2320 Drawings Specifications.pdf

PDF 7 MB Posted

Attached to
Kenosha County Sheriff’s Garage Fire Damage Repair
Solicitation number
2320
Issued by
Kenosha County, Kellnersville Village, Wisconsin

About this file

This is a specification document for Kenosha County, Wisconsin, for the Sheriff's Garage Fire Damage Repair project (Bid #2320), prepared by Kueny Architects, LLC, dated July 12, 2023. The project involves fire damage restoration of a 4,345 square foot one-story pre-engineered metal storage facility, with the primary fire-damaged area comprising 1,350 square feet. Work is to be executed under a single prime general contractor agreement that includes plumbing, heating, ventilation, and electrical work. The specifications establish comprehensive general requirements covering project coordination, meetings, submittals, quality control, temporary facilities and controls, material and equipment handling, contract closeout procedures, and final cleaning standards. A preconstruction meeting is required within 15 days of the Notice to Proceed, with regular progress meetings thereafter as needed. Shop drawings, product data, and samples must be submitted at least 14 days before needed for installation, with the Architect providing review within ten working days. The contractor is responsible for obtaining all permits and conducting utility locates prior to work commencement.

The specifications require contractors to maintain quality control through continuous on-site and off-site inspections, with the Architect conducting periodic inspections as specified in their agreement with the County. All submittals must comply with referenced standards and manufacturer specifications, with the contractor bearing responsibility for accuracy and completeness of submissions. The contractor must provide temporary facilities including heating, cooling, ventilation, electricity, water, sanitary facilities, fire protection equipment, construction aids, and dust and water control measures. Final payment is contingent upon submission of project record documents, operating and maintenance manuals with Owner instruction, warranties and bonds, evidence of regulatory compliance, a final waiver of lien, and proof that maintenance personnel have received complete operational training. The contractor is responsible for all costs associated with cutting, patching, and repair of damaged work caused by their own operations or deficiencies, while costs for work performed on the Architect's written instructions are borne by the Owner.

View the file

Other files

File Type Posted
2320 Addendum 1.pdf PDF
2320 Bid Documents.pdf PDF
Vendor Responsibility Form Construction.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATION FOR

PROJECT:

Kenosha County - Sheriff’s Garage – Fire Damage Repair

OWNER:

Kenosha County 4777 88th Avenue Kenosha WI 53144

SPECIFICATION DATE:

July 12, 2023

Bid #2320

K U E N Y A R C H I T E C T S, L. L. C.

THIS PAGE INTENTIONALLY LEFT BLANK

KENOSHA COUNTY – SHERIFF’S GARAGE – FIRE DAMAGE REPAIR

BID #2320

KENOSHA, WISCONSIN

ARCHITECT KUENY ARCHITECTS, LLC

10505 Corporate Drive Suite #100 Pleasant Prairie, Wisconsin 53158

PHONE (262) 857-8101

FAX (262) 857-8103

Jon P. Wallenkamp, AIA Project Manager jonw@kuenyarch.com

PROJECT MANAGER KUENY ARCHITECTS, LLC

10505 Corporate Drive Suite #100 Pleasant Prairie, Wisconsin 53158

PHONE (262) 857-8101

FAX (262) 857-8103

Lee S. Anderson lee@kuenyarch.com mailto:jonw@kuenyarch.com mailto:lee@kuenyarch.com

#2320 - Kenosha County – Sheriff’s Garage – Fire Damage Repair

July 12, 2023 TC-1

TABLE OF CONTENTS

TABLE OF CONTENTS

Title Page 1 page Table of Contents 8 pages

BIDDING AND CONTRACT DOCUMENTS

DIVISION 1 GENERAL REQUIREMENTS

01 10 00 SUMMARY OF WORK .......................................................................... 2 pages

01 30 00 PROJECT COORDINATION ................................................................ 6 pages

01 31 19 PROJECT MEETINGS .......................................................................... 4 pages

01 33 00 SUBMITTALS ........................................................................................ 5 pages

01 45 00 QUALITY REQUIREMENTS ................................................................. 2 pages

01 50 00 TEMPORARY FACILITIES AND CONTROLS ...................................... 8 pages

01 60 00 MATERIAL AND EQUIPMENT ............................................................. 7 pages

01 70 00 CONTRACT CLOSEOUT ..................................................................... 7 pages

01 73 29 CUTTING AND PATCHING .................................................................. 3 pages

01 77 16 FINAL CLEANING ................................................................................. 5 pages

DIVISION 2 EXISTING CONDITIONS

02 41 13 BUILDING DEMOLITION ...................................................................... 4 pages

DIVISION 13 SPECIAL CONSTRUCTION

02 41 13 METAL BUILDING SYSTEMS .............................................................. 5 pages

ATTACHMENTS

ATTACHMENT A – SUMMARY OF WORK / QUANTITIES .................................. 2 pages

ATTACHMENT B – PHOTOS ................................................................................ 9 pages

ATTACHMENT C1 – OVERALL FLOOR PLAN – WORK AREA……………………1 page

ATTACHMENT C2 – WORK AREA – FLOOR PLANS……………………………….1 page

ATTACHMENT C3 – WORK AREA – MEP PLANS…………………………………..1 page

Kenosha County - Sheriff’s Garage – Fire Damage Repair

July 12, 2023 01 10 00-1

SUMMARY OF WORK

SECTION 01 10 00 SUMMARY OF WORK

SCOPE Applicable provisions of the General and Supplementary Conditions and Division 1 govern work under this Section

INDEX 1.1 Work Covered by Contract Documents 1.4 Work Sequence

1.2 Contracts 1.5 Contractors use of Premises

1.3 Work by Others

PART 1 GENERAL

1.1 Work Covered by Contract Documents

A. The Project consists of fire damage restoration of a 4,345 square foot one story pre-engineered metal storage facility. The primary fire damaged area consists of a 1,350 square foot area.

