This Addendum 2 to the Dartmouth DCTV renovation project modifies the bidding documents for the Town of Dartmouth's exterior renovation work at 247 Russells Mills Road, South Dartmouth, Massachusetts. The addendum, issued August 3, 2026, adds unit pricing line items for plywood underlayment replacement (per square foot), additional trim replacement above called-out scope (per linear foot), and 2x6 pressure-treated framing replacement at termite-damaged areas (per linear foot). The document reissues the bid forms to include unit price information and provides a right-sized drawing set at 24x36 inches, with alternative access via Dropbox link. A questions and answers section clarifies project scope, including confirmation that electrical fixtures are to be removed and new ones installed only in select locations; band board replacement is localized to rotted sections on the east elevation addition; ramp railings (not the ramp itself) are to be replaced; a full-time superintendent is not required, only during active construction; the project duration is three months; hazardous materials testing was completed in 2017 with window caulking found free of asbestos, though contractors must assume all exterior paint contains lead; and a Heavy-Duty Dehumidifier Model H-12683 from ULINE is specified for Alternate 3. The addendum also incorporates a Limited Asbestos Building Materials Inspection Report dated January 15, 2017, which documents identified asbestos-containing materials including air cell and grey pipe insulation with chrysotile content and contaminated soil in the basement and kitchen crawl spaces, with recommendations for proper removal by licensed asbestos contractors.

The updated bid forms require contractors to acknowledge receipt of Addendum 2 and provide a total proposed contract price along with costs for three alternates (elimination of roof overhang scope, substitution of white cedar for red cedar shingles, and basement dehumidifier installation) and unit pricing for the three newly specified line items. General bidders must include sub-bids for painting work (Section 09 0009) and certify they have been in business under their present name, have not failed to complete awarded work, and can provide three recent historic restoration projects of similar nature. Sub-bidders must certify OSHA 10-hour safety training completion for all employees, comply with prevailing wage requirements, and provide evidence of similar recent project experience. The documents require performance and payment bonds equal to the contract price and establish a bona fide bid certification under penalty of perjury, with bidders further certifying they are not debarred from public construction work under Massachusetts General Laws.

View the file

Other files

File Type Posted
2510 Dartmouth DCTV-Addendum 1.pdf PDF
Bid Drawings.pdf PDF
2510 DCTV Bid Specifications.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Renovations to the Dartmouth DCTV 247 Russells Mills Road, South Dartmouth, MA 02748

Addendum 2 August 3, 2026

BTGA Project #2510 ADDENDUM 2 Brewster Thornton Group Architects, LLP SECTION 09 0000 - 1

ADDENDUM 2

1.01 GENERAL

This Addendum forms a part of the Contract Documents and modifies the Bidding Documents dated 04/17/26. Acknowledge receipt of this Addendum in the space provided in the Bid Form. Failure to do so may disqualify the Bidder.

This Addendum consists of 2 pages plus the following:

1. Hazardous Material Testing Report

2. Section 00 4100 Form for General Bid.

3. Section 00 4102 Form for Filed Sub-Bid.

4. Right-sized drawing set (24x36).

1.02 CHANGES TO THE PROJECT MANUAL

1. Section 01 2200 Unit Prices – Part 3.1: Add “C. Linear foot cost to replace 2x6 PT framing at possible termite-damaged areas.”

2. Replace Section 00 4100 Form for General Bid to include Unit price information.

3. Replace Section 00 4102 Form for Filed Sub-Bid to include Unit price information.

1.03 CHANGES TO THE DRAWINGS

1. Drawings have been reissued with this addendum at their appropriate size (24”x36”). If there are still issues viewing the drawings at the intended scale, please download directly from the link below:

https://www.dropbox.com/scl/fo/kbfpbp6khsmn1tanjta26/AFKAWHfb0HYyUu3id7GKphM?rlkey=k kl723dtsskf571slddf4gaxh&st=hxdk9bp7&dl=0

1.04 QUESTIONS AND ANSWERS

1. Question: Electrical Fixtures: Please clarify the project scope for electrical fixtures. Are new fixtures to be furnished and installed as part of this contract? More specifically, are the existing fixtures that are being removed being reinstalled with new fixtures? More specifically, do the side entry doors get new lights on each side?

Answer: The existing light fixtures are to be removed and disposed of, per D201 and D202, Demolition Exterior Elevations. New light fixtures are to be furnished and installed in select locations only, per A201 Exterior Elevations (above the front door) and 8/A502 Typical Roof Overhang (in the new roof overhangs).

2. Question: Band Board Replacement: Please confirm whether the band board is to be replaced as part of the project. If replacement is required, please identify the locations and extent of the work.

Answer: The upper band trim is largely to remain. Replacement is localized to the rotted section on the East elevation addition, as noted on 2/A201.

3. Question: Ramp Reconstruction: Please confirm whether the existing ramp is to be rebuilt. If so, please provide the required scope, dimensions, and any applicable accessibility requirements.

Addendum 2 August 3, 2026

BTGA Project #2510 ADDENDUM 2 Brewster Thornton Group Architects, LLP SECTION 09 0000 - 2

Answer: No, the intent is not to replace the ramp itself. The railings in this location are to be replaced. Any gaps in the ramp due to the removal of the existing railing system and installation of the new system should be patched in kind.

4. Question: Full-Time Superintendent: Please confirm whether a full-time on-site superintendent is required for the duration of the project or only during active construction operations.

Answer: A full-time superintendent is not required. The superintendent is only required to be on site while active construction is being completed by their own workforce or subcontractors.

5. Question: Project Duration: Please confirm the anticipated project timeline. The specifications reference approximately three (3) months; please verify that this is the required contract duration.

Answer: Three (3) months is the assumed project duration for this scope of work.

6. Question: Hazardous Materials: Please confirm whether a hazardous materials inspection and/or survey (including asbestos, lead paint, mold, etc., if applicable) has been completed. If available, please provide the report for contractor review.

Answer: Hazardous material testing was completed in 2017. Window caulking was found not to contain asbestos. Given lead paint testing was not completed at that time, the contractor should assume all exterior paint contains lead and utilize proper safety equipment/protocols for its removal.

7. Question: Is there a set number of days for Time of Completion for this project? Can't seem to find it within the specifications. Please Advise.

Answer: 3 months.

8. Question: Alternate 3, is there a BOD and work plan for the dehumidifier? Only indicates to install 1 dehumidifier and connect to sump. Does the dehumidifier need to be wired back to the circuit breaker, is there an available outlet near the sump? Please Advise.

Answer: BOD: ULINE Heavy-Duty Dehumidifier, Model No: H-12683.

9. Question: There's unit pricing indicated for this project, upon reviewing the Unit Pricing spec. Is there predetermined unit pricing for the two schedules? If not, is there a Unit pricing form to fill out for bid submission? Please Advise

Answer: No, there is no predetermined price. The unit line items have been updated in the bid forms.

END DOCUMENT

LIMITED ASBESTOS BUILDING MATERIALS INSPECTION REPORT

COMMUNITY TELEVISION BUILDING BASEMENT

247 RUSSELLS MILLS ROAD

DARTMOUTH, MASSACHUSETTS 02748

PREPARED FOR:

MR. PETER CHASSE

DARTMOUTH COMMUNITY TELEVISION

247 RUSSELLS MILLS ROAD

DARTMOUTH, MASSACHUSETTS 02748

PREPARED BY:

ATC GROUP SERVICES, LLC

500 WEST CUMMINGS PARK, SUITE 3750

WOBURN, MASSACHUSETTS 01801

ATC PROJECT 6000002570

January 15, 2017

Asbestos Inspection, Community Television Building, Dartmouth, MA

ATC Project No. 6000002570

TABLE OF CONTENTS

1.0 EXECUTIVE SUMMARY

1.1 ASBESTOS

2.0 ASBESTOS CONTAINING MATERIALS SURVEY

2.1 SAMPLING METHODOLOGY

2.2 ASBESTOS-CONTAINING MATERIALS

Table 1: Summary of Identified Asbestos-Containing Materials Table 2: Summary of Non Asbestos-Containing Materials

2.3 ANALYTICAL METHOD

2.4 CONSIDERATION FOR HIDDEN MATERIALS

2.5 RECOMMENDATIONS

APPENDICES

APPENDIX A: ASBESTOS BULK SAMPLE ANALYSIS RESULTS BY PLM

1.0 EXECUTIVE SUMMARY

ATC Group Services, LLC (ATC) was retained by Mr. Peter Chasse to perform an asbestos building materials survey in support of the upcoming renovation project at the Community Television Building Basement, which is located at 247 Russells Mills Road, in Dartmouth, Massachusetts. The inspection was performed in accordance with ATC Proposal 060-2016-0445.

