252754FB_Technical_Specifications.pdf
PDF 469 KB Posted
- Solicitation number
- 252754FB
- Issued by
- Sarasota County, Siesta Key CDP, Florida
About this file
This document is a technical specification for the Sarasota County Benderson Park South Shoreline Stabilization Project, prepared by Aptim Environmental & Infrastructure, LLC for Sarasota County. The project involves revetment construction, breakwater construction, steel sheet pile installation, and upland backfill and restoration along portions of the southern and eastern shoreline of Benderson Lake. The work includes excavation, stone placement, geotextile installation, and concrete work, with construction activities limited to 8:00 a.m. to 6:00 p.m. and no work permitted on county holidays. The contractor is responsible for obtaining necessary permits, conducting surveys, maintaining access routes, and ensuring safety and environmental protection during the project.
The technical specifications provide detailed requirements for materials and installation, including specifications for armor stone (with specific weight and dimension requirements), geotextile, concrete, and steel sheet piles. The contractor must provide certified stone from approved quarries, conduct drop tests, and meet strict quality control standards. Payment will be based on in-place contract unit prices, with careful measurement and documentation of materials placed. The project emphasizes minimal environmental disturbance, requiring restoration of access routes and staging areas to pre-construction conditions. Daily quality control reports are mandatory, and the contractor must have a safety officer on-site during complex work activities.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 9
TECHNICAL
SPECIFICATIONS
SARASOTA COUNTY
BENDERSON PARK
SOUTH SHORELINE STABILIZATION PROJECT
SECTIONS 4, 7, AND East
TECHNICAL SPECIFICATIONS
Prepared for:
SARASOTA COUNTY
Prepared by:
Aptim Environmental & Infrastructure, LLC
6401 Congress Avenue, Suite 140 Boca Raton Fl 33487
COA 9317
Douglas W. Mann, P.E. 44046
May 2025
This item has been digitally signed and sealed by Douglas W. Mann, P.E. on the specified date using a digital signature. Printed copies of this document are not considered signed and sealed and the signature must be verified on any electronic copies.
TS-i
BENDERSON PARK
SOUTH SHORELINE STABILIZATION PROJECT
SECTIONS 4, 7, AND East
TECHNICAL SPECIFICATIONS
Table of Contents
SCOPE OF WORK
SUBMITTALS AND NOTIFICATIONS
SURVEY REQUIREMENTS
SURVEY LAYOUT AND CONTROL
RECORD DRAWINGS
AS-BUILT DRAWINGS
ACCESS, WORK AREAS, AND STORAGE AREAS
PERMISSIBLE WORK DAYS AND HOURS
NOTIFICATION & OBSERVATION
PROTECTION OF EXISTING STRUCTURES FROM CONSTRUCTION
NOISE CONTROL
SITE CLEAN-UP
EXAMINATION & FINAL ACCEPTANCE
PART 2 – MATERIALS
ARMOR STONE
GEOTEXTILE
CONCRETE MATERIALS
REINFORCING STEEL
EXPANSION JOINT MATERIALS
PART 3 – EXECUTION
EXCAVATION/SAND FILL
TRANSPORTATION OF MATERIALS
MISPLACED MATERIALS
GEOTEXTILE INSTALLATION
ARMOR STONE INSTALLATION
STEEL SHEET PILE INSTALLATION
CONCRETE PLACEMENT SPECIFICATIONS FOR CONCRETE CAP
CONCRETE FORMWORKERS AND FINISHERS
CONCRETE TRANSPORTATION
REBAR SPLICING
CONCRETE WASHOUT
TS-ii
BENDERSON PARK
SOUTH SHORELINE STABILIZATION PROJECT
SECTIONS 4, 7, AND East
TECHNICAL SPECIFICATIONS
Table of Contents (CONT’D)
Appendix A – Daily Quality Control Report
TS-1
TECHNICAL PROVISIONS
PART 1 - GENERAL
1. SCOPE OF WORK.
The WORK covered in this section consists of furnishing all plant, labor, equipment, tools, supplies and material, and of performing all operations and surveys in connection with the revetment construction, breakwater construction, steel sheet pile installation, and upland backfill and restoration along portions of the southern and eastern shoreline of Benderson Lake in accordance with the Plans and Specifications.
1.1. Permits. The COUNTY has obtained the Southwest Florida Water Management District Permit, and the USACE Nationwide 3 and 13 permit is required for this project. The CONTRACTOR shall comply with all conditions of the permits. All WORK shall comply with the requirements of the permits, which are included in the Bid Package. Any modifications to said permits will be addressed through an addendum by the COUNTY.
1.2. Other Permits. The CONTRACTOR is solely responsible for obtaining, at his/her cost, all other approvals for the mining and transporting of stone and all other material to the project site. This includes, but is not limited to, any and all roadway permits, customs clearances, local building department permits, and business licenses required to bring material to the site.
1.3. Water Levels. The lake is weir controlled at elevation 19.0 feet NAVD and receives stormwater discharges from upstream. The lake typically fluctuates from 19.0 feet NAVD to around 21 feet NAVD. Historical accounts of higher water levels have been reported.
CONTRACTOR will need to be able to adjust the work procedures to reflect the changing water elevations.
2. SUBMITTALS AND NOTIFICATIONS.
The CONTRACTOR shall submit the following items to the ENGINEER at the appropriate times:
2.1. Construction Schedule and Methods. A minimum of seven (7) days prior to the pre-construction conference, the CONTRACTOR shall prepare and submit to the ENGINEER, for approval, a practicable construction schedule and methodology statement for construction of each portion of the WORK. No WORK on site shall begin until the schedule is accepted by the ENGINEER and the COUNTY. Acceptance by the ENGINEER and COUNTY indicates an acknowledgement and not an endorsement of the CONTRACTOR’s means and methods.