All work is to be done in strict compliance with the plans and specifications prepared by Kueny Architects, L.L.C., of Pleasant Prairie, Wisconsin, which have heretofore been approved by Kenosha County.

B. Bids under the GENERAL CONTRACTOR will include plumbing, heating and ventilation and the electrical work.

C. Related Requirements Specified Elsewhere: The Conditions of the Contract – General and Supplementary, and these General Requirements shall apply with equal force and effect to all Contractors engaged in this Work.

D. Contractor’s Duties

1. Except as specifically noted, provide and pay for:

a. Labor and materials, tools and equipment. (See General Conditions).

b. Other facilities and services necessary for proper execution and completion of

Work.

2. Permits, fees licenses, notices: the contractor is required to obtain all permits.

3. Comply with codes, ordinances, rules, regulations, orders and other requirements of public authorities which bear on performance of Work.

4. Promptly submit written notice to Architect of observed variance of Contract

Documents from legal requirements. It is not the Contractor’s responsibility to make certain that Drawings and Specifications comply with codes and regulations.

a. Appropriate modifications to Contract Documents will adjust necessary changes.

b. Assume responsibility for work known to be contrary to such requirements, without notice.

5. Enforce strict discipline and good order among employees. Do not employ Work of:

a. Unfit persons.

b. Persons not skilled in assigned tasks.

6. It will be the affected Contractor’s responsibility to call the utility companies prior to and while work is in progress to obtain utility locations and clearances within the work limits.

Kenosha County - Sheriff’s Garage – Fire Damage Repair

01 10 00-2 July 12, 2023

SUMMARY OF WORK

1.2 Contracts: (See General Conditions)

A. Construct Work under one single prime Contract:

1. Prime Restoration Contractor

1.3 Work Sequence

A. Construct Work in stages: The General Contractor will determine the schedule. All

Contractor’s will be required to keep up with General Contractor’s schedule.

1.4 Contractors use of Premises

A. Confine operations at site to areas permitted by:

1. Law

2. Ordinances

3. Permits

4. Contract Documents

B. Do not unreasonably encumber site with materials or equipment. Do not interfere with other projects underway during the same time period.

C. Do not load structure with weight that will endanger structure.

D. Assume full responsibility for protection and safe keeping of products stored on premises.

E. Move any stored products which interfere with operations of Owner or other Contractors.

F. Obtain and pay for use of additional storage or work areas needed for operations.

G. Use Site: The contractor is required to work with and around Owner’s existing operations.

#2320 - Kenosha County - Sheriff’s Garage – Fire Damage Repair

July 12, 2023 01 30 00-1

PROJECT COORDINATION

SECTION 01 30 00 PROJECT COORDINATION

SCOPE Applicable provisions of the General and Supplementary Conditions and Division 1 govern work under this Section.

INDEX 1.1 Description

2.1 Project Manager

3.1 General Duties of Project Managers

3.2 Coordination Between Contractors at the Project Site

PART 1 GENERAL

1.1 Description

A. Work Included

1. General Contractor will coordinate the Work of the entire Project.

2. The General Contractor shall:

a. Coordinate work of their own employees and subcontractors.

b. Expedite their work to assure compliance with schedules.

c. Coordinate their work with that of other prime contractors and work by Owner.

d. Comply with orders and instructions of the Owner.

B. Related Work Specified Elsewhere: Division 1.

PART 2 PERSONNEL

2.1 Project Manager

A. The General Contractor and each of the Mechanical and Electrical sub-contractors shall designate a qualified project manager for the duration of the construction work.

1. Qualification:

a. Experienced in field work of the type required for this Project.

2. Submit name to Architect.

PART 3 EXECUTION

3.1 General Duties of Project Managers

A. Construction Organization and Start-up

1. Project Managers shall establish on-site lines of authority and communications:

a. Establish procedures for intra-project communication:

(1) Submittals

(2) Reports and records

(3) Recommendations

(4) Schedules

(5) Resolution of conflicts.

b. Interpret Contract Documents:

(1) Consult with Architect to obtain interpretations.

(2) Assist in resolution of questions or conflicts which may arise.

(3) Transmit written interpretations to Prime Contractors, and to other concerned parties.

#2320 - Kenosha County - Sheriff’s Garage – Fire Damage

01 30 00-2 July 12, 2023

PROJECT COORDINATION

c. Assist in obtaining permits and approvals:

(1) Building permits and special permits required for Work or for temporary facilities.

(2) Verify that contractors and subcontractors have obtained inspections for

Work and for temporary facilities.

B. Project Manager Duties

1. Prepare Coordination Drawings as required to resolve conflicts and to assure coordination of the work of, or affected by, mechanical and electrical trades, or by special equipment requirements.

a. Submit to Architect.

b. Reproduce and distribute copies to concerned parties after Architect review.

2. Inspection and Testing:

a. Inspect work to assure performance in accord with requirements of Contract

Documents.

b. Administer special testing and inspections of suspect Work.

c. Reject Work which does not comply with requirements of Contract Documents.

d. Coordinate Testing Laboratory Services:

(1) Verify that required laboratory personnel are present.

(2) Verify that tests are made in accord with specified standards.

(3) Review test reports for compliance with specified criteria.

(4) Recommend and administer any required retesting.

3. Monitor the use of temporary utilities:

a. Verify that adequate services are provided and maintained.

b. Coordinate installation, operation and maintenance, to verify compliance with project requirements and with Contract Documents.

c. Coordinate use of Owner’s facilities.

4. Monitor Contractors’ periodic cleaning:

a. Enforce compliance with Specification.

b. Resolve any conflicts.

