240176_ATT11_Submittal_Register.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- Tinker AFB MAC BOA - WWYK240176 - REPLACE INDUSTRIAL WASTE LIFT STATIONS 6N & 6S, B62501
- Solicitation number
- FA813726R0012
About this file
This is a Submittal Register for the Tinker Air Force Base project to Replace Industrial Waste Lift Stations 6N & 6S (Contract No. WWYK240176, B62501). The document establishes a comprehensive schedule of required contractor submittals organized by specification section and categorized by submittal type, including preconstruction submittals, product data, design data, test reports, certificates, manufacturer's instructions, operation and maintenance data, and closeout submittals. Key preconstruction submittals include Entry Access List, Health and Safety Plan, Restoration Plan, Storm Water Pollution Prevention Plan, AF Form 3952 (Chemical/Hazardous Material Request/Authorization), Spray Painting Plan, Construction Debris Analysis Plan, Baseline Construction Schedule, Baseline Design Schedule, Design Quality Control Plan, and Quality Control Plan. Critical design-related submittals encompass Design and Code Checklists, Interim Design Submittals, Interior and Exterior Building Finishes Scheme, Final Design Submittals, and Design Complete Documents, with the Contractor responsible for providing these items within specified timeframes referenced in the specification sections.
Ongoing submittals during construction include Monthly Updates to the schedule, 3-Week Look Ahead Schedules, Monthly Hazardous Material Usage Reports, Monthly Debris Management Reports, and QC Documentation provided weekly with Contract Progress Reports. Closeout submittals required at project completion include Working As-Built Drawings, Record Drawings, and DD Form 1354. The register also specifies operation and maintenance deliverables such as O&M Manuals, O&M Database, Training Plan, Training Content, Training Outline, and Validation of Training Completion, with training materials due 30 days prior to scheduled training and 14 days prior to content delivery. All submittals are classified as either Government (G), Architect/Engineer (A/E), or as required (R) or conditional (C) items, with designated reviewers and approval authorities responsible for timely processing and feedback to the contractor.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal Register_General Requ
| TITLE: | Tinker AFB General Requirements Specification (Div 00-01) | SUBMITTAL REGISTER | ||||||||||||||||
| JOB NAME: | Replace Industrial Waste Lift Stations 6N & 6S | |||||||||||||||||
| LOCATION: | B62501 | |||||||||||||||||
| CONTRACT NO: | ||||||||||||||||||
| CONTRACTOR: | ||||||||||||||||||
| CONTRACTOR SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | ||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) |
| Line | Activity # | Transmittal # | Specification Section | SD # | Submittal Description | Item Submitted | Paragraph # | Classification: GOVT or A/E Reviewer | Submit | Approval Needed By | Material Needed By | Action Code | Date Of Action | Date FWD to APPR / Auth Date RCD From CONTR | Date FWD To Other Revwr | Date RCD From Other Reviewer | Action Code | Date Of Action | Mailed To CONTR/ Date RCD From APPR Authority | Remarks | |
| 1 | 00 70 00 | 01 | Preconstruction Submittals | Entry Access List | 1.6 | G | |||||||||||||||
| 2 | 00 70 00 | 01 | Preconstruction Submittals | Key Issue Receipt | 1.3.12.1 | ||||||||||||||||
| 3 | 00 70 00 | 06 | Test Reports | Pre-Construction Testing Record | 1.3.11 | G | |||||||||||||||
| 4 | 00 70 00 | 07 | Certificates | Welding, Cutting and Brazing Permit | 1.4 | G | |||||||||||||||
| 5 | 00 70 00 | 11 | Closeout Submittals | Key Return Receipt | 1.3.12.1 | ||||||||||||||||
| 6 | 00 71 00 | 01 | Preconstruction Submittals | Health and Safety Plan | 1.3 | G | |||||||||||||||
| 7 | 00 71 00 | 07 | Certificates | Safety Meetings | 1.3 | ||||||||||||||||
| 8 | 00 71 00 | 07 | Certificates | FOD Awareness and Prevention Training | 1.4 | ||||||||||||||||
| 9 | 00 72 00 | 01 | Preconstruction Submittals | Restoration Plan | 1.3.2 | G | |||||||||||||||
| 10 | 00 72 00 | 01 | Preconstruction Submittals | Storm Water Pollution Prevention Plan | 1.3.3.2 | G | |||||||||||||||
| 11 | 00 72 00 | 01 | Preconstruction Submittals | AF Form 3952 Chemical/Hazardous Material Request/Authorization | 1.4 | G | |||||||||||||||
| 12 | 00 72 00 | 01 | Preconstruction Submittals | Spray Painting Plan | 1.9 | G | |||||||||||||||
| 13 | 00 72 00 | 01 | Preconstruction Submittals | Environmental Management System Awareness Training | 1.1 | ||||||||||||||||
| 14 | 00 72 00 | 03 | Product Data | Affirmative Procurement Documentation or Green Statement | 1.3.10 | G | Provide only one. Reference specification for additional information | ||||||||||||||
| 15 | 00 72 00 | 07 | Cerificates | Fire Ant Federal Compliance Agreement or state phyto-sanitary certificate | 1.3.4.1 | ||||||||||||||||
