23Q0005 RFQ.docx
DOCX document 63 KB Posted
- Attached to
- CUTLER 480 SUB SERVICE Federal contract opportunity
- Solicitation number
- N7027223Q0005
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 480sublayout.jpg | JPG image | |
| typical AK-2-25nameplate.jpg | JPG image | |
| Station service (SE-5-1) disconnector cabinet.jpg | JPG image | |
| Cutler PP one-line 4-2014.pdf | ||
| Bustienameplate.jpg | JPG image | |
| typical AK-2-50 nameplate.jpg | JPG image |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Naval Computer and Telecommunications Area Master Station, Atlantic Combined Synopsis and Solicitation Notice Information
1. This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in FAR Subpart 12.6, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; proposals are being requested and a written solicitation will not be issued.
2. The solicitation number is N7027223Q0005 and is being issued as a Request for Quotes (RFQ).
3. The solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Circular (FAC) 2023-01 Effective 30 Dec 2022 and DFARS DPN 20221230 (Effective 30 December 2022) Edition located on https://www.acquisition.gov
4. The associated NAICS code is 238210 and the associated PSC code is J029 for this procurement:
|_| is not being set-aside for small businesses.
|X| is being set-aside for small business. The small business size standard is $16.5 M
5. The Statement of Work (SOW) below lists the required services to be performed:
Price submission shall be itemized to identify all applicable rates, fees, hours, and material costs.
PRICING STRUCTURE:
| ITEM |
| QTY |
| PRICE |
| EXT PRICE |
AIRFARE
LODGING
M&I
TRANSPORTATION
SUBTOTAL
LABOR
TRAVEL
OT/HOLIDAY
MATERIAL
SUBTOTAL
GRAND TOTAL
NCTS HR DET CUTLER, ME
480 SUBSTATION
STATEMENT OF WORK
1.0 BACKGROUND
The Naval Computer and Telecommunications Station Hampton Roads Detachment (NCTS HR DET) Cutler, Maine has a requirement for troubleshooting and repair of an existing 480 VAC substation.
The 480 VAC substation is located in the power plant (B103). The substation consists of 2 each 4160:480 VAC transformers, 2 SE-5-2 interrupters, 4 GE AK-2-50 breakers, and 8 GE AK-2-25 breakers. This substation supports all 480 VAC equipment in the power plant. Presently, one of the SE-5-2 interrupters is stuck in the closed position. The conditions of the AK-2-25s and AK-2-50s are known to be dirty and occasionally reluctant to close properly. Of the eight AK-2-25 breakers, one is spare and not installed in the gear. The vendor shall first inspect and repair this breaker to allow its use as a known-to-be good spare during the rest of the project. The next operation will be to free and verify operation of the stuck SE-5-2 interrupter prior to any other work. There will be a limited period for an outage to support this second operation, so the vendor will need to develop a plan and coordinate with plant personnel to ensure that the work is completed in the allotted time. Once that interrupter is operational, the AK-2-50 tie breaker can be opened and one side of the split 480 bus can be powered down and allow work on the breakers on that side. It is required for the vendor to pull breakers for inspection, cleaning and repair one at a time and to install the spare breaker, as needed, in place to power critical requirements while the extracted breaker undergoes repair. Short coordinated 480 outages may be granted to support this SOW. All of the breakers in the substation, the bus-work, and contact assemblies are to be inspected, cleaned and repaired on-site. Off-site repairs or replacement are undesirable due to the nature of our mission support and will need to be negotiated on a case by case basis.
2.0 SCOPE OF WORK
The purpose of this contract is to execute repair and refurbishment activities to return this sub-station to full operation, allowing it to supply the power that ensures fully operational submarine telecommunications and readiness. The vendor shall supply troubleshooting, consulting and repair services to NCTS HR DET Cutler, Maine. A pre-bid site visit is required, due to the unique nature of the application. The vendor is required to supply all parts and materials. OEM parts are required when available, and non-OEM parts will be used only after coordination with the technical point of contact. The vendors technical staff must have verified hands-on experience with refurbishment of GE AK series breakers and have access to OEM parts. No government furnished equipment or materials will be provided. The vendor will have full access to applicable service literature in the possession of NCTS HR Det Cutler after award. The Navy does not warrantee that the existing literature is complete or accurate. Unexpected damage or repairs beyond the scope of work are required to be authorized by the contracting officer. Power outage requests must be coordinated with Cutler power plant staff, and will likely be available only on Mondays. All outages will have a not less than 30 minute recall time attached. All work shall be performed during normal business hours, typically 0730-1600 M-F.
The 480 substation includes overcurrent and differential relays for the Cat AUX generator, and various digi-trip devices on the AK series breakers. All of these settings shall be recorded, the devices tested for operation, and the data presented at the end of the project as part of a complete “As Left” document that outlines all work carried out under this project.
The metric for a successful repair for the 480 VAC sub-station will be demonstration of successful opening and closing of the active breakers in the 480 substation. High potential testing is not allowed.
3.0 PERSONNEL QUALIFICATIONS
3.1 The vendor shall be certified or qualified, and have demonstrable experience in installation, maintenance and repair of medium voltage (up to 4160 VAC) switch gear and particularly the GE AK series breakers and SE-5-2 interrupters.