2.2. Material and Equipment Transport, Storage, and Access. At least seven (7) days prior to the pre-construction conference, the CONTRACTOR shall provide to the ENGINEER a description of the routes and areas he intends to use to transport and store material and equipment during the construction. The description shall also describe how the
TS-2
CONTRACTOR intends to access the work area. All transport routes, work areas, storage areas, access areas, and facilities are subject to review by the COUNTY and ENGINEER for compliance with the Plans and Specifications. See additional requirements for development of a maintenance of traffic plan.
2.3. Contact List. At least seven (7) days prior to the pre-construction conference, the
CONTRACTOR shall submit a list of project personnel, including subcontractors, and their telephone, e-mail address, telefax, and other numbers by which key personnel can be reached for purposes of notification and other matters discussed in these specifications.
Nevertheless, the CONTRACTOR remains responsible for all WORK and shall be the point of contact and in responsible charge of the subcontractors during the duration of the
WORK.
2.4. Daily Quality Control Reports. The CONTRACTOR shall submit daily reports that summarize the WORK completed at the end of each workday. Daily Quality Control Reports shall be submitted every contract day during the construction period (even when no WORK is done) between the time at which the Notice to Proceed is issued and the time of Final Acceptance. Reports shall be submitted by 2:00 p.m. to the ENGINEER and the COUNTY on a daily basis via e-mail. The reports shall include all work activity including, but not limited to, the location (coordinates or stationing) of WORK, daily and cumulative quantities (tonnage) of stones placed, quality control surveys, weather conditions, personnel, materials, and on-site equipment. A copy of the required daily report is included in Appendix A of the Technical Provisions.
2.5. Stone Certification. At least seven (7) days prior to the pre-construction conference, information regarding the stone source and stone certification with the name, location and telephone number of the vendor(s) and quarry(s) from which stone materials will be supplied, shall be provided to the ENGINEER for review prior to delivery of stone material to the project site. The stone certification shall be based upon an independent laboratory analysis of the armor stone's specific gravity and shall indicate the standards by which the results were developed. Certifications are required for the armor stone (see Section 14).
2.6. Fabric Certification. At least seven (7) days prior to the pre-construction conference, the
CONTRACTOR shall submit to the ENGINEER for approval, the following:
2.6.1. Product samples and documentation of compliance with the specifications of the geotextile.
2.7. Certified Stone Quantity. The CONTRACTOR shall provide records of the net weight of armor stone transported to the work site. The CONTRACTOR shall provide the ENGINEER with a weekly cumulative total of all stone delivered to the project site and a total of all stone placed by weight. Signed weight tickets and any other records shall be provided to the ENGINEER and/or the COUNTY weekly.
TS-3
2.8. Surveys. Pre-construction surveys shall be submitted seven (7) days prior to construction.
Quality control surveys shall be submitted daily with the Daily Quality Control Reports (Section 2.4). Post-construction surveys shall be submitted within fourteen (14) days after substantial completion or conditional acceptance pending survey review. See Section 3.
2.9. As-Built Drawings. As-Built drawings (Section 6) shall be submitted within fourteen (14) days after final acceptance.
2.10 Maintenance of Traffic and Traffic Control. For the protection of traffic in public or private roads and ways, the CONTRACTOR shall provide, place, and maintain the necessary barricades, traffic cones, warning signs, lights, and other safety devices in accordance with the requirements of the “Manual of Uniform Traffic Control Devices, Part VI - Traffic Controls for Street and Highway Construction and Maintenance Operations,” published by U.S. Department of Transportation, Federal Highway Administration, and the Florida Department of Transportation (FDOT) Design Standards Index 600 Series (current edition).
2.10.1 The CONTRACTOR shall take the necessary precautions for the protection of the Work and the safety of the public. Advance construction zone warning signs shall be permanently mounted at the frequency and interval directed by the Index 600 series. Portable work zone signs for daily use shall be mounted on temporary barricades or weighted bases meeting the Index 600 series requirements.
2.10.2 CONTRACTOR shall prepare a Maintenance of Traffic Plan for submittal to the ENGINEER and the Sarasota County Public Works Department for acceptance.
2.10.3 CONTRACTOR shall incorporate best management practices to minimize sand, mud, or aggregate from being tracked onto paved public roads by construction vehicles or runoff.
2.10.4 The CONTRACTOR shall remove traffic control devices when no longer needed or not in use.
2.10.5 Temporary lane closures of North Cattleman Road, Athletes Drive, and World
Championship Drive are not authorized.
2.10.6 The park has a paved multi use pedestrian path that circles the lake and crosses through and/or adjacent to the project site. CONTRACTOR will need to cross the path to bring equipment and materials to the project site. CONTRACTOR shall include proposed methods in their maintenance of traffic plan to maintain, or temporarily relocate the pedestrian path as part of their WORK and facilitate continued public use of the path during construction.
TS-4
2.11 Maintenance of Traffic Certification
2.11.1 Traffic Control Plans shall be prepared a Florida registered professional engineer, with FDOT Advanced Maintenance of Traffic certification.
2.11.2 Traffic control plan implementation shall be directed by a certified FDOT Work Zone Traffic Control Supervisor.
2.11.3 Flaggers shall be qualified in accordance with FDOT Basic Maintenance of Traffic certification.
2.11.4 CONTRATOR shall submit copies of all Maintenance of Traffic personnel certifications to the ENGINEER prior to implementation of any Plans.
2.12 Road Use-General. Nothing herein shall be construed to entitle the CONTRACTOR to the exclusive use of any public road or parking area during the performance of the WORK hereunder, and it shall conduct its operations to not interfere unnecessarily with the authorized work of utility companies or other agencies in such streets, alleyways, or parking areas. No road shall be closed to the public without first obtaining permission of the COUNTY and proper governmental authority.