ATC’s scope of work for the asbestos materials building inspection included a limited survey for asbestos-containing materials (ACM). As a part of this inspection, ATC performed a limited asbestos inspection in representative interior areas of the basement and crawl space areas, to the degree feasible. In addition, ATC performed an inspection of the exterior basement window areas. ATC did not perform an inspection of roofing areas, foundation wall areas below grade, or any other areas of the building not included in the scope of work for this survey.

1.1 Asbestos

Section 2.0 discusses the ACM survey and sampling methodology. This survey involved a visual inspection, inventory, and bulk sampling of suspect ACM, including locating and quantifying the identified ACM. ATC inspected representative interior and exterior basement areas as a part of this inspection. In addition, ATC performed an inspection of the exterior basement window areas. ATC did not perform an inspection of roofing areas, foundation areas below grade, or any other areas of the building not included in the scope of work for this survey.

The asbestos survey was performed by a Massachusetts Division of Labor Standards (DLS)-certified Asbestos Inspector Logan Fitzgerald (AI-900711) on December 29, 2016. A total of twenty-eight (28) samples of suspect ACM were collected with twenty-four (24) analyzed to determine asbestos content. The ATC inspector performed both the visual inspection and bulk sampling in the building according to methods outlined in the U.S. Environmental Protection Agency (EPA) guidance document titled, "Guidance for Controlling Asbestos-Containing Materials in Buildings" (Document No. 560/5-85/024). The Polarized Light Microscopy (PLM) bulk sample analytical results are included in Appendix A.

Limitations

Our professional services have been performed, our findings obtained and our recommendations prepared in accordance with customary principles and practices in the field of environmental science and engineering. This statement is in lieu of other statements either expressed or implied. This report does not warrant against future operations or conditions, nor does it warrant against operations or conditions present of a type or at a location not investigated.

Environmental evaluations are limited in the sense that conclusions and recommendations are developed and information obtained from limited research and secondary sources. Except as set forth in this report, ATC has made no independent investigations as to the accuracy or completeness of the information derived from the secondary sources and personal interviews and has presumed that such information was accurate and complete.

This report is intended for the sole use of Dartmouth Community Television. The scope of services performed in execution of this evaluation may not be appropriate to satisfy the needs of other users, and use or re-use of this document or the findings, conclusions, or recommendations found therein, is at risk of said user.

CERIFICATION OF RESULTS

This report has been prepared for the exclusive use of Dartmouth Community Television. Photocopying of this document by parties other than those designated by Dartmouth Community Television, or use of this document for purposes other than intended, is prohibited.

Respectfully submitted this 15th day of January, 2017

Sincerely, ATC Group Services, LLC

Logan Fitzgerald Asbestos Inspector for ATC Group Services, LLC Cell: 774-273-0571 Email: logan.fitzgerald@atcassociates.com

Bryan Thompson Division Manager, Building Sciences For ATC Group Services, LLC Direct Line: 781-404-1375 Email: bryan.thompson@atcassociates.com mailto:logan.fitzgerald@atcassociates.com mailto:bryan.thompson@atcassociates.com

2.0 ASBESTOS CONTAINING MATERIALS SURVEY

2.1 Sampling Methodology

The survey was performed by Mr. Logan Fitzgerald, a Massachusetts DLS-certified Asbestos Inspector (License No. AI-900711), on December 29, 2016. Bulk samples, representing individual homogenous areas of suspect materials, were collected in a randomly distributed manner, in accordance with the methods outlined below.

Building materials generally exist in the form of thermal systems insulation (TSI), surfacing materials, and miscellaneous materials. The following generally illustrates the sampling strategy employed by ATC where feasible:

(a) Surfacing materials - In a randomly distributed manner, collect bulk samples of surfacing materials, representative of each homogeneous area, and not assumed to be ACM.

(1) Collect at least three (3) bulk samples from each homogeneous area that is less than or equal to 1,000 square feet (ft2).

(2) Collect at least five (5) bulk samples from each homogeneous area that is greater than 1,000 ft2, but less than or equal to 5,000 ft2.

(3) Collect at least seven (7) bulk samples from each homogeneous area that is greater than 5,000 ft2.

(b) Thermal systems insulation -

(1) In a randomly distributed manner, collect at a minimum, three (3) bulk samples of thermal systems insulation material, representative of each homogeneous area, and not assumed to be ACM.

(2) Collect, at a minimum, one (1) bulk sample of patched thermal systems insulation, representative of each homogenous area, and not assumed to be ACM, providing the section of patch was less than six (6) linear or square feet.

(3) Collect, at a minimum, three (3) representative bulk samples of each insulated mechanical system not assumed to be ACM, including, but not limited to cementitious material used on pipe fittings such as tees, elbows, or valves.

Representative sampling was conducted in a manner sufficient as to identify whether each homogenous area is either asbestos or non-asbestos containing.

(4) Bulk samples are not required to be collected from any homogeneous area where the accredited asbestos inspector has determined that the thermal systems insulation is a non-suspect material (i.e., fiberglass, foam glass, rubber, or any other non-ACM).

(c) Miscellaneous materials - Collect, at a minimum, two (2) representative bulk sample of each miscellaneous material not assumed to be ACM, including, but not limited to ceiling tiles, floor tiles, associated floor tile mastic, roofing materials, waterproofing, etc.

Representative sampling was conducted in a manner sufficient as to identify whether each homogenous area is either asbestos or non-asbestos containing.

2.2 Asbestos-Containing Materials

ATC conducted the asbestos survey in representative areas, including accessible interior and exterior areas throughout the Basement, located at 247 Russells Mills Road, in Dartmouth, Massachusetts. In consideration that the building is scheduled for renovation, ATC performed limited exploratory renovation, to the degree feasible, in representative interior locations of the basement to identify the presence of hidden ACM. ATC did not perform an ACM inspection of any roofing material. Note that ATC did not survey any materials located outside of the basement and kitchen crawl space.

The following table presents a list of the identified, confirmed ACMs and assumed ACMs in the buildings.

Note: ACM is defined by the MA DEP as any material or product containing one percent or greater asbestos by weight.

Table 1: Summary of Identified Asbestos-Containing Materials Community Television Building Basement

247 Russells Mills Road, Dartmouth, Massachusetts

Location Material Estimated Quantity Result

Basement

Basement Crawl Space Air Cell Pipe Insulation1 700 ln ft 70% Chrysotile

Contaminated Soil2 3,000 sq ft 70% Chrysotile

Room on Left Side of Kitchen Grey Pipe Insulation 70 ln ft 50% Chrysotile

Room on the Right Side of Kitchen Air Cell Pipe Insulation 40 ln ft 70% Chrysotile

Kitchen Crawl Space Grey Pipe Insulation3 50 ln ft 5% Chrysotile

5% Amosite

Contaminated Soil2 500 sq ft 5% Chrysotile 5% Amosite

Ln ft – Linear Feet sq ft – Square Feet

1 The air cell pipe insulation was found to contain asbestos. The material is located on pipes within the crawl space and has become deteriorated and debris from this material is located throughout the soil floor.

