- HX-8 IN Dia. SCH 140 Pipe
- Solicitation number
- N3904025Q0020
About this file
This is an attachment to Exhibit A providing additional DD1423 information for contract N3904025P0020 related to material certification requirements for Portsmouth Naval Shipyard (PNSY). The document outlines detailed requirements for vendor certifications, testing, and documentation.
The attachment specifies that vendors must obtain PNSY approval for procedures before performing tests and must provide certifications for all tests, inspections, and examinations with each material shipment. Key requirements include Certificates of Compliance with specific attestation language, chemical analysis certifications showing complete test results, mechanical properties certifications including actual test data for tensile/yield/elongation properties, and seamless certifications when applicable. All certifications must include material identification, contract numbers, heat/lot numbers, and be signed by the vendor's quality assurance official. The document includes a template for the Certificate of Compliance form showing required fields for material identification and compliance statements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Individual Repair Parts Ordering Data (IRPOD).pdf | ||
| 25Q0020_RFQ.pdf | ||
| 25Q0020_Exhibit A.pdf | ||
| 25Q0020_Combined Synopsis Solicitation.pdf | ||
| 25Q0020_Attachment 1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
24RX19751 Page 1 of 3
ATTACHMENT (1) to EXHIBIT A
ADDITIONAL DD1423 INFORMATION
CONTRACT No: N3904025P0020
ITEM: 0002
A. PROCEDURE APPROVALS:
A.l. Vendor procedures that require approval, shall be submitted to Portsmouth Naval Shipyard (PNSY), ATTN:
CODE Portsmouth Naval Shipyard approval shall be obtained by the vendor prior to performing the applicable tests.
B. MATERIAL CERTIFICATION:
B.1. Certifications for all tests, inspections, and examinations listed below shall be supplied with each shipment of material. The vendor (contractor or subcontractor) is liable for conducting all tests, analyses, inspections, and examinations, etc. as specified by the contract and specifications whether certifications are required or not.
Certifications shall be supplied as outlined in paragraph B.2 below.
(a) Certificate of Compliance.
(b) See IRPOD Section 6.1.3 for the listing of required certifications/reports. For MIL-DTL-23226, see paragraph 4.1.4 and Figure 1 for required information included on the "Certification of Quality
Conformance".
B.2. Certifications shall be supplied per the following instructions:
B.2.1. The certifications shall specifically list each test, inspection, and examination identified above and separately certify the results by signature and title of the vendor official designated responsible for quality assurance. Each certification shall contain either original or exact copies of quantitative or qualitative test reports, as applicable, issued by the testing organization; data transcribed to another organization's form is not acceptable. If the vendor performs the laboratory testing, the certification will note, "original laboratory reports are on file at our facility". Certifications must be complete and objective.
B.2.2. Material identification shall be included on all copies of certifications. Certifications shall be made identifiable by containing the contract number, and the heat/lot number or vendor traceability number marked on the material.
B.2.3. For Certificate of Compliance (when required):
B.2.3.1. The following certification statement shall appear with the reports attesting that:
"The inspection and test reports (as applicable) provided represent the actual attributes of the items furnished on this contract and indicate full compliance with all contract requirements. I attest that all items furnished on this contract are in full compliance with all contract requirements."
B.2.3.2. The Certificate of Compliance shall contain the signature and title of the vendor official designated responsible for Quality Assurance.
B.2.3.3. A sample Certificate of Compliance is provided at the end of this attachment.
B.2.4. For Chemical Analysis Certification (when required):
B.2.4.1. Provide a photostatic copy of certification originated by the test facility performing the chemical analysis (A photostat of the original Mill Certification is acceptable).
B.2.4.2. The chemical analysis certification shall include a tabulation of the complete chemical test analysis.
24RX19751 Page 2 of 3
Traceability (marking on finished item} is fabricated from raw material
Heat Treat No.
(when applicable}
Date _
(name and signature of Authorized Company Rep}
B.2.4.3. If the specification requires more than one chemical analysis be performed (i.e., two or more samples), the certification shall include the results of all the analyses (i.e., results for each sample must be shown).
B.2.5. For Mechanical Properties Certification (when required):
B.2.5.1. Provide a photostatic copy of certification originated by the test facility performing the mechanical properties test on the material after performance of all processes which change the mechanical properties of the material, such as heat treating, forging, cold working, etc. (A photostat of the original Mill Certification is acceptable only if no processes were performed to change the material properties).
B.2.5.2. The mechanical properties certification shall include the actual test data for tensile, yield, elongation, reduction in area, and hardness when required by the specification.
B.2.5.3. If the specification requires more than one mechanical properties test be performed (i.e., two or more samples), the certification shall include the results of all the tests (i.e., results for each sample must be shown).
B.2.S.4. When the mechanical properties are altered by heat treatment, forging, or other altering process, the original certification data report shall be over-stamped or annotated with the following information:
B.2.6. For Seamless Certification (when required):
B.2.6.1. The material seamless certification shall consist of a specific statement that the material is seamless (e.g., "material is certified seamless", "material shown on this report is seamless", etc.).
24RX19751 Page 3 of 3
CERTIFICATE OF COMPLIANCE
COMPANY NAME
MATERIAL IDENTIFICATION (COMPLETE APPLICABLE ITEMS)
CONTRACT NO. DELIVERY ORDER NO. _
ITEM NO.
NATIONAL/LOCAL STOCK NO. NSN/LSN
MANUFACTURER'SPART NO.
MANUFACTURER'S SERIAL NO.
DRAWING AND PIECE NO.
MANUFACTURER'S LOT/HEAT NO. (AS MARKED ON THE MATERIAL): _
VENDOR TRACEABILITY NO. (AS MARKED ON THE MATERIAL):
ALL INSPECTION AND TEST REPORTS REQUIRED BY ATTACHMENT l TO EXHIBIT A (DD FORM 1423) FOR TRACEABILITY TO EACH
CONTRACT ITEM MUST ACCOMPANY THIS SIGNED STATEMENT:
THE INSPECTION AND TEST REPORTS (AS APPLICABLE) PROVIDED REPRESENT THE ACTUAL ATTRIBUTES OF THE ITEMS FURNISHED ON
THIS CONTRACT AND INDICATE FULL COMPLIANCE WITH ALL CONTRACT REQUIREMENTS. I ATTEST THAT ALL ITEMS FURNISHED ON THIS
CONTRACT ARE IN FULL COMPLIANCE WITH ALL CONTRACT REQUIREMENTS.
SIGNATURE DATE
QUALITY ASSURANCE OFFICIAL
TITLE