Campground Restroom Replacement Project Summary
This document is a set of construction plans and project specifications prepared by the Iowa Department of Natural Resources Engineering Section for the Campground Restroom Replacement project at Pikes Peak State Park in Clayton County, Iowa. The project involves the removal of an existing vault restroom building, one tree stump, and existing sidewalk, with backfilling of the building demolition void using modified subbase. A new prefabricated concrete vault restroom building (single pit, right entry model manufactured by Huffcutt Concrete Inc.) will be installed with electrical service connection, new reinforced concrete sidewalk, ADA parking space with painted markings, concrete parking bumper, and associated site improvements. Additional work includes site grading, erosion control measures, seeding, and stockpiling of crushed stone. The project contains specific material quantities: 146 tons of modified subbase for backfill, 27 tons of modified subbase under new pavement, 32 tons of Class A crushed stone base, 57 square yards of reinforced PCC pavement, 9 square yards of reinforced PCC sidewalk, and 80 linear feet of electrical connection. Construction is limited to Monday through Thursday operations to avoid interference with campground visitors. The bid closing date and time is November 19, 2026, at 3:00 PM, with electronic bid submission required. A site visit and inspection of actual job conditions prior to bidding are mandatory.
The contract specifications require all work to conform to applicable codes and ordinances, with the contractor responsible for utility disconnection and termination, waste disposal, and erosion control maintenance throughout the project duration. The prefabricated restroom building has a specified finish floor elevation of 1,106.40 feet and must be installed on 9 inches of compacted Class A crushed stone with tank excavation extending a minimum of 12 inches beyond tank sides. The contractor must coordinate acceptable road closures and traffic control plans with the DNR District Engineer and notify the District Engineer of the expected building delivery date prior to installation. The document specifies that cutting of the tree stump shall be performed only between October 1st and March 31st, and a licensed electrician must be used for the electrical connection with verification of wire sizing and potential inspection by the State Fire Marshal. No payment for overhaul will be allowed for material hauled to disposal sites, and no material placement is permitted within rights-of-way unless specifically approved by the DNR Engineer.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 25-03-22-01 - Bid Package.pdf | ||
| 25-03-22-01 - Attachment C - Building Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
This project includes the removal of existing sidewalk, one tree stump, and one vault restroom building. The void from the building demolition will be backfilled with modified subbase and compacted. A new vault restroom building with an electrical service connection, sidewalk, ADA parking space will be installed on the same site. Painting, site grading, erosion control, seeding, and stockpiling crushed stone are also included.
Iowa DNR
Daniel Pfeifer
515-901-6261 daniel.pfeifer@dnr.iowa.gov
6200 Park Ave. Ste 200
Des Moines, IA 50321
Iowa Department of Natural Resources Construction Documents for
Pikes Peak State Park Clayton County, Iowa
Campground Restroom Replacement Project No. 25-03-22-01
Project Location Map
N
Sheet Index
Cover Sheet Project Overview Quantities & Information General Information Existing Site Plan Proposed Site Plan Details
Iowa DNR
Ken Howe
319-240-3553 kenneth.howe@dnr.iowa.gov
Directory Project Manager
Organization
Contact
Phone
Address
City, State, Zip
District Engineer Organization
Contact
Phone
Address
City, State, Zip
Project Description
Project Number:
25-03-22-01
Bid Date:
11/19/2026
Iowa Department of Natural Resources Engineering Section - 6200 Park Ave., Suite 200 Des Moines, IA 50321-1270
Campground Restroom Replacement Pikes Peak State Park, Clayton County
Sheet No:Drawn by: DP
M
Sh ar ed d riv es
\D N
R
LW
B
EN
G Pr oj ec ts \2
2_ Cl ay to n\
-0 3-
-0
Pi ke s P ea k
- V au lt To ile t\
5_ De sig n\
C3 D\
-0
3-
-0
Pi ke s - R es tr oo m
Fo r B id
.d w g
/3 0/
:4
PM
Pl ot
D at e:
Revision For Bid
Date 10-30-26
Cover Sheet
Project Area
Kenneth Howe Date License Number: 21932 My license renewal date is December 31, 2026 Pages or sheets covered by this seal:
All
I hereby certify that this engineering document was prepared by me or under my direct personal supervision and that I am a duly licensed Professional Engineer under the laws of the State of Iowa.
