bay) Parking 42,000 sf / flr 210,000 sf total
Three Story 91,151 gsf Essential Services First Floor 50% Second & Third 50%
Visitor Parking
Entry / Public Plaza
Garage / Service Access
Garage Top Outdoor Animal Services Area
30,234 gsf Non-Essential Services Under Parking
Two Story 29,180 gsf Animal Services
Garage Top Outdoor Animal Services Area
Outdoor Roof Area for Ess
Not Included
| • | Tactical Simulation Building |
| • | 100 Yard Outdoor Range |
| • | K9 Training |
Outdoor / Expansion Space
City Center Dr.
Site Option B - City Center Massing Studies
Two Story 32,000 gsf Animal Services
Five Story (two Bay) Parking 42,000 sf / flr 210,000 sf total
Three Story 91,151 gsf Essential Services First Floor 50% Second & Third 50%
Visitor Parking City Center Dr.
Entry / Public Plaza
Garage / Service Access
Garage Top Outdoor Animal Services Area
30,234 gsf Non-Essential Services Under Parking
Two Story 29,180 gsf Animal Services
Garage Top Outdoor Animal Services Area
Outdoor Roof Area for Ess
Not Included
| • | Tactical Simulation Building |
| • | 100 Yard Outdoor Range |
| • | K9 Training |
Outdoor / Expansion Space
Preliminary Site & Massing Study
Included here are the Site and Massing Studies for the City Center Site. Through the process of site analysis, programming and cost estimating, the City Center site was deemed to be unsuitable based on the following:
| • | Inadequate size for at grade parking |
| • | Inadequate size and location for outdoor training (shooting range, K9 training and Tactical Simulation Building) |
| • | Less appropriate site adjacencies for associated noise. |
| • | Costs associated with construction site access and work hours |
| • | Costs associated with proximity to Hayward fault |
Site Option B - City Center
COST ESTIMATE SUMMARY CANG Site
The following Cost Estimate Summary was performed by HLCM, a Professional Cost Estimating Consultant and is based on the Program, Site and Massing Studies.
Numbers include:
| • | Construction Start January 2027 |
| • | To Mid-point of Construction Escalation |
| • | CWA Labor Cost |
| • | Soft Costs |
Notes
$92,053,274
$ 1,900,000
$ 336,806,162
$ 54,348,330 $2,431,380 $2,260,232 $1,022,570 $2,327,378 $8,160,967 $9,009,202 $5,613,947 $2,453,568 $1,975,342 $3,259,439 $1,090,919
Moved to Future Phase Reduce to Align W/ Materials Handling Survey Moved to Phase 2 Removed Removed SWAT Briefing Room Reduced Capacity Reduced Indoor Range From 50-Yard to 25-Yard Reduced Future Growth by %5 & Reduced Workstation Size Removed 1 of the Multi-Purpose Rooms Reduced to 1 Exam Bay Removed Break Room & Waiting Area Reduced Lobby
Total Reduction
Total Add
Base Estimate - CANG Site
Scope Alignment
Animal Services Property & Evidence Tactical Simulation Building K-9 Special Response Unit Jail Indoor Firing Range Office Area Public Spaces / MPR Crime Lab Vehicle Exam Bay Youth & Family Services Break & Lobby Public Spaces Main Lobby
$1,900,000 Add (4) Outdoor 50-Yard LanesOutdoor Range
$246,652,888Total Cost
COST ESTIMATE SUMMARY City Center Site
The following Cost Estimate Summary was performed by HLCM, a Professional Cost Estimating Consultant and is based on the Program, Site and Massing Studies.
*Note: The City Center Total Costs is not directly comparable to the CANG site costs. The City Center Site does not include program features included at the CANG site including Outdoor Fire Range, Tactical Simulation Building & K9 Training”
Numbers include:
| • | Construction Start January 2027 |
| • | To Mid-point of Construction Escalation |
| • | CWA Labor Cost |
| • | Soft Costs |
Notes
$ 92,627,237
$ 0
$ 351,881,024
$ 54,753,003 $0 $2,491,414 $0 $1,032,670 $2,346,460 $8,220,450 $9,076,955 $7,956,541 $2,745,426 $1,991,073 $1,464,560 $548,685
Moved to Future Phase Site Area Reduction in Phase 1 Reduce to Align W/ Materials Handling Survey Not Included Removed Removed SWAT Briefing Room Reduced Capacity Reduced Indoor Range From 50-Yard to 25-Yard Reduced Future Growth by %5 & Reduced Workstation Size Removed 1 of the Multi-Purpose Rooms Reduced to 1 Exam Bay Removed Break Room & Waiting Area Reduced Lobby
Total Reduction
Total Add
Base Estimate - City Center Site
Scope Alignment
Animal Services Site Area Property & Evidence Tactical Simulation Building K-9 Special Response Unit Jail Indoor Firing Range Office Area Public Spaces / MPR Crime Lab Vehicle Exam Bay Youth & Family Services Break & Lobby Public Spaces Main Lobby
$0 Not IncludedOutdoor Range
$ 259,253,787Total Cost
SITE SELECTION
Site selection has been based on 11 primary criteria that have been weighted via the process of site analysis, project programming and cost estimation.
