This Statement of Work (SOW) details the parking lot refurbishment project for the Federal Aviation Administration (FAA) Air Traffic Control Tower (ATCT) located in Savannah, Georgia. The project scope includes comprehensive site improvements such as pressure washing concrete hardscapes, cleaning and preparing asphalt surfaces, repairing cracks, applying two-coat seal coating, restriping parking lot markings, replacing two rubber speed bumps, replacing dumpster swing gates, repainting bollards, and installing a new larger scissor lift.
The project requires strict adherence to FAA Operational Risk Management, OSHA safety regulations, and technical specifications. Contractors must provide a detailed project schedule, maintain site accessibility, ensure minimal disruption to facility operations, and coordinate closely with local FAA personnel. The work must be completed with careful phasing, and the contractor will be responsible for a one-year warranty on materials and workmanship. Key requirements include submitting project schedules, work plans, safety data sheets, and coordinating all activities with the FAA facilities representative to ensure continuous operation of this mission-critical air traffic control facility.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FEDERAL AVIATION ADMINISTRATION
STATEMENT OF WORK
SAV ATCT – Parking Lot Refurbishment Project Savannah, GA June 12, 2025
1. GENERAL:
This statement of work sets forth the requirements for refurbishing parking lot and site at SAV ATCT located in Savannah, Georgia.
All work must be in accordance with the following:
a) FAA Operational Risk Management (ORMP) requirements
b) OSHA CFR 29 Part 1926 – Safety and Health Regulations for Construction
c) OSHA CFR 29 Part 1910 – General Industry Standards Applicable to Construction Industry
d) FAA EOSH, Safety Data Sheet Review and Approval
e) Electrical Safety, Lock-Out/Tag-Out procedures
f) Technical Specifications
2. BACKGROUND:
The SAV ATCT located in Savannah, Georgia is a mission critical facility supporting air traffic control operations. The existing parking lot has deteriorated beyond safe, acceptable standards due to prolonged seasonal weathering, exposure, erosion/consolidation, and continued traffic use and must be restored.
3. PRE-BID CONFERENCE:
A pre-bid conference may be set up for potential vendors to perform an initial site survey to observe onsite conditions and review project scope of work. If requested in advance, subsequent site visits may be further arranged to accomplish this critical task; however, additional pre-bid site visits are not guaranteed and dependent on local FAA personnel availability. Pre-Bid request for information (RFIs) may be submitted to the FAA to clarify project requirements.
4. GENERAL CONDITIONS:
a) Contractor must provide a project schedule outlining all phases and sub-phases of the work and impact on the facility. All work will need to be scheduled and performed to minimize the impact on the facility.
b) Contractor must provide a plan illustrating the phasing of work to ensure accessibility to facility and site is always maintained during the duration of work. The facility must remain in full operation during the entire duration of work. All work must be scheduled and phased to not obstruct facility personnel site access during project.
c) Contractor must maintain a clean site and remove temporary equipment if obstructing/disrupting operations. This includes immediate containment and/or removal of any debris that may become washed out, wind borne, or potential site hazard of any kind.
d) All debris and generated waste must be disposed in a manner that is not in conflict with local sanitary regulations. Disposal of any kind will not be permitted in the FAA trash containers.
e) Contractor must coordinate mobilization and staging procedures with the local FAA facilities personnel.
f) Construction staging, deliveries, storage, and handling of materials must be field coordinated with local facilities personnel.
g) Contractor must provide ample and suitable sanitary conveniences with proper enclosures and hand washing facilities in accordance with CFR Part 1926, Subpart D for the use of the workers employed on the work. Temporary toilets must be properly maintained and serviced on a regular basis. Secure temporary toilets to prevent possible overturning.
h) Contractor must provide Safey Data Sheets (SDS) for all materials to be reviewed and approved by FAA Environmental Safety Occupational Health personnel prior to activity start.
i) Coordinate working hours with the Contracting Officer and local FAA facilities representative. No work will be permitted on Federal Holidays.
