2525N093 Amendment 3.pdf

PDF 340 KB Posted

Attached to
ITB 2525N093 Yukon River Bridge Redecking (FHWA Funded)
Solicitation number
ITB 2525N093 Yukon River Bridge Redecking (FHWA Funded)
Issued by
Fairbanks North Star Borough, Alaska

About this file

This is Amendment Three to ITB 2525N093 issued by the Alaska Department of Transportation & Public Facilities (DOT&PF) for the Yukon River Bridge Redecking project. The amendment provides answers to bidder questions and must be signed and returned with bids by March 10, 2025 at 2:00 PM Alaska Time. The document clarifies that a 250ft x 75ft secured storage area (expandable if needed) will be provided at the DOT Seven Mile camp maintenance yard, along with adequate offloading space to accommodate trailers and equipment like zoom booms, skid steers, or dozers.

The amendment outlines key operational details including that suppliers must coordinate with Maintenance and Operations staff for site access, and specifies that while no formal delivery sign-off is required, DOT&PF staff will be available to show suppliers the unloading/storage areas and inspect materials upon arrival. Project contacts are provided, including Jason Sakalaskas (Head Maintenance Chief), Jeff Russell (Maintenance Superintendent), and Guan Griffin (Construction Project Manager). The amendment notes that materials can be rejected at any point if they fail to meet ITB specifications or are damaged during transport/unloading.

View the file

Other files

File Type Posted
2525N093 Amendment 2.pdf PDF
2525N093 Amendment 1.pdf PDF
ITB 2525N093 Yukon River Bridge Redecking.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF ALASKA ITB NUMBER 2525N093

AMENDMENT NUMBER THREE (3)

AMENDMENT ISSUING OFFICE:

THIS IS NOT AN ORDER DATE AMENDMENT ISSUED: March 5, 2025

DUE DATE: March 10, 2025 at 2:00 PM. (Alaska Time)

This is a mandatory return Amendment. Your bid may be considered non-responsive if this signed amendment is not received [in addition to your bid] by the date and time bids are due.

Vendor Signature: _____________________________ Date: ___________

Printed Name: _____________________________

Offerors Name: _____________________________

The purpose of this Amendment #3 is to:

• Provide answers to questions received.

Questions and answers

Question #1:

What size of area will be allocated for storage(estimate 50’x150’ needed) and is this area secured?

Answer #1:

A 250ft X 75ft area will be allocated for storage, but can be extended to accommodate supplies. The area is fenced in and secured. Supplier will need to contact Maintenance and Operations to get entry into site.

Question #2:

Is the off-load area attached to storage area and have enough room for trailer and allow zoom boom to access each side?

Answer #2:

Offload area will be in front of the storage area in the DOT Seven Mile camp maintenance yard and has extra room to allow for unloading on both sides of trailer using a zoom boom, skid steer, or dozer.

ITB TITLE: Yukon River Bridge Redecking

Department of Transportation & Public Facilities Statewide Contracting & Procurement

P.O. Box 112500 (3132 Channel Drive, Room 350)

Juneau, Alaska 99811-2500

ITB 2525N093 Yukon River Bridge Redecking Amendment #1

Question #3:

Is a State AK DOT person be on hand to supervise off-load and sign off on delivery?

Answer #3:

It is the responsibility of the Supplier to handle communications with Jason Sakalaskas ( Head Maintenance and operations Chief: jason.sakalaskas@alaska.gov ) along with Jeff Russell (Maintenance and Operations Superintendent: jeff.russell@alaska.gov) for access into Seven Mile camp. Construction Project Manager Guan Griffin (guan.griffin@alaska.gov) can be contacted as well. No sign off on delivery will be necessary.

An AK DOT&PF person will be available to show supplier unloading area and storage area. Upon arrival of materials the project manager will assign the project engineer/other field staff to inspect and verify materials that have arrived on site. Materials can be rejected at any time during the project if they are deemed to not meet the specifications or quality outlined in the invitation to bid (ITB), or are damaged during travel/unloading at Seven mile camp.

Signature: _____________________________ Date: _______________

Name: Adam Tolles Title: Procurement Specialist

03/05/2025 mailto:jason.sakalaskas@alaska.gov mailto:jeff.russell@alaska.gov mailto:guan.griffin@alaska.gov

ITB TITLE: Yukon River Bridge Redecking