The criteria have been designated with Green, Yellow, Red designation to indicate suitability to meet the criteria.
Most Advantageous
Moderate
Least Advantageous
Site Option Community Service
Community Access
Community Advantages
Program Optimization
Project Costs
Site Expansion
Availability of Utilities
Site Hazards
Construction Duration
Topography & Soils
Site A
CANG
Site B City Center
Community Challenges
Site A - CANG
| • | Located somewhat more centrally |
| • | Intersection of Winton & Hesperian traffic impact |
| • | Easy access to 880 |
Site B - City Center
| • | Located on far northern edge of Hayward |
| • | Located in City Center and near other governmental entities |
| • | No immediate access to major highways |
Site Selection Community Serviceability
Community Service
Community Access
Community Advantages
Program Optimization
Project Costs
Availability of Utilities
Site Hazards
Construction Duration
Topography & Soils
Site A
CANG
Site B City Center
Community Challenges
Site A - CANG
| • | Not in close proximity to immediate residential |
| • | Closer proximity to most of Hayward |
Site B - City Center
• In close proximity to residential and commercial downtown and governmental services
| • | Remote from most of Hayward |
| • | More accessible from public transit |
Site Selection Community Access
Site Expansion
Community Service
Community Access
Community Advantages
Program Optimization
Project Costs
Availability of Utilities
Site Hazards
Construction Duration
Topography & Soils
Site A
CANG
Site B City Center
Community Challenges
Site A - CANG
| • | Noise & activity located away from residential |
| • | Proximity to Fire Station & Training Center |
Site B - City Center
| • | Police presence in City Center |
| • | Development of vacant site in urban core |
Site Selection Community Advantages
Community Service
Community Access
Community Advantages
Program Optimization
Project Costs
Availability of Utilities
Site Hazards
Construction Duration
Topography & Soils
Site A
CANG
Site B City Center
Community Challenges
Site A - CANG
• Feels less embedded into the community
Site B - City Center
| • | Noise and Activity in dense area of City Center & residential |
| • | Designated Future Residential in Downtown Specific Plan |
| • | Center of site designated as potentially historic in Downtown |
Specific Plan
• Likely will not comply with the form and use vision for the “Mixed-
Use Gateway” outlined in the Downtown Specific Plan
Site Selection Community Challenges
Community Service
Community Access
Community Advantages
Program Optimization
Project Costs
Availability of Utilities
Site Hazards
Construction Duration
Topography & Soils
Site A
CANG
Site B City Center
Community Challenges
Site A - CANG
| • | Better fits all program needs |
| • | Proximity to Fire Station & Training Center |
| • | More opportunity for outdoor program space & flexibility |
| • | Potential Phasing |
| • | Future Expansion Potential |
Site B - City Center
| • | May be challenged to meet all program needs |
| • | May require less ideal programmatic relationships |
| • | Less opportunity for future growth |
| • | Require more vertical construction |
Site Selection Program Optimization
Community Service
Community Access
Community Advantages
Program Optimization
Project Costs
Availability of Utilities
Site Hazards
Construction Duration
Topography & Soils
Site A
CANG
Site B City Center
Community Challenges
Site Selection Site Expansion
Site Expansion
Site A - CANG
• Provides more flexibility for site to flex to meet the needs of the program and the budget
Site B - City Center
• Fixed site size with no flexibility to expand.
Community Service
Community Access
Community Advantages
Program Optimization
Project Costs
Availability of Utilities
Site Hazards
Construction Duration
Topography & Soils
Site A
CANG
Site B City Center
Community Challenges
Site Selection Availability of Utilities
Site Expansion
Site A - CANG
• Has suitable access to all utilities
Site B - City Center
• Has suitable access to all utilities
Community Service
Community Access
Community Advantages
Program Optimization
Project Costs
Availability of Utilities
Site Hazards
Construction Duration
Topography & Soils
Site A
CANG
Site B City Center
Community Challenges
Site A - CANG
• Federal Aviation Administration (FAA) review: All proposed commercial projects exceeding 40 feet in height must undergo review by the FAA. Taller projects may be permitted if the FAA determines they do not pose a hazard. (see Airport exhibit)
• Drone compatibility TBD
Site B - City Center
• Dense urban area in close proximity to Hayward fault
Site Selection Site Hazards
Community Service
Community Access
Community Advantages
Program Optimization
Project Costs
Availability of Utilities
Site Hazards
Construction Duration
Topography & Soils
Site A
CANG
Site B City Center
Community Challenges
Site A - CANG
| • | Within Seismic Liquefaction Zone | |
| • | (Fire Training Soils Report indicates shallow foundations) | |
| • | Additional site remediation may be required | |
| • | Previously developed site | |
| • | Level site |
Site B - City Center
| • | Borders Seismic Liquefaction Zone |
| • | Previously developed site |
| • | Some grade challenges |
Site Selection Topography & Soils
Community Service
Community Access
Community Advantages
Program Optimization
Project Costs
Availability of Utilities
Site Hazards
Construction Duration
Topography & Soils
Site A
CANG
Site B City Center
Community Challenges
Site A - CANG
| • | Ample site area for construction operations |
| • | Good access from major roads |
| • | Flexible work times due to remoteness from residential areas |
Site B - City Center
| • | Limited site area for construction operations |
| • | More vertical construction = extended construction time |
| • | Site access through dense urban area |
| • | Limited work times due to adjacent residential area |
Site Selection Construction Duration
Community Service
Community Access
Community Advantages
Program Optimization
Project Costs
Availability of Utilities
Site Hazards
Construction Duration
Topography & Soils
Site A
CANG
Site B City Center
Community Challenges
Site A - CANG
| • | Lower design category for seismic = less costs | |
| • | May support 2-story construction | |
| • | May require deep foundations due to liquefaction | |
| • | (Fire Training Soils Report indicates shallow foundations) |
Site B - City Center
| • | Higher design category for seismic = more costs |
| • | More likely requires more vertical construction |
| • | Dense urban area project location may extend construction timeline |
Site Selection Project Costs
Site A - CANG
The former California Air National Guard site adjacent to the Hayward Executive Airport has been determined to the most optimal site for the development of a new Hayward Public Safety Facility. The availability of site area and expansion of site area will permit the greatest flexibility to meet the needs of the program within the city’s budget.
