This is Addendum #1 issued by Kenosha County, Wisconsin for Bid #2505 Additional Stand-alone Housing Kenosha Detention Center, with bids due Wednesday, February 26, 2025 at 3:00 PM Local Time at the County of Kenosha Purchasing Division. The addendum provides clarifications regarding electrical, plumbing, and structural requirements for the housing units. Key specifications include a 200 amp 120/240v 3 Phase electrical panel located on the south wall near the back door, with WE-Energies responsible for installing new electric service and meters while the electrical contractor must connect the panels to the meters. The general contractor must install 3" insulation around water pipes from 4 ft below grade level and install heat tape with a 20 amp dedicated circuit.
The addendum includes revisions to the foundation plan, adding four concrete piers under doors and anchor tie-downs rated for minimum ultimate loads of 4,725 lbs and working loads of 3,150 lbs installed to 4'-0" depth. Detailed specifications are provided for ramps and stairs construction using treated lumber, including 5/4" x 6" deck boards, 2x8 joists at 12" on center, 4x4 posts, and 8" diameter concrete post supports. The document includes a floor plan showing a two-bedroom layout with bathroom, kitchen/dining area, and mechanical room, along with foundation details showing pier locations and specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2505 Bid Documents.pdf | ||
| 2505 Drawings.pdf | ||
| 2505 Specifications.pdf | ||
| Vendor Responsibility Form Construction.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Additional Stand-alone Housing Kenosha Detention Center Bid #2505
ADDENDUM # 1
February 12, 2025
BIDS DUE: WEDNESDAY, February 26, 2025 at 3:00 Local Time at The County of Kenosha Purchasing Division located on 1010 56th Street, Second Floor Kenosha, WI 53140 at that time Bids will be opened publicly for consideration by the Owner.
To all Contract Bidders of record.
This Addendum is issued to modify, explain or correct the original Drawings and Specifications as noted below, and is hereby made a part of the Contract documents.
Please attach this Addendum to the Specifications in your possession. Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject Bidder to disqualification.
This Addendum consists of (2) written pages and (1) Attachment.
QUESTIONS AND ANSWERS
1. Is there an electrical panel in the new home or where is the panel?
a. The home comes with a 200 amp 120/240v 3 Phase panel which is located on the south wall near the back door.
2. Are electrical hook ups the Contractor’s responsibility? Is WE-Energies going to be involved?
a. Yes. A new 200 amp service will be required for each home. We-Energies will install a new electric service and meter and the electrical contractor will have to hook up the 200 amp panel that comes with each house to the electric meter.
3. Who will be responsible for insulating the water pipes?
a. GC will install a min of 3” insulation around the pipes from 4 ft below grade level up to point of connection. Also, for the main water supply line, a heat tape will be installed with a new 20 amp dedicated circuit.
-2-
REVISIONS TO THE DRAWINGS
SHEET A201 – FLOOR & FOUNDATION PLAN
1. DETAIL #2 – HOME FOUNDATION PLAN
a. See revised sheet for changes to the concrete piers. Four (4) piers were added under the doors. See reinforcing schedule added to this sheet.
b. See revised sheet for added anchor tie-downs. Tie-downs should be provided where shown or per the manufacturer’s instructions (whichever is greater). Anchors shall be tested and listed to resist a minimum ultimate load of 4,725 lbs. and a minimum working load of 3,150 lbs. Anchors shall be installed to a minimum depth of 4’-0” and protected against weather deterioration and corrosion. Additionally, provide an equivalent stabilizer plate for use with the tie-down anchor. Anchor depth shall be sized using a torque probe on site. For bidding purposes, assume the soil is clay, sandy clay, silty clay, clayey silt, silt and sandy silt with a vertical foundation pressure of 1,500 psf.
c. Home shall be strapped to the anchors per the manufacturer's instructions. Straps must be a minimum of 1¼” x 0.035” zinc-coated steel strapping conforming to ASTM D3953-97, Type 1, Grade 1, Finish B with a minimum allowable load capacity of 3,150 lbs. and a minimum ultimate load of 4,725 lbs.
2. RAMPS AND STAIRS
a. Framed ramps and stairs shall be constructed of treated lumber. The ramp shall have a slope of no greater than 1:12 with a flat section as shown on the plan.
b. Decking shall be 5/4” x 6” deck boards fastened with counter sunk exterior grade decking screws.
c. Joists shall be treated 2x8s @ 12” o.c. spanning 7’-6” maximum. Joists to bear on a double 2x8 beam, one on each side of the posts.
d. Posts shall be treated 4x4s fastened to each concrete post support with a galvanized post base. See revised foundation plan for approximate locations.
e. 8” diameter concrete post base supports to 3’-0” below grade shall be provided as shown on the revised foundation plan.
f. Ramps and stairs to have treated wood handrails and guard rails. Guard rails to have wood pickets spaced no greater than as will allow the passage of a 4” sphere.