5. Arrange for delivery of Owner-furnished products.

a. Inspect for condition at delivery.

b. Turn over to appropriate Contractor, obtain receipt.

6. Changes and Substitutions:

a. Recommend necessary or desirable changes to Owner and to Architect.

b. Review subcontractors’ requests for changes and substitutions; submit recommendations to Owner and to Architect.

c. Assist Architect in negotiating Change Orders.

d. Promptly notify all subcontractors of pending changes or substitutions.

7. Provide cost control for Project:

a. Revise and refine the approved estimate of construction cost periodically:

(1) Record actual costs, and estimates for uncompleted work.

(2) Incorporate approved changes as they occur.

(3) Develop cash flow reports and projections.

b. Maintain cost accounting records for authorized work performed under:

(1) Unit costs.

(2) Actual costs for labor and materials.

(3) Other basis requiring accounting records.

c. Implement procedures for review and processing of Contractor’s applications for progress payments and for final payments.

(1) Review each application for payment, submit recommendations to Architect.

July 12, 2023 01 30 00-3

PROJECT COORDINATION

8. Maintain Reports and Records at Job Site, available to Architect and Owner.

a. Daily lob of progress of Work.

b. Records:

(1) Contracts

(2) Purchase orders.

(3) Materials and equipment records.

(4) Applicable handbooks, codes and standards.

c. Obtain information from subcontractors, and maintain file of record documents.

d. Assemble documentation for handling of claims and disputes.

9. Coordinate the work schedules of the subcontractors:

a. Among the work of the trades specified in Division 23 and 26.

b. With the work of trades specified in Division 2 through 26.

10. Coordinate the schedules of subcontractors.

a. Verify timely deliveries of Products for installation by other trades.

b. Verify that labor and materials are adequate to maintain schedules.

11. Conduct conferences among subcontractors, and other concerned parties, as necessary to:

a. Maintain coordination and schedules.

b. Resolve matters in dispute.

12. Participate in Project Meetings:

a. Report progress of Work.

b. Recommend needed changes in schedules.

c. Transmit minutes of meetings to trades, as appropriate.

13. Temporary Utilities:

a. Coordinate installation, operation and maintenance, to verify compliance with

Project requirements and with Contract Documents.

b. Verify adequacy of service at required locations.

14. Shop Drawings, Product Data Samples:

a. Prior to submittal, review for compliance with Contract Documents.

(1) Check field dimensions and clearance dimensions.

(2) Check relation to available space.

(3) Check anchor bolt settings.

(4) Review the effect of any changes on the work of other contracts or trades.

(5) Check compatibility with equipment and work of other trades.

(6) Check motor voltages and control characteristics.

(7) Coordinate controls and interlocks:

(a) Voltages

(b) Wiring of pneumatic electric switches or relays.

(8) Coordinate wiring and control diagrams.

15. Job Site Visits:

a. Project Managers shall visit Site monthly until work of their Contract begins.

b. Visit site weekly after Contractor has begun.

16. Verify that subcontractors maintain accurate record documents.

17. Observe Work for compliance with requirements of Contract Documents.

a. Maintain list of observed deficiencies and discrepancies.

b. Promptly report deficiencies or discrepancies to Architect.

c. Record results, including time and date of start-up.

18. Equipment Startup:

a. Check to assure that utilities and specified connections are complete and that equipment is in operable condition.

b. Observe test, adjust and balance.

01 30 00-4 July 12, 2023

c. Record results, including time and date of start-up.

19. Inspection and Acceptance of Equipment:

a. Prior to inspection, check that equipment is clean, repainted as required, tested and operational.

b. Assist inspector; prepare list of items to be completed or corrected.

c. Should acceptance and operation of equipment constitute the beginning of the specified warrantee period, prepare and transmit written notice to Architect for the Owner.

20. Assemble Record Documents from subcontractors, transmit to Architect.

C. Project Manager’s Close-out Duties

1. Mechanical and Electrical equipment start-up:

a. Coordinate check-out of utilities, operational systems and equipment.

b. Assist in initial start-up and testing.

c. Record dates of start of operation of systems and equipment.

d. Submit to Owner written notice of beginning of warranty period for equipment put into service.

2. At completion of Work of each Contract, conduct an inspection to assure that:

a. Specified cleaning has been accomplished.

b. Temporary facilities have been removed from site.

3. Substantial Completion:

a. Conduct an inspection to confirm or supplement Contractor’s list of work to be completed or corrected.

b. Assist Architect in inspection.

c. Supervise correction and completion of work as established in Certificate of

Substantial Completion.

4. When Owner occupies a portion of Project prior to final completion, coordinate established responsibilities of Contractor and Owner.

5. Final Completion:

a. When each Contractor determines the Work is finally complete, conduct an inspection to verify completion of Work.

b. Assist Architect in inspection.

6. Administration of Contract Closeout:

a. Receive and review subcontractors’ final submittals.

b. Transmit to Architect with recommendations for action.

D. Additional Duties of General Contractor’s Project Manager

1. Control the use of Site:

a. Supervise field engineering and site layout.

b. Allocate space for each Prime Contractor’s use for field offices, sheds and work and storage areas.

c. Allocate field office and storage space, and work and storage areas, for use of each Prime Contractor.

d. Establish access, traffic and parking allocations and regulations.

e. Monitor use of site during construction.

2. Construction Schedules:

a. Coordinate schedules of the several Prime Contractors.

b. Prepare a detailed schedule of basic operations for all Prime Contractors.

(1) Each Prime Contractor shall prepare sub-schedules to comply with critical phases.

July 12, 2023 01 30 00-5

PROJECT COORDINATION

c. Monitor schedules as work progresses:

(1) Identify potential variances between scheduled and probable completion dates for each phase.

(2) Recommend to Owner adjustments in schedule to meet required completion dates.

