25-0431 AS4300 G575 INSTALL GENERATOR ATS - SOW.pdf
PDF 3 MB Posted
- Attached to
- Install Generator and ATS G575 and AS4300
- Solicitation number
- N4008526R9001
About this file
This is an electrical installation design document for a generator and automatic transfer switch (ATS) project at MCB Camp Lejeune, North Carolina, project number 25-0431. The project involves installing new generators at two locations: Building G575 (Camp Geiger Waste Water Pump Station) and AS4300 (NRAS Douglas Gate Entry). Key details include removing existing electrical infrastructure and installing new 200KW (G575) and 25KW (AS4300) diesel generators with subbase fuel tanks, new automatic transfer switches, concrete equipment pads, gravel drives, and associated electrical conduits and wiring. The design specifications cover detailed requirements for generator placement, grounding, electrical connections, and site preparation, with specific notes on excavation, concrete pad construction, and compliance with electrical codes and local regulations. The project involves government-furnished generators to be installed by the contractor, with precise technical specifications for electrical connections, pad construction, and system integration.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VICINITY MAP G575
AREA MAP G575
LOCATION MAP G575
MCB CAMP LEJEUNE, NORTH CAROLINA
25-0431 INSTALL GENERATOR & ATS
25-0431 T1
BLDG
G575
SHEET # SHEET NAME
T2 G1 E1 E2
TITLE SHEET/AREA MAPS BLDG AS4300
GENERAL NOTES
ELECTRICAL PLANS/OVERVIEW BLDG G575
ELECTRICAL PLANS/DETAILS BLDG G575
DRAWING INDEX
T1 TITLE SHEET/AREA MAPS BLDG G575
E3 E4
PROPOSED WORK AREA AS4300
ELECTRICAL PLANS/OVERVIEW BLDG AS4300
E5 ELECTRICAL PLANS/DETAILS BLDG AS4300
VICINITY MAP AS4300 AREA MAP AS4300
LOCATION MAP AS4300
MCB CAMP LEJEUNE, NORTH CAROLINA
25-0431 INSTALL GENERATOR & ATS
25-0431 T2
BLDG
AS4300
1. ALL ELECTRICAL WORK SHALL BE IN FULL COMPLIANCE WITH NFPA 70, THE NORTH CAROLINA STATE BUILDING CODE, ALL LOCAL CODES AND ORDINANCES AND IN ACCORDANCE WITH THE REQUIREMENTS OF THE LOCAL AUTHORITY HAVING
JURISDICTION.
2. ALL EQUIPMENT PROVIDED BY THE CONTRACTOR SHALL BE LISTED AND LABELED BY A NATIONALLY-RECOGNIZED TESTING AGENCY, ACCEPTABLE TO THE AUTHORITY HAVING JURISDICTION, FOR THE CONDITIONS OF INSTALLATION. ALL MATERIAL, EQUIPMENT AND DEVICES SHALL BE NEW CURRENT PRODUCTS OF MANUFACTURERS REGULARLY ENGAGED IN THE PRODUCTION OF SUCH PRODUCTS. EQUIPMENT SHALL BE SUITABLE FOR ITS APPLICATION (E.G. WHEN INSTALLED OUTDOORS, IT
SHALL BE WEATHERPROOF, ETC.)
3. THE CONTRACTOR SHALL REVIEW ALL DRAWINGS AND SPECIFICATIONS FOR WORK REQUIREMENTS, THE AMOUNT OF SPACE AVAILABLE FOR ELECTRICAL EQUIPMENT, AND LAYOUT HIS WORK IN A COMPATIBLE AND COMPLEMENTARY MANNER.
4. THE CONTRACTOR SHALL ALSO BE RESPONSIBLE FOR THOROUGHLY FAMILIARIZING HIMSELF WITH ANY CONTRACTUAL REQUIREMENTS AS MAY BE SET FORTH IN THE OTHER DIVISIONS OF THE PROJECT SPECIFICATIONS.