685 690
WVE
E
E
A202
A202
A202 bedroom closet bathroom bedroom hall closet mech kitchen/drining
A201
52' - 0"
H1
H4
HA HB HC HD HE HF HG HH HJ
H2
H3
/4
/2
/4
35' - 3 7/8"
17' - 3 3/4" 3' - 6" 15' - 0"
/4
5' - 0"
1" / 1'-0" 1" / 1'-0" (max. slope)
(06 10 00) TREATED WOOD RAMP & RAILING
(06 10 00) TREATED WOOD
STAIRS & RAILING
(06 10 00) TREATED WOOD
DECKING
A201
5' - 0"
COMPACTED GRAVEL
(06 10 00) TREATED WOOD
STAIRS & RAILING
CONNECT ELECTRICAL SERVICE TO
EXISTING 200 AMP 120/240V 3PH PANEL
A202
A202
A202
A202
A201
H1
H4
HA HB HC HD HE HF HG HH HJ
H2
H3
/4
/2
/4
2' - 0" 8' - 0" 8' - 0" 8' - 0" 8' - 0" 8' - 0" 8' - 0" 2' - 0"
52' - 0"
A201
(03 30 00) SONOTUBE PIERS PER SCHEDULE
PRIMARY PIERS UNDER MAIN BEAMS
TOP OF ALL PIERS @ 867.33
3' - 0" 8' - 2"
15' - 10" 3' - 0"
(03 30 00) ADDITIONAL PIERS @ DOORS
VERIFY LOCATION WITH MANUFACTURER
(06 10 00) SIDE WALL GROUND ANCHORS
PER MANUFACTURER'S INSTRUCTIONS
(06 10 00) END WALL GROUND ANCHORS
PER MANUFACTURER'S INSTRUCTIONS
(03 30 00) 8" DIA. CONCRETE POST
SUPPORT TO 3'-0" BELOW GRADE
TYPICAL AT FRAMED STAIR / RAMP
(03 30 00) 8" DIA. CONCRETE POST
SUPPORT TO 3'-0" BELOW GRADE
TYPICAL AT FRAMED STAIR / RAMP
P-2 P-2
P-2P-2
P-2
P-2 P-2
P-2
P-1 P-1
P-2
P-2 P-2
P-2
P-2
P-2
P-1 P-1
H1 H4H2 H3
F .V
13' - 4"
(03 30 00) SONOTUBE PIERS PER PLAN
REINFORCING PER SCHEDULE.
F
IE
L D
V E
R
IF
Y
A201
A201
LVL = 686
LVL = 688.67
LVL = 682
TOP OF PIERS AT
867.33 (TYP.)
H4
(06 10 00) 2x4 @ 16" O.C.
(06 10 00) 1/2" TREATED
PLYWOOD WITH TYVEK
BUILDING WRAPPING PAPER
CEMENT BOARD SIDING BY GC.
(06 10 00) TIES @ 48" OC.
F
IE
L D
V E
R
IF
Y
/4
P R
E -M
A N
U F
A C
T U
R E
D H
O M
E P
E R
S P
E C
S
6" COMPACTED GRAVEL
CEMENT BOARD SIDING
BY C.G.
(06 10 00) COMPLETE SKIRT TO
BE INSTALLED AROUND HOME.
LVL = 686
LVL = 688.67
PROPOSED MODULAR UNITS
#1 #2
BASE BID
(2) MAYNARD HOMES (2-BED ROOM) BY
CHAMPION (06 10 00)
ALTERNATE
(1) MAYNARD (2-BED ROOM) AND (1) THRIFTY
(1-BED ROOM) BY CHAMPION (06 10 00)
686.00
685.56685.71 MATCH EXISTING GRADE
GRAVEL = 686
HOME LVL = 688.67
kuenyarch.com ©2025 Kueny Architects L.L.C. - All Rights Reserved
PLAN NORTH
SCALE: As indicated
A201Kenosha County - KCDC - Additional Stand-Alone Housing Kenosha Detention Center - Bid # 2505
01.23.2025
Floor & Foundation Plan
4777 88th Ave, Kenosha, WI 53144
1/4" = 1'-0"1 Enlarged Floor Plan
6 New Modular Home - 3D View
1/4" = 1'-0"2 Home - Foundation Plan
1/4" = 1'-0"3 Typ. Section - NS 3/4" = 1'-0"4 Typ. Skirting Detail
1" = 20'-0"5 Exit Route
Addendum #1 February 10, 2025
PIER SCHEDULE
MARK DIAMETER REINFORCING
P-1 12" (3) #4 VERT. BARS & #3 TIES @ 12" O.C.
P-2 36" (12) #6 VERT. BARS & #3 TIES @ 10" O.C.
| 2505 Addendum #1 Drawings.pdf |
| Sheets |
| A201 - Floor & Foundation Plan |