AutoCAD SHX Text A
AutoCAD SHX Text N
AutoCAD SHX Text I
AutoCAD SHX Text O
AutoCAD SHX Text W
AutoCAD SHX Text I
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text P
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text N
AutoCAD SHX Text E
AutoCAD SHX Text C
AutoCAD SHX Text I
AutoCAD SHX Text L
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text I
AutoCAD SHX Text G
AutoCAD SHX Text N
AutoCAD SHX Text E
AutoCAD SHX Text L
AutoCAD SHX Text A
AutoCAD SHX Text
KENNETH HOWE 21932
Source: Esri, Vantor, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community Powered by Esri Source: Esri, Vantor, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community Powered by Esri
Project Number:
25-03-22-01
Bid Date:
11/19/2026
Iowa Department of Natural Resources Engineering Section - 6200 Park Ave., Suite 200 Des Moines, IA 50321-1270
Campground Restroom Replacement Pikes Peak State Park, Clayton County
Sheet No:Drawn by: DP
M
Sh ar ed d riv es
\D N
R
LW
B
EN
G Pr oj ec ts \2
2_ Cl ay to n\
-0 3-
-0
Pi ke s P ea k
- V au lt To ile t\
5_ De sig n\
C3 D\
-0
3-
-0
Pi ke s - R es tr oo m
Fo r B id
.d w g
/3 0/
:4
PM
Pl ot
D at e:
Revision For Bid
Date 10-30-26 2Project Overview
Project Location
0' 200' 400'
N
Pikes Peak State Park Campground
Vault Toilet - Project Location
Pikes Peak Road
Pikes Peak Scenic Overlook
25-03-22-01 Bid Date:
11/19/2026 Iowa Department of Natural Resources
Engineering Section - 6200 Park Ave., Suite 200 Des Moines, IA 50321-1270
Campground Restroom Replacement Pikes Peak State Park, Clayton County
Sheet No:Drawn by: DP
M
Sh ar ed d riv es
\D N
R
LW
B
EN
G Pr oj ec ts \2
2_ Cl ay to n\
-0 3-
-0
Pi ke s P ea k
- V au lt To ile t\
5_ De sig n\
C3 D\
-0
3-
-0
Pi ke s - R es tr oo m
Fo r B id
.d w g
/3 0/
:4
PM
Pl ot
D at e:
Revision For Bid
Date 10-30-26
Quantities & Information
Estimate Reference Information
1. Clearing and Grubbing - Remove tree stump designated by the plan sheets. Damage to trees which are not designated for removal shall not be tolerated. Off site disposal is the responsibility of the contractor. No burning or burying is allowed in the park. Cutting shall be performed between October 1st and March 31st.
2. Subbase, Modified Subbase - Use under pavement and sidewalk, see details. Subbase must extend 2' beyond the edge of pavement. Additionally, use modified subbase to backfill hole from building removal. Compact the material, lifts must not exceed 8" loose thickness.
3. Pavement, Reinforced PCC, 6", Iowa DOT C4 Mix - See pavement detail. Excavation and Subgrade preparation is incidental. 'C' joints shall be sawcut at 12' maximum. Use 'BT' joints for abutting pours. Use 'BT' joint abutting existing road or parking lot. All joints must comply with SUDAS 7010.
4. Removal of Sidewalk - Contractor must remove the existing sidewalk and base as indicated in the plan sheets. All saw cuts shall be incidental. See general note 5.
5. Sidewalk, Reinforced PCC, 6" - See sidewalk detail. Excavation and subgrade preparation is incidental.
6. Painted Pavement Markings, High-Build, Waterborne - Wait a minimum of 14 days after concrete is placed to begin painting PCC, unless otherwise approved by DNR District Engineer.
7. Temporary Traffic Control - Traffic control is required for the duration that construction impedes campground visitor traffic, e.g., building installation. Coordinate acceptable road closure and traffic control plan with DNR District Engineer.
8. Traffic Sign, ADA Parking - Install signs as shown on plan sheets. This line item includes the sign, all accessories, and installation. Signs shall be mounted to the restroom building wall at a mounting height of 5'.
9. Seeding, Fertilizing, and Mulching, Type 1 - Use between March 1 and May 31.
10. Wattles, 9", Wildlife Friendly - Wattles must be EG-Tube Sock by Ero-Guard or approved equivalent. Install as needed and as directed by DNR District Engineer.