4.0 CONTRACTOR RQUIREMENTS / SPECIFIC TASKS
4.1 The vendor shall provide complete contact information to include full names, telephone number, and e-mail address for all personnel assigned to work this contract. Vendor personnel assigned to hands-on breaker repair must provide a CV or resume detailing the experience described in section 3.1.
4.2 The vendor shall supply all labor, travel and expenses.
4.3 The vendor shall complete a pre-bid visit to survey the subject equipment.
4.4 The vendor shall supply the power plant with a complete “as-left” document at the end of the project that details all work carried out and all recorded settings from the various protective relays. This document should include drawings and text covering all work under the project.
5.0 EMERGENT AND UNFORSEEN REPAIRS
Emergent and unforeseen repairs are required to be authorized by the contracting officer.
6.0 ADMINISTRATION
6.1 DELIVERY LOCATION
NCTS HR DET Cutler 175 Ridge Road Cutler, Maine 04626
6.2 HOURS OF OPERATION
8:00AM – 4:00PM
6.5 PERIOD OF PERFORMANCE
Estimated period of performance: 01May2023 to 04June2023
6.6 METHOD OF PAYMENT
Payment for this contract shall be made via Wide Area Workflow (WAWF). The government reserves the right to change this method only by a contract modification if necessary.
7.0 SECURITY AND BASE ENTRY
7.1 Cutler base security requires 100% ID check at all times. The vendor shall contact the GTPOC within 3 days of contract award and will be provided with the current requirements for base access. DET Cutler is a tenant command. After entering the base, all contractor personnel must go directly to the B100 admin office and receive a temporary pass to enter DET Cutler space
7.2 All vendor equipment, personnel and vehicles are subject to inspection and search by US government security officials (or designated representatives) upon entry to any government owned and/or operated installations and facilities.
7.3 Vendor personnel shall comply with all local base/installation security procedures required to gain access to US Government facilities and other assets (as necessary).
7.4 If directed by US Government security officials (or designated representatives), the vendor shall remove (and replace as necessary) vendor personnel and/or its representatives considered a security risk at no additional cost to the government.
8.0 SECURITY CLEARANCE
The vendor is not required to have a security clearance to perform any of the services listed within this contract.
9.0 ACCESS TO GOVERNMENT FACILITIES
9.1 Government facilities will be made available to the contractor. Scheduling and access to facilities will be coordinated through the GTPOC.
9.2 Deleted.
10.0 AUTHORIZED CHANGES BY THE CONTRACTING OFFICER
10.2 The vendor shall not comply with any order, direction or request of government personnel unless it is issued in writing and signed by the Contracting Officer, or is pursuant to specific authority included as part of this contract.
10.2 The Contracting Officer is the only person authorized to approve changes in any of the requirements of this contract and notwithstanding provisions contained elsewhere in this contract, the said authority remains solely the Contracting Officer’s.
WAGE DETERMINATION
The following wage determination, in accordance with the Service Contract Labor Standards, as amended, is hereby incorporated by reference into the contract and compliance with the same as mandatory: WD 15-4007 (Rev.-22) dtd 12/27/2022
Note for shipping:
The Government requests that shipping costs be incorporated into the price of each item rather than a separate line for total shipping costs. The Government will spread the shipping costs across all lines upon award if quoted as a separate line item.
TOTAL: ___________
Estimated POP if Different than Requested Date____________
Provide the following information with your quote plus any additional information which is applicable to the materials list. Any items that are not applicable please designate with N/A.
Provide any contract numbers for purchase orders in which you have previously performed this work: ______________________________________________.
Firm Fixed Price Total (includes all charges): $__________________________.
Company Name: __________________
CAGE Code: ____________________
DUNS Number: ____________________
Tax Identification Number: _____________________
6. The government intends on awarding a Firm-Fixed Price contract on this requirement.
7. The required delivery and acceptance date N/A
8. The provision at FAR 52.212-1, Instructions to Offerors – Commercial applies to this acquisition and is incorporated by reference. The provision is amended as follows:
52.212-1 (ADDENDUM) ADDITIONAL INSTRUCTIONS TO OFFERORS--COMMERCIAL ITEMS
a. Any inconsistency between FAR Provision 52.212-1 and the Addendum to FAR 52.212-1 shall be solved by giving precedence to the Addendum to FAR 52.212-1.
b. After receipt of quotes the Government may, with or without notice, negotiate with and, if desired, seek quote revisions from as many or as few quoters as it, in its discretion, deems appropriate.
c. The term “offeror” or “offer” as used in FAR 52.212-1 shall be understood to mean “quoter” and “quote,” respectively. Further, the term “award” shall be understood to describe the Government’s issuance of an order.
d. The Government will consider all quotes that are timely received and may consider late quotes. Failure of a quote to address any items required in the submission package may make a quote unacceptable.
e. Paragraph (b) of FAR Provision 52.212-1, Submission of Offers, is amended as follows:
| In addition to the quote submission requirements stated in FAR provision 52.212-1, quoters shall provide the following, as part of the quote submission package, no later than the required time and date for quote submission: |
| Responsible sources shall provide the following: |
1. Price quote which identifies the requested item(s), unit price inclusive of shipping (if any), and extended price
2. Total Firm Fixed price
3. Any Discount Terms
4. Estimated time of delivery
5. Technical Submission Requirements
a. For Parts/Supply buy, the quote shall contain a description including part number and title for each item listed in the solicitation to allow the Government to verify that the quoted parts match the requirements listed in the requirements schedule.
b. For a Services buy, the quote shall contain all pre-award submission/certification requirements as defined in the statement of work (SOW).