2.13 General Plans and Information. The CONTRACTOR shall provide the following additional submittals at least seven (7) days prior to commencement of the WORK:
2.13.1 Shop Plans/Working Plans
2.13.2 Pre-Construction Condition Photographs
2.13.3 Survey and Layout Plan
2.13.4 Quality Control Plan
2.13.5 Accident Prevention Plan
2.13.6 Environmental Protection Plan
2.13.7 Hurricane and Severe Storm Plan
2.13.8 Transport, Storage, and Access Plan
2.14 Notifications. The CONTRACTOR shall provide the following notifications in writing to the ENGINEER at the appropriate times, if applicable:
2.14.1 Notification of Survey or Layout Discrepancy
2.14.2 Notification of Cultural Resource Discovery
2.14.3 Notification of Misplaced Material
2.14.4 Notification of Occurrence of Delays in Work
2.14.5 Claims and Disputes
2.14.6 Reports of All Inspections, Surveys, and Tests and Remedial Actions
TS-5
3 SURVEY REQUIREMENTS.
3.1 Survey Components. The CONTRACTOR shall measure and submit to the ENGINEER plan and profile surveys of the structures depicting the following:
3.1.1 The pre-construction conditions.
3.1.2 The design templates for the structure.
3.1.3 The final in-place location, elevation, and extent of the excavations (i.e.
post-construction survey).
3.1.4 The final constructed location, elevation, and extent of the revetment’s armor stone (i.e. post-construction survey).
3.2 Profile Spacing-Structures. The pre- and post-revetment construction surveys shall be measured along transects that are perpendicular to the alignment of the structure as specified in the construction plans and they are spaced no more than 50 feet apart.
Additional survey transects shall also be taken at any change in the orientation of the structure.
3.3 Survey Points. A sufficient number of points shall be taken along each profile to accurately represent the general shape and average trend of the constructed lines and grades, but with a spacing of no more than 5 feet. Elevations of any stone shall be measured by selecting a point on the stone that represents the average elevation of the top of the stone (determined visually). If any survey results do not accurately represent the structure, the CONTRACTOR shall resurvey any portion of a structure at no additional cost to the COUNTY. Survey transects shall extend a minimum of 10 feet (and contain at least two survey points) beyond the edge of the structure’s footprint (including the foundation), in both north and south directions. Uncovering the structure may be required to complete the survey.
3.4 Submission Requirements. All survey data should be submitted in electronic ASCII x,y,z format. All survey data shall also be submitted in graphical form with the pre-project conditions, design templates, allowable tolerances, and post-project conditions depicted. The plan view shall depict the location and extent (area in square feet) of the revetment foundations and revetment repairs or enhancements. The cross-sections shall depict the elevation of the excavations and the rock revetment. All cross-sections shall include the data and the identifying baseline station number. All survey information submitted, and included in any depiction, shall include the date of the survey. Vertical elevations shall be in feet referenced to the NAVD 1988 datum.
Horizontal distances shall be in feet. Locations shall be specified in Florida State Plane grid coordinates, NAD 1983 datum. Survey cross section drawings shall be at an appropriate scale with the horizontal scale equal to the vertical scale for all rock work.
TS-6
3.5 Personnel. All surveys shall be performed under the direction of an independent Florida licensed professional surveyor and mapper (P.S.M.). All surveys shall meet minimum technical standards.
4 SURVEY LAYOUT AND CONTROL.
4.1 Horizontal and Vertical Limits. The CONTRACTOR shall establish their survey control for the WORK. The CONTRACTOR shall layout the horizontal and vertical limits of the WORK from the tabulated control provided in the Plans. A baseline with coordinates was established for engineering purposes. The CONTRACTOR may elect to establish a different baseline subject to approval of the ENGINEER. The CONTRACTOR shall be responsible for maintaining the accurate alignment and configuration of the rock revetment during construction. The CONTRACTOR shall not scale dimensions from the Plans for the purposes of work layout. The CONTRACTOR shall be responsible for all measurements that may be required for the execution of the WORK to the location and limit marks prescribed in the drawings and in these specifications. Based on the pre-construction survey, the ENGINEER reserves the right to modify the locations and elevations of the structure as may be required to meet changed conditions. If the CONTRACTOR discovers a conflict during layout of the work, the CONTRACTOR shall notify the ENGINEER.
4.2 Temporary Benchmarks. If the CONTRACTOR elects to establish temporary benchmarks throughout the work site, they shall be established by a closed loop of levels from a permanent benchmark or a line of levels between two permanent benchmarks. Any such temporary benchmark shall be located upon fixed objects such as utilities, roadways, driven stakes, etc. to assure reliability throughout the duration of the WORK.
4.3 Construction Layout. The CONTRACTOR shall complete the layout of the WORK and shall furnish, at his own expense, such stakes, templates, platforms, equipment, tools and material, and all labor as may be required in laying out any part of the WORK from the monuments, control data, and elevations. The CONTRACTOR shall maintain and preserve the established stakes and other marks. If such marks are destroyed by the CONTRACTOR, they may be replaced by the CONTRACTOR at his discretion, and the expense of replacement will be deducted from any amounts due or to become due. WORK may be suspended at any time when location and limit marks established by the CONTRACTOR are not adequate to facilitate checking of the WORK.
4.4 Drawing Modification. All levels and measurements as given on the drawings are binding for the CONTRACTOR. The ENGINEER reserves the right to modify the locations and elevations of the limit marks as may be required to meet changed conditions or as a result of necessary modifications to the Contract work. Modifications to the drawings will not form the basis for a change in unit price unless the modifications increase or decrease the quantity of WORK by twenty-five percent (25%) or more.
TS-7
5 RECORD DRAWINGS.
The CONTRACTOR shall maintain a separate set of full-size contract drawings, marked up in red, to indicate current, as-built conditions. These drawings shall be maintained at or near the site in a current condition at all times until completion of the WORK. The drawings shall be available for review by the ENGINEER or COUNTY, or their respective representatives at all times. All variations from the contract drawings, for whatever reason, including those occasioned by modifications, optional materials, and the required coordination between trades, shall be indicated.