ATC has provided an assumed quantity for this material based on observations throughout the representative crawl space area.

2 The soil in the crawl space is contaminated with asbestos containing pipe insulation. ATC recommends that as a part of the abatement project in this area that two (2) inches of top soil will need to be removed.

ATC has provided an assumed quantity of this material based on observations throughout the representative crawl space area.

3 The pipe insulation was found to contain asbestos. The material is located on pipes within the kitchen crawl space and has become deteriorated and debris from this material is located throughout the soil floor.

The kitchen crawl space is a separate area from the crawl space located in the basement. ATC has provided an assumed quantity for this material based on observations throughout representative kitchen crawl space area.

The following table presents a list of suspect materials in the building that were determined not to contain asbestos, based upon laboratory analysis of samples.

Table 2: Summary of Non Asbestos-Containing Materials Community Television Building Basement

247 Russells Mills Road, Dartmouth, Massachusetts

Material Sample Location(s) Grey Ceiling Plaster

Entry Room, Room on the Right

White Skim Coat Associated with Grey Ceiling Plaster

Grey Wall Plaster Orange Skim Coat Associated with

Grey Wall Plaster Grey Plaster Below Stairs Left Room

Masonry Caulking White Window Caulking Associated with

2’ x 4’ Window Exterior Basement Window White Window Caulking Associated with

1’ x 2’ Window

2.3 Analytical Method

Bulk samples of suspect materials were analyzed by Asbestos Identification Laboratory, of Woburn, Massachusetts (AIL) using the EPA approved method (EPA/600R-93/116) for polarized light microscopy with dispersion staining (PLM/DS), using the visual estimation technique for asbestos quantification. By using the PLM/DS method, a trained microscopist is able to identify and distinguish between asbestos group minerals and other fibrous materials such as cellulose (paper), mineral (rock), wood or glass fiber.

The quantity of each of these substances is estimated on a weight basis and recorded as a percent. Only the asbestos content, if any, is recorded in the bulk sample ‘Report of Analysis’ (Appendix A). If a material contains 1% asbestos or greater, it is considered to be asbestos-containing material. Upon client request, or at the recommendation of the analyst, the ‘Point Counting Method’ may be used to verify the presence/absence of asbestos when a sample contains less than 10% asbestos by visual estimate.

AIL is certified by the Massachusetts DLS (certification #AA000208) to perform all types of asbestos analysis. AIL, is also accredited by the EPA National Voluntary Laboratory Accreditation Program (NVLAP).

The PLM/DS analytical method is modeled after 40 CFR Part 763, Subpart F, Appendix A: "Interim Method for the Determination of Asbestos in Bulk Insulation Samples."

2.4 Consideration for Hidden Materials

ATC’s scope of work for the asbestos materials building inspection included a limited survey for asbestos-containing materials. As a part of this inspection, ATC performed a limited asbestos inspection in representative interior areas of the basement and crawl space areas, to the degree feasible. In addition, ATC performed an inspection of the exterior basement window areas. ATC did not perform an inspection of roofing areas, foundation wall areas below grade, or any other areas of the building not included in the scope of work for this survey.

Note that ATC did not disassemble mechanical equipment or electrical gear that may have suspect ACM internal components.

ATC recommends that if a suspect material has not been positively identified, but is similar in mode of occurrence or physical properties as other identified ACM, it should be considered asbestos containing.

Only through further sampling and analysis should a suspect material be identified as non-asbestos.

2.5 Recommendations

ATC recommends that all identified ACM that may be impacted in the future be properly removed and disposed by a Massachusetts-licensed Asbestos Contractor prior to disturbance.

ATC recommends that precautions be taken to prevent unauthorized disturbance of ACM identified in this report.

APPENDIX A

ASBESTOS BULK SAMPLE ANALYSIS RESULTS BY PLM

Batch: 18730

165 New Boston St., Ste 227 Woburn, MA 01801

781-932-9600 Web: www.asbestosidentificationlab.com

Email: mikemanning@asbestosidentificationlab.com

Asbestos Identification Laboratory

Dear Bryan Thompson, Thank you Bryan Thompson for your business.

Michael Manning Owner/Director

Asbestos Identification Laboratory has completed the analysis of the samples from your office for the above referenced project .

The information and analysis contained in this report have been generated using the EPA /600/R-93/116 Method for the Determination of Asbestos in Bulk Building Materials. Materials or products that contain more than 1% of any kind or combination of asbestos are considered an asbestos containing building material as determined by the EPA. This Polarized Light Microscope (PLM) technique may be performed either by visual estimation or point counting. Point counting provides a determination of the area percentage of asbestos in a sample. If the asbestos is estimated to be less than 10% by visual estimation of friable material, the determination may be repeated using the point counting technique. The results of the point counting supersede visual PLM results. Results in this report only relate to the items tested. This report may not be used by the customer to claim product endorsement by NVLAP or any other U.S. Government Agency.

Laboratory results represent the analysis of samples as submitted by the customer. Information regarding sample location, description, area, volume, etc., was provided by the customer. Asbestos Identification Laboratory is not responsible for sample collection activities or analytical method limitations. Unless notified in writing to return samples, Asbestos Identification Laboratory discards customer samples after 30 days. Samples containing subsamples or layers will be analyzed separately when applicable. Reports are kept at Asbestos Identification Laboratory for three years. This report shall not be reproduced, except in full, without the written consent of Asbestos Identification Laboratory.

Work Received:

2017-01-03

2016-12-29

DCTV Public Access Basement- Dartmouth, MA

Bryan Thompson ATC Group Services, Woburn 500 West Cummings Park Suite 3750 Woburn, MA 01801 2016-12-29

Project Number:

Project Name:

January 03, 2017

Date Sampled:

Analysis Method: BULK PLM ANALYSIS EPA/600/R-93/116

Work Analyzed:

• NVLAP Lab Code: 200919-0

• Massachusetts Certification License: AA000208

• State of Connecticut, Department of Public Health Approved Environmental Laboratory Registration Number: PH-0142

• State of Maine, Department of Environmental Protection Asbestos Analytical Laboratory License Number: LB-0078(Bulk) LA-0087(Air)

• State of Rhode Island and Providence Plantations. Department of Health Certification: AAL-121

• State of Vermont, Department of Health Environmental Health License AL934461

Work Received:

2017-01-03

2016-12-29

DCTV Public Access Basement- Dartmouth, MA

Bryan Thompson ATC Group Services, Woburn 500 West Cummings Park Suite 3750 Woburn, MA 01801 2016-12-29

Project Number:

Project Name:

January 03, 2017

Date Sampled:

Analysis Method: BULK PLM ANALYSIS EPA/600/R-93/116

Work Analyzed:

Asbestos % Material Color Non-Asbestos % Location FieldID

LabID gray Non-Fibrous 100

208584

1A Entry RoomGrey Ceiling Plaster None Detected gray Non-Fibrous 100

208585

1B Room on the RightGrey Ceiling Plaster None Detected gray Non-Fibrous 100

208586

1C Room on the RightGrey Ceiling Plaster None Detected white Non-Fibrous 100

208587

2A Entry RoomWhite Skim Coat Assoc w/ Grey Ceiling Plaster

None Detected white Non-Fibrous 100

208588

2B Room on the RightWhite Skim Coat Assoc w/ Grey Ceiling Plaster

None Detected white Non-Fibrous 100

208589

2C Room on the RightWhite Skim Coat Assoc w/ Grey Ceiling Plaster

None Detected gray Non-Fibrous 100

208590

3A Entry RoomGrey Wall Plaster None Detected gray Non-Fibrous 100

208591

3B Room on the RightGrey Wall Plaster None Detected gray Non-Fibrous 100

208592

3C Room on the RightGrey Wall Plaster None Detected orange Non-Fibrous 100

208593

4A Entry RoomOrange Skim Coat Assoc w/ Grey Wall Plaster

None Detected orange Non-Fibrous 100

208594

4B Entry RoomOrange Skim Coat Assoc w/ Grey Wall Plaster

None Detected orange Non-Fibrous 100

208595

4C Entry RoomOrange Skim Coat Assoc w/ Grey Wall Plaster

None Detected gray Non-Fibrous 100

208596

5A Below StairsGrey Plaster None Detected gray Non-Fibrous 100

208597

5B Below StairsGrey Plaster None Detected

Page 1 of 2Tuesday 03 January

Asbestos % Material Color Non-Asbestos % Location FieldID

LabID gray Non-Fibrous 100

208598

6A Left RoomMasonry Caulking None Detected gray Non-Fibrous 100

208599

6B Left RoomMasonry Caulking None Detected

Detected Chrysotile 70 gray Non-Fibrous 30

208600

7A Crawl SpaceWhite Air Cell Pipe Insulation

208601

7B Crawl SpaceWhite Air Cell Pipe Insulation

Not Analyzed

Detected Chrysotile 50 gray Non-Fibrous 50

208602

8A Left RoomGrey Pipe Insulation

208603

8B Left RoomGrey Pipe Insulation Not Analyzed

Detected Chrysotile 70 gray Non-Fibrous 30

208604

9A Room on the Right SideGrey Air Cell Pipe Insulation

208605

9B Room on the Right SideGrey Air Cell Pipe Insulation

Not Analyzed

Detected Chrysotile 5 Amosite 5 gray Cellulose 70 Non-Fibrous 20

208606

10A Kitchen Crawl SpaceGrey Pipe Insulation

208607

10B Kitchen Crawl SpaceGrey Pipe Insulation Not Analyzed multi Non-Fibrous 100

208608

11A Basement WindowWhite Window Caulking Assoc w/ 2x4 Basement Window

None Detected multi Non-Fibrous 100

208609

11B Basement WindowWhite Window Caulking Assoc w/ 2x4 Basement Window

None Detected white Non-Fibrous 100

208610

12A Basement WindowWhite Window Caulking Assoc w/ 1x2 Basement Window

None Detected white Non-Fibrous 100

208611

12B Basement WindowWhite Window Caulking Assoc w/ 1x2 Basement Window

None Detected

Analyzed by: 18730Batch:

Page 2 of 2Tuesday 03 January End of Report

Addendum 2: August 3, 2026

BTGA Project #2510 FORM FOR GENERAL BID Brewster Thornton Group Architects, LLP SECTION 00 4100 - 1

SECTION 00 4100

FORM FOR GENERAL BID

To the Awarding Authority:

A. The Undersigned proposes to furnish all labor and materials required for the Renovation to the Dartmouth DCTV at 247 Russells Mills Road, South Dartmouth, MA 02748, in accordance with the accompanying plans and specifications prepared by Brewster Thornton Group Architects, LLP for the contract price specified below, subject to additions and deductions according to the terms of the specifications.

B. This bid includes the following addenda:

Addendum 1, dated ___________________

Addendum 2, dated ___________________

C. The total proposed contract price is ____________________________dollars ($________________).

For Alternate No. 1 (Eliminate the roof overhang scope at exterior doors):

Subtract $_______________

For Alternate No. 2 (Replace red cedar shingles with white cedar shingles):

Subtract $_______________

For Alternate No. 3 (Install one (1) dehumidifier in the basement):

Add $_______________

D. Unit Pricing:

Cost for plywood underlayment replacement:

$_____________ per Square Foot.

Cost of additional trim replacement (above what is called out on the documents):

$___________ per Linear Foot.

Cost to replace 2x6 PT framing at possible termite-damaged areas:

$___________ per Linear Foot.

E. The subdivision of the proposed contract work is as follows:

Item 1. Work of the general contractor, being all work other than that covered by Item 2.

SUB-TOTAL OF ITEM 1 WORK: $

Addendum 2: August 3, 2026

BTGA Project #2510 FORM FOR GENERAL BID Brewster Thornton Group Architects, LLP SECTION 00 4100 - 2

Item 2. Sub-bids as follows:

Section No. Subtrade

Name of Sub-Bidder Amount

09 0009 Painting $

TOTAL OF ITEM 2: $

The undersigned agrees that each of the above-named sub-bidders will be used for the work indicated at the amount stated, unless a substitution is made. The undersigned further agrees to pay the premiums for the performance and payment bonds furnished by sub-bidders as requested herein and that all of the cost of all such premiums is included in the amount set forth in Item 1 of this bid.

The undersigned agrees that if he is selected as general contractor, he will promptly confer with the awarding authority on the question of sub-bidders; and that the awarding authority may substitute for any sub-bid listed above a sub-bid filed with the awarding authority by another sub-bidder for the sub-trade against whose standing and ability the undersigned makes no objection; and that the undersigned will use all such finally selected sub-bidders at the amounts named in their respective sub-bids and be in every way as responsible for them and their work as if they had been originally named in this general bid, the total contract price being adjusted to conform thereto.

F. The undersigned offers the following information as evidence of the contractor’s qualifications to perform the work as bid upon according to all the requirements of the plans and specifications:

1. Have been in business under present business name __________ years.

2. Ever failed to complete any work awarded? __________________

3. List at least three recent historic restoration projects of a similar nature:

Building Owner Architect Contract Amount

G. The undersigned agrees that, if he is selected as general contractor, he will within five days, Saturdays, Sundays and legal holidays excluded, after presentation thereof by the awarding authority, execute a contract in accordance with the terms of this bid and furnish a performance bond and also a labor and materials or payment bond, each of a surety company qualified to do business under the laws of the commonwealth and satisfactory to the awarding authority and each in the sum of the contract price, the premiums for which are to be paid by the general contractor and are included in the contract price;

provided, however, that if there is more than 1 surety company, the surety companies shall be jointly and severally liable.

The undersigned hereby certifies that he is able to furnish labor that can work in harmony with all other elements of labor employed or to be employed on the work; that all employees to be employed at the worksite will have successfully completed a course in construction safety and health approved by the United States Occupational Safety and Health Administration that is at least 10 hours in duration at the time the employee begins work and who shall furnish documentation of successful completion of said

Addendum 2: August 3, 2026

BTGA Project #2510 FORM FOR GENERAL BID Brewster Thornton Group Architects, LLP SECTION 00 4100 - 3 course with the first certified payroll report for each employee; and that he will comply fully with all laws and regulations applicable to awards made subject to section 44A.

The undersigned further certifies under the penalties of perjury that this bid is in all respects bona fide, fair and made without collusion or fraud with any other person. As used in this subsection the word “person” shall mean any natural person, joint venture, partnership, corporation or other business or legal entity. The undersigned further certifies under penalty of perjury that the said undersigned is not presently debarred from doing public construction work in the commonwealth under the provisions of section twenty-nine F of chapter twenty-nine, or any other applicable debarment provisions of any other chapter of the General Laws or any rule or regulation promulgated thereunder.