6. Responses to the solicitation are due 1400 pm est on February 24, 2022. Quotes may be e-mailed to Kathryn Santos at kathryn.l.santos.civ@us.navy.mil. To be considered timely, an E-mail quote must be received in its entirety in the designated E-mail inbox by the due date and time for quote submission. Quotes received after that time will be considered at the Government’s sole discretion. Please reference the solicitation number on your quote.
| Primary Point of Contact: Kathryn Santos kathryn.l.santos.civ@us.navy.mil |
| Secondary Point of Contact: Robert Joas robert.p.joas.civ@us.navy.mil |
| The Government will consider all quotes that are timely received and may consider late quotes in accordance with 52.212-1. Failure of a quote to address any items listed in the attached submission package may make a quote unacceptable. |
9. Provision 52.212-2 Evaluation—Commercial Items (Oct 2014) applies to this acquisition.
(a) The Government may award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:
(i) technical capability of the item offered to meet the Government requirement;
(ii) price;
Award shall be made to the lowest priced technically acceptable offeror in LPTA solicitations.
To be considered a technically acceptable solution for a parts procurement, the quoted parts shall meet the solicitation requirements including required parts, delivery dates, and terms and conditions stated in the solicitation. To be considered a technically acceptable solution for a service, the quoted service shall meet the solicitation requirements including terms and conditions stated in the solicitation. The quote shall state that all aspects of the technical requirement, including required delivery date and part numbers, can be met.
If utilized, a past performance evaluation will be conducted in accordance with FAR 13.106-2(b)(3)(ii)(C). The Government intends to utilize the Government Wide Past Performance Information Retrieval System (PPIRS) for past performance evaluations as a basis for anticipating successful/unsuccessful performance on this required effort. To be considered acceptable for past performance, a search of the PPIRS must reveal no negative past performance information for the recent and relevant records. In the event there are no recent and/or relevant PPIRS records, the quoter may submit information on recent and relevant subcontracts and/or commercial contracts. If no recent and relevant contracts are available in PPIRS or submitted by the offeror, the quoter’s past performance record shall be considered “unknown.” In the context of acceptable or unacceptable, “unknown” past performance shall be considered “acceptable.” To be considered recent, the effort must either still be in progress or have been completed within the previous three (3) years from date of this draft award notice. To be considered relevant the record should be similar in terms of complexity, scope, and magnitude. “Scope” is defined as experience in areas defined in the SOW. “Magnitude” is defined as the measure of similarity of the volume, dollar value, and/or duration of work actually performed under the quoter’s submitted contracts to the SOW. At the quoter’s discretion, additional past performance information may be submitted with the quote as a supplement to PPIRS. If furnished, this submission will be evaluated in accordance with the procedures described above.
The Government will evaluate quoted pricing for reasonableness utilizing techniques described in FAR 13.106-3.
(b) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror by the Government within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer’s specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.
10. All Offerors must include a completed copy of FAR 52.212-3, Offeror Representations and Certifications – Commercial Items with its offer.
11. Clause 52.212-4 Contract Terms and Conditions – Commercial items, applies to this acquisition.
Offers/quotes submitted in response to this solicitation shall not contain nor be subject to the offeror's/vendor's standard commercial terms and conditions. Any offer/quote submitted in response to this solicitation which includes the offeror's/vendor's standard commercial terms and conditions may be considered a material defect and may be rejected as being non-responsive to the solicitation.
12. Clause 52.212-5, Contract Terms and Conditions Required to Implement Statutes or Executive Orders – Commercial Items, applies to this acquisition along with the following FAR Clauses cited in the clause are applicable.
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(2) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015)
(3) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(4) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Public Laws 108-77, 108-78 (19 U.S.C. 3805 note)).
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the contracting officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
___ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (Sept 2006), with Alternate I (Oct 1995) (41 U.S.C. 4704 and 10 U.S.C. 2402).
___ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Oct 2015) (41 U.S.C. 3509).
___ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (Jun 2010) (Section 1553 of Pub L. 111-5) (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009).
_XX_ (4) 52.204-10, Reporting Executive compensation and First-Tier Subcontract Awards (Oct 2016) (Pub. L. 109-282) (31 U.S.C. 6101 note).
___ (5) [Reserved] ___ (6) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).
___ (7) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).
_XX_ (8) 52.209-6, Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Oct 2015) (31 U.S.C. 6101 note).
___ (9) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (Jul 2013) (41 U.S.C. 2313).
___ (10) [Reserved] ___ (11) (i) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (Nov 2011) (15 U.S.C. 657a).
___ (ii) Alternate I (Nov 2011) of 52.219-3.
___ (12) (i) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Oct 2014) (if the offeror elects to waive the preference, it shall so indicate in its offer)(15 U.S.C. 657a).