Site Selection Final Selection
Site Option Community Service
Community Access
Community Advantages
Program Optimization
Project Costs
Availability of Utilities
Site Hazards
Construction Duration
Topography & Soils
Site A
CANG
Site B City Center
Community Challenges
DELIVERY METHODS
The construction delivery method is the approach used to design and construct a project. It defines how the project team is structured, how contracts are established, and how responsibilities, risks, costs, and schedules are managed among the owner, designer, and contractor. The traditional delivery method and common to CIP projects in the City is Design-Bid-Build. Other alternative delivery methods include Design–Build, Progressive Design-Build, Construction Manager at Risk, and Public Private Partnership (P3). Each delivery method offers different advantages related to cost control, schedule certainty, and collaboration.
Design–Bid–Build (DBB): the traditional project delivery method in which the owner contracts separately with a designer and a construction contractor. The designer completes the full design and prepares construction documents, after which the project is competitively bid and awarded to a contractor. Construction begins only after design is complete. This approach provides clear roles, strong pricing competition, and a well-defined scope, but it can result in longer schedules and limited collaboration between design and construction teams.
Design–Build (DB): DB is a delivery method in which the owner contracts with a single entity that is responsible for both design and construction. The design-builder integrates design and construction services under one contract, allowing for overlapping phases, earlier cost certainty, and faster project delivery. This method reduces owner coordination responsibilities and can minimize disputes, though it requires the owner to clearly define performance requirements at the outset.
Progressive Design–Build (PDB): PDB is a form of design–build in which the owner selects a design-builder primarily based on qualifications rather than a fixed price. The design-builder works collaboratively with the owner during early design to develop scope, schedule, and cost, with pricing established later as the design advances. This approach emphasizes transparency, shared risk management, and flexibility to refine project goals while maintaining the benefits of integrated delivery.
Construction Manager at Risk (CMAR): CMAR is a delivery method in which the owner contracts with a construction manager during the design phase to provide constructibility input, cost estimating, and scheduling services. The construction manager later assumes the role of general contractor and provides a guaranteed maximum price, taking responsibility for delivering the project within that price. CMAR promotes early collaboration and cost control while preserving a separate designer–owner relationship.
Public–Private Partnership (P3). P3 is a customized contractual arrangement in which a public agency partners with a private entity to deliver a public facility. The private partner may be responsible for design, construction, and financing, (e.g., a Progressive Design-Build-Finance or DBF P3 model), as well as flexibly structuring operation, and/or maintenance responsibilities over short-, medium-, and long-term periods (e.g., a DBF+OM P3 model). P3s leverage private-sector developer expertise and financing to deliver complex projects more efficiently, with risks allocated to the party best able to manage them and performance guarantees provided by the development partner.
Selecting an appropriate construction delivery method ensures that the project is delivered efficiently, transparently, and in alignment with the goal for accountability, budget control, and timely completion. For this project, the Public–Private Partnership (P3) delivery method is considered the most advantageous because it combines strong cost and schedule certainty with enhanced accountability and transparency. Under a P3 structure, the project can be delivered with a guaranteed maximum price (GMP), contractual schedule commitments, and liquidated damages for late delivery, providing the City with meaningful protections against cost overruns and delays. The P3 approach supports an open-book delivery process, with full cost transparency and audit rights retained by the City, while maintaining public-sector safeguards such as competitively bid trade packages. This structure also enables efficient risk allocation to the parties best able to manage those risks and allows any cost savings achieved during delivery to revert to the City. Collectively, these features provide a high level of fiscal control, performance accountability, and delivery certainty, making the P3 delivery method the most appropriate choice for this project.
DELIVERY METHOD EVALUATION
The project Delivery Method Evaluation below is based on general observations and experience and will vary project to project.
Site Option Control Cost Certainty
Owner Resources
Quality Time
Each delivery method offers a different balance of cost, schedule, risk, and owner involvement. Design-Bid-Build provides the highest degree of control over the design outcome, but that control comes with increased exposure to change-order risk and the longest delivery timeline. CM@Risk improves coordination and cost certainty through early contractor involvement, but still requires active Owner oversight throughout design development.