11. Wattle, Removal - Remove all wattles unless directed otherwise by DNR District Engineer.
12. Mobilization - Work is permitted Monday to Thursday. To avoid interference with campground visitors, work is not permitted Friday, Saturday or Sunday.
13. Remove Existing Restroom Building w/ Vault - Remove building and vault per per plans. Contractor responsible for pumping tank(s) before removal and removal and disposal of all building and underground tank debris. See General Note 5. Excavation is incidental. Contractor responsible for disconnecting and terminating utilities, if present.
14. Prefabricated Concrete Restroom Building (Single Vault) - Refer to the Specifications Manual. Furnish and install a prefabricated single pit vault building (Model: Iowa Single Vault - Right Entry) as manufactured by Huffcutt Concrete Inc. of Chippewa Falls, Wisconsin, or approved equal. Due to long lead times, Contractor should prepare submittal information and order the building as soon as possible after the contract is executed. Building shall be equipped for a 120/240V, single phase electrical service connection. Building must have solar vent fan. Dewatering, excavation, and other tasks associated with building installation are incidental to this line item. Contractor shall excavate a minimum of 12" beyond the sides of the tank. Tank (5' depth) shall be placed on 9" of compacted Class A crusted stone.
Assemble building and backfill against the tank with Class A crushed stone to finished surface, compact. Follow Manufacturer recommendations during installation.
15. Concrete Parking Bumper - Furnish and install 5" Concrete Parking Bumper per detail.
16. Electrical Connection to Building – Install electrical connection as shown in plans. Includes all necessary connections, boxes, wire and conduit as needed to meet NEC and Iowa Electric Code. A licensed Electrician shall be used and organize an inspection with the State Fire Marshal, if needed. The Electrician shall verify sizing of all proposed wires.
Detectable warning tape, 3" wide shall be placed in trenches a minimum 24” below grade and is incidental.
17. Class A Crushed Stone Base - Use as backfill and bedding material around the new restroom building.
18. Class A Crushed Stone, Stockpile - Stockpile in location determined by DNR District Engineer.
19. Site Grading - Includes all work to reach finished grade and restore disturbed areas. See General note 1.
25-03-22-01 Bid Date:
11/19/2026 Iowa Department of Natural Resources
Engineering Section - 6200 Park Ave., Suite 200 Des Moines, IA 50321-1270
Campground Restroom Replacement Pikes Peak State Park, Clayton County
Sheet No:Drawn by: DP
M
Sh ar ed d riv es
\D N
R
LW
B
EN
G Pr oj ec ts \2
2_ Cl ay to n\
-0 3-
-0
Pi ke s P ea k
- V au lt To ile t\
5_ De sig n\
C3 D\
-0
3-
-0
Pi ke s - R es tr oo m
Fo r B id
.d w g
/3 0/
:4
PM
Pl ot
D at e:
Revision For Bid
Date 10-30-26
General Information
General Information
1. Verify actual locations and elevations with DNR Engineer. DNR to provide construction survey.
2. All work shall conform to and be performed in accordance with all applicable codes and ordinances.
3. The contractor shall visit the site and inspect the project area and thoroughly familiarize themselves with the actual job conditions prior to bidding and the start of work. Failure to visit the project site shall not relieve the contractor from performing the work in accordance to the plans, specification, special provisions and contract.
4. The contractor shall verify, at the site, all dimensions and conditions shown on the plans and shall notify the DNR Engineer of any discrepancies, omissions, and/or conflicts prior to proceeding with the work.
5. It shall be the contractor’s responsibility to provide waste areas or disposal sites for excess material (excavated material or broken concrete) which is not desirable to be incorporated into the work involved on this project. No payment for overhaul will be allowed for material hauled to these sites.
No material shall be placed within the right-of-way, unless specifically stated in the plans or approved by the DNR Engineer.
6. The contractor shall not disturb desirable grass areas and desirable trees outside the construction limits. The contractor will not be permitted to park or service vehicles and equipment or use these areas for storage of materials. Storage, parking and service areas will be subject to the approval of the DNR Engineer.