___ (ii) Alternate I (Jan 2011) of 52.219-4.
___ (13) [Reserved] _XX_ (14) (i) 52.219-6, Notice of Total Small Business Aside (Nov 2011) (15 U.S.C. 644).
___ (ii) Alternate I (Nov 2011).
___ (iii) Alternate II (Nov 2011).
___ (15) (i) 52.219-7, Notice of Partial Small Business Set-Aside (June 2003) (15 U.S.C. 644).
___ (ii) Alternate I (Oct 1995) of 52.219-7.
___ (iii) Alternate II (Mar 2004) of 52.219-7.
___ (16) 52.219-8, Utilization of Small Business Concerns (Nov 2016) (15 U.S.C. 637(d)(2) and (3)).
___ (17) (i) 52.219-9, Small Business Subcontracting Plan (Jan 2017) (15 U.S.C. 637 (d)(4)).
___ (ii) Alternate I (Nov 2016) of 52.219-9.
___ (iii) Alternate II (Nov 2016) of 52.219-9.
___ (iv) Alternate III (Nov 2016) of 52.219-9.
___ (v) Alternate IV (Nov 2016) of 52.219-9.
___ (18) 52.219-13, Notice of Set-Aside of Orders (Nov 2011) (15 U.S.C. 644(r)).
___ (19) 52.219-14, Limitations on Subcontracting (Jan 2017) (15 U.S.C. 637(a)(14)).
___ (20) 52.219-16, Liquidated Damages—Subcontracting Plan (Jan 1999) (15 U.S.C. 637(d)(4)(F)(i)).
___ (21) 52.219-27, Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (Nov 2011) (15 U.S.C. 657f).
_XX_ (22) 52.219-28, Post Award Small Business Program Rerepresentation (Jul 2013) (15 U.S.C. 632(a)(2)).
___ (23) 52.219-29, Notice of Set-Aside for, or Sole Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns (Dec 2015) (15 U.S.C. 637(m)).
___ (24) 52.219-30, Notice of Set-Aside for, or Sole Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (Dec 2015) (15 U.S.C. 637(m)).
_XX_ (25) 52.222-3, Convict Labor (June 2003) (E.O. 11755).
_XX_ (26) 52.222-19, Child Labor—Cooperation with Authorities and Remedies (Oct 2016) (E.O. 13126).
_XX_ (27) 52.222-21, Prohibition of Segregated Facilities (Apr 2015).
_XX_ (28) 52.222-26, Equal Opportunity (Sep 2016) (E.O. 11246).
___ (29) 52.222-35, Equal Opportunity for Veterans (Oct 2015) (38 U.S.C. 4212).
_XX_ (30) 52.222-36, Equal Opportunity for Workers with Disabilities (Jul 2014) (29 U.S.C. 793).
___ (31) 52.222-37, Employment Reports on Veterans (Feb 2016) (38 U.S.C. 4212).
___ (32) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496).
_XX_ (33) (i) 52.222-50, Combating Trafficking in Persons (Mar 2015) (22 U.S.C. chapter 78 and E.O. 13627).
___ (ii) Alternate I (Mar 2015) of 52.222-50, (22 U.S.C. chapter 78 and E.O. 13627).
___ (34) 52.222-54, Employment Eligibility Verification (Oct 2015). (E. O. 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial items as prescribed in 22.1803.)
___ (35) 52.222-59, Compliance with Labor Laws (Executive Order 13673) (Oct 2016). (Applies at $50 million for solicitations and resultant contracts issued from October 25, 2016 through April 24, 2017; applies at $500,000 for solicitations and resultant contracts issued after April 24, 2017).
Note to paragraph (b)(35): By a court order issued on October 24, 2016, 52.222-59 is enjoined indefinitely as of the date of the order. The enjoined paragraph will become effective immediately if the court terminates the injunction. At that time, DoD, GSA, and NASA will publish a document in the Federal Register advising the public of the termination of the injunction.
___ (36) 52.222-60, Paycheck Transparency (Executive Order 13673) (Oct 2016).
___ (37) (i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008) (42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
___ (ii) Alternate I (May 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
___ (38) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Jun 2016) (E.O.13693).
___ (39) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (Jun 2016) (E.O. 13693).
___ (40) (i) 52.223-13, Acquisition of EPEAT® -Registered Imaging Equipment (Jun 2014) (E.O.s 13423 and 13514 ___ (ii) Alternate I (Oct 2015) of 52.223-13.
___ (41) (i) 52.223-14, Acquisition of EPEAT® -Registered Television (Jun 2014) (E.O.s 13423 and 13514).
___ (ii) Alternate I (Jun 2014) of 52.223-14.
___ (42) 52.223-15, Energy Efficiency in Energy-Consuming Products (Dec 2007) (42 U.S.C. 8259b).
___ (43) (i) 52.223-16, Acquisition of EPEAT® -Registered Personal Computer Products (Oct 2015) (E.O.s 13423 and 13514).
___ (ii) Alternate I (Jun 2014) of 52.223-16.
_XX_ (44) 52.223-18, Encouraging Contractor Policies to Ban Text Messaging while Driving (Aug 2011) (E.O. 13513).
___ (45) 52.223-20, Aerosols (Jun 2016) (E.O. 13693).
___ (46) 52.223-21, Foams (Jun 2016) (E.O. 13696).
___ (47) (i) 52.224-3, Privacy Training (Jan 2017) (5 U.S.C. 552a).
___ (ii) Alternate I (Jan 2017) of 52.224-3.
___ (48) 52.225-1, Buy American--Supplies (May 2014) (41 U.S.C. chapter 83).
___ (49) (i) 52.225-3, Buy American--Free Trade Agreements--Israeli Trade Act (May 2014) (41 U.S.C. chapter 83, 19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, Pub. L. 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109-283, 110-138, 112-41, 112-42, and 112-43).