5. SCOPE:
The contractor is responsible for accomplishing all items of work listed within the statement of work in accordance with applicable drawings and manufacturers’ technical specifications. The scope of work includes the following:
a) Pressure wash and clean existing concrete hardscapes including curbs, gutters, drainage flumes, splash pads, wheel stops, and sidewalks.
b) Clean and prepare parking lot asphalt surfaces for seal coat application per seal coat manufacturer’s written instructions. Surface preparation includes treating oil and grease spots with manufacturers recommend oil spot primer/sealer.
c) Repair, seal, and patch existing cracks and soft spots in asphalt parking surfaces per seal coat manufacturer’s written instructions. Existing cracks in asphalt parking must be repaired with products compatible with asphalt seal coating. Any patched areas must be fully cured prior to seal coat application.
d) Apply two (2) coat parking lot seal coat system per manufacturer’s written instructions and as indicated on plan:
a. First coat must include:
i. Clean, silica sand, 50/70 sieve (minimum 3-5 lbs. per 1 gallon of sealer).
ii. High potency, acrylic emulsion-based additive for fast drying, performance boosting, color enhancing and viscosity building (minimum 1%-2%, no more than 3%).
b. Apply second coat perpendicular direction of the first coat to ensure even coverage.
c. Allow the first coat to dry sufficiently to take light traffic without scuffing prior to second coat application. The seal coating system must be fully cured prior to allowing vehicle traffic on the finished surface and application of parking lot striping traffic paint.
e) Apply parking lot striping, fast drying 100% acrylic traffic paint at existing parking lot lines, stalls, markings, and stenciling (Handicap, Arrows, GOV, No Parking, Unloading) per manufacturer’s written instructions. Color, markings, and layout to match existing.
f) Apply parking lot striping, fast drying 100% acrylic traffic paint for two (2) new “No Parking” and hatching zones per manufacturer’s written instructions.
a. Match new hatching, stenciling, and layout to existing “No Parking” zone.
b. Location: See aerial view with approximate locations along existing curb at GOV parking and
Engine Generator Building. Coordinate exact location with onsite representative.
c. Color: White.
g) Replace two (2) existing rubber speed bumps and hardware at entrance and exit gates.
a. Remove two (2) existing rubber speed bumps and hardware at entrance and exit gates.
b. Provide and install two (2) new, heavy-duty/deluxe rubber, 72“x12”x3” (LxWxH), yellow/black, speed bumps at entrance and exit gates; one (1) speed bump per gate.
c. Provide and install new heavy-duty/deluxe rubber, 9”x12”x3” (LxWxH), black end caps on new speed bumps; two (2) end caps per new speed bump.
d. Fully adhere new speed bump/end caps using manufacturer compatible adhesive and secure with fourteen (14) inch galvanized steel, asphalt spikes per manufacturer's written instructions.
h) Prepare and paint existing bollards:
a. Clean and prepare bollard surface to be painted per manufacturer's written instructions.
b. Apply one (1) coat of primer and two (2) coats of paint on existing steel bollards per the following:
i. Type: Exterior, Compatible with existing bollard material
ii. Color: Match existing.
iii. Apply primer and top coatings per manufacturer’s written instructions.
i) Remove existing dumpster doors. Provide and install two (2) new dumpster swing gates, Ametco Manufacturing Corporation or approved equal, per the following and manufacturers’ written instructions:
a. Type: Steel fence swing gates, Ametco Manufacturing Corporation or equivalent
b. Style: Fixed louver with 80% direct visual screening
c. Hinge Type: Heavy Duty, steel hinge with stainless steel pin and chrome ball bearing.
d. Latch Type:
i. Provide and install two (2) pad lockable cane bolts (one (1) per gate) with 5/8” x 18” stainless steel cane bolt. Provide and install new embedment sleeves sized to accept new cane bolt.