(3) Adjust schedules of Contractors as required.

(4) Document changes in schedule, submit to Owner, Architect and to involved

Contractors.

d. Observe work of each Contractor to monitor compliance with schedule.

(1) Verify that labor and equipment are adequate for the work and the schedule.

(2) Verify that product procurement schedules are adequate.

(3) Verify that product deliveries are adequate to maintain schedule.

(4) Report noncompliance to Owner, with recommendation for changes.

3.2 Coordination Between Contractors at the Project Site

A. All Contractors and all subcontractors shall coordinate their work with adjacent work and shall cooperate with all other trades so as to facilitate the general progress of the Work.

Each trade shall afford all other trades every reasonable opportunity for the installation of their work and for the storage of their material. In no case will any Contractor be permitted to exclude from the premises or work, any other Contractor or their employees, or interfere with any Contractor in the executing or installation of their work.

B. Each trade shall perform its work in proper sequence in relation to that of other contractors or trades and as approved by the Architect. Any cost caused by defective or ill-timed work shall be borne by the trade responsible therefore.

C. Each Contractor shall arrange their Work and dispose of their materials so as not to interfere with the Work or storage of materials of other Contractors and each shall join their work to that of others in accord with the intent of the Drawings and Specifications.

D. All mechanical and electrical contractors shall work in cooperation with the General Contractor and with each other, and fit their piping, ductwork, conduit, etc., into the structure as job conditions may demand. All final decisions as to the right-of-way and run of pipe, ducts etc., shall be made by the Architect or his/her representative at prearranged meetings with responsible representatives of the mechanical and electrical contractors.

E. Each Contractor shall give due notice and proper information to other Contractors of any special provisions necessary for the placing or setting of their work coming in contact with work of other Contractors. Failing to do so in proper time, they will be held responsible and shall pay for any and all alterations and repairs necessitated by such neglect.

F. It shall be the responsibility of all Contractors and all subcontractors to keep constant check on the progress of the Work so that the particular trade can insure proper preparation for installation of that trade’s work and not cause delay in the progress of the Work. It shall be the responsibility of each contractor to periodically make inspections of work in progress and to notify the Architect when work is complete in compliance with Specifications and Drawings.

G. Contractors for Fire Protection, Plumbing, Heating and Ventilating and Electrical Work shall check and cross check the Drawings and Specifications of other trades to inform

01 30 00-6 July 12, 2023 themselves of the work interrelated with their work.

H. Any voluntary effort on the part of the Architect to expedite the notice to other Contractors shall not relieve any Contractor of their primary responsibility to give such notice.

I. Contractors shall determine as far in advance as possible the exact size of openings and guarantee them to the General Contractor.

J. All Contractors working on the site shall coordinate storage of materials on ground slabs and on above ground floor and roof members so as not to exceed the design live load shown on the Drawings. Material storage will not be allowed on any cantilevered members. Contractors will take immediate remedial action when so directed by the Architect.

July 12, 2023 01 31 19-1

PROJECT MEETINGS

SECTION 01 31 19 PROJECT MEETINGS

SCOPE Applicable provisions of the General and Supplementary Conditions and Division 1 govern work under this Section.

INDEX 1.1 Description

2.1 Pre-Construction Meetings 2.4 One Year Warranty Review Meetings

2.2 Progress Meetings 3.1 Representatives List

2.3 Completion Inspection Meeting 3.2 Meetings

A. Work Included: Throughout the course of the Work, in order to provide coordination of the Project, the Architect will schedule meetings which will include but are not limited to:

1. Preconstruction Conference

2. Progress Meetings

3. Completion Inspection Meeting

B. Related Requirements Specified in Other Sections

1. Summary of Work Section 01 10 00

2. Quality Control Section 01 45 00

3. Construction Schedules Section 01 30 00

4. Submittals Shop Drawings and Samples Section 01 33 00

5. Project Record Documents Section 01 70 00

6. Operating and Maintenance Data Section 01 70 00

C. Related Requirements in Other Parts of the Project Manual

1. Pre-Bid Conference: Instruction to Bidders

D. Definitions: See General Conditions

PART 2 PRODUCTS

2.1 Preconstruction Meeting

A. Schedule within 15 days after date of Notice to Proceed.

B. Location: The Architect will designate a central site convenient for all parties.

C. Attendance

1. All persons named on the Representatives List described in Part 3 of this Section.

2. Major subcontractors.

3. Major suppliers.

4. Others as appropriate.

D. Suggested Agendum

1. Distribution and discussion of:

a. List of major subcontractors and suppliers

b. Projected construction schedules.

01 31 19-2 July 12, 2023

PROJECT MEETINGS

2. Critical work sequencing.

3. Major equipment deliveries and priorities.

4. Project coordination; designation or responsible personnel.

5. Procedures and processing of:

a. Field decisions

b. Proposal requests

c. Submittals

d. Change orders

e. Application for payment

6. Adequacy of distribution of Contract Documents.

7. Procedures for maintaining Record Documents.

8. Use of premises:

a. Office, work and storage areas.

b. Owner’s requirements.

9. Construction facilities, controls and construction aids.

10. Temporary utilities.

11. Safety and first-aid procedures.

12. Security procedures.

13. Housekeeping procedures.

2.2 Progress Meetings

A. Schedule regular periodic meetings, as required.

B. Hold called meetings as required by progress of the Work.

C. Location of the Meetings: The project site or location designated by the owner.

D. Attendance

1. Architect’s, Owner’s and Contractor’s representatives as shown on Representatives

List in Part 3 of this Section.

