24_050 Addend 1.pdf
PDF 1 MB Posted
- Solicitation number
- PE-66799-NONST-2024-000000007
- Issued by
- Fulton County, Georgia
About this file
This document is an Addendum for Invitation to Bid (ITB) Bid #24-050 Autrey Mill Preserve Natural Amphitheater Construction issued by the City of Johns Creek, Georgia. The addendum provides answers to questions asked by prospective bidders, clarifies the scope of work, and includes additional specifications and drawings related to the project. Key details include the construction of a natural amphitheater at the Autrey Mill Nature Preserve, with specifications for the weathered steel roof, wood decking, railings, electrical, and concrete work. The project timeline and completion date are not explicitly stated, but the addendum notes that weathered steel may have a longer lead time that should be considered. Bidders are required to acknowledge receipt of the addendum in their proposal package.
The addendum provides unit pricing information for handling unsuitable soils, but does not disclose the overall project budget. Contractors are responsible for obtaining necessary permits, while the City will handle geotechnical testing and coordination with the landscape architect. The bid is open to all qualified general contractors, and no set-asides or incumbents are mentioned.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum Description
Answer to questions asked in BidNet up until the Q&A deadline
Notice Modifications
Category Modifications
Added Documents[A]
Please review all documents and specifications related to this solicitation.
Notice Information From Value To Value
No entries
Added Categories
No Categories Added
Removed Categories
No Categories Removed
Document Size Uploaded Date Language
Q&A Document 1.pdf [pdf] 11 Kb 02/09/2024 09:13 AM EST English
24-050 - Autrey Mill Nature Preserve Amphitheater Construction- Addendum1.pdf [pdf]
6 Mb 02/09/2024 09:23 AM EST English
24-050 Addendum #1.pdf [pdf] 161 Kb 02/09/2024 09:27 AM EST English
24-050 - Autrey Mill Nature Preserve Amphitheater Constr... Addendum No: 1 (Draft)
02/09/2024 09:28 AM EST Page 1 of 1
Purchasing Division 11360 Lakefield Drive | Johns Creek, GA 30097 | JohnsCreekGA.gov | 678-512-3200 | Fax: 678-512-3244
ADDENDUM #1
Invitation to Bid (ITB)
Bid #24-050 Autrey Mill Preserve Natural Amphitheater Construction
To All Prospective Offerors:
To follow is Addendum Number 1 for the above solicitation.
1. Answers to questions asked in BidNet up until the Q&A deadline (attached)
2. Design Specification document (attached)
All addendums are electronically acknowledged at submission of bid within BidNet. Firms shall include this acknowledgement of receiving ITB 24-050 addendum #1 in your proposal package with your forms and documents.
Firm: ______________________________________
Signature: __________________________________
Date:__________________
Questions & Answers - 1
Project 24-050 - Autrey Mill Nature Preserve Amphitheater Construction
Buying Organization The City of Johns Creek
No Question/Answer Question Date
Q1 Question: Amphitheater Questions
1.What is the budget for this project
2.Is a Geotech survey required for this project?
3. What type of decking is required?
4. Will you require wood roof decking/sheathing under metal roof panels none is specified.
5. Will you provide elevation drawings for the amphitheater structure? What are the heights of posts and the roof slope?
6. Do you have additional specifications for the weathered steel roof decking? Do you have a supplier you have selected from?
7. What are the specifications for electrical?
8. Weathered steel may take over 10 weeks to arrive. Will that affect completion date penalties?
9. There are no landscaping pans in this set of plans. How is that going to be handled?
10. Do you have elevation information for the railings? The drawing does not clearly indicate where railings will be installed
11. Do you have a supplier that the railings are selected from? Do you have a color for the railings?
01/23/2024
No Question/Answer Question Date
Answer: 1.What is the budget for this project?
A. The City of Johns Creek is not releasing the budget at this time. The award will be provided to the lowest and most responsible bid submitted.
2.Is a Geotech survey required for this project?
A. No.
3. What type of decking is required?
A. See Sheet S-2, Addendum #1.
4. Will you require wood roof decking/sheathing under metal roof panels none is specified.
A. Yes, see attached product specifications for roof underlayment and foam closure, to be applied as directed by steel roofing manufacturer’s recommendations.
5. Will you provide elevation drawings for the amphitheater structure? What are the heights of posts and the roof slope?
A. Yes, see Sheets S-2, S-3, C-5.1 and Addendum #1.
6. Do you have additional specifications for the weathered steel roof decking? Do you have a supplier you have selected from?