ii. Provide and install a new swing gate, slide bolt latch.
iii. New latches must be compatible with new dumpster, swing gates and installed per manufacturer’s written instructions.
e. Color: Provide manufacturer’s standard color chart to onsite representative for selection.
j) Replace existing lift with new, larger unit – Presto ECOA DSL Series or approved equal. Coordinate final location of the lift with the onsite representative. Install new lift in existing concrete base/pit and ensure final installation is compliant with manufacturer’s written instructions, specifications, and warranty conditions.
a. Minimum Capacity: 2000lbs
b. Minimum Platform Size: 48”x72” or 84"
c. Base size: Size compatible with existing concrete pit dimensions.
d. Options:
i. Throw over plate, 18”x Platform Width
ii. Removable, 42” high steel guardrail with mid-rail and toe board.
iii. Retrofit package for operator protection, and an excess flow protector prevent sudden drop in event hydraulic line is damaged.
e. Motor: 3 HP
f. Provide manufacturer’s operation and maintenance manual
g. Provide end user training of new lift functionality and periodic maintenance.
h. Provide manufacturer’s warranty documentation.
k) Contractors must maintain a clean and organized site during construction. Upon passing the final Construction Acceptance Inspection (CAI), Contractor must clean up and demobilize without disruption.
l) The Contractor must warranty material and workmanship for a period of one (1) year and/or no less than the manufacturers’ materials warranty, starting from the date of final project acceptance by the
FAA.
6. CONSTRUCTION SCHEDULE:
The work plan and schedule prepared by the contractor must consist of a logical narrative plan. Include construction activities, submittal and approval of materials, samples, and shop drawings (if applicable), the procurement of critical materials and equipment, fabrication of special materials and equipment along with their installation and testing.
Within fifteen (15) calendar days of contract award, the contractor must submit the schedule and work plan.
Notice to Proceed (NTP) will not be issued until the schedule and phasing plan is approved.
FAA Maintenance Moratoriums:
A maintenance moratorium is imposed annually by Technical Operations during the following peak holiday travel periods:
1. Memorial Day
2. Independence Day
3. Labor Day
4. Thanksgiving
5. Christmas and New Year’s
Maintenance and hard moratorium dates and times may be provided upon request.
Local Moratorium Events – The dates, times, and affected facilities for local moratorium events are determined at the district level in consultation with local Air Traffic. Coordinate with FAA onsite representative for Local Moratorium events.
Moratorium Waivers – No work is permitted during maintenance moratoriums. Coordinate waiver requests with FAA onsite representative. Moratorium waivers must be submitted via the Maintenance Moratorium Waiver System (MMWS) and are not guaranteed. No moratorium waivers will be granted during hard moratorium dates and times.
7. SPECIAL PRECAUTIONS and SAFETY:
Project facilities are United States Government, Federal Aviation Administration (FAA) facilities used in Air Traffic Control. Loss of Human Life may result from service interruption. Any person who interferes with Air Traffic Control, damages, or trespasses on this property will be prosecuted under Federal law. All persons, vendors or suppliers requiring facility access must coordinate entry with the local facility personnel at least 24 hours in advance.
General Safety Provisions – Safe working conditions must be provided and maintained for all onsite personnel for the full duration of project. Work in surroundings or under working conditions that are unsanitary, hazardous, or dangerous to the health and safety of the employee must not be permitted.
Accident Prevention – An accident prevention program must be maintained onsite to ensure frequent and regular inspections of the job site, materials, and equipment are conducted by a designated competent person.
Competent Persons – Competent person training documentation must be provided where required by 29 CFR 1910 and 29 CFR 1926, such as fall protection and crane/rigging operations. Additional training records may be required on a case-by-case basis.
Use of Equipment – All machinery, tools, material, or equipment utilized must follow OSHA regulations. Only employees qualified by training and/or experience must be permitted to operate equipment and machinery.
Accident Reporting – All accidents must be reported immediately to the local FAA facilities personnel.