Date ____________________

(Name of General Bidder)

By ___________________________________________________

(Name of Person Signing Bid and Title)

(Business Address)

(City and State)

END OF FORM

Addendum 2: August 3, 2026

BTGA Project #2510 FORM FOR FILED SUB-BID Brewster Thornton Group Architects, LLP SECTION 00 4102 - 1

SECTION 00 4102

FORM FOR FILED SUB-BID

The undersigned proposes to furnish all labor and materials required for completing, in accordance with the hereinafter described plans, specifications, and addenda prepared by Brewster Thornton Group Architects, LLP for the Renovations to the Dartmouth DCTV, located at 247 Russells Mills Road, South

Dartmouth, MA 02748 for one of the following sections of work:

Section 09 0009

A. This bid includes the following addenda:

Addendum 1, dated ___________________

Addendum 2, dated ___________________

Addendum 3, dated ___________________

B. The total proposed sub-contract price is _________________________dollars ($________________).

For Alternate No. 1 (Eliminate Roof Overhangs):

Subtract $_______________

For Alternate No. 2 (Replace red cedar shingles with shite cedar shingles):

Subtract $_______________

For Alternate No. 3 (Install one (1) dehumidifier in the basement):

Add $_______________

C. Unit Pricing:

Cost for plywood underlayment replacement:

$_____________ per Square Foot.

Cost of additional trim replacement (above what is called out on the documents):

$___________ per Linear Foot.

Cost to replace 2x6 PT framing at possible termite-damaged areas:

$___________ per Linear Foot.

Brewster Thornton Group Architects, LLP SECTION 00 4102 - 2

D. This Sub-Bid

May be used by any General Bidder Except:

May only be used by the following General Bidders:

[To exclude general bidders, insert “X” in one box only and fill in blank following that box. Do not answer C if no general bidders are excluded.]

E. The undersigned agrees that, if he is selected as a sub-bidder, they will, within 5 days, Saturdays, Sundays and legal holidays excluded, after presentation of a subcontract by the general bidder selected as the general contractor, execute with such general bidder a subcontract in accordance with the terms of this sub-bid, and contingent upon the execution of the general contract, and, if requested so to do in the general bid by the general bidder, who shall pay the premiums therefor, or if prequalification is required pursuant to section 44D3/4, furnish a performance and payment bond of a surety company qualified to do business under the laws of the commonwealth and satisfactory to the awarding authority, in the full sum of the subcontract price.

F. The names of all persons, firms, and corporations subcontracting to the undersigned as part of the work:

Name Class of Work Bid Price

G. The undersigned agrees that the above list of bids to the undersigned represents bona fide bids based on the hereinbefore described plans, specifications and addenda and that, if the undersigned is awarded the contract, they will be used for the work indicated at the amounts stated, if satisfactory to the awarding authority.

H. The undersigned further agrees to be bound to the general contractor by the terms of the hereinbefore described plans, specifications, including all general conditions stated therein, and addenda, and to assume toward him all the obligations and responsibilities that he, by those documents, assumes toward the owner.

I. The undersigned offers the following information as evidence of the contractor’s qualifications to perform the work as bid upon according to all the requirements of the plans and specifications:

1. Have been in business under present business name __________ years.

2. Ever failed to complete any work awarded? __________________

3. List one or more recent buildings with names of general contractor and architect on which you served as a subcontractor for work of similar characteristics as required for the above-named building:

Brewster Thornton Group Architects, LLP SECTION 00 4102 - 3

Building Architect General Contractor Contract Amount

J. The undersigned hereby certifies that he is able to furnish labor that can work in harmony with all other elements of labor employed or to be employed on the work; that all employees to be employed at the worksite will have successfully completed a course in construction safety and health approved by the United States Occupational Safety and Health Administration that is at least 10 hours in duration at the time the employee begins work and who shall furnish documentation of successful completion of said course with the first certified payroll report for each employee; and that he will comply fully with all laws and regulations applicable to awards of subcontracts subject to section 44F.

The undersigned further certifies under penalties of perjury that this sub-bid is in all respects bona fide, fair and made without collusion or fraud with any other person. As used in this subsection the word "person'' shall mean any natural person, joint venture, partnership, corporation or other business or legal entity. The undersigned further certifies under penalty of perjury that the said undersigned is not presently debarred from doing public construction work in the commonwealth under the provisions of section twenty-nine F of chapter twenty-nine, or any other applicable debarment provisions of any other chapter of the General Laws or any rule or regulation promulgated thereunder.

Date: __________________

(Name of Sub-bidder)

By: ______________________________________________________ (Title and Name of Person Signing Bid)

(Business Address)

END OF FORM

BREWSTER THORNTON

GROUP ARCHITECTS, LLP

PROJECT NUMBER

PROJECT NAME

RENOVATIONS TO THE

ARCHITECT

CLIENT

TOWN OF DARTMOUTH

317 IRON HORSE WAY

SUITE 202

PROVIDENCE, RI 02908

BREWSTERTHORNTON.COM

401 . 861 . 1600

LOCUS MAP : NTS

247 RUSSELLS MILLS ROAD

DARTMOUTH, MA 02748

PROJECT ISSUE

DARTMOUTH COMMUNITY MEDIA

STRUCTURAL

ENGINEERS

E2 ENGINEERS

2532 MAIN ST

SUITE 206

CONCORD, MA 01742

DARTMOUTH DCTV

247 RUSSELLS MILLS RD, SOUTH DARTMOUTH, MA 02748

DARTMOUTH DCTV

BID DOCUMENTS

BTGA #2510

04/17/26

AREA OF

WORK

R U

S S E L L S M

IL

L S R

D

ELM

STR

EET

G E O

R G

E S

T

T H E R E S A S

T

A R R O

W H E A D L

N

RUSSELLS MILLS RD

U T

IC

A

L N

RUSSELLS M

ILLS R

D

U T

IC

A

L N

SEM

INOLE RD

MISHAWUM DR

SAGAMORE DR

DRAWING LIST

SHEET SHEET NAME

GENERAL

G000 COVER SHEET

G001 COMMON ABBR., GENERAL LEGEND, AND NOTES

G002 EXISTING PHOTOS / SCOPE

G003 EXISTING PHOTOS / SCOPE

DEMOLITION

D201 DEMOLITION EXTERIOR ELEVATION

D202 DEMOLITION EXTERIOR ELEVATION

ARCHITECTURAL

A100 ROOF PLAN AND SITE PLAN

A201 EXTERIOR ELEVATIONS

A202 EXTERIOR ELEVATIONS

A501 DETAILS

A502 DETAILS

christines NJG Stamp MA

COMMON ABBREVIATIONS

ABV ABOVE

A/C AIR CONDITION

ACC. ACCESS(IBLE)

ACT ACOUSTICAL CEILING TILE

ADA AMERICANS WITH DISABILITY ACT

ADDL ADDITIONAL

ADJ. ADJUSTABLE (OR) ADJACENT

A/E ARCHITECT/ENGINEER

A.S.F ABOVE SUBFLOOR

A.F. ABOVE FLOOR

A.F.F. ABOVE FINISH FLOOR

AHJ AUTHORITY HAVING JURISDICTION

AL./ALUM. ALUMINUM

ALT. ALTERNATE

ANOD. ANODIZED

ARCH. ARCHITECT(URAL)

A.P. ACCESS PANEL

APP. APPROXIMATE

APT APARTMENT

APPROX. APPROXIMATE

ASI ARCHITECT’S SUPPLEMENTAL

INSTRUCTION

AUTO. AUTOMATIC

AUX. AUXILIARY

BAS BUILDING AUTOMATION SYSTEM

BD BOARD

BDRM BEDROOM

BFE BOTTOM OF FROST ELEVATION

BITUM. BITUMINOUS

BLDG BUILDING

BLW BELOW

BSMT BASEMENT

BOTT. BOTTOM

B.O.F BOTTOM OF FOOTING

B.O. BLOW OFF VENT

BLKG BLOCKING

BIT. BITUMEN OR BITUMENOUS

BLUEBD BLUEBOARD

(VENEER PLASTER BASE)

BRK BRICK

BRZ BRONZE

BTWN BETWEEN

CAB. CABINET

C.F.M.F. COLD-FORMED METAL FRAMING

CG COLUMN GRID

C.L. CENTER LINE

CLL CONTRACT LIMIT LINE

CLO CLOSET

CLG CEILING

CLR CLEAR(ANCE)