These variations shall be shown in the same general detail utilized in the contract drawings. The marked-up drawings may be utilized for preparation of the as-built drawings, but may not be substituted for the as-built drawings. The CONTRACTOR shall provide a set of Record Drawings for verification to the ENGINEER with each monthly pay estimate request, prior to processing the payment request. At final completion and acceptance of the WORK, the CONTRACTOR shall provide the original Record Drawings to the ENGINEER. The ENGINEER reserves the right to withhold final payment until acceptable Record Drawings have been submitted. No separate payment will be made for Record Drawings.
6 AS-BUILT DRAWINGS.
The CONTRACTOR shall submit to the ENGINEER, for approval, the surveyed profile data of the WORK in addition to a surveyed plan view of the WORK. The profile and plan view information must be submitted to the ENGINEER within fourteen (14) calendar days of the completion of the site work.
6.1 The profile data shall be that described in Section 3.
6.2 Upon completion of the WORK, the CONTRACTOR shall sign the as-built drawings in the following manner: “I CERTIFY THAT THESE DRAWINGS INDICATE
CONSTRUCTION AS ACTUALLY PERFORMED AND ARE AN ACCURATE
REPRESENTATION OF THE SPECIFIED WORK.” The COUNTY reserves the right to withhold final payment until acceptable as-built drawings have been submitted.
6.3 The CONTRACTOR shall provide the ENGINEER any CAD files created in preparation of the as-built drawings.
7 ACCESS, WORK AREAS, AND STORAGE AREAS.
7.1 General. The general location and extent of the construction access, staging area, and work area are indicated in the Plans. Access points should be minimized as much as practicable.
Unless otherwise directed in writing by the COUNTY, the CONTRACTOR is responsible for removing existing vegetation, fencing and other impediments, as necessary, to allow equipment access and material deliveries to the work area. The CONTRACTOR shall landscape and restore those areas where access routes and staging areas are developed.
The cost of preparing and maintaining and restoring the Project area shall be included in
TS-8
the lump sum cost for Restore Construction Access. The CONTRACTOR shall take appropriate measures to prevent damage.
7.2 Construction Access. The CONTRACTOR may deliver equipment, materials, and personnel to the project area by land access from Cattlemen Road and other roads within the park. The CONTRACTOR is responsible for adhering to all weight and traffic regulations on all roadways and is responsible for paying all tolls.
7.3 Staging Area. The staging and material storage areas provided by the COUNTY are shown in the Plans. The CONTRACTOR shall cordon off and/or fence the staging area to secure the area from the public. The fence shall be a minimum of six (6) feet in height and remain upright and in place during the WORK. The staging area must be restored upon project completion. If additional staging areas are available, they shall be procured by, and at the expense of, the CONTRACTOR. The staging area must be restored upon project completion to the pre-construction conditions at the cost of the CONTRACTOR.
The CONTRACTOR shall avoid impact to existing vegetation within the staging area to the greatest extent practicable. There are overhead electric transmission lines within the general vicinity of the staging areas. These lines should be protected at all times.
7.4 Exclusion of Public. The CONTRACTOR shall accomplish the WORK in such a manner so as to minimize disruption to park road traffic and the use of the pedestrian path. It is the CONTRACTOR’s responsibility to exclude the public for safety purposes from the construction access, equipment access route, staging area, and active work areas in the immediate vicinity of the work, transport operations, or any other area that may be dangerous to the public. The CONTRACTOR shall minimize the areas closed to the public to what is required to safely conduct the work. The portable public bathrooms in the southeastern corner of the park shall remain accessible to the public and for maintenance.
7.5 Safety Personnel Requirement. The CONTRACTOR shall have at the project site a trained
Safety and Occupational Health person (Safety Officer) whose primary role is to manage the CONTRACTOR's accident prevention program. The Safety Officer shall be on duty during any WORK of a complex nature including, but not limited to, transport of materials; movement of equipment; work on or around structures; work to construct the revetment and breakwater; work to install the steel sheet piles, or when other potentially hazardous activities are occurring. The Safety Officer shall report to, and work directly for, the CONTRACTOR's superintendent or the corporate safety office. The Safety Officer shall have the authority to take immediate steps to correct unsafe or unhealthful conditions. The presence of the Safety Officer will not abrogate safety responsibilities of all other personnel.
8 PERMISSIBLE WORK DAYS AND HOURS.
8.1 Project Time. Construction activity shall be limited to 8:00 a.m. to 6:00 p.m. unless otherwise authorized by the COUNTY. Lighting of the work site is prohibited.
TS-9
8.2 Holidays. No heavy construction work shall be allowed during any COUNTY recognized holiday. Survey work shall be permitted.
8.3 Special Events. The COUNTY will identify at the time of issuance of a Notice to Proceed, any previously scheduled events to occur within the park that will necessitate modification of the CONTRACTOR’s work plan or schedule. If the events require the shutdown of operations, additional contract time will be granted to the CONTRACTOR.
9 NOTIFICATION & OBSERVATION.
9.1. Notification. The CONTRACTOR shall specifically notify the COUNTY and ENGINEER of the CONTRACTOR’s intended date of commencement of the following work milestones at least seven (7) days prior:
9.1.1. Mobilization and material delivery;
9.1.2. Commencement of the site work;
9.1.3. Establishment of horizontal and vertical control work;
9.1.4. Conducting pre- and post-construction surveys;
9.1.5. Drop test at the quarry (Part 2, Section 14.5);
9.1.6. Expected completion of the revetment structures;
9.1.7. Expected completion of the wetland planter breakwater structures;
9.1.8. Expected completion of steel sheet pile installation;
9.1.9. Expected completion of concrete cap;
9.1.10. Expected substantial completion of the entire work;
9.1.11. Expected completion of the entire work.
9.2. Project Uncovering. The presence or absence of the ENGINEER shall not relieve the
CONTRACTOR of their responsibility to properly execute the WORK in close accordance with these Specifications and the Plans. The ENGINEER may order any element of the WORK uncovered, at no additional expense to the COUNTY, in the event the WORK was not observed by the ENGINEER or surveyed (Part 1, Section 3) prior to covering. This condition applies to any source of sand coverage, including from natural processes such as waves and tides.