Accident and investigation reports are to be copied to the local FAA facilities personnel. within 48 hours.
Accident scenes must not be disturbed until a full and complete accident investigation has been undertaken with the local FAA facilities personnel and other required personnel.
The FAA will not be held responsible for safety inspections to ensure conformance with the OSHA safety regulations; however, the FAA reserves the right to notify the Contractor of any deficiencies regarding worker safety.
8. SUPPLIES AND EQUIPMENT
Shipping and Receiving of Materials – FAA will not be responsible for shipping or receiving any material relating to this project.
Protection of Materials – All materials and supplies to be incorporated into this project must be protected and maintained in like new condition.
Storage of Materials – Temporary storage units/containers for material associated with work may be located on site for the duration of the project. The size and location of storage must be coordinated with the local FAA facilities personnel.
9. FAA RESPONSIBILITIES:
The following FAA Responsibilities applicable to this Statement of Work include:
a) Access – FAA will provide escort services and onsite access to the subject facility.
b) Supervision – FAA will provide facilities representative oversight for onsite contracted activities.
c) Document Review – FAA will review submittals for contractor plans, schedule, product data sheets, safety data sheets for all products, equipment, and materials. FAA will provide contractor one set of review comments with the following stipulations:
Data marked “Approved as Noted” is satisfactory, contingent upon contractor acceptance of corrections and/or notations, and if accepted does not require re-submittal. Data marked “Not Approved” does not meet job requirements, and contractor must re-submit on proper basis.
10. SUBMITTALS:
The following initial deliverables must be submitted and approved prior to start of work:
Electronic .pdf copies of the project schedule.
Electronic .pdf copies of work phasing plan.
Electronic .pdf copies of the submittals including shop drawings, details, manufacturers’ product data sheets (PDS), and safety data sheets (SDS) for all proposed construction materials.
11. PROJECT LOCATION:
SAV ATCT
Address: Savannah Hilton Head International Airport, 100 Melaver Drive, Savannah, GA GPS Coordinates: 32.137576, -81.207760
12. CONTACTS:
The following is a list of primary contracts involved in the project: Please contact us if you have any additional questions or concerns.
FAA SAV SSC, LOCAL CONTACTS
Johnathan Timms, SSC Manager (904)-318-2362
FAA REGIONAL & DISTRICT OFFICE CONTACTS
Chad E. Heurter, JAX District NIM (A) (470) 352-0845 Tim O’Leary, DFM (803) 822-0847
13. ATTACHMENTS:
1. Site Photos
2. New “No Parking” Zones, Aerial View.
ATTACHMENT 1 – SITE PHOTOS
Photo 1: Existing scissor lift to be replaced.
Photo 2: Existing scissor lift to be replaced.
Photo 3: Existing scissor lift to be replaced.
Photo 4: Concrete to be pressure washed. (Typ.)
Photo 5: Concrete to be pressure washed. (Typ.)
Photo 6: Concrete to be pressure washed. (Typ.)
Photo 7: Concrete to be pressure washed. (Typ.)
Photo 8: Existing unloading zone stenciling. (Typ.)
Photo 9: Existing unloading zone stenciling. (Typ.)
Photo 10: Concrete hardscape to be pressure washed and bollards to be re-painted. (Typ.)
Photo 11: Existing dumpster swing gate to be replaced.
Photo 12: Existing dumpster swing gate to be replaced.
Photo 13: Existing GOV parking markings and stenciling.
Photo 14: Existing Handicap parking markings and stenciling.
Photo 15: Concrete to be pressure washed. (Typ.)
Photo 16: Approximate location of new “No Parking” zone.
Photo 17: Approximate location of new “No Parking”
Photo 18: Approximate location of new “No Parking”
Photo 19: Concrete to be pressure washed. (Typ.)
ATTACHEMENT 2 – NEW “NO PARKING” ZONES, AERIAL VIEW