___ (ii) Alternate I (May 2014) of 52.225-3.
___ (iii) Alternate II (May 2014) of 52.225-3.
___ (iv) Alternate III (May 2014) of 52.225-3.
___ (50) 52.225-5, Trade Agreements (Oct 2016) (19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).
_XX_ (51) 52.225-13, Restrictions on Certain Foreign Purchases (Jun 2008) (E.O.’s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).
___ (52) 52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. 2302 Note).
___ (53) 52.226-4, Notice of Disaster or Emergency Area Set-Aside (Nov 2007) (42 U.S.C. 5150).
___ (54) 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (Nov 2007) (42 U.S.C. 5150).
___ (55) 52.232-29, Terms for Financing of Purchases of Commercial Items (Feb 2002) (41 U.S.C. 4505), 10 U.S.C. 2307(f)).
___ (56) 52.232-30, Installment Payments for Commercial Items (Jan 2017) (41 U.S.C. 4505, 10 U.S.C. 2307(f)).
_XX_ (57) 52.232-33, Payment by Electronic Funds Transfer— System for Award Management (Jul 2013) (31 U.S.C. 3332).
___ (58) 52.232-34, Payment by Electronic Funds Transfer—Other Than System for Award Management (Jul 2013) (31 U.S.C. 3332).
___ (59) 52.232-36, Payment by Third Party (May 2014) (31 U.S.C. 3332).
___ (60) 52.239-1, Privacy or Security Safeguards (Aug 1996) (5 U.S.C. 552a).
___ (61) 52.242-5, Payments to Small Business Subcontractors (Jan 2017) (15 U.S.C. 637(d)(12)).
___ (62) (i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Feb 2006) (46 U.S.C. Appx 1241(b) and 10 U.S.C. 2631).
___ (ii) Alternate I (Apr 2003) of 52.247-64.
(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or executive orders applicable to acquisitions of commercial items:
___ (1) 52.222-17, Nondisplacement of Qualified Workers (May 2014) (E.O. 13495) _XX_ (2) 52.222-41, Service Contract Labor Standards (May 2014) (41 U.S.C. chapter 67.).
_XX_ (3) 52.222-42, Statement of Equivalent Rates for Federal Hires (May 2014) (29 U.S.C. 206 and 41 U.S.C. chapter 67).
___ (4) 52.222-43, Fair Labor Standards Act and Service Contract Labor Standards -- Price Adjustment (Multiple Year and Option Contracts) (May 2014) (29 U.S.C.206 and 41 U.S.C. chapter 67).
___ (5) 52.222-44, Fair Labor Standards Act and Service Contract Labor Standards -- Price Adjustment (May 2014) (29 U.S.C. 206 and 41 U.S.C. chapter 67).
___ (6) 52.222-51, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Requirements (May 2014) (41 U.S.C. chapter 67).
___ (7) 52.222-53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services--Requirements (May 2014) (41 U.S.C. chapter 67).
_XX_ (8) 52.222-55, Minimum Wages Under Executive Order 13658 (Dec 2015) (E.O. 13658).
_XX_ (9) 52.222-62, Paid Sick Leave Under Executive Order 13706 (JAN 2017) (E.O. 13706).
___ (10) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations. (May 2014) (42 U.S.C. 1792).
___ (11) 52.237-11, Accepting and Dispensing of $1 Coin (Sep 2008) (31 U.S.C. 5112(p)(1)).
(d) Comptroller General Examination of Record The Contractor shall comply with the provisions of this paragraph (d) if this contract was awarded using other than sealed bid, is in excess of the simplified acquisition threshold, and does not contain the clause at 52.215-2, Audit and Records -- Negotiation.
(1) The Comptroller General of the United States, or an authorized representative of the Comptroller General, shall have access to and right to examine any of the Contractor’s directly pertinent records involving transactions related to this contract.
(2) The Contractor shall make available at its offices at all reasonable times the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR Subpart 4.7, Contractor Records Retention, of the other clauses of this contract. If this contract is completely or partially terminated, the records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement. Records relating to appeals under the disputes clause or to litigation or the settlement of claims arising under or relating to this contract shall be made available until such appeals, litigation, or claims are finally resolved.
(3) As used in this clause, records include books, documents, accounting procedures and practices, and other data, regardless of type and regardless of form. This does not require the Contractor to create or maintain any record that the Contractor does not maintain in the ordinary course of business or pursuant to a provision of law.
(e)
(1) Notwithstanding the requirements of the clauses in paragraphs (a), (b), (c) and (d) of this clause, the Contractor is not required to flow down any FAR clause, other than those in this paragraph (e)(1) in a subcontract for commercial items. Unless otherwise indicated below, the extent of the flow down shall be as required by the clause—
(i) 52.203-13, Contractor Code of Business Ethics and Conduct (Oct 2015) (41 U.S.C. 3509).
(ii) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(iii) 52.219-8, Utilization of Small Business Concerns (Nov 2016) (15 U.S.C. 637(d)(2) and (3)), in all subcontracts that offer further subcontracting opportunities. If the subcontract (except subcontracts to small business concerns) exceeds $700,000 ($1.5 million for construction of any public facility), the subcontractor must include 52.219-8 in lower tier subcontracts that offer subcontracting opportunities.