7. Where utilities and fixtures are shown as Existing on the plans or encountered within the construction area, it shall be the responsibility of the contractor to notify the DNR Engineer of those utilities prior to the beginning of any construction. The contractor shall be afforded access to these facilities for necessary modification of services. Underground facilities, structures and utilities have been plotted from available surveys and records and therefore their locations must be considered approximate only. It is possible there may be others, the existence of which is presently not known or shown. It is the contractor’s responsibility to determine their existence and exact location and to avoid damage thereto. No claims for additional compensation will be allowed to the contractor for any interference or delay caused by such work.
8. The contractor shall shape graded area to maintain surface drainage. All elevations are to finish grade.
9. The contractor is expected to have materials, equipment, and labor available on a daily basis to install and maintain erosion control features on the project. This may involve seeding, silt fence, rock ditch checks, silt basins or silt dikes.
10. Work is permitted Monday to Thursday. To avoid interference with campground visitors, work is not permitted Friday, Saturday or Sunday.
11. Due to long lead times, Contractor should prepare submittal information and order the building as soon as possible after the contract is executed.
Contractor to notify DNR District Engineer of expected building delivery date, once known.
Legend Existing Proposed Description
Ground
Lakes, Wetlands, Rivers, Streams
Rip Rap
Seeding
RECP (Erosion matting)
Silt Fence or Erosion Control
Flow Arrow
Trees
Fence
Demolition or Removal
Gravel
Concrete
Asphalt
Water Main
Hydrant
Water Valve
Sanitary Sewer
Sanitary Sewer Manhole
Storm Sewer or Culvert
Storm Sewer Intake or Manhole
Electrical
Communications or Fiber
Gas
AutoCAD SHX Text H
AutoCAD SHX Text Y
AutoCAD SHX Text D
AutoCAD SHX Text
WV
AutoCAD SHX Text H
AutoCAD SHX Text Y
AutoCAD SHX Text D
AutoCAD SHX Text
WV
AutoCAD SHX Text S
AutoCAD SHX Text D
AutoCAD SHX Text S
AutoCAD SHX Text D
0' 5' 10'
N
Project Number:
25-03-22-01
Bid Date:
11/19/2026
Iowa Department of Natural Resources Engineering Section - 6200 Park Ave., Suite 200 Des Moines, IA 50321-1270
Campground Restroom Replacement Pikes Peak State Park, Clayton County
Sheet No:Drawn by: DP
M
Sh ar ed d riv es
\D N
R
LW
B
EN
G Pr oj ec ts \2
2_ Cl ay to n\
-0 3-
-0
Pi ke s P ea k
- V au lt To ile t\
5_ De sig n\
C3 D\
-0
3-
-0
Pi ke s - R es tr oo m
Fo r B id
.d w g
/3 0/
:4
PM
Pl ot
D at e:
Revision For Bid
Date 10-30-26 5Existing Site Plan
Existing Campground Road
Existing Campground Road
Remove existing stump, to accommodate grading.
Approximate Diameter 48" Grubbing, (80 Units)
Existing Electrical Cabinet
Remove existing sidewalk (24 SY)Existing Campsite
Existing Campsite
Existi ng Campsite
Notes:
1. Seed all disturbed areas per ERI notes.
2. Install Wattles as necessary, or as directed by DNR District Engineer.
Remove existing building (1 Each) Modified Subbase (146 Tons)
Pump tank(s) before removal. Remove and dispose of all building and underground tank debris. Backfill hole with Modified Subbase.
Compact backfill, Lifts not to exceed 8" loose thickness.
Notify DNR District Engineer 2 week before expected removal.
1.06%
1.80%
5.23%
7.76%
3.75%
1.50%
1106.19
1106.33 1106.40
1106.33
1106.02
1105.25 (Match exsiting road, typ.)
