This is a Bid Schedule for Collier County, Florida's Stan Gober Memorial Bridge Rehabilitation Project (ITB 25-8367), a comprehensive infrastructure restoration initiative for Bridge No. 030184 over Marco Channel. The project encompasses extensive bridge rehabilitation work including concrete repairs, cathodic protection systems, structural beam treatments, deck restoration, and scour protection measures. Key line items include removal of existing concrete (2,137 square yards), installation of cathodic protection systems via zinc arc spray (4,802 square feet), concrete class IV topping with shrinkage-reducing admixture (89.1 cubic yards), bridge deck grooving (2,137 square yards), cleaning and sealing of concrete surfaces (81,048 square feet), riprap-rubble for bank and shore stabilization (5,872 tons), bedding stone (1,961 tons), bridge deck expansion joint rehabilitation with poured joints (1,064 linear feet), and various structural treatments including galvanic anodes and integral column and pile jackets. A non-mandatory pre-bid meeting is scheduled for April 22, 2025, at 10:00 a.m. at the Collier County Procurement Services Conference Room, with sealed bids due electronically by May 23, 2025, at 3:00 p.m. local time. The contract requires substantial completion within 365 calendar days from the Notice to Proceed and final completion within 30 calendar days after Punch List delivery.
The total project budget is estimated at $9,924,556.00, with an additional owner's allowance of $900,000 for unforeseen conditions or owner-directed work that will be expended through Change Order with proper Time and Materials documentation. The bid schedule presents all line items with unit prices and total amounts to be completed by bidders; the inclusion of the owner's allowance is not a guarantee of payment and represents a contingency reserve only. Bidders must possess an FDOT-qualified Bridge Contractor designation and a valid State of Florida General Contractor license. Liquidated damages are assessed at $1,281.00 per calendar day for failure to achieve Substantial Completion, and the contract will be awarded to the lowest responsive and responsible bidder. Work is restricted to hours between 7:00 a.m. and 7:00 p.m., Monday through Friday. The project involves work within the Rookery Bay National Estuarine Research Reserve with environmental considerations including turbidity monitoring and marine habitat protection as authorized by Department of the Army Permit.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Stan Gober Memorial Bridge Rehabilitation | |||||
| Construction ITB 25-8367 | |||||
| Bid Schedule | |||||
| Item No. | DESCRIPTION | UNIT | QTY | Unit Price | TOTAL AMOUNT |
| 101-1 | MOBILIZATION | LS | 1 | $ - 0 | $ - 0 |
| 102-1 | MAINTENANCE OF TRAFFIC | LS | 1 | $ - 0 | $ - 0 |
| 104-11 | FLOATING TURBIDITY BARRIER | LF | 3,150 | $ - 0 | $ - 0 |
| 104-30 | TURBIDITY MONITORING | LS | 1 | $ - 0 | $ - 0 |
| 110-3-10 | LADDERS AND PLATFORMS, REMOVE | EA | 2 | $ - 0 | $ - 0 |
| 110-4-10 | REMOVAL OF EXIST CONC | SY | 2,137 | $ - 0 | $ - 0 |
| 400-4-47 | CONCRETE CLASS IV, CAST IN PLACE TOPPING WITH SRA | CY | 89.1 | $ - 0 | $ - 0 |
| 400-7-1 | BRIDGE DECK GROOVING | SY | 2,137 | $ - 0 | $ - 0 |
| 400-142-2 | CATHODIC PROTECTION SYSTEM, ZINC ARC SPRAY | SF | 4,802 | $ - 0 | $ - 0 |
| 400-142-10 | EMBEDDED GALVANIC ANODE | EA | 6 | $ - 0 | $ - 0 |
| 400-142-11 | GALVANIC OVERBUILD WITH ANODES FOR FOOTINGS/STRUTS | SF | 13,854 | $ - 0 | $ - 0 |
| 401-70-5 | RESTORE SPALLED AREAS, CONTRACTOR'S OPTION | CF | 79 | $ - 0 | $ - 0 |
| 413-150 | PENETRATING CORROSION INHIBITOR | GA | 933 | $ - 0 | $ - 0 |
| 413-154 | CLEANING AND SEALING CONCRETE SURFACES - PENETRANT SEALER OR METHACRYLATES | SF | 81,048 | $ - 0 | $ - 0 |
| 457-2-131 | CATHODIC PROTECTION INTEGRAL COLUMN JACKET, NON-STRUCUTRAL, GALVANIC SYSTEM | LF | 108 | $ - 0 | $ - 0 |
| 457-2-221 | CATHODIC PROTECTION INTEGRAL PILE JACKET, STRUCTURAL, 16.1-30" GALVANIC SYSTEM | LF | 8 | $ - 0 | $ - 0 |
| 458-1-21 | BRIDGE DECK EXPANSION JNT, REHAB, POURED JOINT WITH BACKER ROD | LF | 1,064 | $ - 0 | $ - 0 |
| 470-75-2 | TIMBER FENDER SYSTEM REPAIR | LS | 1 | $ - 0 | $ - 0 |
| 530-3-3 | RIPRAP-RUBBLE, BANK AND SHORE | TN | 5,872 | $ - 0 | $ - 0 |
| 530-74 | BEDDING STONE | TN | 1,961 | $ - 0 | $ - 0 |
| 561-1-1 | COATING EXISTING STRUCTURAL STEEL, BEARING | EA | 4 | $ - 0 | $ - 0 |
| 630-2-30 | CONDUIT ANCHOR REPLACE | EA | 1 | $ - 0 | $ - 0 |
| 630-2-31 | CONDUIT REPAIR/REPLACE | LF | 100 | $ - 0 | $ - 0 |
| 706-1-3 | RAISED PAVEMENT MARKER, TYPE B | EA | 44 | $ - 0 | $ - 0 |
| 711-16-101 | THERMOPLASTIC, STANDARD-OTHER SURFACES, WHITE, SOLID, 6" | GM | 0.04 | $ - 0 | $ - 0 |
| 711-16-201 | THERMOPLASTIC, STANDARD-OTHER SURFACES, YELLOW, SOLID, 6" | GM | 0.04 | $ - 0 | $ - 0 |
| 713-103-101 | PERMANENT TAPE, WHITE, SOLID, 6" FOR CONCRETE BRIDGES | GM | 0.44 | $ - 0 | $ - 0 |
| 713-103-201 | PERMANENT TAPE, YELLOW, SOLID, 6" FOR CONCRETE BRIDGES | GM | 0.54 | $ - 0 | $ - 0 |
| TOTAL BID AMOUNT | $ - 0 |
* Staff has allocated $900,000.00 in Owner's Allowance - for Owners Use as Directed. This Allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of Owners Allowance will be made through Change Order with proper documentation of Time and Materials supporting the change.