(iv) 52.222-17, Nondisplacement of Qualified Workers (May 2014) (E.O. 13495). Flow down required in accordance with paragraph (1) of FAR clause 52.222-17.
(v) 52.222-21, Prohibition of Segregated Facilities (Apr 2015).
(vi) 52.222-26, Equal Opportunity (Sep 2016) (E.O. 11246).
(vii) 52.222-35, Equal Opportunity for Veterans (Oct 2015) (38 U.S.C. 4212).
(viii) 52.222-36, Equal Opportunity for Workers with Disabilities (Jul 2014) (29 U.S.C. 793).
(ix) 52.222-37, Employment Reports on Veterans (Feb 2016) (38 U.S.C. 4212).
(x) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496). Flow down required in accordance with paragraph (f) of FAR clause 52.222-40.
(xi) 52.222-41, Service Contract Labor Standards (May 2014), (41 U.S.C. chapter 67).
(xii) (A) 52.222-50, Combating Trafficking in Persons (Mar 2015) (22 U.S.C. chapter 78 and E.O. 13627).
(B) Alternate I (Mar 2015) of 52.222-50 (22 U.S.C. chapter 78 E.O. 13627).
(xiii) 52.222-51, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Requirements (May 2014) (41 U.S.C. chapter 67.)
(xiv) 52.222-53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services--Requirements (May 2014) (41 U.S.C. chapter 67)
(xv) 52.222-54, Employment Eligibility Verification (Oct 2015) (E. O. 12989).
(xvi) 52.222-55, Minimum Wages Under Executive Order 13658 (Dec 2015).
(xvii) 52.222-59, Compliance with Labor Laws (Executive Order 13673) (Oct 2016) (Applies at $50 million for solicitations and resultant contracts issued from October 25, 2016 through April 24, 2017; applies at $500,000 for solicitations and resultant contracts issued after April 24, 2017).
Note to paragraph (e)(1)(xvii): By a court order issued on October 24, 2016, 52.222-59 is enjoined indefinitely as of the date of the order. The enjoined paragraph will become effective immediately if the court terminates the injunction. At that time, DoD, GSA, and NASA will publish a document in the Federal Register advising the public of the termination of the injunction.
(xviii) 52.222-60, Paycheck Transparency (Executive Order 13673) (Oct 2016).
(xix) 52.222-62, Paid sick Leave Under Executive Order 13706 (JAN 2017) (E.O. 13706).
(xx) (A) 52.224-3, Privacy Training (Jan 2017) (5 U.S.C. 552a).
(B) Alternate I (Jan 2017) of 52.224-3.
(xxi) 52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. 2302 Note).
(xxii) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations. (May 2014) (42 U.S.C. 1792). Flow down required in accordance with paragraph (e) of FAR clause 52.226-6.
(xxiii) 52.247-64, Preference for Privately-Owned U.S. Flag Commercial Vessels (Feb 2006) (46 U.S.C. Appx 1241(b) and 10 U.S.C. 2631). Flow down required in accordance with paragraph (d) of FAR clause 52.247-64.
(2) While not required, the Contractor may include in its subcontracts for commercial items a minimal number of additional clauses necessary to satisfy its contractual obligations.
(End of Clause) Alternate I (Feb 2000). As prescribed in 12.301(b)(4)(i), delete paragraph (d) from the basic clause, redesignate paragraph (e) as paragraph (d), and revise the reference to “paragraphs (a), (b), (c), or (d) of this clause” in the redesignated paragraph (d) to read “paragraphs (a), (b), and (c) of this clause”.
Alternate II (JAN 2017). As prescribed in 12.301(b)(4)(ii), substitute the following paragraphs (d)(1) and (e)(1) for paragraphs (d)(1) and (e)(1) of the basic clause as follows:
(d)
(1) The Comptroller General of the United States, an appropriate Inspector General appointed under section 3 or 8G of the Inspector General Act of 1978 (5 U.S.C. App.), or an authorized representative of either of the foregoing officials shall have access to and right to—
(i) Examine any of the Contractor’s or any subcontractors’ records that pertain to, and involve transactions relating to, this contract; and
(ii) Interview any officer or employee regarding such transactions.
(e)
(1) Notwithstanding the requirements of the clauses in paragraphs (a), (b), and (c), of this clause, the Contractor is not required to flow down any FAR clause in a subcontract for commercial items, other than—
(i) Paragraph (d) of this clause. This paragraph flows down to all subcontracts, except the authority of the Inspector General under paragraph (d)(1)(ii) does not flow down; and
(ii) Those clauses listed in this paragraph (e)(1). Unless otherwise indicated below, the extent of the flow down shall be as required by the clause—
(A) 52.203–13, Contractor Code of Business Ethics and Conduct (Oct 2015) (41 U.S.C. 3509).
(B) 52.203-15, Whistleblower Protections Under the American Recovery and Reinvestment Act of 2009 (Jun 2010) (Section 1553 of Pub. L. 111-5).
(C) 52.219–8, Utilization of Small Business Concerns (Nov 2016) (15 U.S.C. 637(d)(2) and (3)), in all subcontracts that offer further subcontracting opportunities. If the subcontract (except subcontracts to small business concerns) exceeds $700,000 ($1.5 million for construction of any public facility), the subcontractor must include 52.219-8 in lower tier subcontracts that offer subcontracting opportunities.