1105.29
1106.07
1106.98 1106.86
1106.74
E: 5,545,815.05 N: 3,833,466.78
EL: 1,106.40
E: 5,545,808.86 N: 3,833,461.71
EL: 1,106.40
E: 5,545,799.24 N: 3,833,473.47
EL: 1,106.40
E: 5,545,805.43 N: 3,833,478.53
EL: 1,106.40
0' 5' 10'
N
Project Number:
25-03-22-01
Bid Date:
11/19/2026
Iowa Department of Natural Resources Engineering Section - 6200 Park Ave., Suite 200 Des Moines, IA 50321-1270
Campground Restroom Replacement Pikes Peak State Park, Clayton County
Sheet No:Drawn by: DP
M
Sh ar ed d riv es
\D N
R
LW
B
EN
G Pr oj ec ts \2
2_ Cl ay to n\
-0 3-
-0
Pi ke s P ea k
- V au lt To ile t\
5_ De sig n\
C3 D\
-0
3-
-0
Pi ke s - R es tr oo m
Fo r B id
.d w g
/3 0/
:4
PM
Pl ot
D at e:
Revision For Bid
Date 10-30-26 6Proposed Site Plan
Install Electrical Connection to building.
See ERI Note. Approximately 80 LF. Field verify where service connection must enter building with manufacturer.
Subbase, Modified Subbase (27 Tons) Sidewalk, Reinforced PCC, 6" (9 SY), See Detail Pavement, Reinforced PCC, 6" (57 SY), See Detail Tie into existing road elevation.
Existing Campground Road - Protect road pavement. Position crane off roadways during building installation.
Existing Campground Road
Existing Electrical Box
Existing Campsite
Existi ng Campsite
Prefabricated Restroom Building - Right Entry (1 Each) - Excavation Incidental Class A Crushed Stone Base (32 Tons)
ADA Traffic Sign - Install on Building (1 Each)
Finish Floor 1106.40' Install expansion joint between sidewalk and building.
Grade away from building at maximum 5:1 slope
Notes:
1. Seed all disturbed areas per ERI notes.
2. Install Wattles as necessary, or as directed by DNR District Engineer.
Painted Pavement Markings (0.2 STA) 6' Parking Bumper (1 Each)
Site Grading (Lump Sum)
Existing Campsite
25-03-22-01 Bid Date:
11/19/2026 Iowa Department of Natural Resources
Engineering Section - 6200 Park Ave., Suite 200 Des Moines, IA 50321-1270
Campground Restroom Replacement Pikes Peak State Park, Clayton County
Sheet No:Drawn by: DP
M
Sh ar ed d riv es
\D N
R
LW
B
EN
G Pr oj ec ts \2
2_ Cl ay to n\
-0 3-
-0
Pi ke s P ea k
- V au lt To ile t\
5_ De sig n\
C3 D\
-0
3-
-0
Pi ke s - R es tr oo m
Fo r B id
.d w g
/3 0/
:4
PM
Pl ot
D at e:
Revision For Bid
Date 10-30-26
Details
3'1' 1'
6"
6"
Sidewalk Cross Section - 5' Width Not To Scale
6" Reinforced PCC
6" (min.) Modified Subbase
#4 Bar, Longitudianal, 36" O.C.
1. Install expansion joint between proposed sidewalk and building.
2. Joints per SUDAS.
3. Use 'BT' joint between pavement and sidewalk.
4. Contraction joint must be sawcut at 5' maximum spacing and must be cut to a depth of 1 4 of the slab thickness.
5. Minimum Lap Splice Length shall be 24".
6"
6"
30" 30" 6" Reinforced PCC
6" PCC Parking Lot Not To Scale
6" (min.) Modified Subbase
#4 Bar, 30" O.C., Each way
Notes:
1. Subbase - Maximum 8" loose thickness lifts. Placement, compaction, and final elevation of subbase per SUDAS 2010.
2. Joints per SUDAS.
3. Use 'BT' joint between pavement and sidewalk.
4. Contraction joint must be sawcut at 12' maximum spacing and must be cut to a depth of 1 4 of the slab thickness.
5. Minimum Lap Splice Length shall be 24".
#4 Bar, Transverse, 30" O.C.(typ.)
| Sheets and Views |
| 25-03-22-01 Pikes - Restroom - For Bid-1 |
| 25-03-22-01 Pikes - Restroom - For Bid-2 |
| 25-03-22-01 Pikes - Restroom - For Bid-3 |
| 25-03-22-01 Pikes - Restroom - For Bid-4 |
| 25-03-22-01 Pikes - Restroom - For Bid-5 |
| 25-03-22-01 Pikes - Restroom - For Bid-6 |
| 25-03-22-01 Pikes - Restroom - For Bid-7 |
| 2026-11-02T12:48:54-0600 | |
| Ken Howe, P.E. |
File details come from the government source that posted it. Updated .