C.J. CONTROL JOINT

CMU CONCRETE MASONRY UNIT

CO CASED OPENING

COL. COLUMN

COMP. COMPRESS(ED), (ION). (IBLE)

CONC. CONCRETE

CONST. CONSTRUCTION

CONT. CONTINU(E), (OUS)

COORD. COORDINATE

CPT CARPET

CPR COPPER

C.T. CERAMIC TILE

C.U.H. CABINET UNIT HEATER

DBL DOUBLE

DEMO DEMO(LISH), (LITION)

DEG DEGREES

DET. DETAIL

D.F. DRINKING FOUNTAIN

DH DOUBLE HUNG

DIA. DIAMETER

DIAG. DIAGONAL

DIM. DIMENSION

DISP. DISPOSE

DN DOWN

DR DOOR

DS DOWNSPOUT

DTL DETAIL

DWG DRAWING

DWGS DRAWINGS

DX DUPLEX

EA. EACH

EL. ELEVATION

ELEC. ELECTRIC(AL)

ELEV. ELEVATOR

EMER. EMERGENCY

EMS EMERGENCY MANAGEMENT

SYSTEM

E.J. EXPANSION JOINT

EQ EQUAL

EQUIP EQUIPMENT

ETR EXISTING TO REMAIN

EV EXHAUST VENT

EX. EXISTING

EXIST. EXISTING

EXG EXISTING

EXT. EXTERIOR

O.C. ON CENTER

O.H. OPPOSITE HAND

OPNG OPENING

OPP OPPOSITE

ORIG. ORIGINAL

OHD OVERHEAD

OZ. OUNCE

PCC PRE-CAST CONCRETE

PERP PERPENDICULAR

PL PLATE

PLAM PLASTIC LAMINATE

PNL PANEL

PNT PAINT

PPL PEOPLE

PTD PAINTED

PR PAIR

PREP PREPARATION

P.T. PRESSURE TREATED

PTN PARTITION

PWD PLYWOOD

P.V. PLUMBING VENT

Q.T. QUARRY TILE

R# RADIUS

R RISER

R.B. RESILENT BASE

RCP REFLECTED CEILING PLAN

R&D REMOVE & DISPOSE

R.D. ROOF DRAIN

RE: REFER TO

REF. REFER

REFR REFRIGERATOR

REQ. REQUIRE(D)

RES. RESILIENT

REV. REVISION

R.H. RIGHT HAND

RM ROOM

R.O. ROUGH OPENING

RWB RUBBER WALL BASE

SCHED. SCHEDULE

SD SIDE

SECT. SECTION

SF SQUARE FEET

SF SUB FLOOR

S.GASKET SMOKE GASKET

SGL SAFETY GLASS

SHT SHEET

SHTH SHEATHING

SIM. SIMILAR

SPEC. SPEC (-IFIED) (-IFICATION)

SRL SUBMITTAL REVIEW LETTER

SQ. SQUARE

S.S. STAINLESS STEEL

S.S.M. SOLID SURFACE MATERIAL

STC SOUND TRANSMISSION COEFFICIENT

STD STANDARD

STOR. STORAGE

STL STEEL

STRUCT. STRUCTURAL

SUSP. SUSPEND(ED)

SYS. SYSTEM

T TREAD

T&G TONGUE AND GROOVE

TEL. TELEPHONE

TEMP TEMPORARY

TGL TEMPERED GLASS

THK THICK(NESS)

THRESH THRESHOLD

T.O. TOP OF ________________

T.O.F. TOP OF FOOTING

T.O.S. TOP OF SHELF

T.O.W. TOP OF WALL

TS TUBE STEEL

TSTAT THERMOSTAT

TYP. TYPICAL

TZ TERRAZZO

U.H. UNIT HEATER

U.N.O. UNLESS NOTED OTHERWISE

V.A.T. VINYL ASBESTOS TILE

VCT VINYL COMPOSITION TILE

VERT. VERTICAL

V.I.F. VERIFY IN FIELD

V.R. VAPOR RETARDER

W/ WITH

W.C. WATER CLOSET

WD WOOD

WDW WINDOW

WSU WATERPROOF SHINGLE UNDERLAYMENT

WWF WELDED WIRE FABRIC

Z.C.C. ZINC COATED COPPER

@ AT

& AND

F.A. FIRE ALARM

F.A.R. FLOOR AREA RATIO

F.C.U. FAN COIL UNIT

F.D. FLOOR DRAIN

F.E. FIRE EXTINGUISHER

FEC FIRE EXTINGUISHER CABINET

FF&E FURNITURE, FIXTURE, AND

EQUIPMENT

FGL FIBERGLASS

FIN. FINISH

FIN.CLG FINISH CEILING

FIN.FLR FINISH FLOOR

FIN.SCH FINISH SCHEDULE

FIXT. FIXTURE

FLR. FLOOR

FLUOR. FLUORESCENT

FND. FOUNDATION

F.O. FACE OF _____________

F.P. FIRE PROTECTION

F.RATING FIRE RATING

FR FIRE RETARDANT

FRP FIBERGLASS REINFORCED

PLASTIC

FT FEET

FTG FOOTING

FURN. FURNITURE

GA GAGE/GAUGE

GALV GALVANIZED

GB GRAB BAR

GL GLASS

GLAM GLUE LAMINATED BEAM

GLZ GLAZING

GWB GYPSUM BOARD

HC HANDICAP

HDF HIGH DENSITY FIBERBOARD

HM HOLLOW METAL

HDW HARDWARE

HRW HARDWARE

HOR. HORIZONTAL

HR HOUR

HT HEIGHT

IN. INCHES

INCL. INCLUDE(D),(ING)

INFO. INFORMATION

INSUL. INSULATION

INT. INTERIOR

J.C. JANITOR’S CLOSET

J-BOX JUNCTON BOX

JT JOINT

K.B. KNOX BOX

KIT. KITCHEN

LAB. LABORATORY

LAV. LAVATORY

LB POUND(S)

LCC SEE Z.C.C.

L.E.D. LIGHT EMITTING DIODE

LF LIGHT FIXTURE

L.H. LEFT HAND

LIB. LIBRARY

LIN LINOLEUM

LKR LOCKER

LVL LAMINATED VENEER LUMBER

LOC. LOCATION

LVR LOUVER

LVT LUXURY VINYL TILE

MACH. MACHINE

MAS. MASONRY

MAT. MATERIAL

MAX. MAXIMUM

MCT MARMOLEUM COMPOSITION TILE

MECH. MECHANICAL

MED. MEDIUM

MEMB MEMBRANE

MDF MEDIUM DENSITY FIBERBOARD

MIL MILLIMETER

MIN. MINIMUM

MISC. MISCELLANEOUS

M.O. MASONRY OPENING

M.R. MOISTURE RESISTANT

MTL METAL

N.A. NOT APPLICABLE

NAT. NATURAL

N.C. NOISE CRITERIA

N.I.C. NOT IN CONTRACT

NKL NICKEL

NOM. NOMINAL

NO NUMBER

NR NOT RATED

N.R.C. NOISE REDUCTION COEFFICIENT

N.T.S. NOT TO SCALE

(USE OF PUNCTUATION IS OPTIONAL)

1. ALL WORK SHALL CONFORM TO ALL APPLICABLE CODES AND REGULATIONS IN EFFECT AT THE PROJECT SITE.

2. DO NOT SCALE DRAWINGS. FIELD VERIFY ALL DIMENSIONS.

3. THE CONTRACTOR SHALL REPORT ANY AND ALL DISCREPANCIES TO THE ARCHITECT FOR CLARIFICATION BEFORE PROCEEDING.

4. ALL DIMENSIONS OF NEW WORK ARE TO THE FACE OF CONCRETE AND MASONRY, AND THE CENTER OF METAL STUDS AND FRAME OPENINGS

U.N.O.