2. Subcontractors as appropriate to the Agenda.

3. Suppliers as appropriate to the Agenda.

4. Others.

E. Suggested Agendum

1. Review, approval of minutes of previous meeting.

2. Review of Work progress since previous meeting.

3. Field observations, problems, conflicts.

4. Problems which impede Construction Schedule

5. Review of off-site fabrication; delivery schedules.

6. Corrective measures and procedures to regain projected schedule.

7. Revisions to Construction Schedule.

8. Plan progress schedule, during succeeding work period.

9. Coordination of schedule.

10. Review submittal schedules; expedite as required

11. Maintenance of quality standards

12. Review proposed changes for:

a. Effect on Construction Schedule and on completion date.

b. Effect on other contracts of the Project.

13. Other business.

July 12, 2023 01 31 19-3

2.3 Completion Inspection Meeting

A. Schedule after Punch List has been returned to Architect and before final payment.

B. Location: A walk-though of the entire project.

C. Attendance

1. Architect

2. Owner’s Representatives

3. Field Superintendent for each prime Contractor.

4. Subcontractors as requested.

5. Engineers

D. Suggested Agendum

1. Review of Punch List items not completed.

2. Review of Project requirements for determination of final payment.

2.4 One Year Warranty Review Meeting: Approximately 11 months after the date of substantial completion the Architect, Owner and Contractor will inspect the project and develop a list of items to be corrected under the provisions of the One-Year Warranty division of the General Conditions.

3.1 Representative List: After Contracts are awarded, each Contractor will submit to the

Architect the names of the Project Manager and Field Superintendent. The Architect will then compile a list of all the representatives of the Owner, Architect, Engineers and Contractors who are authorized to make decisions about he Project and distribute this list to all interested parties.

3.2 Meetings

A. The General Contractor shall schedule and administer pre-construction meeting, periodic progress meetings and specially called meetings throughout the progress of Work.

1. Prepare agenda for meetings.

2. Distribute written notice of each meeting four days in advance of meeting date.

3. Make physical arrangements for meetings.

4. Preside at meetings.

5. Record the minutes; include all significant proceedings and decision.

6. Reproduce and distribute copies of minutes within three days after each meeting.

a. To all participants in the meeting.

b. To all parties affected by decisions made at the meeting.

B. Representatives of Contractors, Subcontractors and suppliers attending the meeting shall be qualified and authorized to act on behalf of the entity each represents.

01 31 19-4 July 12, 2023

THIS PAGE INTENTIONALLT LEFT BLANK

July 12, 2023 01 33 00-1

SUBMITTALS

SECTION 01 33 00 SUBMITTALS

SCOPE Applicable provisions of the General and Supplementary Conditions and Division 1 govern work under this Section.

INDEX 1.1 Description 2.2 Product Data

1.2 Submittals 2.3 Samples

2.1 Shop Drawings 3.1 Shop Drawings, Product Data and

Samples

A. Work Included

1. To insure that the specified products are furnished and installed in accord with design intent, procedures have been established for advance submittal of design data and for its review by the Architect.

2. Restoration Schedule

3. Progress Reports

4. Shop Drawings

5. Product Data

6. Samples

7. Layout Data

8. Schedule of Values

9. Instruction Manuals

B. Related Requirements Specified Elsewhere

1. General Conditions

a. Progress Schedule

b. Shop Drawings, Product Data and samples

c. Schedule of Values

2. Project Meetings Section 00 31 19

3. Quality Control Section 01 45 00

4. Material and Equipment Section 01 60 00

5. Project Closeout Section 01 70 00

C. Definitions

1. Shop Drawings are drawings, diagrams, illustrations, schedules, performance charts, brochures and other data which are prepared by the Contractor or any subcontractor, manufacturer, supplier or distributor and which illustrate some portion of the Work.

2. Samples are physical examples furnished by the Contractor to illustrate materials, equipment or workmanship and to assist in the establishment of standards by which the work will be judged.

1.2 Submittals

A. Construction Schedule

1. Submit initial schedules within 15 days after date of Award of Contract.

a. Architect will review schedules and return review copy within ten days after receipt.

01 33 00-2 July 12, 2023

SUBMITTALS

b. If required, resubmit within seven days after return of review copy.

2. Submit periodically updated schedules accurately depicting progress to first day of each month.

B. Shop Drawings, Product Data and Samples

1. Schedule submissions at least 14 days before dates reviewed submittals will be needed.

2. Submit number of copies of Shop Drawings, Product Data and Samples which

Contractor required for distribution plus two copies which will be retained by the Architect. An additional copy shall be submitted for mechanical engineers as required.

3. Accompany submittals with transmittal letter, in duplicate, containing:

a. Date

b. Project title and number

c. Contractor’s name and address

d. The number of each Shop Drawing, Product Data and Sample submitted.

4. Submittals shall include:

a. Date and revision dates.

b. Project title and number.

c. The names of:

(1) Architect or Engineer

(2) Contractor

(3) Subcontractor

(4) Supplier

(5) Manufacturer

(6) Separate detailer when pertinent.

d. Identification of product or material.

e. Relation to adjacent structure or materials.

f. Field dimensions, clearly identified as such.

g. Specification Section number.

h. Applicable standards, such as ASTM number.

i. Identification of deviations from Contract Documents.

j. Contractor’s stamp, initialed or signed, certifying to review of submittals, verification of field measurements and compliance with Contract Documents.

5. Resubmission Requirements:

a. Shop Drawings:

(1) Revise initial drawings as required and resubmit as specified for initial submittal.

(2) Indicate on drawings any changes which have been made other than those requested by Architect.

(3) Product Data and Samples: Submit new data and samples as required for initial submittal.

6. Distribution of submittals after review:

a. Distribute copies of Shop Drawings and Product Data which carry Architect’s stamp to:

(1) Contractor’s file

(2) Job-site file

(3) Record document file

(4) Other prime contractors

(5) Affected subcontractors

(6) Suppliers

July 12, 2023 01 33 00-3

SUBMITTALS

(7) Fabricator

(8) Erector

b. Distribute samples as directed.

