- Adams County, Asotin County, Benton County, Chelan County, Clallam County, Clark County, Columbia County, Cowlitz County, Ferry County, Franklin County, Garfield County, Grant County, Grays Harbor County, Island County, Jefferson County, King County, Kitsap County, Kittitas County, Klickitat County, Lewis County, Lincoln County, Mason County, Okanogan County, Pacific County, Pend Oreille County, Pierce County, San Juan County, Skagit County, Skamania County, Snohomish County, Spokane County, Stevens County, Thurston County, Wahkiakum County, Walla Walla County, Whatcom County, Whitman County, Yakima County, Asotin City, Clarkston City, Clarkston Heights-Vineland CDP, West Clarkston-Highland CDP, Benton City, Chelan City, Chelan Falls CDP, Clallam Bay CDP, Lewisville CDP, Rock Island City, Pacific Beach CDP, Whidbey Island Station CDP, Mercer Island City, Pacific City, Bainbridge Island City, Kingston CDP, Kitsap Lake CDP, Kittitas City, Klickitat CDP, Okanogan City, Anderson Island CDP, Fort Lewis CDP, Fox Island CDP, Herron Island CDP, Ketron Island CDP, North Fort Lewis CDP, Raft Island CDP, Stevenson City, Hat Island CDP, Lake Stevens City, Snohomish City, Spokane City, Spokane Valley City, Puget Island CDP, Garfield Town, Yakima City, Washington
About this file
This document is an Exhibit I Road Cost Bid Form for RFQ 24-00018 issued by the Washington Department of Fish and Wildlife (WDFW) for a Harvesting Services Contract. The contract seeks responses from harvesters, logging firms, and equipment operators who have been pre-qualified for the Washington Department of Natural Resources' (DNR) harvester bidding pool. The contract is for the harvesting and delivery of approximately 9,040 tons of timber in one unit on the Scatter Creek Wildlife Area in Thurston County, Washington. The bid form includes line items for various road construction and maintenance activities, including pre-haul and post-haul maintenance, new road construction, light abandonment, and extreme clean-up. Bidders are required to provide unit prices for each line item and calculate a total road cost proposal.
The contract opportunity is open to businesses and individuals across multiple counties in Washington state. Pricing for the road work is required to be submitted on the provided bid form. There are no set-asides or incumbent information provided. Funding for the contract will come from the state of Washington, but specific funding sources and amounts are not disclosed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 24-00018 Exhibit D Harvester Sample Contract.docx | DOCX document | |
| 24-00018 Exhibit G ARRF Rates.pdf | ||
| Exhibit B Bidder Profile 24-00018.docx | DOCX document | |
| 24-00018 Harvester_Performance_Bond.docx | DOCX document | |
| Exhibit C part 2.pdf | ||
| 24-00018 Exhibit E Road Summary.docx | DOCX document | |
| Harvester RFQ 24-00018 SCWAORPRNU.pdf | ||
| Exhibit A cert assurances 24-00018.docx | DOCX document | |
| 24-00018 Exhibit H Harvester Bid Form.docx | DOCX document | |
| Exhibit C Timber Sale Maps.pdf- 24-00018.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT I
RFQ 24-00018
STATE OF WASHINGTON
DEPARTMENT OF FISH AND WILDLIFE (WDFW)
HARVESTING SERVICES CONTRACT
ROAD COST BID FORM
(Print Company Name)
| _______________________________ | _______________________________ | ||
| (Street Address) | (Business Telephone Number) | ||
| _______________________________ | _______________________________ | ||
| (City, State and Zip Code) | (email address) |
Instructions:
1. Enter Contractor’s per station bid rates for each biddable item for road work described in the Road Summary Narrative (Exhibit D).
2. Required items are fixed to the stations listed in the table and the total should reflect the total cost for completing all stations for that item, including materials.
3. Review Road Summary Narrative (Exhibit D) for plans/details on bridge install, complex culvert install, etc..
4. Add all item totals and enter the sum in the Total Road Cost Proposal below the table.
| Road |
| Type |
| Stations |
| Total Stations |
| Price Per Station |
| Total Price |
| Sheetsly Road |
| Pre-Haul Maintenance (Including Rock Lift – See Road Summary) |
| 0+00 ~26+30 |
| 26+30 |
| Sheetsly Road |
| Post-Haul Maintenance |
| 0+00 ~26+30 |
| 26+30 |
| Road 1A |
| New Construction |
| 0+00 ~ 16+45 |
| 16+45 |
| Road 2A |
| New Construction |
| 0+00 ~ 15+02 |
| 15+02 |
| Road 1A |
| Light Abandonment |
| 0+00 ~ 16+45 |
| 16+45 |
| Road 2A |
| Light Abandonment |
| 0+00 ~ 15+02 |
| 15+02 |
1 Station=100’ *Optional Bid Item **Required Bid Item Total Road Proposal Cost = $_________________________
| Extreme Clean-up |
| Type |
| Acreage |
| Price Per Acre |
| Total Price |
Unit 1
Remove All Debris ≥2 inches in Diameter (See Schedule A of Harvester Contract for detail)
| Road Cost Bid Form | Scatter Creek Wildlife Area Oak Release and |
| Prairie Restoration – North Unit | September 16th, 2024 |
File details come from the government source that posted it. Updated .