Progressive Design-Build offers the strongest alignment of cost, quality, and schedule by structuring collaboration from day one. Risk is shared early, and innovation is encouraged, reducing soft costs and accelerating delivery. Public-Private Partnership is most advantageous when the Owner’s goal is to transfer long-term risk, minimize internal resource demands, and lock in lifecycle performance — though it requires acceptance of the lowest direct control over design and long-term asset flexibility.
The following matrix visually reinforces the importance of aligning delivery method selection with the Owner’s priorities — whether that is control, speed, cost certainty, risk transfer, or resource capacity.
Site Option Control Risk Cost Certainty
Collaborative City Staffing
Soft Costs
Design Bid Build
Progressive Design Build
CM@Risk
Public Private Partnership
Quality Time
Summary
| Method | Best When | Biggest Drawback | ||||
| DBB | Maximum owner control over design | Slower, high change-order risk, adversarial | ||||
| CMAR | Balance of control and cost/risk sharing | Can still lead to disputes if design not coordinated | ||||
| PDB | Collaboration, speed, innovation, cost alignment | Reduced owner influence over detailed design | ||||
| P3 | Collaboration, speed, innovation, cost alignment & financing | Structure of team can limit competition |
Most Advantageous
Moderate
Least Advantageous
Delivery Method Evaluation Matrix
SUMMATION OF RECOMMENDATIONS
| Site: | CANG Site | |||
| Site | Size: 9.87 acres | |||
| Cost: | $246,652,888 | |||
| Phases: | 2 w/Future Option for Animal Services | |||
| Bldg Size: | 98,712 gsf | |||
| Schedule: | TBD | |||
| Delivery Method: | TBD |
| Site: | City Center Site | |||
| Site | Size: 5.79 acres | |||
| Cost: | $268,035,686 | |||
| Phases: | 1 w/Future Option for Animal Services | |||
| Bldg Size: | 98,712 gsf + Parking Garage | |||
| Schedule: | TBD | |||
| Delivery Method: | TBD |
Recommended Option
*Note: The City Center Total Costs is not directly comparable to the CANG site costs. The City Center Site does not include program features included at the CANG site including Outdoor Fire Range, Tactical Simulation Building & K9 Training”
$259,253,787
Conceptual Rendering Performance I Camaraderie I Transparency
View from W. Winton Ave.
APPENDIX
| • | Full Building & Site Programs |
| • | Full Cost Estimates |
HAYWARD POLICE DEPARTMENT
PUBLIC SAFETY CENTER
HAYWARD, CALIFORNIA
MCCLAREN, WILSON & LAWRIE ARCHITECTS
LPA
FEBRUARY 9, 2026
POLICE FACILITIES MASTER PLAN
SPACE NEEDS SUMMARIES
FEBRUARY 9, 2026 Project Overview
HAYWARD PUBLIC SAFETY CENTER
SPACE NEEDS ASSESSMENT
Phase 1
Essential Services Building: 79,176 gsf
Non-Essential Services Building: 19,537 gsf
Site / Parking: 7.48 acres
Phase 2
Essential Services Building: 0 gsf
Non-Essential Services Building: 0 gsf
Site / Parking: 0.30 acres
Animal Services Building & Site: future phase or renovation of existing facility
Total
Essential Services Building: 79,176 gsf
Non-Essential Services Building: 19,537 gsf
Total Building: 98,712 gsf
Total Site: 7.78 acres
9.57 acres
9.87 acres
FEBRUARY 9, 2026 Project Overview
SPACE NEEDS ASSESSMENT
Building and Site Square Footage Program This section includes space and staff spreadsheets outlining the assignment of square footage and staff needs. Here are a few explanations of the space needs document format to aid in review:
Programming Milestones This space needs assessment identifies space and staff requirements for three milestones:
• Milestone Space Needs Program 2049 The space contemplated to address projected space needs for the year
2049.
• Milestone Prioritized Program The space prioritized by HPD, reducing scope to stay within budget.
• Milestone Second Phase The space needed on site for future addition of specific functions removed from scope of first phase.
Please note that staffing indicated in growth projections are based on projections furnished by the HPD and do not suggest that staffing will grow at any specific pace, instead the projections identify space needs suitable to serve staffing at those levels (understanding that staffing levels may fluctuate at rates that are faster or slower).
• Building Area Summary
Adjusted net square footage from the detailed spreadsheet pages are entered into the summary page. On the summary page a grossing factor is added to the summary of the adjusted net square footage to arrive at the total gross square footage for the building.
Space Number The space number is included for reference. In some circumstances the space number repeats for a variety of items. This designates where items will reside in the same space.
The program uses three types of square footage; Net, Adjusted Net and
Gross Square foot.
FEBRUARY 9, 2026 Space Summaries
SPACE NEEDS ASSESSMENT
Square Footage Summary
Net Square Footage Net square footage is the direct usable space needed for offices, workstations, file cabinets and equipment such as copy machines.
Direct usable space is identified by space codes (for example: PO = Private
Office and OP = Open Plan workstation) and then support spaces. Staffing is identified by LKR (staff with lockers) and WD (staff with wardrobe at desk).
In some spaces staffing numbers have no assignable office or workstation space. To account for shifted workspaces there is a number of spaces column.