9.3. Noncompliance Notification. The ENGINEER shall notify the CONTRACTOR of any observed non-compliance with the Plans and Specifications and/or applicable Federal, TS-10
State or local laws & regulations, promptly upon discovery. The CONTRACTOR shall, after receipt of such notice, immediately take corrective action. Such notice, when delivered to the CONTRACTOR or his authorized representative, shall be deemed sufficient for the purpose. If the CONTRACTOR fails or refuses to comply promptly, the COUNTY may issue an order stopping all or part of the WORK until satisfactory corrective action has been taken.
10. PROTECTION OF EXISTING STRUCTURES FROM CONSTRUCTION.
10.1. General. CONTRACTOR shall not damage any existing structural components beyond the demolition/excavation requirements depicted in the Plans. Bulkheads, revetments, utilities, upland structures, anchor points, and other structures within and adjacent to the work area shall be protected by the CONTRACTOR to prevent damage thereto by the CONTRACTOR’S operations. Any damage thereto shall be repaired at the CONTRACTOR’s expense.
10.2. Underground Utilities. CONTRACTOR shall call “SUNSHINE” 1-800-432-4770 before beginning any WORK at the project site.
11. NOISE CONTROL.
All lifting, hauling, handling, and rock placement equipment used on this WORK shall be equipped with satisfactory mufflers or other noise abatement devices. The CONTRACTOR shall conduct his operations so as to comply with all Federal, State, and local laws pertaining to noise. The use of horns, whistles, and signals shall be held to the minimum necessary in order to ensure as quiet an operation as possible while maintaining safety on the job site.
12. SITE CLEAN-UP.
12.1. General. It is the intent of the COUNTY that the WORK be accomplished with minimum disturbance to the natural resources adjacent to the work area (specifically, the adjacent upland, park areas, landscaping, trees), and that the immediate and general vicinity of the work area remain in its pre-project state subsequent to completion of the WORK. All materials utilized by the CONTRACTOR during construction shall be removed from the site; including survey stakes, flagging and other temporary survey controls. All rock fragments greater than 0.75 inches in any dimension shall be removed from the embankment and construction access areas. All accesses to the revetment shall be restored to the topographic and vegetative conditions that existed prior to construction.
All costs associated with these activities shall be included in the lump sum price for Site Restoration.
12.1.1. Vegetation. The CONTRCTOR shall submit a restoration plan for review by the COUNTY and ENGINEER to restore any impacted vegetation at the construction access, equipment access route, staging area, and/or work areas.
TS-11
12.2. Lost Material. Should the CONTRACTOR during the progress of the WORK, lose, dump, sink, or misplace any material, including stone fragments, or equipment, the CONTRACTOR shall recover and remove same within twenty-four (24) hours of receipt of said notice at no additional cost to the COUNTY.
12.3. Road Debris. The CONTRACTOR shall immediately have those streets or access roadways used for transport of construction materials swept of spilled stone or stone pieces which resulted from the carriage of material for this WORK. Collected stone or stone pieces shall be disposed of in a legal manner and at his/her own expense.
12.4. Work Area Debris. The CONTRACTOR shall continually inspect the work areas to ensure that all debris left by the CONTRACTOR’s and subcontractor’s workers has been removed from the work areas and properly disposed of. This includes, for example, lunch bags, soda cans, drink cups, etc. Any construction debris generated during mobilization, site preparation, excavation, material placement, and/or demobilization shall be removed on a daily basis such that no debris is left on the work area at the end of the day.
13. EXAMINATION & FINAL ACCEPTANCE.
13.1. Substantial Completion Inspection. The WORK will be thoroughly examined by the ENGINEER as soon as practicable, and no later than two (2) weeks after the ENGINEER receives notification from the CONTRACTOR that the WORK is substantially complete and ready for examination. The CONTRACTOR or his authorized representative will be notified when the examination(s) is (are) to be made and will be permitted to accompany the survey party. The ENGINEER shall issue a notice of substantial completion if appropriate and a list of deficiencies to be remedied by the CONTRACTOR.
13.2. Corrections. Should deficiencies in the WORK be determined relative to the contract drawings and specifications, the CONTRACTOR will be required to correct same at the discretion and direction of the ENGINEER. Corrections to the WORK involving the placement of additional foundation materials and armor stone shall be paid for at the contract rate. No direct payment shall be made for corrections to the WORK involving the removal and replacement of unacceptable foundation materials, stone, or site clean-
up. Upon completion of all deficiencies in the WORK identified during the substantial completion inspection and satisfactory review of the as-built surveys, the ENGINEER will issue a recommendation of final acceptance to the COUNTY.
PART 2 – MATERIALS
14. ARMOR STONE.
14.1. Quality of Stone. All rock proposed for use in the structure is subject to approval by the ENGINEER. The ENGINEER may reject stone at any time prior to final acceptance, and may require disassembly of the structure in order to replace unacceptable stone with acceptable stone. All rock for the revetment shall be hard, dense, non-friable stone from sources proposed by the CONTRACTOR and approved by the ENGINEER. Stones shall
TS-12
be durable and shall not disintegrate from exposure to the elements nor break during handling and installation. The rock shall be free from cracks, seams, drill holes, laminations, weak cleavages and similar defects and shall not fracture when dropped during the drop test (Section 14.4). All stone shall be clean and free from earth, dust, or other refuse. The CONTRACTOR shall clean the stones, via pressure washing, as necessary to comply with the permits. Stones shall be shipped and weighed clean.