5. UNLESS SPECIFICALLY NOTED OTHERWISE, SYSTEMS PROVIDED OR INSTALLED BY THE CONTRACTOR SHALL BE COMPLETE AND FULLY-FUNCTIONING AFTER INSTALLATION. INCIDENTAL COMPONENTS MAY NOT BE SHOWN, AND ALL WORK WHICH MAY BE REASONABLY IMPLIED AS BEING INCIDENTAL TO THIS WORK, BUT REQUIRED FOR THE PROPER OPERATION OF THE EQUIPMENT OR SYSTEM, SHALL BE PROVIDED BY THE CONTRACTOR AND INCLUDED IN THE BID. ADDITIONAL CIRCUITS SHALL BE INSTALLED
WHEREVER NEEDED TO CONFORM TO THE SPECIFIC REQUIREMENTS OF EQUIPMENT.
6. THE WORK SHALL INCLUDE COMPLETE TESTING OF ALL EQUIPMENT AND WIRING AT THE COMPLETION OF WORK AND ANY MINOR CORRECTIONS, CHANGES OR ADJUSTMENTS NECESSARY FOR THE PROPER FUNCTIONING OF THE SYSTEM AND
EQUIPMENT.
7. ALL ELECTRICAL EQUIPMENT SHALL, AT ALL TIMES DURING CONSTRUCTION, BE ADEQUATELY PROTECTED AGAINST MECHANICAL INJURY, OR DAMAGE BY WATER AND/OR THE ELEMENTS. ELECTRICAL EQUIPMENT SHALL NOT BE STORED OUT OF DOORS, BUT SHALL BE STORED IN DRY PERMANENT SHELTERS. IF AN APPARATUS HAS BEEN DAMAGED, OR HAS BEEN SUBJECT TO POSSIBLE INJURY BY WATER OR THE ELEMENTS, SUCH DAMAGE SHALL BE REPLACED AT NO ADDITIONAL COST.
8. DO NOT SCALE ELECTRICAL DRAWINGS. FIELD VERIFY ALL DIMENSIONS.
9. CIRCUIT LAYOUTS ARE NOT INTENDED TO SHOW THE NUMBER OF FITTINGS, OR OTHER INSTALLATION DETAILS. UNLESS NOTED OTHERWISE, THE EXACT ROUTING OF FEEDER AND BRANCH CIRCUIT RACEWAYS AND CABLES IS THE RESPONSIBILITY OF THE CONTRACTOR. RISER AND GENERAL CIRCUIT ARRANGEMENTS ARE SHOWN SCHEMATICALLY/DIAGRAMMATICALLY ONLY.
THE CONTRACTOR SHALL ROUTE CONDUITS AS REQUIRED BY THE CONDITIONS OF THE INSTALLATION.
10. UNLESS DIMENSIONED, DEVICE LOCATIONS SHOWN ON THE DRAWINGS ARE APPROXIMATE. ADJUST EXACT LOCATIONS AS REQUIRED TO SERVE THE INTENDED PURPOSE. IF NOT DIMENSIONED ON THE ELECTRICAL DRAWINGS, VERIFY EXACT LOCATION
WITH THE CONTRACTING OFFICER PRIOR TO ROUGH-IN.
11. SEAL ALL CONDUIT OPENINGS THROUGH EXTERIOR BUILDING WALLS WATERTIGHT.
12. ALL MOTORS AND OTHER VIBRATING EQUIPMENT SHALL BE CONNECTED TO THE CONDUIT SYSTEM BY MEANS OF A SHORT SECTION (18 INCH MINIMUM) OF FLEXIBLE CONDUIT UNLESS OTHERWISE INDICATED. AN EQUIPMENT GROUNDING CONDUCTOR SHALL BE INSTALLED INSIDE THE FLEXIBLE CONDUIT AND TERMINATE AT THE LOAD END WITH AN APPROVED
GROUNDING CLAMP OR LUG.
13. PRIOR TO TRENCHING IN ANY AREA, THE CONTRACTOR SHALL CONTACT ELECTRICAL, COMMUNICATIONS/DATA/FIBER, CABLE TELEVISION, GAS AND WATER UTILITY PROVIDERS AND HAVE ALL UTILITIES IN THE AREA IDENTIFIED. DAMAGE TO ANY UNDERGROUND UTILITIES OR STRUCTURES SHALL BE REPAIRED BY THE CONTRACTOR AT NO ADDITIONAL COST TO THE PROJECT.
