About this file
This is an Addendum No. 1 issued by the Athens-Clarke County Public Utilities Department on June 17, 2025, for the J.G. Beacham Water Treatment Plant Sodium Hypo Tank Rehabilitation project. The addendum clarifies contract requirements and modifies specifications for interested bidders. Proposals must be received by 3:00 p.m. local time on July 10, 2025. All bidders are required to acknowledge receipt of this addendum and any other addenda as part of their bid submission; failure to do so may result in bid rejection.
The addendum removes the requirement for a Georgia Utility Contractor License, which was previously specified as mandatory for the project. Additionally, Section 00425 is removed from the contract documents, and Section 00100 Paragraph 3.07.E.4 is removed from the specifications. These changes clarify that the FRP (Fiberglass Reinforced Plastic) industry-related license requirement is no longer applicable to this project, addressing a significant barrier to entry for qualified contractors unfamiliar with this specific Georgia licensing requirement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 25044 BID JG Beacham WTP Sodium Hypo Tank Reh.pdf | ||
| J_G_ Beacham WTP Sodium Hypo Tank Rehab Bid A.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO. 1
ISSUE DATE: June 17, 2025
For
J.G. Beacham WTP Sodium Hypo Tank Rehab
Athens-Clarke County Public Utilities Department
Proposals to be received until 3:00 p.m., local time, July 10, 2025
Receipt of this addendum, and all other addenda, should be acknowledged as part of your
Bid. Failure to acknowledge receipt of the addenda may result in rejection of the Bid. This addendum forms a part of the Contract Documents
Please note the following CHANGES/CLARIFICATIONS to the above referenced
Contract Documents as follows:
QUESTIONS AND CLARIFICATIONS
1. Question: We don't have a Georgia Utility Contactor License. I wasn't even aware such existed that was applicable to the FRP industry. Can it be waived?
Answer: The requirement for a Georgia Utility Contractor License is removed from the project.
SPECIFICATIONS
1. REMOVE Section 00425 from Contract Documents.
2. REMOVE Section 00100 Paragraph 3.07.E.4
End Addendum No. 1