Weighed trucks shall not contain sand, silt, dirt, or other quarried materials.
14.2. Stone Dimension and Weight. The faces of all stones shall be roughly angular, not rounded, in shape. The least dimension of each stone shall not be less than one-third (1/3) of the greatest dimension of that stone. Flat armor stone will not be accepted.
Stones shall be any of the following:
14.2.1. Embankment Armor Stone
14.2.1.1. 9 inch to 18 inch diameter with fifty percent (50%) greater than 14 inches.
14.2.1.2. SFWMD Type B riprap will be accepted. Minimum weights are 15 pounds.
Maximum weights are 100 pounds, with 50% greater than 50 pounds.
14.2.1.3. FDOT Section 530-2.1.3.1 Bank and Shore Protection. Minimum 60 pounds, maximum 700 pounds with 50% greater than 300 pounds.
14.2.1.4. Alternatively, the stones can be 1 foot to 2 foot diameter riprap with 50% greater than 1.5 feet in diameter.
14.2.2. Wetland Planter Breakwater Armor Stone
14.2.2.1.1. 300 to 500 pound limestone, or equivalent, with 50% greater than
400 pounds.
14.2.3 Wetland Planter Breakwater foundation stone
14.2.3.1 30 to 50 pound limestone, with fifty (50%) above 40 pounds.
14.2.3.2 SFWMD Type B riprap will be accepted. Minimum weights are 15 pounds.
Maximum weights are 100 pounds, with 50% greater than 50 pounds.
Stone gradation shall be based on a representative sample of not less than 10.0 cubic yards. Each stone in the sample shall be individually weighed/measured, and a cumulative plot of percent lighter (by weight) versus stone weight in pounds shall be submitted. The CONTRACTOR shall also select ten (10) representative armor stones from the quarry and have each stone weighed. Each weighted stone shall be clearly marked with its weight. The weighted stones that meet the specifications shall be placed in a convenient location in the quarry where the CONTRACTOR can compare future selected stones for possible shipment to the project site.
14.3 Armor Stone Unit Weight. The CONTRACTOR shall provide certified results of laboratory testing conducted by an independent lab to determine the unit weight and specific gravity of the stone. Tests shall be conducted within 90 days of the start of construction. The tests shall be conducted on a minimum of ten (10) samples randomly selected from the quarry proposed for use. The test shall be ASTM C127. The minimum unit weight of the armor stone is 140 pcf (saturated, surface dried) and the minimum specific gravity shall be 2.24. All 10 samples shall meet or exceed these minimum
TS-13
standards. Failure of the test on the first set of 10 samples and a following set of 10 samples will be cause for rejection of the quarry and/or quarrying process. Stones that fail the test shall not be incorporated into the WORK. The initial test and any additional test required because of failure of the initial test sample will be made at no cost to the COUNTY. The CONTRACTOR may not use more than one quarry without prior approval of the ENGINEER. The ENGINEER will require additional tests, at no expense to the COUNTY, if additional quarries are requested.
14.4 Drop Test at the Quarry. A drop test will be performed on a ten (10) stone sample at the rock quarry. The drop test will be performed by the CONTRACTOR in the presence of the ENGINEER. The CONTRACTOR shall give the ENGINEER one (1) week notice of the drop test. The drop test will consist of dropping the armor stone from a height of five (5) feet onto an 8’ x 8’ steel plate. The steel plate shall be a minimum of 1” thick and be placed on flat, firm ground. Acceptable stone will not fracture when dropped.
The stone should be examined carefully before testing as well as afterward. Failure criteria are breakage, development of new cracks, and opening of old cracks. All ten
(10) stones must pass the drop test to approve the quarry, quarrying process, and stone selection. Stones that fail the test shall not be incorporated into the WORK. Should any of the stones from the first sample fail the drop test, the CONTRACTOR may select a new ten (10) stone sample and repeat the test after approval from the ENGINEER.
14.5 Drop Tests at the Project Site. Drop tests may be requested on individual stones at the project site at any time by the ENGINEER to check stone quality. Stones that are not tested after requested by the ENGINEER, or that fail the drop test, will be rejected and shall be removed from the site by the CONTRACTOR at no expense to the COUNTY.
The CONTRACTOR shall be prepared to perform a drop test within the limits of Construction Work/Staging Area at no additional expense to the COUNTY.
14.6 Non-Specification Armor Stone. The ENGINEER reserves the right to refuse payment for armor stone delivered to the site that does not meet these specifications. The CONTRACTOR shall remove unacceptable stone from the work site at no additional expense to the COUNTY. Unacceptable stone removed from the site shall be returned to the quarry, the CONTRACTOR's yard, or otherwise disposed of in a legal manner.
The CONTRACTOR shall have a quality control representative at the site to review materials delivered to the site.
15 GEOTEXTILE.
15.2 Description. Geotextile shall be TC Mirafi Filterweave 700 or equivalent. Equivalent geotextiles will be determined by the ENGINEER by comparing strength and dimensional specifications provided by the manufacturer. The geotextile shall have the following properties.
Property Units Minimum Average Roll Value
MD1 CD2
Wide Width Tensile Strength lb/ft (kN/m) 2,700 (39) 1,740 (25)
TS-14
Grab Tensile Strength lbs (kN) 370 (1.6) 250 (1.1) Trapezoidal Tear Strength lbs (kN) 100 (0.4) 60 (0.3) Puncture Strength lbs (kN) 120 (0.5) Apparent Opening Size (AOS) mm (U.S. Sieve) 0.212 (70) Percent Open Area % 4-6 Permittivity sec-1 0.28 Flow Rate Gal/min/ft2
(l/min/m2) 18 (733)
UV Resistance (at 500 hours) % 90 Notes:
1. MD dimension is along roll length.
2. CD dimension is across roll width.
16 CONCRETE MATERIALS.
16.1 Concrete for the steel sheet pile cap shall be a 5000 psi compressive strength concrete mix, suitable for pumping into place. Concrete shall have a water to cement ratio of less than 0.4. Admixtures shall include air entraining agents which produce at least 3% air by volume.