14. ALL UNDERGROUND RACEWAYS SHALL BE IDENTIFIED BY UNDERGROUND LINE MARKING TAPE LOCATED DIRECTLY ABOVE
THE RACEWAY AT 6 TO 8 INCHES BELOW FINISHED GRADE.
15. INSTALLATION INFORMATION PACKED WITH DEVICES AND EQUIPMENT SHALL BE RETAINED FOR INCLUSION IN THE
OPERATIONS AND MAINTENANCE MANUALS.
16. EXISTING CIRCUITING WHERE SHOWN IS FOR CONVENIENCE PURPOSES ONLY. VERIFICATION OF EXISTING WIRING DESTINATION, TERMINATION AND ADDITIONS OF NEW LOADS IS THE RESPONSIBILITY OF THE CONTRACTOR.
17. THE CONTRACTOR SHALL VISIT THE SITE AND BECOME FAMILIAR WITH THE EXISTING ELECTRICAL SYSTEMS AND THE EXISTING BUILDING. THE SUBMISSION OF THE PROPOSAL BY THE CONTRACTOR SHALL BE CONSIDERED EVIDENCE THAT THEY OR THEIR REPRESENTATIVE HAS VISITED THE SITE AND BUILDINGS AND NOTED THE LOCATION AND CONDITIONS UNDER WHICH THE WORK WILL BE PERFORMED AND THAT THEY TAKES FULL RESPONSIBILITY OF ALL FACTORS GOVERNING THEIR WORK. NO EXTRAS WILL BE CONSIDERED BECAUSE OF ADDITIONAL WORK NECESSITATED BY EXISTING JOB CONDITIONS THAT ARE NOT
INDICATED ON THE DRAWINGS.
GENERAL ELECTRICAL NOTES
25-0431 G1
ENVIRONMENTAL REQUIREMENTS G575
1. IF CONTAMINANTS ARE SUSPECTED THROUGH ODORS OR VISUAL OBSERVATION DURING CONSTRUCTION ACTIVITIES, IMMEDIATELY STOP WORK, CALL 911, AND CONTACT EQB AT 910-451-9641 FOR FURTHER INSTRUCTIONS.
2. THERE ARE NO KNOWN MONITORING WELLS IN THE PROJECT AREAS BUT IF AN UNMARKED WELL IS DISCOVERED AND INADVERTENTLY DAMAGED, IMMEDIATELY CONTACT EQB AT 910-451-9641 FOR FURTHER INSTRUCTIONS.
3. THE PROPOSED PROJECT AREA IS WITHIN PREVIOUSLY INVESTIGATED HISTORIC SURFACE DANGER ZONES (UXO-24)THAT HAS LAND USE CONTROLS IN PLACE. SOIL TAKEN OFF BASE FROM THIS SITE MAY NEED TO BE SCREENED FOR UXO, PLEASE COORDINATE WITH THE IR PM. 3R UXO SAFETY AWARENESS TRAINING IS REQUIRED FOR ALL CONSTRUCTION PERSONNEL. 3R SAFETY AWARENESS TRAINING IS AVAILABLE ONLINE AT THE FOLLOWING LINK: HTTP://WWW.LEJEUNE.MARINES.MIL/OFFICES- STAFF/ENVIRONMENTAL-MGMT/TRAINING-VIDEO/. SHOULD A MUNITIONS-RELATED ITEM BE FOUND DURING CONSTRUCTION, FOLLOW APPROPRIATE NOTIFICATIONS AS DETAILED IN THE 3R TRAINING. ANY MUNITIONS RELATED ITEM FOUND DURING PROJECT CONSTRUCTION SHOULD ADDITIONALLY BE REPORTED TO EMD WITHIN 10 DAYS (THOMAS RICHARD, 910-451-9641) TO DETERMINE IF ADDITIONAL EVALUATION AND PRECAUTIONS ARE NECESSARY (EXPLOSIVES SAFETY SUBMISSION, UXO TECH SUPPORT, ETC). ADDITIONAL UXO SAFETY RESOURCES AVAILABLE AT: CONSTRUCTION -DENIX (OSD.MIL) HTTPS:// WWW.DENIX.OSD.MIL/UXO/FOR-WORKCREWS/CONSTRUCTION/INDEX.HTML. IN ADDITION, NOTIFICATION TO THE STATE AND U.S. EPA IS REQUIRED A MINIMUM 60 DAYS PRIOR TO START OF CONSTRUCTION TO ENSURE COMPLIANCE WITH EXISTING LAND USE RESTRICTIONS. THE NOTIFICATION SHALL BE DONE BY THE INSTALLATION'S ENVIRONMENTAL MANAGEMENT DIVISION AND COORDINATED VIA THE CONSTRUCTION CONTRACTOR. IF GEOTECHNICAL BORINGS FOR NECESSARY FOR DESIGN, YOU WILL NEED TO COORDINATE NOTIFICATIONS WITH THE INSTALLATION RESTORATION PROGRAM. A MAP OF PROPOSED BORING LOCATIONS WILL BE REQUIRED. NOTIFICATIONS WILL NEED TO BE COORDINATED 60+ DAYS AHEAD OF CONSTRUCTION AND
SEPARATE FROM THE CONSTRUCTION NOTIFICATIONS.
4. THIS PROJECT IS WITHIN THE AQUIFER USE CONTROL BOUNDARY ASSOCIATED WITH IR SITE 35, OPERABLE UNIT (OU) 10. ALL WORK CONDUCTED IN AN IDENTIFIED EPA NPL OU OR RCRA SWMU MUST ADHERE TO THE PROVISIONS DETAILED IN 29 CFR
1910.120 OCCUPATIONAL SAFETY AND HEALTH STANDARDS, HAZARDOUS MATERIALS, HAZARDOUS WASTE OPERATIONS AND
EMERGENCY RESPONSE.
5. IF DRILLING FLUIDS OR OTHER SUBSTANCES/COMPOUNDS/PRODUCTS ARE INJECTED INTO THE GROUND SURFACE, SAFETY DATA SHEETS MUST BE SENT TO EQB FOR REVIEW AND SCREENING OF POTENTIAL CONTAMINANTS.
6. THE PROPOSED ACTION INVOLVES CONSTRUCTION WITHIN SITE UXO-24,WHICH WAS IDENTIFIED AS A RADIOLOGICAL AREA OF INTEREST DUE TO HISTORIC OPERATIONAL USE AND PROXIMITY TO A FORMER DUMP SITE. IT IS RECOMMENDED THAT IF ANY RADIOLOGICAL WASTE DEBRIS IS ENCOUNTERED DURING CONSTRUCTION ACTIVITIES, IMMEDIATELY STOP WORK, CALL
911. EXAMPLES OF RADIOLOGICAL ITEMS OF CONCERN ARE OLD MILITARY EQUIPMENT WITH DIALS OR GAUGES. IF ANOMALIES CANNOT BE AVOIDED, FURTHER INPUT FROM RASO IS REQUIRED FOR WORK TO CONTINUE. CONTACT: IR PROGRAM, 910-451- 9641/9610.
ENVIRONMENTAL REQUIREMENTS AS4300
1. IF CONTAMINANTS ARE SUSPECTED THROUGH ODORS OR VISUAL OBSERVATION DURING CONSTRUCTION ACTIVITIES, IMMEDIATELY STOP WORK, CALL 911, AND CONTACT EQB AT 910-451-9641 FOR FURTHER INSTRUCTIONS.
2. THERE ARE NO KNOWN MONITORING WELLS IN THE PROJECT AREAS BUT IF AN UNMARKED WELL IS DISCOVERED AND INADVERTENTLY DAMAGED, IMMEDIATELY CONTACT EQB AT 910-451-9641 FOR FURTHER INSTRUCTIONS.