Adjusted Net Area At the bottom of each list of net square footages there is a circulation factor. This is square footage needed to provide for aisles and walk around space to connect spaces within each area of the building.
Net
Square
Feet
Adj. Net
Square
Feet
FEBRUARY 9, 2026 Space Summaries
SPACE NEEDS ASSESSMENT
Square Footage Summary
The circulation factor varies depending upon the needs of each space group. For example, most spaces have a circulation factor of 25%, though some technical spaces require a larger circulation, yet bulk areas (such as the evidence) require smaller circulation factors. When the net space and circulation factor are added the result is the adjusted net area.
Gross Square Footage The adjusted net area is totaled on the summary page where a grossing factor (sometimes referred to as an “efficiency” factor) is added to allow for the space that is lost to wall / partition thicknesses, structural columns, the corridors that connect each area of the building and support spaces for janitor closets, premise wiring closets, mechanical rooms and electrical rooms).
Gross
Square
Feet
SPACE NEEDS ASSESSMENT
Site / Parking Summary
FEBRUARY 9, 2026 Space and Site Summaries
Parking Requirements This section includes space onsite required for staff vehicles, fleet vehicles, and visitors. These are split between secure parking for staff and fleet vehicles, and public parking for visitors.
• Staff Parking
Staff parking requirements are determined by the maximum amount of people working in the building during the largest shift, plus enough parking for people who staff the 24-hour operations to perform a shift changeover.
This means operations such as patrol and dispatch will need parking spaces for both the incoming shift staff and outgoing shift staff.
Other Site Needs This section includes space on site required for infrastructure (antenna tower, generator, dumpsters, etc.), outdoor training spaces (firearms range and tactical simulation building), and storage needs (haz-mat, bikes, etc.).
Program Prioritization
FEBRUARY 9, 2026 Space and Site Summaries
Program Prioritization Reductions to the initial program were required to meet budget. The following reductions were made following feedback from the City and users regarding the priorities of each group
• Public Spaces
The prioritizing of the program led to a reduction of the public lobby and the removal of one of the community meeting rooms.
• Workstations
The size of workstations were reduced where functionality would not be compromised.
• Animal Services
Animal services was removed from initial scope, with the option to be included in a later phase or located elsewhere.
• Firearms Training
The Indoor firearms range, originally planned to be 50 yards, was reduced to a 25 yard range. The 100yd outdoor range remains in the initial phase with a
(4) lane 50yd outdoor range planned for a future phase. The tactical simulation building also moved to a future phase.
• Property & Evidence
Property and evidence saw a reduction in the number of workstations, drying cabinets, and evidence lockers. Total evidence storage was also reduced by about 1,000 square feet. In total the property and evidence program was reduced by 1,500 square feet.
• K-9
The entirety of the K-9 program was removed from the scope of this project.
• Special Response Unit
The special response unit’s dedicated briefing room was removed from the scope with the assumption the unit could use the patrol briefing room when needed.
• Jail
The jail saw a reduction in storage space, kitchen size, and number of cells.
This reduced the max capacity of the jail from (49) people down to (35) people. This allowed for a reduction of 3,119 square feet.
Program Prioritization
FEBRUARY 9, 2026 Space and Site Summaries
• Emergency Communications
Emergency communications saw a reduction of the size of the break room, and the number of dispatch consoles was reduced from (16) to (14)
• Lockers
There is no proposed reduction to the lockers in this program, but if there is an opportunity to reduce the space needs by 1,318 square feet and reduce the number of lockers required by 63 if open lockers are implemented.
• Vehicle Exam
The prioritized program has reduced the amount of vehicle exam bays to 1
• Youth & Family Services
Reductions made to the youth and family services bureau include the removal of the overflow counseling rooms, the waiting room, and the dedicated breakroom.
Hayward, California
Public Safety Center
Space Needs Assessment
• Summary •
2/9/2026
Milestones
LKR = Staff W/Lockers
WD = Staff W/Wardrobe at Desk
Public Spaces
1.00 Public Spaces 0 0 0 0 5,714 3,683
Includes Community Meeting / Multi-purpose
Room
Administration
2.00 Police Administration 7 8 7 8 3,824 3,709
3.00 Internal Affairs 3 2 3 2 910 900
4.00 Police Wellness 0 1 0 1 760 760
Community Services Division
5.00 District Operations Unit 25 0 25 0 0 0
6.00 Traffic 10 1 10 1 1,143 1,093
7.00 Personnel & Training 2 4 2 4 1,433 1,333
8.00 Youth & Family Services 0 37 0 37 5,405 3,910
9.00 Volunteer (Reserves) Program 1 0 1 0 410 390
Investigations Division
10.00 Criminal Investigations 27 6 27 6 5,088 4,758
11.00 Special Investigations 26 6 26 6 4,365 4,115
12.00 Shared Investigations Spaces 0 0 0 0 1,823 1,823
13.00 Crime Lab 0 0 0 0 3,184 2,384
Patrol Division
14.00 Patrol 120 0 120 0 6,398 5,973
15.00 K9 7 0 7 0 - - See Support Building
16.00 Special Response Unit 0 0 0 0 - - See Support Building
Support Service Division
17.00 Records 0 19 0 19 3,684 3,189
18.00 Emergency Communications 0 59 0 59 5,420 4,796
reduction in break room size, workstation size, and dispatch consoles from 16 to 14
19.00 Real Time Information Center
(RTIC)
0 3 0 3 930 855
20.00 Animal Services 0 17 0 0 - -
21.00 Jail 25 0 25 0 7,073 3,954 49 max capacity reduced to 35
22.00 Property & Evidence 0 6 0 6 - - See Support Building
23.00 I.T. 0 14 0 14 580 540
Shared Spaces
24.00 Shared Staff Areas 0 0 0 0 8,586 8,586
Fitness / Lunch / Lockers. Traditional lockers assumed, 1,318sf reduction available if open lockers are used
25.00 Facilities Support 0 1 0 1 957 957
26.00 Ground Level Shared Spaces 0 0 0 0 1,643 1,643
27.00 2nd Level Shared Spaces 0 0 0 0 2,205 2,205
28.00 3rd Level Shared Spaces 0 0 0 0 1,429 1,429
72,959 62,980
Total Staff 253 184 253 167
Remarks
Square Footage
Space Needs
Program
Staffing
Prioritized
Program
437 420
Space Needs
Program
Prioritized
Program
LKR WD LKR WD
McClaren, Wilson + Lawrie, Inc.