A. Yes, Western States Metal Roofing, Phoenix, AZ, (877) 787-5467.
7. What are the specifications for electrical?
A. Electrical specifications are shown on Sheet E-3.0, Electrical Specifications.
8. Weathered steel may take over 10 weeks to arrive. Will that affect completion date penalties?
A. No, but alternate suppliers with a shorter lead time should be considered.
9. There are no landscaping plans in this set of plans. How is that going to be handled?
A. Due to the limited nature of the project, there is currently no landscaping in the project.
10. Do you have elevation information for the railings? The drawing does not clearly indicate where railings will be installed.
A. Yes, see Sheets C-5.1 and Addendum #1
11. Do you have a supplier that the railings are selected from? Do you have a color for the railings?
A. Yes, Fabregas Design Services, Athens, GA, (706)296 -8051. All railing posts and caps to be weathered steel, which arrives on site as a black color. All handrail gripping surfaces to be stainless steel. All cabling to be stainless steel. See image in addendum for reference.
Q2 Question: Traffic Control
No work is being done within the pavement of Autrey Mill Road, and all traffic north of the jobsite is local to the park only. Please verify that Traffic Control certifications per page 5 of the Bid Packet is not a project requirement.
Answer: A. Correct.
01/31/2024
Q3 Question: Bid Submission
Bullet point on page 16 of the Bid Packet states that the Prime Contractor is required to submit E-verify affidavits for each subcontractor. Please confirm this is not required in the bid submission, but may be submitted after project award.
Answer: Only the Prime Contractor is to turn in a Everify document included in bid packet at time of bid submission.
01/31/2024
Q4 Question: Asphalt cutting
On C-0.1, a note calls out "Existing Asphalt Drive (to be sawcut & removed)." The arrow for this note points to an area outside the LOD. Please verify this is not in the Scope of Work for this project.
Answer: A. This is not included in the Scope of Work for this project.
01/31/2024
Q5 Question: Utility Work
On C-0.1, a note calls out "Existing SS line located by GIS. Contractor to TV main line..." The arrow for this note points to an area outside the LOD. Please verify this is not in the Scope of Work for this project.
Answer: A. This is not included in the Scope of Work for this project.
01/31/2024
Q6 Question: Tree Clearing
On C-0.1, a note calls for review by landscape architect prior to removal of any trees. Please verify this review by landscape arch is others' responsibility.
Answer: A. Review by landscape architect is others’ responsibility. Contractor to notify Owner’s
Representative when trees are flagged for demo. Owner’s Representative will contact landscape architect to visit site and review/confirm trees for removal. Owner’s Representative will then notify
Contractor to proceed with demolition and removal.
01/31/2024
Q7 Question: Utility Work
On C-2.1, a Site Note call for plastic pipe to be wrapped with location wire & tape. As the Scope OW includes no new storm pipe work. Please verify this is not in SOW for this project.
Answer: A. This is not included in the Scope of Work for this project.
01/31/2024
Q8 Question: Utility Work
On C-2.1, a note calls for "Contractor to field locate existing 12" HDPE and connect to ID Dome 104," however, "ID Dome 104" does not appear in the drawings. Please clarify what is intended here.
Answer: A. This is not included in the Scope of Work for this project.
01/31/2024
Q9 Question: Concrete Work
Please verify that the proposed concrete pad is intended to be placed directly over the underground pipe.
Answer: A. Confirmed.
01/31/2024
Q10 Question: Erosion Control
On C-4.3.1, a tag labeled "CeC2" appears just outside the LOD on the left side. Please clarify what this means. This symbol is not defined in the Erosion Control sheets.
Answer: A. See table in lower right, Sheet C-4.2. Soil Type is Cecil Sandy Loam, 6 to 10 percent slopes, moderately eroded.
01/31/2024
Q11 Question: Alternate Scope
On C-5, the detail for Amphitheater Seating shows seats supported by 6x6 posts with concrete footings.
Are 6x6 posts to be fully-embedded? Are the post footings connected to each other by a concrete beam?
Answer: A. 6X6 posts are to be embedded a minimum of 18”. Post footings are not designed to be connected with a grade beam, but a grade beam would be accepted as a zero-cost equivalent.
01/31/2024
Q12 Question: Stainless Cable Handrail
Please provide drawing showing extents of cable rails and pipe handrails.