3. 3R UXO SAFETY AWARENESS TRAINING IS RECOMMENDED FOR ALL CONSTRUCTION WORKERS AS A PRECAUTION GIVEN THAT CAMP LEJEUNE HAS BEEN AN ACTIVE MILITARY BASE SINCE THE 1940S. 3R SAFETY AWARENESS TRAINING IS AVAILABLE ONLINE AT THE FOLLOWING LINK: HTTP://WWW.LEJEUNE.MARINES.MIL/OFFICES-STAFF/ENVIRONMENTAL-MGMT/TRAINING-VIDEO/.
SHOULD A MUNITIONS-RELATED ITEM BE FOUND DURING CONSTRUCTION, FOLLOW APPROPRIATE NOTIFICATIONS AS DETAILED IN THE 3R TRAINING. ANY MUNITIONS RELATED ITEM FOUND DURING PROJECT CONSTRUCTION SHOULD ADDITIONALLY BE REPORTED TO EMD WITHIN 10 DAYS (T.RICHARD, 910-451-9641) TO DETERMINE IF ADDITIONAL EVALUATION AND PRECAUTIONS ARE NECESSARY (EXPLOSIVES SAFETY SUBMISSION, UXO TECH SUPPORT, ETC). ADDITIONAL UXO SAFETY RESOURCES AVAILABLE AT: CONSTRUCTION - DENIX (OSD.MIL) HTTPS://WWW.DENIX.OSD.MIL/UXO/FOR-WORK-CREWS/
CONSTRUCTION/INDEX.HTML
4. IF DRILLING FLUIDS OR OTHER SUBSTANCES/COMPOUNDS/PRODUCTS ARE INJECTED INTO THE GROUND SURFACE, SAFETY DATA SHEETS MUST BE SENT TO EQB FOR REVIEW AND SCREENING OF POTENTIAL CONTAMINANTS.
U P
ATS
MAIN
MCC
UPS
CONT
CAB
G
EN
ER
AT
O R
FUEL
TANK
TRANSFORMER
22FT
11FT 6IN
57IN
57IN
24IN
12IN
SITE FENCING SITE FENCING SITE FENCINGSITE FENCING
SITE FEN
CIN
G
SITE FEN
CIN
G
25-0431 E1
EQUIPMENT LAYOUT - G575 CAMP GEIGER WASTE WATER PUMP STATION
NOT TO SCALE
NEW GENERATOR/WORKING PLATFORM CONCRETE
PAD TO BE INSTALLED BY CONTRACTOR
XFMR
PANEL
A
ATS
PANEL A
POWER RISER DIAGRAM - G575 CAMP GEIGER WASTE WATER PUMP STATION
NOT TO SCALE
3000 PSI CONCRETE
PAD
GRADE
GENERATOR SET FURNISHED
BY GOVERNMENT.
INSTALLED BY CONTRACTOR
1. PROVIDE 8" CONCRETE PAD W/ 6x6 - 10 GAUGE WIRE MESH (LIFTED TO CENTER OF POUR) ON 6" WELL
COMPACTED GRAVEL BASE.
2. SIZE PAD AS INDICATED AND PROVIDE GRADUAL SLOPE FOR DRAINAGE.
3. VERIFY EXACT PAD SIZE REQUIREMENTS AND RACEWAY STUB-UP LOCATIONS WITH GOVERNMENT POC PRIOR
TO ROUGH-IN AND POURING OF PAD.
4. SECURE GENERATOR TO PAD IN ACCORDANCE WITH MANUFACTURER’S RECOMMENDATION.
NOTES:
GENERATOR PAD DETAIL
NOT TO SCALE
3' (TYP)
EDGE OF GENERATOR
¾” X 10' GROUND ROD (TYP)
# 4/0 AWG BARE COPPER GROUND RING
MINIMUM 2' 6 “ BELOW GRADE
# 4/0 AWG BARE COPPER TO GENERATOR
FRAME (PROTECT FROM PHYSICAL DAMAGE)
GENERATOR GROUND RING DETAIL
NOT TO SCALE
GRAVEL BASE
GRADE
SUB-BASE FUEL TANK
SUB-BASE FUEL TANK
600A/3P
MAIN
C1 C2
C3 C4
C5
Demolition -
1. Remove the existing 480Y/277 volt, 3 phase, 4 wire, 400 amp, 4 pole automatic transfer switch.
2. Remove the existing secondary conductors from the transfer switch to the enclosed circuit breaker (main).
3. Remove the existing secondary conductors from the automatic transfer switch to the 200KW generator.
4. The existing secondary conductors from the automatic transfer switch to the motor control center are to remain and be reconnected to the new automatic transfer switch.