In Collaboration With
LPA
Summary 1
Space Needs Assessment
• Summary •
2/9/2026
72,959 62,980
Stair / Elevator Factor 3 3,600 3,600 Initial assumption - 3-story building
Grossing Factor 20% 14,592 12,596
91,151 79,176
678 0
3,048 1,550
5,905 4,403
16,660 11,035 Indoor 25-yd range
- - See Site
26,290 16,988
Grossing Factor 15% 3,944 2,548
30,234 19,537
121,385 98,712
29,180 0
Grossing Factor 0% 0 0
29,180 0
150,565 98,712
Animal Services (Not Essential Services)
20.00 Animal Services
Total Gross Square Footage
Total Gross Square Footage Main + Support Building + Animal Services
Total Gross Square Footage
Main Essential Services Building
Sub-Total Adjusted Net Square Footage
Support Building (Not Essential Services)
29.00 Firearms Range & Specialized Training
Total Gross Square Footage
Total Gross Square Footage Main + Support Building
30.00 Tactical Simulation Building
16.00 Special Response Unit
15.00 K9
22.00 Property & Evidence
Sub-Total Adjusted Net Square Footage
McClaren, Wilson + Lawrie, Inc.
In Collaboration With
Summary 2
Space Needs Assessment
• Itemized Spaces •
2/9/2026
Milestones
S p a ce
N e e d s
P ri o ri ti ze
P ro g ra m
S p e d s
P ri o ri g ra m
LKR = Staff W/Lockers
WD = Staff W/Wardrobe at
Desk
LKR WD LKR WD
1.00 Public Spaces
1.01 Public Entry Vestibule 1 1 100 100 100
For energy efficiency and safety. Provide after hours call station to dispatch. Provide electronic door lock/unlock to records & dispatch. Recommendation: Use ballistically rated doors between Vest and
Lobby.
1.02 Public Lobby 1 1 500 1,000 500 Professional / Durable / Calming
• Front Public Services
Counter Positions
4 4 SCTR 192 192
Protected transaction window to Lobby
(access from Records).
1.03 Public Restrooms 2 2 T3 450 450
Traditional M/W Restrooms sized to service Multi-Purpose Rms. May save SF if gender-free restrooms design is employed.
1.04 Report Taking / Visitor
Consultation Room
2 2 CNSL1 160 160
May also serve as an after hours area of refuge rm. for arrival in distress / if so, requires second exit to secure corridor. No recording needed
• Livescan 1 1 LIVE 25 25 Securable cabinet in one of the report taking rooms
Public Meeting/Multi-Purpose Rms
1.05 Community Mtg. A / Multi-
Purpose / Training Rm.
45 45 25 1,125 1,125
1.06 Community Mtg. B / Multi-
Purpose / Training Rm.
45 0 25 1,125 0
1.07 Chair / Table / AV Rm. 1 1 STOR3 144 144
1.08 Warming Kitchen 1 1 250 250 250
Net Square Feet 0 0 0 0 4,571 2,946
Circulation 25% 1143 737
Adjusted Net Square Feet 5,714 3,683
Recommend: Use folding tables / stack chairs. Also use for public educations (CPR classes, citizen's academies etc.) Rm. Also use for press briefing. Incl: Lectern, LED
Monitors, doors to Lobby and to secure corridor.
Space No: Number of Spaces
Space
Code
RemarksArea Totals
Prioritized
Program
Space Needs
Program
Staffing Projection
McClaren, Wilson + Lawrie, Inc.
