About this file

This is an Addendum No. 1 issued by Engineering Resource Group, Inc. for the University of Southern Mississippi's Hillcrest Chilled Water Upgrades project in Hattiesburg, Mississippi. The addendum modifies the original bidding documents and clarifies project requirements for sealed proposals due October 22, 2026 at 10:00 a.m. at the Physical Plant Department Conference Room in Hattiesburg. The pre-bid conference date has been changed to Wednesday, October 7th, 2026 at 9:30 a.m. The scope of work encompasses furnishing all labor, materials, and equipment necessary for the chiller plant upgrade as detailed in drawings and specifications prepared by Engineering Resource Group, Inc., dated September 16, 2026. A single contract will be awarded for the complete project.

Plans and specifications are available for purchase at $150.00 per set (non-refundable). Bid responses must be submitted in duplicate on provided blank bid forms and accompanied by bid security equal to at least 5% of the base bid in the form of a certified check or acceptable bid bond. Bid security is payable unconditionally to the University of Southern Mississippi and will be forfeited as liquidated damages should an awarded bidder fail to execute the contract or post required performance and payment bonds. No bid may be withdrawn for 45 days after the scheduled closing time. All bidders must comply with Mississippi Code requirements, including Chapter 3, Title 31, and any awarded contract must be bonded in accordance with Chapter 5, Title 31. Non-resident bidders must comply with Section 31-3-21(3) of the Mississippi Code of 1972. Electronic bid submission is available through the Mississippi Department of Finance and Administration portal.

View the file

Other files

File Type Posted
download.pdf PDF
LEGAL AD - HILLCREST CHILLER PLANT UPGRADE.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ENGINEERING RESOURCE GROUP 250 Katherine Drive ▪ Flowood, MS 39232 ▪ (601) 362-3552 2030 Pass Road, Suite A ▪ Biloxi, MS 39531 ▪ (228) 388-8740

September 29, 2026

ADDENDUM NO. ONE (1)

USM HILLCREST CHILLED WATER UPGRADES

HATTIESBURG, MS

ERG P.N. 25.139

I. Bidder acknowledges that it is Bidder’s responsibility to ascertain whether any Addenda have been issued and if so, to obtain copies of such Addenda. Bidder therefore agrees to be bound by all Addenda that have been issued for this Bid.

This Addendum forms a part of the Contract Documents and modifies the original Bidding Documents and consists of 1 page (plus attachments). The following clarifications, changes, additions, or deletions shall be made to the following documents as indicated, and all other conditions shall remain the same.

II. PERTAINING TO THE SPECIFICATIONS

A. Section - Advertisement for Bids – Pre-bid Conference date changed to Wednesday, October 7th 2026, at 9:30 am.

If there are any questions, please contact Engineering Resource Group, Inc.

Phone: (601) 362-3552 Fax: (601) 366-6418 e-mail: knelson@ergms.com

END OF ADDENDUM NO. 1