5. The existing 200KW generator shall remain and be abandoned in place.
Installation –
1. Provide and install new 480Y/277 volt, 3 phase, 4 wire, 400 amp, 4 pole, closed transition automatic transfer switch on existing concrete pad.
2. Provide and install new conductors from automatic transfer switch to the existing enclosed circuit breaker (main). Existing conduits may be modified as required and reused.
3. Install new government furnished 200KW diesel generator with 1200 gallon subbase fuel tank and working platform. Generator and working platform shall be placed on new 11ft 6in x 22ft x 8” thick concrete pad.
4. Provide and install new conduit and conductors from the generator to the new automatic transfer switch.
5. All terminations shall have corrosion inhibitor applied due to the corrosive gases present.
* ALL NEW PENETRATIONS THROUGH EXTERIOR WALLS INTO THE GENERATOR/MCC ROOM MUST BE AIRTIGHT TO PREVENT HYDROGEN SULFIDE GAS FROM INTRUDING THE SPACE
AND DAMAGING ELECTRICAL/ELECTRONIC EQUIPMENT.
DESCRIPTION OF WORK
25-0431 E2
POWER/CONTROL CONDUIT AND CABLE SCHEDULE
CONDUIT CONDUIT WIRE
NO.
C1
SIZE NO. SIZE
¾” RMC 5 14 AWG
FROM
ATS CONTROL
TO
GENERATOR CONTROL PANEL
REMARKS
2 BLK 2 RED 1 GRN
C2 4" RMC 4
500 KCMIL
3 AWG
ATS “EM” LUGS GENERATOR BRKR
C3 ¾” RMC 5 12 AWG
PANEL A GENERATOR BLOCK HEATER &
BATTERY CHARGER
CIRCUITS A-10, A-12
(SEPARATE NUETRALS)
C4 4" RMC 4
500 KCMIL
3 AWG
ATS “LOAD” LUGS MOTOR CONTROL CENTER EXISTIING TO BE
RECONNECTED
C5 4" RMC 4
500 KCMIL
3 AWG
ATS “LINE” LUGS MAIN ENCLOSED CIRCUIT
BREAKER
A
B
C
N
G
AB
C
N
GFP GFP
CIRCUIT
BREAKER
FOUR
POLE
ATS
CIRCUIT
BREAKER GEN SET
FROM
UTILITY
G N C B A
BOND TO HOUSING TO LOAD
GROUND
RING
TYPICAL FOUR-POLE ATS CONFIGURATION
NOT TO SCALE
GROUNDING
ELECTRODE
EQUIPMENT SCHEDULE
1 200KW 600A MCB 480Y/277V 3PH GENERATOR SET WITH WORKING PLATFORM TO BE
FURNISHED BY THE GOVERNMENT AND INSTALLED BY CONTRACTOR
2 400A, 480Y/277V, 4 POLE, 35kAIC, CLOSED TRANSITION, WITH BYPASS ISOLATION
AUTOMATIC TRANSFER SWITCH TO BE FURNISHED AND INSTALLED BY CONTRACTOR
ITEM EQUIPMENT DESCRIPTION
3 EXISTING MAIN ENCLOSED CIRCUIT BREAKER 300A 480V 3 POLE 30kAIC SERVICE
ENTRANCE RATED IN NEMA-1 ENCLOSURE
4 EXISTING PANELBOARD A, 225A MCB 208Y/120V 3 PHASE 4 WIRE 22kAIC
5 EXISTING MOTOR CONTROL CENTER, 600A MLO 480Y/277V 3 PHASE 4 WIRE 22kAIC
WORK AREA - AS4300 NRAS DOUGLAS GATE ENTRY
NOT TO SCALE
25-0431 E3
GRAVEL PAD
GRADE
COMPACTED DIRT AND GEO-FABRIC
UNDISTURBED SOIL
- REMOVE 6 INCHES OF GRASS AND SOIL IN THE OUTLINED AREA
- COMPACT EXCAVATED AREA AND INSTALL 8OZ GEO-TEXTILE FABRIC
- INSTALL 6 INCH BY 6 INCH 4000 PSI CONCRETE BORDER ON THREE SIDES
- INSTALL 6 INCHES OF #57 CRUSHED STONE
6"6"
6"
CONCRETE BORDER
30'
30'
24" CLASS V REINFORCED CONCRETE PIPE
STREET EDGE STREET EDGE STREET EDGE
GRAVEL DRIVE WITH 24" RCP
Gravel Pad and Drive Notes
- Excavate the area indicated in the sketch approximately 6 inches deep and compact the base.