In Collaboration With
Itemized Spaces 1
Space Needs Assessment
• Itemized Spaces •
2/9/2026
Milestones
S p e d s
P ri o ri g ra m
S p e d s
P ri o ri g ra m
LKR = Staff W/Lockers
WD = Staff W/Wardrobe at
Desk
LKR WD LKR WD
Space No: Number of Spaces
Space
Code
RemarksArea Totals
Prioritized
Program
Space Needs
Program
Staffing Projection
2.00 Police Administration
2.01 Chief of Police 1 1 1 1 PO6 240 240 W/Table 4 chairs
2.02 Deputy Chief 1 1 1 1 PO5 224 224
2.03 Community Services Captain 1 1 1 1 PO4 180 180
2.04 Investigations Captain 1 1 1 1 PO4 180 180
2.05 Patrol Captain 1 1 1 1 PO4 180 180
2.06 Support Services Captain 1 1 1 1 PO4 180 180
2.07 SS Admin Lt. 1 1 1 1 PO3 168 168
2.08 Accreditation 1 1 1 1 PO1 108 108 CALEA & Lexipol
2.09 Admin Open Office
• Admin Supervisor 1 1 1 1 OP4 OP3 80 72
• Police Program Analyst 1 1 1 1 OP4 OP3 80 72
• Community Engagement
Specialist
1 1 1 1 OP4 OP3 80 72
• Inv. Admin Secretary 1 1 1 1 OP4 OP3 80 72
• Patrol Admin Secretary 1 1 1 1 OP4 OP3 80 72
• Sr. Management Analyst 1 1 1 1 OP4 OP3 80 72
• Support Services Admin
Secretary
1 1 1 1 OP4 OP3 80 72
• Hoteling desks 2 2 OP3 OP2 144 108 assessors, guests of command staff
Admin Support Spaces
2.09 Escorted Visitor Waiting Area 1 1 WTG06 144 144
Viewed by admin open office staff.
Adjacent to interview suite
2.09 Copy Alcove 1 1 CPY1 24 24
2.09 Coffee Alcove 1 1 COF1 24 24
2.10 Visitor Restroom 1 1 T1 64 64 Adjacent to waiting area
2.11 Secure File Room
• Inv. Admin File Storage 2 2 FL4 40 40
• Budget Analyst Lateral Files 4 4 FL4 80 80
• CALEA Files 2 2 FL1 16 16
2.12 Admin. Conf. Room (12) 1 1 CNF16 365 365
Access from Chief's office and Corridor (to be shared).
2.13 Admin Toilet Shower 1 1 T4 90 90
Suggest: Connecting hall from Chief's office to Admin Conf Rm.
2.14 Supply Closet 1 1 STOR1 48 48 Office supplies
Net Square Feet 7 8 7 8 3,059 2,967
Circulation 25% 765 742
Adjusted Net Square Feet 3,824 3,709
McClaren, Wilson + Lawrie, Inc.
In Collaboration With
Itemized Spaces 2
Space Needs Assessment
• Itemized Spaces •
2/9/2026
Milestones
S p e d s
P ri o ri g ra m
S p e d s
P ri o ri g ra m
LKR = Staff W/Lockers
WD = Staff W/Wardrobe at
Desk
LKR WD LKR WD
Space No: Number of Spaces
Space
Code
RemarksArea Totals
Prioritized
Program
Space Needs
Program
Staffing Projection
3.00 Internal Affairs Command Staff Adjacency. Discreet entry
3.01 Lieutenant 1 1 1 1 PO3 168 168
W/Table 4 chairs? Or shared interview room
3.02 Sergeants 2 2 2 2 PO2 240 240
W/Table 4 chairs? Or shared interview room
3.03 Future Office 1 1 1 1 PO2 120 120
3.04 CSO/Secretary? 1 1 1 1 OP3 80 72
IA Support Spaces
3.05 Secure File Storage 6 6 FL4 120 120 Files maintained 5-15 yrs
Interview / Conference Room LCD Monitor. Interview recording. See shared conference room 27.01
Net Square Feet 3 2 3 2 728 720
Circulation 25% 182 180
Adjusted Net Square Feet 910 900
McClaren, Wilson + Lawrie, Inc.
In Collaboration With
Itemized Spaces 3
Space Needs Assessment
• Itemized Spaces •
2/9/2026
Milestones
S p e d s
P ri o ri g ra m
S p e d s
P ri o ri g ra m
LKR = Staff W/Lockers
WD = Staff W/Wardrobe at
Desk
LKR WD LKR WD
Space No: Number of Spaces
Space
Code
RemarksArea Totals
Prioritized
Program
Space Needs
Program
Staffing Projection
4.00 Police Wellness
4.01 Police Wellness Specialist 1 1 1 1 PO5 224 224
Mental Health Services. Specialty seating w/ sofa
4.02 Hoteling Office 1 1 PO1 108 108 Chaplain / Clinician
Wellness Support
4.03 Sound Isolation Vestibule 1 1 132 132 132
4.04 Waiting Room 1 1 WTG06 144 144 calming feature / water? Place for kids
Net Square Feet 0 1 0 1 608 608
Circulation 25% 152 152
Adjusted Net Square Feet 760 760
McClaren, Wilson + Lawrie, Inc.