Answer: A. See Sheets C-5.1 and Addendum #1
01/31/2024
Q13 Question: Concrete Work
Please verify that the Standard Duty Concrete Paving detail on C-5 is to be used for the concrete landing pad at the base of the stairs.
Answer: A. Verified.
01/31/2024
Q14 Question: Wood Framing
On S-2, the Roof Framing Plan shows 8x16 LSV beams. Please indicate what type of engineered lumber to use hear - LVL, PSL, Paralam, gluelam?
Answer: A. Rough sawn lumber.
01/31/2024
Q15 Question: Electrical Scope
On E-2.0, the Luminaire Schedule lists Fixture type "B" as a pole-mounted light. This fixture does not appear on the plans. Please clarify.
Answer: A. This is not included in the Scope of Work for this project.
01/31/2024
Q16 Question: Electrical Scope
On E-2.0, Note #3 to the Luminaire Schedule refers to a detail for the pole base on the same sheet, but this detail does not appear. Please provide detail if this is required.
Answer: A. This is not included in the Scope of Work for this project.
01/31/2024
Q17 Question: Wood Framing
On S-3, several details show decking, but do not make clear what material is to be used in which location, however section 061519, part 2, of the manual specifies tongue & groove 2x6 and 1x6 decking. Please verify walk surface is 2x6 and roof deck is 1x6.
Answer: A. Verified.
01/31/2024
Q18 Question: Roofing Material
On S-3, detail 11 indicates "24" wide weathered steel deck" with wood screws and neoprene washers.
Please clarify what is meant by "weathered." Is a specification available?
Answer: A. Weathering steel, often referred to by the trademark COR-TEN steel and sometimes written without the hyphen as corten steel, is a group of steel alloys which were developed to eliminate the need for painting, and form a stable rust-like appearance after several years' exposure to weather. See attached Specification Section 05 7000 Decorative Metal.
02/01/2024
Q19 Question: Requirements is a GC license required?
Answer: A: GC license required only if bids are over $100,000
02/05/2024
Q20 Question: Earthwork Question
Does the site balance? If not can we adjust to make site balance to prevent export/Import?
Answer: A. The grading shown is designed to smooth the slope that currently exists on site and create a more uniform sheet flow of runoff. Contractor may adjust the grading to make the site balance, preventing export/import.
02/05/2024
Q21 Question: Unsuitable Soils
Is there any unit prices for unsuitable soils?
Is this project unclassified ( is the contractor responsible for unsuitable soils)?
Answer: A. There are several unit prices noted in Section 01 2200 Unit Prices of the Specifications for unsuitable soils.
02/05/2024
Q22 Question: Alternate 1
Is there a place to add the alternate 1? When you go to place bid it just asks for lump sum.
Answer: When you place a bid, there are two line items. The second line item is marked add alternate-
1.
02/05/2024
Q23 Question: Geo Technical Testing and Permits
Who is responsible for geo-tech and permits?
Answer: A: Geo tech will not be required. The contractor is responsible for all construction related permits.
02/05/2024
Q24 Question: Concrete Work
On S-1, Foundation Plan note #3 specifies that the top of footings is at 12 inches below grade. Section
2/S-3 showing a section of a typical footing and pier indicates the height of the pier varies. In the section, the pier projects above grade approximately 6 inches. Shall we assume all piers are 18 inches from top of footing to top of pier?
Answer: Yes. 18" assumption is fine
02/07/2024
Q25 Question: Survey and Control Points
We normally see published TBM or BM elevations on DWGS, as well as some way to get on the engineers horizontal control; IE boundary information or control points shown in the AUTOCAD DWG file. Some of these projects do show existing structure elevation some do not. So that there will be no
“assumptions” we would like confirmation that the AutoCAD DWGS will provide both horizontal and vertical control points?
Answer: A: Confirmed.
02/07/2024
Q26 Question: More info on LSV Beams
What are the specs on the LSV beams. Can I get more information on the type of beam you are looking for? Same question for the 8x8 beams.
Answer: A: . Yes, see Sheets S-0 and S-2, Addendum #1.
02/07/2024
| Addendum Description |
| Notice Modifications |
| Category Modifications |
| 24-050 Addendum #1.pdf |
| 24-050 Addendum #1.pdf |
| Q&A Document 1 (4) (1).pdf |
| Questions & Answers - 1 |