- Install non-woven 8 oz geotextile fabric where excavated.
- Install 6" x 6" 3000 psi concrete border on pad (no border on the gravel drive).
- The gravel drive shall butt up to the existing asphalt street.
- Fill the excavated area with #57 stone.
1. Excavate indicated area and install concrete border as directed.
2. Provide and install equipment rack with service panel and government furnished automatic transfer switch. Ensure the service panel and automatic transfer switch face west. This will prevent the display on the automatic transfer switch from being bleached out by the sun.
3. Provide and install conduit and wire from pole mounted transformer to service panel and from the service panel to the automatic transfer switch. Install conduit and wire from automatic transfer switch to generator pad location and from the automatic transfer switch to the existing service pole and terminate at new weatherhead on the service mast.
4. Provide and install conduit and wire from service panel to the generator location for block heater and battery charger.
5. Remove the existing service disconnect, conduit and conductors complete. Install 12” x 12” x 6” NEMA 3R junction box at this location.
4. Provide and install 100” x 56” x 8” concrete pad for generator.
5. Provide and install 20’ long 24” class v reinforced concrete pipe in the existing swale.
6. Provide and install 6” of #57 stone in the excavated area ensuring there is a minimum of 12” of cover on the reinforced concrete pipe.
7. Place the government furnished 25KW generator with 78 gallon sub-base fuel tank on the concrete pad and make all connections.
8. Test for proper operation.
SPACING TO SUPPORT
EQUIPMENT PROVIDED
PROVIDED FOR
CONDUIT SUPPORT
6' 0"
2' 0"
3" RIGID GALVANIZED PIPE
WITH THREADED CAP SPACED
TO SUPPORT EQUIPMENT
GRADE
EQUIPMENT RACK DETAIL
NOT TO SCALE
CONCRETE
UTILITY POLE, TRANSFORMER, AND AREA
LIGHT INSTALLED BY GOVERNMENT
GENERATOR PAD
DESCRIPTION OF WORK
15'
25-0431 E4
EQUIPMENT RACK
GRAVEL PAD AND DRIVE DETAIL
NOT TO SCALE
LEAVE 3FT OF FREE CONDUCTOR FOR ATTACHMENT
TO SERVICE DROP BY GOVERNMENT
NEW SERVICE MAST
1 - 6 G, ¾” C
POWER RISER DIAGRAM - AS4300 NRAS DOUGLAS GATE ENTRY
NOT TO SCALE
3000 PSI
CONCRETE
PAD
GRADE
GENERATOR SET FURNISHED BY
GOVERNMENT. INSTALLED BY
CONTRACTOR
1. PROVIDE 8" CONCRETE PAD W/ 6x6 - 10 GAUGE WIRE MESH (LIFTED TO CENTER OF POUR) ON 6" WELL
COMPACTED GRAVEL BASE.
2. SIZE PAD SO THAT OUTER EDGE OF PAD EXTENDS 12" BEYOND ENCLOSURE AND PROVIDE GRADUAL SLOPE FOR
DRAINAGE.
3. VERIFY EXACT PAD SIZE REQUIREMENTS AND RACEWAY STUB-UP LOCATIONS WITH GOVERNMENT POC PRIOR TO
ROUGH-IN AND POURING OF PAD.