In Collaboration With
Itemized Spaces 4
Space Needs Assessment
• Itemized Spaces •
2/9/2026
Milestones
S p e d s
P ri o ri g ra m
S p e d s
P ri o ri g ra m
LKR = Staff W/Lockers
WD = Staff W/Wardrobe at
Desk
LKR WD LKR WD
Space No: Number of Spaces
Space
Code
RemarksArea Totals
Prioritized
Program
Space Needs
Program
Staffing Projection
5.00 District Operations Unit Operations to remain remote
Lieutenant 1 1 Office with traffic
Northern District
Sergeant 1 1 1 1
Police Officer 3 3 3 3
Downtown Police Officer 2 2 2 2
Crime Prevention Specialist 1 1 1 1
CSO 1 1 1 1
AVA CSO 1 1 1 1
Southern District
Sergeant 1 1 1 1
Police Officer 1 1 1 1
Measure C Police Officer 1 1 1 1
Crime Prevention Specialist 1 1 1 1
CSO 1 1 1 1
10 10 10 10
Support Spaces
Storage Room Literature, Toy Drive, Seasonal Items
Conf. Room (6)
Large Meeting Room See Multi-Purpose Rooms 1.05 & 1.06
Copy Alcove
Coffee Alcove
Net Square Feet 25 0 25 0 0 0
Circulation 25% 0 0
Adjusted Net Square Feet 0 0
McClaren, Wilson + Lawrie, Inc.
In Collaboration With
Itemized Spaces 5
Space Needs Assessment
• Itemized Spaces •
2/9/2026
Milestones
S p e d s
P ri o ri g ra m
S p e d s
P ri o ri g ra m
LKR = Staff W/Lockers
WD = Staff W/Wardrobe at
Desk
LKR WD LKR WD
Space No: Number of Spaces
Space
Code
RemarksArea Totals
Prioritized
Program
Space Needs
Program
Staffing Projection
6.00 Traffic 4 Staff
6.01 Lieutenant 1 1 PO3 168 168 For staffing see district operations
Sergeant 1 1 Locate with patrol watch office
6.02 Police Officer 9 9 5 5 OP3 400 360 Need space for blueprints
6.02 CSO 1 1 1 1 OP2 54 54
Support Spaces
6.02 Plan Review tables 2 2 WTBL1 188 188
6.02 Plan Storage 2 2 MAP 56 56
6.02 Personal Files 9 9 FL1 72 72
6.03 Storage 1 1 STOR3 144 144
RADAR & LIDAR Charging, LEICA 3D
Imagers, PAS Devices
Conference Room See shared conference room 26.01
Net Square Feet 10 1 10 1 914 874
Circulation 25% 229 219
Adjusted Net Square Feet 1,143 1,093
McClaren, Wilson + Lawrie, Inc.
In Collaboration With
Itemized Spaces 6
Space Needs Assessment
• Itemized Spaces •
2/9/2026
Milestones
S p e d s
P ri o ri g ra m
S p e d s
P ri o ri g ra m
LKR = Staff W/Lockers
WD = Staff W/Wardrobe at
Desk
LKR WD LKR WD
Space No: Number of Spaces
Space
Code
RemarksArea Totals
Prioritized
Program
Space Needs
Program
Staffing Projection
7.00 Personnel & Training 4 staff + CSOs?
7.01 Lieutenant 1 1 1 1 PO3 168 168
Table w/ 2 chairs, conducts 1-on-1 interviews
7.02 Sergeant 1 1 1 1 OP3 80 72
7.02 Personnel Operations 3 3 3 3 OP2 216 162
7.02 CSO 1 1 1 1 OP2 54 54
7.02 Hotel Desks 2 2 OP1 108 90
Modified duty, retired-annuitants, background investigators, auditors, wellness, retirement consultants, etc.
• Trainee Space 20 20 Use shared conference room
Support Spaces
7.02 Supply Cabinet 2 2 CAB4 32 32
7.03 Secure File Room 16 16 FL4 320 320
7.04 Secure Storage 1 1 STOR3 144 144 Issue equipment (tasers etc.) Dept. wide
7.05 Coffee Alcove 1 1 COF1 24 24
Classroom (50) 50 50 25 Host regional trainings. Use shared Multi-
Purpose Room B 1.06
DT / ARCON / Simulator Training See support building 29.09
DT Storage See support building 29.10
Conference Room (12) See shared conference room 26.02
Conference / Interview Rooms (6) See shared conference room 26.01
Copy Alcove See shared copy room 26.04
Net Square Feet 2 4 2 4 1,146 1,066
Circulation 25% 287 267
Adjusted Net Square Feet 1,433 1,333
McClaren, Wilson + Lawrie, Inc.
In Collaboration With
Itemized Spaces 7
Space Needs Assessment
• Itemized Spaces •
2/9/2026
Milestones
S p e d s
P ri o ri g ra m
S p e d s
P ri o ri g ra m
LKR = Staff W/Lockers
WD = Staff W/Wardrobe at
Desk
LKR WD LKR WD
Space No: Number of Spaces
Space
Code
RemarksArea Totals
Prioritized
Program
Space Needs
Program
Staffing Projection
District Operations Unit adjacency
8.00 Youth & Family Services
Lobby and Reception
8.01 Main Lobby/Waiting 1 1 400 400 400
To have separate entry from main police department to provide a sense of separation and reduce anxiety, fear with adjacency to a police department.
8.02 Private Consult Room 1 1 140 140 140
Used for private/confidential conversations with youth, parents, and staff members.
Meeting Rooms
8.03 Small Meeting Room 1 1…