This document is Addendum One for Kenosha County's Request for Bid (RFB) #2515 for the Kenosha County Center DPW Elevator Repair project. The addendum provides clarification on two key points: the estimated project budget is $75,000, and the county confirms the elevator jack will be specified for the current 8' rise instead of the originally planned 14' 2" additional travel distance. The county explicitly states they will never build an addition on that side of the building, thus approving the shorter jack specification. The addendum includes revised drawings for the DPW elevator repair, which show the correct travel distance of 8'-0" from the lower level to the upper level.

The document appears to be part of a larger bid process for an elevator repair project, with a focus on technical specifications and precise measurements. The addendum serves to provide official confirmation and documentation of design modifications, ensuring bidders have the most current information for their proposals. By releasing this addendum, Kenosha County is maintaining transparency in the procurement process and providing clear guidance to potential contractors about the specific requirements of the elevator repair project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFB #2515 Addendum One Page 1 of 1

Yes.

Questions & Answers:

Q1. What is the estimated budget?

A. The estimated budget is $75,000.

Q2. The original jack was speced to have another 14' 2" of travel to it for future additions. So, what that means is that the jack cylinder goes a lot farther in the ground than expected. So, does the county want to retain that 14' 2" of additional jack for future rise or should we spec the new jack for the current 8' of rise? The future rise is doable but if there is no need for it.

A. We will never build an addition on that side of the building. The County is OK with the proposed 8’ jack.

Attachments:

Please see the following attachments:

Revised Drawings for DPW Elevator Repair

Please see attached revised drawing for the DPW elevator repair. This revised drawing shows the correct travel distance of the elevator (distance from lower level to upper level) of 8’-0”.

End Addendum 1

KENOSHA COUNTY

RFB #2515 ADDENDUM ONE DATED 7/23/2025

Kenosha County Center DPW Elevator Repair

WORK AREA

7 5/8" 6'-1" 7 5/8"

Elev-1.0

/8

/8

/8

SCOPE OF WORK

REMOVE & REPLACE EXISTING

ELEVATOR CYLINDER

LEVEL 1

0'-0"

LEVEL 2

15'-2"

SCOPE OF WORK

REMOVE & REPLACE

EXISTING ELEV. CYLINDER

EXISTING ELEV. PIT

EXISTING ELEV. DOOR

TO REMAIN

Lower Level

-8'-0"

"1

1.0KUENY ARCHITECTS, LLC

10505 CORPORATE DRIVE - SUITE 100 PLEASANT PRAIRIE, WI 53158 PHONE (262) 857-8101 FAX (262) 857 8103

SITE MAP GENERAL NOTES

1. All concrete to test 4000 psi in 28 days.

2. Verify all dimensions, access, utilities and working conditions in the field.

3. Conform to all applicable codes, ordinances and safety standards.

4. Obtain and pay for all required permits and fees.

5. Notify Architect immediately if work cannot proceed as shown on Drawings or as described in the Specifications.

6. No concrete to be poured without Architect's prior review.

7. All Contractor's to co-operate with all trades, Owner's and Architect's representatives.

8. Leave site clean, neat and free of debris at all times.

9. Each Prime and Sub-contractor is responsible for having read each page of the Specifications, Drawings, Addenda and Change Orders.

10. Guard against interfering with Owner's operations.

11. These Drawings contain no provisions or procedures for on-site safety.

Each Contractor and their employees are responsible to follow all laws and ordinances and provide their own engineering to provide a safe work place.

12. The locations of existing underground utilities, shown on these Drawings, are shown in an approximate way only and have not been independently verified by the Owner or its representatives. The Contractor shall determine the exact location of all existing utilities before commencing work, and agrees to be fully responsible for any and all damages which might be occassioned by the Contractor's failure to exactly locate and preserve any and all underground utilities.

13. Services perform for this project have been conducted in a manner consistent with the level of care and skill ordinarily exercised by members of the profession currently practicing in this area under similar budget and time constraints. No warranty, expressed or implied, is made.

MATERIAL INDICATIONS

DRAWING LEGEND

New or Required Point Elevation

Existing Point Elevation

Existing Contours

New or Required Contours

A Grid Lines

3.1 Building Section

Wall Section

Room/Space Number

Door Number

SHEET INDEX

Earth Backfill

Rigid Insulation

Concrete Block

Aluminum

Lumber (Rough)

Steel

Sand Fill

Concrete

Finished Wood

Stone Fill

Plywood

Batt Insulation

4.1

Room 1

101 Interior Elevation

Detail Section

5.1

7.1

CONSULTANTS

5.1

Detail Number

Page Number

Exterior Elevation

2.1

1 Wall Tag

+ 100.0

+ 100.0

+ 100.0

+ 100.0

Kenosha County DPW Elevator Bid #2515 Kenosha County Center

19600 75th St, Bristol, WI 53104

June 26, 2025

Kenosha County DPW Elevator Bid #2515 Kenosha County Center

ARCHITECT Kueny Architects 10505 Corporate Drive, Suite 100

(262) 857-8101 Pleasant Prairie, Wisconsin 53158 Architect of Record - Jon P. Wallenkamp

1" = 40'-0"1 2025 - Elevator - Existing Plan

1/4" = 1'-0"2 Enlarged Plan

1/4" = 1'-0"3 Elevator Section

ARCHITECTURAL

Elev-1.0 Title Sheet - Plans & Details

ADDENDUM #1

(02) Kenosha County Center_Elevator Plan_AD1 - BID PLAN - 2025.07.16.pdf
Sheets
Elev-1.0 - Title Sheet - Plans & Details

File details come from the government source that posted it. Updated .