7. Note: Architect will not accept any drawing or data that has been transmitted by means of telephone facsimile or electronic mail.

8. Provide sufficient space for both Contractors and Architect’s Review Stamp.

2.1 Shop Drawings

A. Original drawings, prepared by Contractor, subcontractor, supplier or distributor, which illustrate some portion of the Work; showing fabrication, layout, setting or erection details.

B. Prepared by a qualified detailer.

C. Identify details by reference to sheet, room schedule, detail numbers or other identification for coordinating with Contract Drawings.

D. Reproductions for Submittals: Five copies in blue or black line on white background.

E. Unless otherwise specifically directed by the Architect, make all Shop Drawings accurately to a scale sufficiently large to show all pertinent features of the item and its method of connection to the Work.

F. One set of corrected drawings used for fabrication will be made available on the Owner’s request.

2.2 Product Data

A. Manufacturer’s Standard Schematic Drawings:

1. Modify drawings to delete information which is not applicable to project.

2. Supplement standard information to provide additional information applicable to project.

B. Manufacturer’s catalog sheets, brochures, diagrams, schedules, performance charts, illustrations and other standard descriptive data.

1. Clearly mark each copy to identify pertinent materials, products or models.

2. Show dimensions and clearances required.

3. Shop performance characteristics and capacities.

4. Show wiring diagrams and controls.

2.3 Samples

A. Physical examples to illustrate materials, equipment or workmanship, and to establish standards by which completed work is judged.

B. Office Samples: Of sufficient size and quantity to clearly illustrate:

1. Functional characteristics of product or material, with integrally related parts and attachment devices.

01 33 00-4 July 12, 2023

SUBMITTALS

2. Colors: Submit accurate color charts and pattern charts to the Architect for review and selection as required. Indicate any cost differential between samples.

3. After review, samples may be used in construction of Project.

C. Field Samples and Mock-ups: Erect at Project site at location acceptable to the Architect.

3.1 Shop Drawings, Product Data and Samples

A. Contractor Responsibilities

1. Review Shop Drawings, Product Data and Samples prior to submission. The

Contractor will be responsible to submit samples which are to be available during the period of construction.

2. Verify

a. Field measurements

b. Field construction criteria

c. Catalog numbers and similar data.

3. Secure all necessary approvals from public agencies and others and signify by stamp, or other means, that they have been secured.

4. Coordinate each submittal with requirements of Work, Contract Documents, all trades, and public agencies involved.

5. Contractor’s responsibility for errors and omissions in submittals is not relieved by Architect’s review of submittals.

6. Contractor’s responsibility for deviations in submittals from requirements of Contract Documents is not relieved by Architect’s review of submittals, unless Architect gives written acceptance of specific deviations.

7. Notify Architect in writing at time of submission, of deviations in submittals from requirements of Contract Documents.

8. Begin no work which requires submittals until return of submittals with Architect’s stamp and initials or signature indicating review. The Architect takes not responsibility for items delivered to the site and rejected if no Shop Drawings were submitted.

9. After Architect reviews, distribute copies.

B. Architect’s Duties (General Conditions)

1. Review submittals with reasonable promptness.

2. Review for:

a. Design concept of project.

b. Information given in Contract Documents.

3. Review of separate item does not constitute review of an assembly in which item functions.

4. Affix stamp and initials or signature certifying to review of submittal.

5. Return submittals to Contractor for distribution.

6. Review of Shop Drawings by Architect/Engineer shall not be construed as a complete check but will indicate only that the general method of construction and detailing is satisfactory.

Review of such drawings will not relieve Contractor of responsibility for any error which may exist in the submittals as Contractor shall be responsible for dimensions and design of adequate connections, details and satisfactory construction of all work.

July 12, 2023 01 33 00-5

SUBMITTALS

7. The Architect will only check those submittals which have been prepared by the contractor or subcontractor that is actually supplying, fabricating or installing the product to be reviewed. Any evidence that the submittal was prepared by a prime contractor for a subcontractor without the subcontractors knowledge will result in the submittal being return marked Rejected/Resubmit.

8. The Architect’s stamp, affixed to the Shop Drawing, means only what is says; that the submittal has been reviewed and is released for fabrication as is or as noted, must be resubmitted or has been rejected. The stamp does not represent a Change Order Authorization. The Contractor will bear all increased costs for reviewed products that have not been previously approved by the Architect for use on this project.

C. Timing

1. General

a. Make all submittals far enough in advance of scheduled dates of installation to provide all required time for reviews, for securing necessary approvals, for possible revision and resubmittal, and for placing orders and securing delivery.

b. In scheduling, allow at least ten full working days for the Architect’s review following receipt of the submittal.

c. Mechanical and Electrical submittals should be allowed additional lead time for Engineer’s review.

d. Submittals pertaining to color selection are interdependent. No colors will be selected without all samples.

2. Delays: Costs of delays occasioned by tardiness of submittals may backcharged as necessary and shall not be borne by the Owner. Such costs will include the purchase, installation and removal of temporary materials, equipment and fixtures, as required in writing by the Owner, to allow the project to be used or occupied until the permanent materials, equipment and fixtures can be installed. The Owner will not be forced to accept alternate materials, equipment, fixtures or colors because of the failure of the contractor’s to make timely submission of Shop Drawings and product data.