(D) 52.222-21, Prohibition of Segregated Facilities (Apr 2015).
(E) 52.222–26, Equal Opportunity (Sep 2016) (E.O. 11246).
(F) 52.222–35, Equal Opportunity for Veterans (Oct 2015) (38 U.S.C. 4212).
(G) 52.222–36, Equal Opportunity for Workers with Disabilities (Jul 2014) (29 U.S.C. 793).
(H) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496). Flow down required in accordance with paragraph (f) of FAR clause 52.222-40.
(I) 52.222–41, Service Contract Labor Standards (May 2014) (41 U.S.C. chapter 67).
(J) ____ (1) 52.222-50, Combating Trafficking in Persons (Mar 2015) (22 U.S.C. chapter 78 and E.O. 13627).
___ (2) Alternate I (Mar 2015) of 52.222-50 (22 U.S.C. chapter 78 E.O. 13627).
(K) 52.222–51, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Requirements (May 2014) (41 U.S.C. chapter 67).
(L) 52.222–53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services--Requirements (May 2014) (41 U.S.C. chapter 67).
(M) 52.222–54, Employment Eligibility Verification (Oct 2015) (Executive Order 12989).
(N) 52.222-55, Minimum Wages Under Executive Order 13658 (Dec 2015).
(O) 52.222-59, Compliance with Labor Laws (Executive Order 13673), (Oct 2016).
Note to paragraph (e)(1)(ii)(O): By a court order issued on October 24, 2016, 52.222-59 is enjoined indefinitely as of the date of the order. The enjoined paragraph will become effective immediately if the court terminates the injunction. At that time, DoD, GSA, and NASA will publish a document in the Federal Register advising the public of the termination of the injunction.
(P) 52.222-60, Paycheck Transparency (Executive Order 13673) (Oct 2016).
(Q) 52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. 2302 Note).
(R) 52.222-62, Paid sick Leave Under Executive Order 13706 (JAN 2017) (E.O. 13706).
(S) (1) 52.224-3, Privacy Training (Jan 2017) (5 U.S.C. 552).
(2) Alternate I (Jan 2017) of 52.224-3
(T) 52.226–6, Promoting Excess Food Donation to Nonprofit Organizations. (May 2014) (42 U.S.C. 1792). Flow down required in accordance with paragraph (e) of FAR clause 52.226–6.
(T) 52.247–64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Feb 2006) (46 U.S.C. Appx. 1241(b) and 10 U.S.C. 2631). Flow down required in accordance with paragraph (d) of FAR clause 52.247–64.
13. The following additional information is applicable to this acquisition:
| Number |
| Title |
| Date |
| 52.203-18 |
| Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation |
| Jan 17 |
| 52.204-7 |
| System for Award Management |
| Oct 16 |
| 52.204-13 |
| SAM Maintenance |
| Oct 16 |
| 52.204-16 |
| Commercial and Government Entity Code Reporting |
| Jul 16 |
| 52.204-18 |
| Commercial and Government Entity Code Maintenance |
| Jul 16 |
| 52.204-22 |
| Alternative Line Item Proposal |
| Jan 17 |
| 52.204-23 |
| Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities |
| Jul 18 |
| 52.222-41 |
| Service Contract Labor Standards |
| May 14 |
| 52.232-39 |
| Unenforceability of Unauthorized Obligations |
| Jun 13 |
| 52.232-40 |
| Providing Accelerated Payments to Small Business Subcontractors |
| Dec 13 |
| 52.233-3 |
| Protest After Award |
| Aug 96 |
| 52.237-1 |
| Site Visit |
| Apr 84 |
| 52.237-2 |
| Protection of Government Buildings, Equipment, and Vegetation |
| Apr 84 |
| 252.203-7000 |
| Requirements Relating to Compensation of Former DOD Officials |
| Sep 11 |
| 252.203-7002 |
| Requirement to Inform Employees of Whistleblower Rights |
| Sep 13 |
| 252.203-7005 |
| Representation Relating to Compensation of Former DoD Officials |
| Nov 11 |
| 252.204-7003 |
| Control of Government Personnel Work Product |
| Apr 92 |
| 252.204-7008 |
| Compliance with Safeguarding Covered Defense Information Controls |
| Oct 16 |
| 252.204-7009 |
| Limitations on the Use or Disclosure of Third-Party Contractor Information |
| Dec 15 |
| 252.204-7012 |
| Safeguarding Covered Defense Information and Cyber Incident Reporting |
| Oct 16 |
| 252.204-7015 |
| Notice of Authorized Disclosure of Information for Litigation Support |
| May 16 |
| 252.223-7006 |
| Prohibition on Storage, Treatment, and Disposal of Toxic or Hazardous Materials |
| Sep 14 |
| 252.223-7008 |
| Prohibition of Hexavalent Chromium |
| May 11 |
| 252.225-7001 |
| Buy American and Balance of Payments Program |
| Dec 17 |
| 252.225-7002 |
| Qualifying Country Sources as Subcontractors |
| Dec 17 |
| 252.225-7048 |
| Export-Controlled Items |
| Jun 13 |
| 252.232-7003 |
| Electronic Submission of Payment Requests and Receiving Reports |
| Mar 08 |
| 252.232-7010 |
| Levies on Contract Payments |
| Oct 16 |
| 252.244-7000 |
| Subcontracts for Commercial Items |
| Jun 13 |
| 252.246-7003 |
| Notification of Potential Safety Issues |
| Jun 13 |
| 252.247-7023 |
| Transportation of Supplies by Sea |
| Apr 14 |
(End of Provision)
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)
(a) Definitions. As used in this clause--
Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.
Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.
(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall--
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this Web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:
(1) Document type. The Contractor shall use the following document type(s).
INVOICE 2-IN-1
(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.
GOVERNMENT
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table* Field Name in WAWF Data to be entered in WAWF
| Pay Official DoDAAC | N68732 | ||
| Issue By DoDAAC | N70272 | ||
| Admin DoDAAC | N70272 | ||
| Inspect By DoDAAC | ____ | ||
| Ship To Code | ____ | ||
| Ship From Code | ____ | ||
| Mark For Code | ____ | ||
| Service Approver (DoDAAC) | N63038 | ||
| Service Acceptor (DoDAAC) | N63038 | ||
| Accept at Other DoDAAC | ____ | ||
| LPO DoDAAC | N70272 | ||
| DCAA Auditor DoDAAC | ____ | ||
| Other DoDAAC(s) | ____ |
(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.
(5) WAWF email notifications. The Contractor shall enter the email address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.
Samantha.finley@navy.mil
(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
Samantha.finley@navy.mil
(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.
(End of clause)
AUTHORIZED CHANGES ONLY BY THE CONTRACTING OFFICER
(a) Except as specified in paragraph (b) below, no order, statement, or conduct of Government personnel who visit the Contractor's facilities or in any other manner communicate with Contractor personnel during the performance of this contract shall constitute a change under the "Changes" clause of this contract.
(b) The Contractor shall not comply with any order, direction or request of Government personnel unless it is issued in writing and signed by the Contracting Officer, or is pursuant to specific authority otherwise included as a part of this contract.
(c) The Contracting Officer is the only person authorized to approve changes in any of the requirements of this contract and notwithstanding provisions contained elsewhere in this contract, the said authority remains solely with the Contracting Officer. In the event the Contractor effects any change at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in charges incurred as a result thereof.
BASE/REPAIR FACILITY ACCESS
Navy installations have begun transitioning to Defense Biometric Identification System (DBIDS) to enhance base security. Rapid Gate/SURE ID is no longer allowed to accept applications for NCAC credentials and installations are no longer issuing NCAC credentials. The current NCAC card, if contractor has one in their possession, is only valid until July 15th of this year, after that it will not be allowed. All contractors need to report to the Pass and ID office and register for the new DBIDS credential that will replace the NCAC card for no cost. Initially contractors will submit for a 180 day temporary DBIDS pass until their new DBIDS credential can be made.
1. NCAC cards received by Pass and ID will not be issued, instead:
a. NCACS cardholders will have 90 days starting from April 17, 2017 to obtain a temporary DBIDS paper pass. After July 15, 2017, NCACS cards will no longer be accepted for installation access. After the applicant obtains their DBIDS paper pass, they will have an additional 90 days to obtain an actual DBIDS card at no cost to them.
b. To obtain a DBIDS credential and obtain base access; an individual needs to acquire DoD sponsorship, have a thorough identity check, be properly vetted, and have a legitimate reason for base access. Identity checks require a passport or a Real ID Act-compliant state driver's license. Vetting occurs when the individual's background and ID are compared against authoritative criminal justice data bases, and the individual has a letter or official document from the sponsoring organization which articulates the reason for access. When the above criteria are satisfactorily met, DBIDs credentials are issued.
3. One of the added benefits to DBIDS is that the NCACS credentialing process took up to 31 days to complete and the credentialing process for DBIDS only takes 30 to 60 minutes.
DOD Sponsorship shall provide the following;
1) Verify all your NCAC personnel via the list sent out by the Deputy Director of Public Safety. If you have personnel/contractors no longer needing access purge them from your list before sending your update to the Region.
2) The Name of the Company, the company address as well as the Name, Phone Number, and email address of your POC at the company.
3) The requested days of the week and the hours that contractors will need access to the installation? (i.e. 24/7, Monday through Saturday 0600-2000, or some other combination)
4) The installation sponsor for contractors must be an Active Duty CAC card holder or a Federal Employee with a regular CAC credential with an email address ending in navy.mil and in addition must supply an installation phone number and full name of the Sponsor's Full Name, Job Title.
CONTRACTOR DIRECTION
DBIDS website can be found at http://dbids.dmdc.mil/ If you currently have a Navy Commercial Access Control System (NCACS) card (used with Rapidgate), the following is required to get a DBIDS credential:
· Present your NCACS Card and a completed copy of the SECNAV FORM 5512/1 to the base Visitor Control Center representative.
· The VCC will pull up your information in the computer, ensuring all information is current and correct.
· Once your information is validated, a temporary DBIDS credential is provided.
· Your temporary credential will have an expiration date, prior to which you will need to obtain your permanent DBIDS credential (~ 90 days).
· For each additional U.S. Navy installation to which you need access, the first time you visit you only need to bring your DBIDS credential and statement of purpose for base access when arriving at the Visitor Control Center.
· The representative will enter base access authorization and then you may proceed to work.
If you do NOT have an NCACS Card, the following is required to obtain a DBIDS credential:
· Present a letter or official document from the government sponsoring organization that provides the purpose for your access.
· Present…