This is a Statement of Work for the Camp Lincoln AGO Building Structural Support Project located at 1301 North Macarthur Boulevard, Springfield, Illinois. The project scope requires the vendor to provide all labor, materials, and equipment necessary to install additional structural support for the AGO building's mechanical room penthouse to accommodate two new water tanks required for geothermal system upgrades. The primary deliverable is the construction of a new exterior steel roof frame above the existing penthouse to suspend and support the tanks internally, with hanging supports braced to the penthouse floor for seismic restraint. All work must be executed in accordance with attached plans and specifications, conform to design loads, and comply with industry standards. Work hours are limited to 0800 to 1600, Monday through Friday, excluding Federal and State holidays. Site visits are non-mandatory prior to bid submission. Before construction commences, the contractor must submit a Safety Plan, shop drawings, product information, permits, and any other documentation identified in the plans or required by applicable law. The Prime Contractor is responsible for coordinating all roof penetrations and patching with the current warranty holder, Designed Roofing Systems, Inc., to maintain the existing roof warranty.
Vendors must submit quotes via Bid Buy in response to this solicitation. The statement does not identify specific pricing terms, bid amounts, set-asides, incumbent information, funding sources, or contract duration and renewal options. The vendor is required to maintain a clean and debris-free work area at the end of each workday and provide safety barriers around all equipment, crane placement, and materials to prevent unauthorized access to hazardous zones.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Camp Lincoln – AGO Building Structural Support Project
1301 North Macarthur Blvd.
Springfield, IL
1. GENERAL OVERVIEW OF WORK.
The scope of this project is to provide all labor, materials, and equipment necessary to install additional structural support for the AGO building mechanical room penthouse. Upgrades and repairs to the building’s Geothermal system require the addition of two (2) water tanks to be installed inside the existing penthouse. Due to the increased size and weight of these tanks, a new exterior steel roof frame must be constructed above the penthouse to suspend and support the tanks internally.
2. MATERIALS.
a. All materials must conform to the design loads and specifications detailed in the attached plans.
3. EXECUTION.
a. See attached plans for specific dimensions, design details, and material requirements.
b. All work shall be completed in a professional, workmanlike manner in accordance with industry standards.
c. The work area shall remain clean and free of debris at the end of each workday.
d. Vendor shall provide safety barriers for all equipment, crane placement, materials, and other construction areas to prevent unauthorized personnel from entering hazardous zones.
e. Provide a new exposed steel roof frame above the existing penthouse to vertically support the new water holding tanks.
f. Hanging supports will be braced to the penthouse floor for seismic restraint, as detailed in the attached plans.
g. Roof penetration of the penthouse is required. To maintain the current roof warranty, the Prime Contractor is responsible for coordinating and subcontracting all roof penetrations and patching to the current warranty holder: Designed Roofing Systems, Inc.
h. ALL WORK TO BE EXECUTED IN ACCORDANCE WITH ATTACHED PLANS.
4. PERIOD OF PERFORMANCE & LOGISTICS
a. Work Hours: All work shall be conducted between the hours of 0800 to 1600, Monday through Friday, excluding Federal/State holidays.
5. PRICING & BID REQUIREMENTS
a. Vendor to submit quote via Bid Buy.
b. Site visits are non-mandatory prior to bid submission.
c. Before commencement of construction, the contractor shall provide the required Safety Plan and any required submittals, shop drawings, product information, permits or other documentation identified in the plans or required by applicable law.