D. Submittal Schedule: Submittals required by the various Sections of these

Specifications include, but are not necessarily limited to:

01 33 00-6 July 12, 2023

SUBMITTALS

Section Work Fi el d A pp ro va l

Sh op

D ra w in gs

Sa m pl es

C ol or

S el ec tio ns

M an ua ls

In st ru ct io n

M et ho ds

Pr od uc t D at a

01 70 00 Contract Close-out Items X 07 21 00 Insulation X

13 34 19 Metal Building Systems X X X X X X 22 Plumbing X X X X

23 HVAC X X X X

26 Electrical X X X

July 12, 2023 01 45 00-1

QUALITY CONTROL

SECTION 01 45 00 QUALITY CONTROL

SCOPE Applicable provisions of the General and Supplementary Conditions and Division 1 govern work under this Section.

INDEX 1.1 Description 2.2 Documents

1.2 Quality Assurance 3.1 Contractor’s Inspections

1.3 Submittals 3.2 Architect’s Inspections

1.4 Product Handling 3.3 Updated Documents

2.1 Inspections

A. Work Included: During the course of the Work the Contractors will maintain a means of insuring quality control of the Project. Such means of control shall include:

1. On-site construction.

2. Off-site operations.

3. Testing laboratory.

4. Reports

5. Testing and inspection requirements.

6. Updated documents.

B. Related Work Specified Elsewhere: Requirements for quality controls, certification and tests may be described in various Sections of these Specifications and the General Conditions.

C. Work Not Included

1. Selection of testing laboratories employed by Owner.

2. Payment of testing laboratories for initial testing.

1.2 Quality Assurance

A. Qualifications of Inspectors: Quality control personnel shall be familiar with all aspects of the Work and experienced in controlling the finished quality of the Work.

B. Codes and Standards: Testing, when required, will be in accord with all pertinent codes and regulations and with selected standards of the American Society for Testing and Materials.

1.3 Submittals: Test reports, inspection reports and other documents will be submitted to all interested parties.

1.4 Product Handling: Promptly process and distribute all required copies of reports and related instructions to ensure all necessary retesting and/or replacement of materials with the least possible delay in progress of the Work.

July 12, 2023 01 45 00-2

QUALITY CONTROL

2.1 Inspections

A. On-Site: The Contractors will provide the necessary personnel to maintain continuous inspection of the Work to insure compliance with all the requirements of the Contract Documents, all applicable Codes and Manufacturer's recommendations.

B. Off-Site Construction: The Contractors will provide the necessary inspections to insure the adequacy of all items manufactured off site and delivered to the job ready for installation.

2.2 Documents: The Contractors will prepare all documents necessary to comply with the requirements of this Section and deliver same to all interested parties.

3.1 Contractor's Inspections: The Contractor will continuously monitor the quality of the Work. Any work found to be inadequate will be corrected immediately. Any work found inadequate but requiring the consultation of the Architect will be reported to the Architect and then corrected immediately after clarification. Proper inspection procedures by the Contractor will eliminate the need for a Punch List at the completion of the job.

3.2 Architect's Inspections

A. The Architect will perform a periodic inspection of the job as required by his/her agreement with the Owner. The Contractor will immediately carry out the Architect's instructions based on these inspections. The Architect will not assume the role of a full time inspector because of the inadequacies of the inspection procedures of the Contractors.

B. As part of the Architect's inspections, the Contractor will provide the necessary tools and instruments to allow for the on-site verification of all dimensions, grades and elevations.

3.4 Updated Documents

A. Latest Contract Documents: The Contractors will be responsible for prompt distribution to all parties of the latest revised Contract Documents as supplied by the Architect.

B. Record Documents: The Contractors will supply the Architect with record documents for those items which differ from the Contract Documents. This will be done immediately and not be left to the end of the Construction.

July 12, 2023 01 50 00-1

CONSTRUCTION FACILITIES &

TEMPORARY CONTROLS

SECTION 01 50 00 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

SCOPE Applicable provisions of the General and Supplementary Conditions and Division 1 govern work under this Section.

INDEX 1.1 Description 2.6 Project Identification and Signs

1.2 Requirements of Regulatory 2.7 Owner Occupancy

Agencies 3.1 Removal

2.1 Utilities

2.2 Construction Aids

2.3 Barriers

2.4 Security

2.5 Temporary Controls

A. Work Included: Temporary facilities and controls required for this Work include, but are not necessarily limited to:

1. Temporary utilities such as ventilation and light.

2. Sanitary facilities.

3. Enclosures such as tarpaulins, barricades and canopies.

4. Signs.

5. Barriers.

6. Construction elevators and hoists.

7. Special controls such as noise, dust and water.

8. Winter protection.

9. Fire protection.

10. Telephone.

11. Traffic.

B. Related Work Specified Elsewhere

1. Compliance with safety regulations: Comply with all requirements of pertinent regulations as described in the General Conditions of the Contract.

2. Subcontractor equipment: Except that equipment furnished by subcontractors shall comply with all requirements of pertinent safety regulations, the ladders, hoists, planks and similar items normally furnished by individual trades in execution of their own portions of the Work are not part of this Section of these Specifications.

3. Utility hook-up: Installation and hook-up of the various utility lines are described in the pertinent other Sections of these Specifications.

4. Sitework Section 31 20 00

5. Mechanical Materials Division 23

6. Electrical Materials and Lighting Division 26

1.2 Requirements of Regulatory Agencies: Comply with Federal, State and Local codes and regulations.

01 50 00-2 CONSTRUCTION FACILITIES & July 12, 2023

TEMPORARY CONTROLS

2.1 Utilities

A. Temporary Heating, Cooling and Ventilating

1. Conditions Required:

a. Provide and operate equipment required to control temperature and humidity, as necessary to facilitate progress of Work.

b. Provide ventilating and cooling required to maintain adequate conditions.

(1) To control humidity, and to prevent condensation which would have and adverse affect on products and finishes or which would affect application of materials.

(2) To cure installed materials.

c. Ventilation Required:

(1) General: To prevent hazardous accumulations of dust, fumes, mists, vapor or gases in areas occupied during construction.