5. DIMENSIONS NOTED TO EXISTING PLANES SHALL REFER TO THE FINISHED SURFACE OF THE EXISTING WALL, FLOOR, OR CEILING PLANE, UNLESS

NOTED OTHERWISE.

6. ALL ITEMS OF WORK ARE TO BE NEW UNLESS NOTED AS EXISTING.

7. CONTRACTOR SHALL VERIFY ALL DOOR AND WINDOW DIMENSIONS IN FIELD BEFORE PURCHASE.

8. TYPICAL CONSTRUCTION IS INDICATED THROUGHOUT THE PROJECT. REPEATED SIMILAR GRAPHIC REPRESENTATION IS SUFFICIENT. NOTE AT

EACH OCCURRENCE IS NOT REQUIRED.

9. ALL ITEMS DETAILED IN SECTION ARE CONTINUOUS UNLESS NOTED OTHERWISE.

10. FASTENERS, ADHESIVES AND OTHER SYSTEM COMPONENTS TYPICALLY REQUIRED ARE NOT CONSISTENTLY NOTED OR DETAILED. ONLY

UNIQUE CONDITIONS ARE ILLUSTRATED. PROVIDE ALL ITEMS REQUIRED TO SAFELY SECURE, ATTACH OR STABILIZE ALL WORK AS RECOMMENDED

BY IT'S MANUFACTURER, AS REQUIRED BY CODE OR NECESSARY FOR THE ASSEMBLY'S PROPER PERFORMANCE WHETHER OR NOT DETAILED.

11. ALL DRAWINGS AND SPECIFICATIONS ARE COMPLIMENTARY AND MUST BE USED AS A SET FOR COMPLETE CONSTRUCTION INFORMATION.

12. IT SHALL BE THE DUTY OF THE CONTRACTOR TO REQUEST FROM THE ARCHITECT ALL NECESSARY INTERPRETATION OF THE CONTRACT

DOCUMENTS.

13. DRAWINGS ARE FOR ILLUSTRATIVE PURPOSES ONLY AND MAY NOT SHOW ALL DEMOLITION WORK REQUIRED TO COMPLETE THE CONTRACT

WORK.

14. REFER TO PROJECT SPECIFICATIONS FOR ADDITIONAL INFORMATION.

15. DRAWINGS INDICATE APPROXIMATE LOCATION OF FIELD CONDITIONS. VERIFY IN FIELD.

16. DRAWINGS INDICATE SCOPE OF WORK. ACTUAL EXTENT OF WORK TO BE DETERMINED BY FIELD OBSERVATION.

17. DIMENSIONS AND ELEVATIONS INDICATED ON THE DRAWINGS IN REFERENCE TO EXISTING STRUCTURES ARE THE BEST AVAILABLE DATA

OBTAINABLE BUT ARE NOT GUARANTEED BY THE OWNER AND THE OWNER WILL NOT BE RESPONSIBLE FOR THEIR ACCURACY. THE CONTRACTOR

SHALL FIELD CHECK AND VERIFY ALL DIMENSIONS, GRADES, LINES, LEVELS, OR OTHER CONDITIONS OF LIMITATIONS AT THE SITE TO AVOID

CONSTRUCTION ERRORS. IF ANY WORK IS PERFORMED BY THE CONTRACTOR OR ANY OF HIS SUB-CONTRACTORS PRIOR TO ADEQUATE

VERIFICATION OF APPLICABLE DATA, ANY RESULTANT EXTRA COST FOR ADJUSTMENT OF WORK AS REQUIRED TO CONFORM TO EXISTING

LIMITATIONS SHALL BE ASSUMED BY THE CONTRACTOR WITHOUT REIMBURSEMENT OR COMPENSATION BY THE OWNER.

18. OMISSION FROM THE DRAWINGS AND SPECIFICATIONS OF ITEMS WHICH OBVIOUSLY ARE NEEDED TO PROPERLY PERFORM THE WORK, SUCH AS

ATTACHMENTS, BOLTS, HANGERS, ETC., SHALL NOT RELIEVE THE CONTRACTOR FROM FURNISHING AND INSTALLING THEM.

19. IT IS INTENDED THAT ALL DIMENSIONS AND FIGURES ON THE DRAWINGS SHALL AGREE. THE CONTRACTOR SHALL CONFIRM THEM BEFORE

STARTING THE WORK AND SHALL REPORT IN WRITING ALL DISCREPANCIES TO THE ARCHITECT FOR ADJUSTMENT.

GENERAL NOTESGENERAL LEGEND

NAME

EL. ELEVATION

EXTERIOR ELEVATION

INTERIOR ELEVATION

SECTION

BENCHMARK ELEVATION

SPOT ELEVATION

ROOM NAME AND MARK

DOOR MARK

WALL TYPE

WINDOW TYPE

KEY NOTE

A#

A#

EXISTING PARTITION

REVISION#

DETAIL KEY

A#

PHOTO SYMBOL

CONCRETE

RIGID INSULATIONCONCRETE BLOCK

BRICK

DISTURBED EARTH

ENGINEERED WOOD (MDF, HDF,

ETC.)

PLASTIC/PVC

PLYWOOD

RUBBLE

WOOD

ASPHALT SHINGLES

GLASS, VERTICAL SURFACE

GLASS, SPECIALTY

MARBLE/ GRANITE

STEEL/METAL

WOOD SHINGLES

CULTURED STONE

BATT INSULATION

L.O.C.

LIMITS OF CONSTRUCTION

GYPSUM WALLBOARD

ACCESSORY/ FURNITURE /

SPECIALTY EQUIPMENT MARK

REVISION CLOUD

PROJECT NORTH SYMBOL

(DASHED INDICATES TRUE NORTH)

COLUMN GRID LINE

NEW CONSTRUCTION

DETAIL

A#

NEW PARTITION

X

DETAIL CALLOUT

A#

A#

DISCLAIMER: HATCH PATTERN SCALE ADJUSTS BY DRAWING SCALE. SEE OTHER DESIGN DISCIPLINES FOR

ADDITIONAL LEGEND & SCHEDULE INFORMATION.

A# EXISTING CONSTRUCTION

UNDISTURBED EARTH

NORTH

X

X

X

ROOM NAME

SHEET

JOB NO. DATE

ISSUE :

SHEET TITLE

/2

/2

:2 :1

P

M

G001

COMMON

ABBR.,

GENERAL

LEGEND, AND

NOTES

R E

N O

V A

T

IO

N S

T O

T H

E

D A

R T

M O

U T

H D

C T

V R

U S

S E

L L

S M

IL

L

S R

D S

O U

T H

D A

R T

M O

U T

H M

A

04/17/26

BID DOCUMENTS

NO. REVISION DESCRIPTION DATE

UP

SHEET

JOB NO. DATE

ISSUE :

SHEET TITLE

/2

/2

:2 :1

P

M

G002

EXISTING

PHOTOS /

SCOPE

R E

N O

V A

T

IO

N S

T O

T H

E

D A

R T

M O

U T

H D

C T

V R

U S

S E

L L

S M

IL

L

S R

D S

O U

T H

D A

R T

M O

U T

H M

A

04/17/26

BID DOCUMENTS

NO. REVISION DESCRIPTION DATE

1. REMOVE AND REPLACE EXTERIOR CEDAR SHINGLE SIDING AND UNDERLAYMENT. REMOVE AND REPLACE ALL ROTTED

SHEATHING BEHIND SHINGLES.

2. REMOVE AND REPLACE IN KIND ALL ROTTED WOOD TRIM WITH PAINTED COMPOSITE MATERIAL AS INDICATED ON

ELEVATIONS.