16.2 Mix designs shall be submitted to the ENGINEER for approval. Mix design shall include the ready mix plants estimated time for placement from the time of batching.
16.3 Concrete shall be tested for compressive strength a rate of a set of tests for each 30 cy of sidewalk concrete and one set of tests for the tremie pour operation, and one set of tests for the ramp repair. The test shall include 7, 14, and 28 days compressive strength tests. The results shall be supplied to the ENGINEER. Tests shall be in accordance with ASTM C31, C39, and C617.
17 REINFORCING STEEL.
Rebars shall be grade 60 ksi rebars.
18 EXPANSION JOINT MATERIALS.
Expansion joint filler shall be 0.5 inch thick, expansion joint material meeting FDOT Standard Specification 932.
TS-15
PART 3 – EXECUTION
19 EXCAVATION/SAND FILL.
19.2 Excavation. Sand, rock, and/or other debris shall be excavated by the CONTRACTOR as necessary to achieve the specified structure crest elevation and foundation elevation.
The aerial photographs and survey conditions shown in the Plans may not be indicative of conditions at the time of construction. The CONTRACTOR shall estimate the required volume of sand and rock to be excavated prior to making his bid. Existing material excavated for construction of the revetment shall be placed immediately waterward of the structure or used to backfill eroded areas within Section 5. If waves or currents refill any excavated area, the CONTRACTOR shall re-excavate at no cost to the COUNTY.
19.3 Debris. If debris is encountered during excavation, the CONTRACTOR shall remove the debris at no cost to the COUNTY. Any debris excavated shall be removed from the beach and disposed of in an appropriate and legal manner. The costs of debris disposal shall be included in the lump sum cost for Restore Construction Access.
20 TRANSPORTATION OF MATERIALS.
20.2 Method of Transport. The method of transporting construction equipment and materials to and from the work area shall be by truck.
20.3 Traffic Regulations. The CONTRACTOR is responsible for complying with all
Department of Transportation, County, and other local regulations regarding weight limits for bridges, roads, and railways utilized for transport. The CONTRACTOR is likewise responsible for complying with all applicable traffic, safety and speed laws.
Repeated failure of the CONTRACTOR to comply with applicable load and traffic regulations will result in suspension of transport operations until the CONTRACTOR demonstrates to the satisfaction of the COUNTY that the CONTRACTOR has taken sufficient steps to ensure compliance with these regulations. The CONTRACTOR shall notify, and coordinate with, local law enforcement and highway agencies regarding transport activities that shall be undertaken for the WORK.
21 MISPLACED MATERIALS.
If any material is deposited other than in places designated or approved, the CONTRACTOR may be required to remove such misplaced material and redeposit it as directed by the ENGINEER, at the CONTRACTOR's expense. Any physical or environmental damages resulting from the misplaced material shall be the responsibility of the CONTRACTOR. Material lost due to the negligence of the CONTRACTOR shall be replaced by the CONTRACTOR at no additional expense to the COUNTY.
TS-16
22 GEOTEXTILE INSTALLATION.
22.2 Geotextile for Foundations. The geotextile shall be laid loosely, not in a stretched condition, but free of wrinkles and creases. The geotextile shall be lapped a minimum of two (2) feet at ends and sides of geotextile sheets. The geotextile shall be protected at all times during construction and any geotextile damaged shall be removed and replaced with undamaged geotextile at the expense of the CONTRACTOR. A one foot by one foot sample of the geotextile shall be provided to the ENGINEER upon request.
Ends of geotextile shall be wrapped and secured over the toe stones. Geotextile shall be placed perpendicular to the embankment.
23 ARMOR STONE INSTALLATION.
23.2 Armor Stone. Armor stones of the quality and size specified shall be placed in such a manner so as to minimize the void spaces between the stones. The finished surface shall be relatively uniform and shall contain the maximum amount of armor stone as can be obtained by performing the WORK as specified. The structures shall be constructed to the lines and grades shown on the drawings. Stones shall be individually placed in a manner that will prevent rolling or sliding of stone down the slope. Armor stones should be oriented with the longest dimension perpendicular to the structure's alignment, where possible. The stones shall be placed within the boundary of the foundation and not overhang or contact the ground surface. Placing the armor stone by dumping into chutes or by similar methods will not be permitted.
23.2.3 Armor stone shall be placed so as to be in contact with adjacent stones and should interlock to form a compact stable mass. Chinking the voids is not permitted.
Both during construction and upon completion, the structure will be inspected for conformance to the design. The COUNTY will not pay for any stone misplaced or lost during placement.
23.2.4 Placement of stone material during periods of wave energy sufficient to cause displacement of material shall be at the CONTRACTOR's risk. All materials lost or displaced during construction as a result of wave displacement shall be replaced at the CONTRACTOR's expense.
23.3 Tolerances. A vertical tolerance of ± 0.5 feet to the design surface of the revetment crest shall be permitted for projections and depressions of the in-place material. A horizontal tolerance of ± 1.0 feet to the design footprint of the revetment toe shall be permitted for projections and depressions of the in-place material. Placed material that is beyond the maximum tolerance stated herein is ineligible for payment. The ENGINEER may request any stone that exceeds the tolerances be removed by CONTRACTOR at the CONTRACTOR’S expense.
