This document is a bid form for the Fayette County Sheriff's Office Watch Office Renovation project. The project involves the renovation of the watch office located at 155 Johnson Avenue, Fayetteville, GA 30215. The bid form includes line items for various construction-related costs such as permits, mobilization, insurance, supervision, demolition, concrete, masonry, metals, carpentry, roofing, doors and windows, finishes, plumbing, HVAC, and electrical work. The project has a total square footage of an unspecified amount and a completion date that is not provided. The bid form includes several allowances totaling $85,000 for items like new external signage, structural alterations, mechanical and electrical alterations, and low voltage wiring installations and equipment. Additionally, there is a $15,000 contingency for unknowns, resulting in a total bid amount of $100,000.
The bid form does not provide any information regarding pricing terms, set asides, incumbents, funding requirements or sources, or the contract term and renewal options. The document appears to be focused solely on outlining the specific construction-related line items and costs for this renovation project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2436_ITB.pdf | ||
| 2436_B ITB Plans.pdf | ||
| ITB 2436_B Addendum 1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet2
| Bid 2436-B: Fayette County Sheriff's Office Watch Office Renovation |
| BID FORM |
| Project: | FCSO WATCH OFFICE RENOVATION | Plan Date: |
| Address: | 155 JOHNSON AVENUE, FAYETTEVILLE, GA 30215 | Project Start: |
| Square Feet: | Completion Date: | |
| Contractor: | Project Duration: | |
| Address: | ||
| Contact: | ||
| Email: | ||
| Phone: | ||
| Construction Cost |
| Bid Amount | ||
| BASE BID | ||
| General Conditions | ||
| 101 | Permits (BY OWNER) | 0.00 |
| 102 | Mobilization and Field Office | |
| 103 | Performance Bond / 100% Material Payment Bond | |
| 104 | Project Insurance | |
| 105 | Payroll Taxes & Benefits | |
| 106 | Job Supervision | |
| 107 | Field Eng. / Layout /Construction Staking / Testing | |
| 108 | Equipment | |
| 109 | Expendables / Job Trailer / Toilets / Misc. Expenses | |
| 110 | Construction Utilities (Temporary) | |
| 111 | Construction Project Signage Allowance | |
| 112 | General Clean-up & Disposal | |
| Sub Total - General Conditions | $0.00 |
| Building Construction | |
| Division 02 | EXISTING CONDITIONS |
| Selective Demolition | |
| Division 03 | CONCRETE |
| Cast-in-place concrete | |
| Division 04 | MASONRY |
| Unit masonry assemblies | |
| Division 05 | METALS |
| Structural Steel Framing | |
| Pipe & Tube Railings | |
| Division 06 | WOOD, PLASTICS & COMPOSITES |
| Rough Carpentry | |
| Miscellaneous Carpentry | |
| Plastic Laminate faced Architectural Cabinets | |
| Division 07 | THERMAL & MOISTURE PROTECTION |
| Roofing, thermal insulation, sheet metal flashing & sealants | |
| Division 08 | OPENINGS |
| Metal Doors & Frames, flush wood doors, hardware | |
| Aluminum Framed Entrances & Storefronts | |
| Glazing | |
| Division 09 | FINISHES |
| Metal stud partitions | |
| Suspended Ceilings | |
| Ceramic tiling, resilient tile flooring and base | |
| Painting | |
| Division 10 | SPECIALTIES |
| Fire Extinguishers and Accessories | |
| Division 22 | PLUMBING |
| Piping & accessories | |
| Division 23 | HEATING VENTILATION & AIRCONDITIONING |
| Mechanical, insultation & Ductwork | |
| Division 26 | ELECTRICAL |
Sub Total - Building Construction $0.00
| Allowances | ||
| Allowance for new external signage and flagpole | $15,000 | |
| Allowance for additional structural alterations | $10,000 | |
| Allowance for additional Mechanical & Electrical alterations | $10,000 | |
| Allowance for Low Voltage wiring installations & equipment | $50,000 | |
| Sub Total - Allowances | $85,000.00 |
Contingency For Unknowns $15,000
Total Bid $100,000.00