3. REMOVAL VEGETATIVE GROWTH AROUND THE BUILDING, TYPICAL.

6. REGRADE AT FOUNDATION WALLS AT SOUTH AND EAST ELEVATIONS AND INSTALL WATERTABLE TRIM BAND AT ALL SIDES.

8. REPAIR STEPS AT AREAS OF DECAY PER DRAWINGS.

5. INSTALL EXTENDED SPLASH BLOCKS AT ALL DOWNSPOUT LOCATIONS. REMOVE ABANDONED UNDREGROUND DOWNSPOUT

CONNECTIONS.

4. REPLACE EXISTING WINDOW TRIM, TYPICAL OF ALL LOCATIONS.

7. REPAIR FOUNDATION AT AREAS OF DECAY PER DRAWINGS.

NOTE: PHOTOS INDICATE GENERAL CONDITIONS AND SPECIFIC SCOPE. FULL SCOPE OF WORK IS INDICATED ON OTHER SHEETS.

EXISTING KEY PLAN

SHEET

JOB NO. DATE

ISSUE :

SHEET TITLE

/2

/2

:2 :1

P

M

G003

EXISTING

PHOTOS /

SCOPE

R E

N O

V A

T

IO

N S

T O

T H

E

D A

R T

M O

U T

H D

C T

V R

U S

S E

L L

S M

IL

L

S R

D S

O U

T H

D A

R T

M O

U T

H M

A

04/17/26

BID DOCUMENTS

10. REPLACE METAL GRATE AND REPAIR WINDOW WELL. 11. REPLACE EXTERIOR LIGHTING AS NOTED ON DRAWINGS. ALL MECHANICAL, ELECTRICAL, PLUMBING WORK TO BE DONE

DESIGN/BUILD.

12. SAND, PATCH, AND REPAINT BEADBOARD PORCH CEILING. 14. REMOVE ABANDONED OIL PIPING AND PATCH FOUNDATION WALLS.13. INSTALL ROOFS OVER SIDE DOORS. (ALTERNATE)

14. INSTALL DEHUMIDIFIERS AT BASEMENT. (ALTERNATE)

NO. REVISION DESCRIPTION DATE

NOTE: PHOTOS INDICATE GENERAL CONDITIONS AND SPECIFIC SCOPE. FULL SCOPE OF WORK IS INDICATED ON OTHER SHEETS.

9. INSTALL HANDRAILS AT STAIRS.

EXISTING KEY PLAN

16. SOUTH ELEVATION 17. EAST ELEVATION

15. WEST ELEVATION

EXISTING VENT TO

REMAIN

R&D ABANDONED OIL

CONNECTION PIPING

REMOVE AND REINSTALL

UTILITY BOXES AS

NEEDED TO COMPLETE

WORK, TYPICAL

R&D MAILBOX

REMOVE AND REINSTALL UTILITY BOXES AS

NEEDED TO COMPLETE WORK, TYPICAL.

R&D LIGHT FIXTURES, TYP.

R&D WOOD TRIM AND

PANELS

R&D WOOD ALL WINDOW

TRIM. TYPICAL OF THREE (3)

LOCATIONS

R&D METAL AREAWAY

GRATE

R&D HOSEBIB IN

ITS ENTIREY R&D ABANDONED DRAIN PIPES IN

THEIR ENTIRETY, TYPICAL OF ALL

LOCATIONS, ALL SIDES

R&D PAINTED TRIM

BOARD. DECKING

TO REMAIN.

SCRAPE, PATCH, AND PREP

ALL TRIM FOR REPAINTING.

REMOVE AREAS OF ROTTED

TRIM AS NEEDED, TYPICAL OF

ALL PAINTED TRIM, ALL SIDES

REMOVE, PROTECT, AND

REINSTALL GUTTERS AND

DOWNSPOUTS REQUIRED FOR

TRIM REPLACEMENT/PAINTING

WORK, TYPICAL.

R&D ABANDONED CABELING

AND DISH

REMOVE AND REINSTALL

ELECTRICAL CONDUITS AS

NEEDED TO COMPLETE WORK.

REMOVE ALL ABANDONDED MEP

R&D WOOD TRIM AND

PANELS

R&D VINES GROWING

AGAINST THE BUILDING IN

THEIR ENTIRETY, TYPICAL OF

ALL LOCATIONS, ALL SIDES

R&D STAIR RAILINGS IN THEIR

ENTIRETY. SALVAGE ROUND

HANDRAIL FOR REINSTALLATION.

R&D SPLASH BLOCK,

TYPICAL

R&D TRIM

BOARD AT ALL

WINDOWS AND

DOORS, ALL

ELEVATIONS

R&D ALL

WINDOW SILLS,

TYPICAL OF ALL

WINDOWS ON

ALL ELEVATIONS

R&D TRIM BOARD

R&D TRIM IN ITS

ENTIRETY, TYPICAL ALL

WINDOWS AND DOORS

R&D WINDOW TRIM.

WINDOW TO REMAIN

EXISTING

WINDOWS AND

DOORS TO

REMAIN ELECTRICAL CONDUIT.

REMOVE AND REINSTALL AS

NEEDED TO COMPLETE WORK

REMOVE ABANDONED

OIL PIPING.

ELECTRICAL METER

TO REMAIN.

DEMOLITION NOTES

1. PROVIDE TEMPORARY SUPPORT DURING REMOVAL OF ANY AND ALL STRUCTURAL

ELEMENTS.

2. PROTECT ALL AREAS ADJACENT TO OR AFFECTED BY WORK DURING CONSTRUCTION.

PROVIDE DUST CONTAINMENT FOR ALL WORK AREAS.

3. CLEAN WORK AREA AND AREAS AFFECTED BY CUTTING AND PATCHING OPERATIONS.

4. PATCH WALLS & CEILING AT DEMO'D AREAS TO MATCH EXISTING ADJACENT SURFACES.

5. CAP ALL ABANDONED PLUMBING LINES AND ELECTRICAL OUTLETS.

6. ALL PORTIONS OF THE BUILDING TO BE REMOVED SHALL BE LEGALLY DISPOSED OF

OFF-SITE UNLESS DIRECTED OTHERWISE.

7. PRECAUTIONS AND TEMPORARY SHORING SHALL BE PLACED TO MAINTAIN THE

INTEGRITY OF THE EXISTING STRUCTURE THROUGHOUT DEMOLITION AND MASONRY

WORK.

8. CONTRACTOR IS RESPONSIBLE FOR CONTACTING DIG SAFE AND ANY OTHER

AUTHORITIES HAVING JURISDICTION PRIOR TO THE START OF DEMOLITION. COMPLY

WITH GOVERNING CODES AND REGULATIONS. CONTRACTOR IS RESPONSIBLE FOR

OBTAINING ALL NECESSARY PERMITS REQUIRED TO COMPLETE THE WORK.

9. PROVIDE WEATHER TIGHT TEMPORARY PROTECTION FOR ALL OPENINGS IN EXTERIOR

WALLS, ROOF, AND AT WINDOW AND DOOR HEADS.

10. SHOULD SUSPECTED HAZARDOUS MATERIALS BE ENCOUNTERED, CONTRACTOR

SHALL NOTIFY ARCHITECT AND OWNER IMMEDIATELY.

11. PROVIDE CUTTING AND PATCHING WORK TO PROPERLY COMPLETE THE WORK OF THE

PROJECT, COMPLYING WITH PROJECT REQUIREMENTS FOR: a.) STRUCTURAL WORK; b.)

MECHANICAL WORK; c.) VISUAL REQUIREMENTS, INCLUDING DETAILING AND

TOLERANCES.

12. DO NOT CUT AND PATCH IN A MANNER THAT WOULD RESULT IN A FAILURE OF THE

WORK TO PERFORM AS INTENDED, DECREASE ENERGY PERFORMANCE, INCREASE

MAINTENANCE, DECREASE OPERATION LIFE, OR DECREASE SAFETY PERFORMANCE.

13. MATCH EXISTING MATERIALS FOR CUTTING AND…