4. SECURE GENERATOR TO PAD IN ACCORDANCE WITH MANUFACTURER’S RECOMMENDATION.
NOTES:
GENERATOR PAD DETAIL
NOT TO SCALE
3' (TYP)
EDGE OF GENERATOR
¾” X 10' GROUND ROD (TYP)
# 4/0 AWG BARE COPPER
GROUND RING MINIMUM 2' 6 “
BELOW GRADE
# 4/0 AWG BARE COPPER TO GENERATOR
FRAME (PROTECT FROM PHYSICAL DAMAGE)
GENERATOR GROUND RING DETAIL
NOT TO SCALE
GRAVEL BASE
GRADE
SUB-BASE FUEL TANK
SUB-BASE FUEL TANK
3 4
UTILITY POLE, TRANSFORMER, AND AREA
LIGHT INSTALLED BY GOVERNMENT
EXISTING POLE MOUNTED TRANSFORMER
AND OVERHEAD ELECTRICAL SERVICE
EXISTING SERVICE DISCONNECT, SERVICE MAST
AND CONDUCTORS TO BE REMOVED COMPLETE
C1
C2 C3
C4 C6 C7
C5
25-0431 E5
A
B
N
G
AB
N
CIRCUIT
BREAKER
TWO
POLE
ATS
CIRCUIT
BREAKER
GEN SET
FROM
UTILITY
G N B A
BOND TO HOUSING
TO LOAD
GROUND
RING
EQUIPMENT SCHEDULE
1 25KW 100A MCB 120/240V 1 PHASE GENERATOR SET WITH WORKING PLATFORM TO BE
FURNISHED BY THE GOVERNMENT AND INSTALLED BY CONTRACTOR
2 100A, 240V, 2 POLE AUTOMATIC TRANSFER SWITCH TO BE FURNISHED BY THE
GOVERNMENT AND INSTALLED BY CONTRACTOR
ITEM EQUIPMENT DESCRIPTION
3 ELECTRICAL PANEL, 125A MCB, 120/240V, 1 PHASE, 3 WIRE, NEMA 3R, 6 SPACE/12
CIRCUIT, 22kAIC
4 EXISTING PANELBOARD , 100A MCB 120/240V, 1 PHASE, INSIDE GUARDSHACK AS4300
12" X 12" X 6" NEMA 3R JUCNTION BOX TO BE INSTALLED ON THE EXISTING SERVICE POLE
AT THE SERVICE DISCONNECT.5
POWER/CONTROL CONDUIT AND CABLE SCHEDULE
CONDUIT CONDUIT WIRE
NO.
C1
SIZE NO. SIZE
1 ¼” RMC 3 3 AWG
FROM
TRANSFORMER
TO
SERVICE PANEL
REMARKS
C2 1 ¼” RMC 3
3 AWG
8 AWG
ATS “EM” LUGS GENERATOR BRKR
C3 ¾” RMC 5 12 AWG
PANEL A GENERATOR BLOCK HEATER &
BATTERY CHARGER
CIRCUITS A-10, A-12
(SEPARATE NUETRALS)
C4 ¾” RMC 5 14 AWG
ATS CONTOL GENERATOR CONTROL PANEL 2 BLK 2 RED 1 GRN
C5 1 ¼” RMC 3
3 AWG
8 AWG
ATS “LINE” LUGS SERVICE PANEL
C6 1 ¼” RMC 3
3 AWG
8 AWG
ATS “LOAD” LUGS POLE MOUNTED JUNCTION BOX
C7 1 ¼” RMC 3
2 AWG
8 AWG
POLE MOUNTED JUNCTION
BOX SERVICE PANEL EXISTING TO BE REUSED
TYPICAL TWO-POLE ATS CONFIGURATION
NOT TO SCALE
GROUNDING
ELECTRODE *THERE SHALL BE NO NUETRAL GROUND
BOND MADE AT THE GENERATOR
| TITLE/MAP1� |
| TITLE/MAP2� |
| NOTES� |
| NEW WORK G575� |
| DETAILS G575� |
| WORK AREA AS4300� |
| NEW WORK AS4300� |
| DETAILS AS4300� |
| Page-9� |
File details come from the government source that posted it. Updated .