| 16 | 00 72 00 | 07 | Cerificates | Monthly Hazardous Material Usage Report | 1.4 | G | Provide 1st week of each month during construction | ||||||||||||||
| 17 | 00 72 00 | 08 | Manufacturer's Instructions | Safety Data Sheets/Material Safety Data Sheets | 1.4 | ||||||||||||||||
| 18 | 00 72 00 | 11 | Closeout Submittals | Notice of Termination | |||||||||||||||||
| (ODEQ Form 640-572) | 1.3.3.2 | G | |||||||||||||||||||
| 19 | 00 72 00 - Attch 5 | 01 | Preconstruction Submittals | Construction Debris Analysis Plan | 1.2.3 | G | |||||||||||||||
| 20 | 00 72 00 - Attch 5 | 07 | Certificates | Monthly Debris Management Report | 2 | G | Provide 1st week of each month during construction | ||||||||||||||
| 21 | 01 32 16.00 20 | 01 | Preconstruction Submittals | Baseline Construction Schedule | 1.2 | G | Provide within 10 days of NTP. | ||||||||||||||
| 22 | 01 32 16.00 20 | 01 | Preconstruction Submittals | Baseline Design Schedule | 1.2 | G | Provide within 10 days of NTP. | ||||||||||||||
| 23 | 01 32 16.00 20 | 07 | Certificates | Monthly Updates | 1.4 | Provide 1st week of each month during construction, or as directed by CO | |||||||||||||||
| 24 | 01 32 16.00 20 | 07 | Certificates | 3-Week Look Ahead Schedule | 1.6 | Provide weekly with the Contract Progress Report | |||||||||||||||
| 25 | 01 33 00 | 01 | Preconstruction Submittals | Submittal Register | 1.8 | G | |||||||||||||||
| 26 | 01 33 16.00 10 | 01 | Preconstruction Submittals | Design Quality Control Plan | 1.5.1 | G | |||||||||||||||
| 27 | 01 33 16.00 10 | 01 | Preconstruction Submittals | Initial Design Conference | 1.5.2.2 | ||||||||||||||||
| 28 | 01 33 16.00 10 | 01 | Preconstruction Submittals | Preconstruction Conference | 1.5.2.3 | ||||||||||||||||
| 29 | 01 33 16.00 10 | 01 | Preconstruction Submittals | DCM Procedures | 3.5.1 | G | |||||||||||||||
| 30 | 01 33 16.00 10 | 01 | Preconstruction Submittals | Submittal Register | 3.8.4 | G | |||||||||||||||
| 31 | 01 33 16.00 10 | 05 | Design Data | Design and Code Checklists | 1.7.1 | C | |||||||||||||||
| 32 | 01 33 16.00 10 | 05 | Design Data | Interim Design Submittals | 3.2.1 | R | |||||||||||||||
| 33 | 01 33 16.00 10 | 05 | Design Data | Interior And Exterior Building Finishes Scheme | 3.6.5.1.1 | G | |||||||||||||||
| 34 | 01 33 16.00 10 | 05 | Design Data | Conference Documentation | 3.7.3 | ||||||||||||||||
| 35 | 01 33 16.00 10 | 05 | Design Data | Final Design Submittals | 3.8 | R | |||||||||||||||
| 36 | 01 33 16.00 10 | 05 | Design Data | Design Complete Documents | 3.9 | C | |||||||||||||||
| 37 | 01 45 00.00 10 | 01 | Preconstruction Submittals | Quality Control (QC) Plan | 3.2 | G | |||||||||||||||
| 38 | 01 45 00.00 10 | 01 | Preconstruction Submittals | Additional Requirements for Design Quality Control (DQC) Plan | 3.2.2 | G | |||||||||||||||
| 39 | 01 45 00.00 10 | 05 | Design Data | Discipline-Specific Checklists | 3.2.2 | ||||||||||||||||
| 40 | 01 45 00.00 10 | 05 | Design Data | Design Quality Control | 3.9.1 | ||||||||||||||||
| 41 | 01 45 00.00 10 | 06 | Test Reports | QC Documentation | 3.9 | Provide weekly with the Contract Progress Report | |||||||||||||||
| 42 | 01 50 00 | 01 | Preconstruction Submittals | Request for Contractor Staging Area | 1.1 | G | |||||||||||||||
| 43 | 01 50 00 | 01 | Preconstruction Submittals | Photographic Record | 1.3 | ||||||||||||||||
| 44 | 01 78 00 | 03 | Product Data | Warranty Letter | 1.7.1 | ||||||||||||||||
| 45 | 01 78 00 | 10 | Operation and Maintenance Data | Operation and Maintenance Manuals | 3.4 | G | Provide (2) electronic sets (optical media) and (1) hard copy | ||||||||||||||
| 46 | 01 78 00 | 11 | Closeout Submittals | Working As-Built Drawings | 3.1 | G | Provide (2) electronic sets (optical media) and (2) hard copies | ||||||||||||||
| 47 | 01 78 00 | 11 | Closeout Submittals | Record Drawings | 3.3 | G | Provide (2) electronic sets (optical media) and (1) hard copy | ||||||||||||||
| 48 | 01 78 00 | 11 | Closeout Submittals | DD FORM 1354 | 3.6 | G | |||||||||||||||
| 49 | 01 78 23 | 10 | Operation and Maintenance Data | Operation and Maintenance Data | 1.2 | G | Provide 30 days prior to scheduled Training | ||||||||||||||
| 50 | 01 78 23 | 10 | Operation and Maintenance Data | O&M Database | 1.3 | G | |||||||||||||||
| 51 | 01 78 23 | 10 | Operation and Maintenance Data | Training Plan | 3.1.1 | G | Provide 30 days prior to scheduled Final Inspection | ||||||||||||||
| 52 | 01 78 23 | 10 | Operation and Maintenance Data | Training Content | 3.1.2 | G | Provide 14 days prior to scheduled Training | ||||||||||||||
| 53 | 01 78 23 | 10 | Operation and Maintenance Data | Training Outline | 3.1.3 | G | Provide 14 days prior to scheduled Training | ||||||||||||||
| 54 | 01 78 23 | 11 | Closeout Submittals | Validation of Training Completion | 3.1.6 | G |
&8Submittal Register_v3_03/07/22