25M002MZ Facility T71 Flooring Repairs SOW.pdf
PDF 129 KB Posted
- Attached to
- Facility T71 Flooring Repairs
- Solicitation number
- N4008525R9004
About this file
This Statement of Work (SOW) details flooring repair requirements for Facility T71 at Camp Lejeune, North Carolina. The project involves comprehensive interior floor renovation, including removing existing flooring throughout the building, repairing damaged subfloors, sealing floors, and installing new Congoleum Commercial VCT (Vinyl Composition Tile) in "starry night" color and Johnsonite vinyl cove base in "black pearl" color. The contractor must provide all necessary materials, labor, equipment, and supervision, with specific requirements to replace thresholds, wall bases, and ensure proper surface preparation and cleanup.
The solicitation includes comprehensive warranty provisions, requiring the flooring contractor to provide a 5-year warranty for materials and workmanship and a 25-year non-prorated limited warranty against surface wear, static, delamination, edge ravel, zippering, and backing resilience. Submittal requirements include providing manufacturer's product specifications to the contracting officer, and the project is managed under MACC No. 25-0422 with Project No. 25M002MZ. The primary point of contact for the building is Jessica See, reachable at 910-451-1234, and the project is limited to contractors listed on the General Requirements cover page for the ROICC Camp Lejeune area of responsibility.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MACC No. 25-0422 PROJECT No. 25M002MZ MAXIMO No. 5478905
TITLE: Facility T71 Flooring Repairs
ATTACHMENTS:
1. Quantities Sheet
SCOPE OF WORK: The contractor shall provide all material, labor, equipment, and supervision required to accomplish the following:
GENERAL DESCRIPTION: This scope of work is to be accomplished at Building T71 located on Range Maintenance Road at Camp Lejeune, North Carolina. The contractor shall remove flooring thru out building, repair any damaged subfloor, seal floors, install new VCT and cove base.
GENERAL SPECIFICATIONS: The contractor shall follow the general specifications unless noted in the project area description section. All measurements on the attached sketches are for reference use only. The contractor shall take their own field measurements in determining required material and costs. All work performed shall meet or exceed SPECIFICATIONS THAT
ARE ATTACHED.
PROJECT AREA DESCRIPTIONS: See attached Work Area Sketches for additional details.
The contractor shall remove flooring thru out the building and repair any damaged subfloor. The contractor shall seal subfloor with Ardex floor sealer or equivalent. The contractor shall install Congoleum Commercial VCT AL256. Color shall be starry night or equivalent. The contractor shall install Johnsonite vinyl cove base color black pearl.
PREPARATION:
1. The contractor shall take the necessary precautions to prepare and protect personal property, government property, and work areas during the accomplishment of work for this scope.
INTERIOR FLOOR REPAIRS:
1. Contractor shall replace any threshold between carpet and other flooring as needed.
2. Existing flooring should be removed and replaced to manufactures specifications.
3. Replace any vinyl wall base that is disturbed.
4. Sealant shall be applied before carpet is installed.
SPECIAL CONDITIONS
1. Clean all over-spray, drips, splatters, and spills resulting from accomplishing work for this project.
2. Repair, refinish areas damaged or disturbed by new work to be provided under this contract.
3. Properly remove, haul, and dispose of all debris. The contractor shall not utilize the dumpster provided by Camp Lejeune for the occupants.
SCHEDULING AND ACCESS:
• The Primary Point of Contact for the building are as follows: Building T71 is Jessica See at
910-451-1234
ENVIRONMENTAL REQUIREMENTS: None Identified
SUBMITTALS:
1. The contractor shall submit to the contracting officer, the manufacturer’s product specifications, complete with technical products data being used for this project.
2. Submittal should be marked for project number.
MATERIAL SPECIFICATIONS:
1. VCT
a. See attached specifications.
2. SEALANT
a. See attached specifications.
WARRANTY:
1) Flooring contractor shall provide a 5- year warranty for defects in materials and workmanship and provide a 25-year non-prorated limited warranty against excessive surface wear and static, delamination, edge ravel, zippering, and backing resilient.
| PREPARATION: |
| INTERIOR FLOOR REPAIRS: |