23.4 Bid Tonnage. The tonnage of armor stone in the bid assumes that there are no voids and accounts for zero tolerance. Unless changed by the ENGINEER, the bid tonnage is the maximum pay tonnage. The CONTRACTOR shall make his own estimate prior to
TS-17
making his bid. The bid tonnage assumes 140 pcf stone is used to fill the template. If a higher unit weight stone is used, it is possible that the final elevation of the structures will be between the lower tolerance and the template. Regardless of the stone density, the minimum tolerances shall be met.
23.5 Test Section. At the start of the work, the CONTRACTOR shall complete a 50-foot test section of the first revetment section under construction prior to performing WORK on other sections of the revetment. The CONTRACTOR shall notify the ENGINEER that the test section is complete and shall submit a survey consisting of at least two cross-sections to the ENGINEER. The ENGINEER may observe the section to determine compliance with the construction Plans and Specifications. The CONTRACTOR may continue construction of the structure prior to the ENGINEER’s written approval of the test section; however, materials placed prior to the ENGINEER’s approval of the test section are subject to remediation at the CONTRACTOR’s own risk and cost.
23.6 Basis of Payment. The stone will be paid for at the in-place contract unit price per tons of armor stone. Payment shall be based upon the per unit items constructed by the CONTRACTOR and accepted by the ENGINEER on the basis of both suitable documentation provided and observation of the WORK. Documentation of the WORK shall include the survey of the completed work and a certified weight determination of the quantity of material delivered to the site and placed within the lines and grades as described in these Plans and Specifications. Stone shall be measured by the ton, saturated surface-dry. Measurement shall be by railroad scales, truck scales, barge displacement, volume measurements or other method approved by the ENGINEER. The ENGINEER shall approve which of the methods, i.e. railroad scales, truck scales, barge displacement, or volume measurements, is to be used. Duplicates of the sworn certifications of weight shall be furnished with each load of material and presented to the job inspector/superintendent for their signature. Certificates of weight, which do not bear the signature of the job inspector/superintendent, will not be considered for payment. The WORK specified under this Section, upon acceptance by the ENGINEER, shall be paid for under the Bid Item “FURNISH AND INSTALL
ARMORSTONE”.
24 STEEL SHEET PILE INSTALLATION.
24.1 Steel sheet piles shall be Nucor SKS-16, steel grade shall be A572, grade 50, supplied by COUNTY.
24.2 The steel sheet piles shall be installed to preserve the edge of gravel pathway.
24.3 CONTRACTOR shall review the tolerances between the gravel pathway and proposed revetment prior to installing the steel sheet pile. Field stake the project limits for COUNTY approval prior to installation.
25 CONCRETE PLACEMENT SPECIFICATIONS FOR CONCRETE CAP.
a. Forms for this WORK shall be made of either wood or metal. They shall be straight and free of warp or bends. They shall have sufficient strength and rigidity, when staked, to resist the
TS-18
pressure of the concrete without springing. If wooden forms are used, they shall be of adequate section and shall have a flat surface on top. Forms shall have a depth at least equal to the vertical dimensions for the depth of the concrete being deposited against them. Forms for the repair shall be placed and set to lines, grades and elevations as shown on the drawings.
b. The forms shall be secured on the prepared surface so as to resist the pressure of the concrete without springing. When ready for the concrete to be deposited, they shall not vary from the approved line and grade and shall be kept until the concrete has set.
c. All faces adjacent to the forms shall be spaded so that after the forms are removed, the surface of the faces will be smooth, even, and free of honeycomb. No concrete shall be poured during unfavorable weather or sea conditions. All steel reinforcing shall be pressure washed with fresh water prior to placing the concrete. Steel shall be placed as shown in the Plans. All steel shall have 4 inches of concrete cover (minimum).
d. Just prior to placing the concrete, the sub-grade, and any wooden forms shall be moistened.
The concrete shall be placed in the forms and tamped and vibrated in place so that all honeycombs, especially under other structural elements, will be eliminated and sufficient mortar brought to a smooth finish by means of a float.
f. Repair sections not constructed according to these specifications shall be removed and replaced.
g. Top surface shall be finished with a heavy broom finish. CONTRACTOR shall demonstrate the finish at time of steel reinforcement inspection. Heavy broom finish shall be consistent throughout the installation.
26 CONCRETE FORMWORKERS AND FINISHERS.
The CONTRACTOR shall supply a sufficient number of experienced concrete formworkers and finishers in order to complete the WORK. All formworkers and finishers shall be supervised by a concrete foreman who has a thorough understanding of the construction plans, specifications, and references specifications. No substandard workmanship will be accepted.
27 CONCRETE TRANSPORTATION.
Concrete delivered from a ready mix plant shall be transported and placed in the form within the specified time limits of the mix design. Supplied mix design shall include placement time limits.
Concrete not placed within the time limits will be rejected and not included in the WORK.
CONTRACTOR shall bear all cost for rejected concrete. Concrete shall not be placed in the forms until the reinforcing steel placement has been approved by the ENGINEER.
28 REBAR SPLICING.
The Rebar splices shall be in conformance with ACI-318 (latest edition).
TS-19
29 CONCRETE WASHOUT.
The COUNTY will not permit the wash out of concrete trucks on park property unless the CONTRACTOR provides a water tight container for such purposes and eventually discharges the container at a lawful off-site location.
APPENDIX A
Benderson Park South Shoreline Stabilization Project
DAILY QUALITY CONTROL REPORT
Date: ___________ Report No.___________
(Report is due by 2:00 p.m. of the following day)
WEATHER: (Clear) (P. Cloudy) (Cloudy) TEMP. Min. Max.
Wind Speed _______ mph Direction _____ Wave Height: _______ feet Wave Direction: _______
Armor Stone placed on which structure_________________________
1. Work Performed Today: (Indicate location and description of work performed)
2. Results of Surveillance: (Include satisfactory work completed or deficiencies with action to be taken)
3. Verbal Instructions…
This is the start of the file's text. The full file is on GovTribe.