(a) Provide local exhaust ventilation to prevent harmful dispersal of hazardous substances into atmosphere of occupied areas.

(b) Dispose of exhaust materials in a manner which will not result in harmful exposure to persons.

(c) Ventilate storage spaces containing hazardous or volatile materials.

2. Use of Permanent System:

a. Prior to used of permanent system, obtain written permission of Owner, which will define:

(1) Conditions of use.

(2) Provisions relating to guarantees on equipment.

3. Materials:

a. Comply with applicable Sections of Division 23, Mechanical.

b. Materials may be new or used, but must be adequate for the purposes intended, and must not violate requirements of applicable codes and standards.

4. Equipment:

a. Provide required facilities, including piping, wiring and controls, as appropriate.

5. Installation:

a. Comply with applicable Sections of Division 23, Mechanical.

6. Removal:

a. Completely remove temporary materials and equipment when use is no longer required.

b. Restore existing equipment used for temporary services to original or better condition.

c. Restore permanent equipment used for temporary services to specified condition.

d. Remove temporary filters and install new.

B. Temporary Electricity (See applicable sections of Division 26 Electrical)

1. Use of Permanent System:

a. Prior to use of permanent system for construction purposes, obtain written permission of Owner.

b. Maintain permanent system as specified for temporary facilities.

2. Materials and Equipment:

a. General:

July 12, 2023 01 50 00-3

CONSTRUCTION FACILITIES &

TEMPORARY CONTROLS

(1) Comply with applicable sections – Division 26 Electrical.

(2) Products may be new or used, but must be adequate in capacity for required usage, and must not violate requirements of applicable codes and standards.

(3) Each trade will provide all extension cords.

3. Installation:

a. Comply with applicable requirements specified in Sections of Division 26, Electrical.

b. Maintain system to provide continuous service.

(1) Verify proper operation of safety devices.

4. Removal:

a. Completely remove temporary materials and equipment:

(1) When construction needs can be met by use of permanent installation.

(2) At completion of Project.

b. Restore existing facilities used for temporary services to original or better

c. Restore permanent facilities used for temporary services to specified condition.

C. Temporary Lighting

1. The Electrical Contractor will provide temporary artificial lighting in enclosed areas and for all areas when natural light does not meet minimum requirements for:

a. Construction work.

(1) For work areas: uniform illumination of 20 foot-candles minimum or as required for execution of work.

b. Security.

(1) For work areas: temporary security lighting at building entrances 1 foot-candle minimum within 10 feet of entrance.

(2) For staging and storage areas: temporary security lighting at staging and storage areas 1 foot-candle average.

2. Use of Permanent System: Prior to use of permanent lighting system, obtain written permission of Owner. Use of permanent system shall not shorten guarantee period.

3. Materials:

a. Comply with applicable requirements specified in Sections of Division 26, Electrical.

b. Maintain lighting and provide routine repairs.

c. Immediately prior to final inspection, clean fixtures and replace defective lamps and any other defective parts.

D. Temporary Gas and Water

1. Construction Water and Gas:

2. Use of Permanent System:

a. Prior to use of permanent system for construction purposes, obtain written permission of Owner.

3. Materials:

a. General:

(1) Comply with applicable sections of Division 23 – Mechanical

(2) Materials may be new or used, but must be adequate for purpose required, must be sanitary, and must not violate requirements of applicable codes.

4. Installation:

a. Comply with applicable requirements specified in Sections of Division 23, Mechanical.

b. Maintain system to provide continuous service.

01 50 00-4

TEMPORARY CONTROLS

c. Modify and extend service as work progress requires.

d. When necessary to maintain pressure, provide temporary pumps, tanks and compressors.

5. Removal:

a. Completely remove temporary materials and equipment.

(1) When construction can be met by use of permanent installation.

(2) At completion of Project.

b. Clean and repair damage caused by installation or use of temporary facilities.

c. Restore existing facilities, used for temporary services, to original or better

d. Restore permanent facilities, used for temporary services, to specified condition.

E. Temporary Sanitary Facilities

a. Toilet Facilities:

(1) Portable toilets or temporary flush toilets at Contractor’s option.

2. Removal:

a. Remove portable units when no longer required.

b. Remove temporary flush toilets when the space is ready for finishing and adequate facilities are provided elsewhere.

c. Completely remove temporary materials and equipment at completion of project.

d. Clean and repair areas used for temporary purposes; replace damaged fixtures, surfaces and accessories.

F. Temporary Fire Protection: The General Contractor shall provide and maintain, in working order, during the entire construction period, a minimum of three (3) fire extinguishers on each floor level including basement of the building, one in temporary office and such other fire protective equipment and devices as is deems necessary and suitable for any possible class of type of fires. They shall be non-freeze type such as A- B-C rated dry chemical extinguishers of not less than 10 pound capacity each. In addition each contractor who maintains an enclosed shed on the premises shall install and maintain in an accessible location one or more similar non-freezing type of fire extinguisher in each shed. Provisions of Local, State or Federal requirements, where more restrictive, shall comply.

2.2 Construction Aids

A. General: Materials may be new or used, suitable for the intended purpose, but must not violate requirements of applicable codes and standards.

B. Construction Aids

1. Provide construction aids and equipment required by personnel to facilitate the execution of the Work; scaffolds, staging, ladders, stairs, ramps, runways, platforms, railings, hoists, cranes, chutes and other such facilities and equipment.

2. When permanent stair framing is in place, provide temporary treads, platforms and railings, for use by construction personnel.

C. Construction Elevators and Hoists: The Contractors shall furnish, install and maintain all necessary material hoists, skips, tools, equipment, scaffolding, etc., in approved locations and in sufficient quantities to properly expedite the Work and protect the public.

The Contractors will be responsible for the operation of their equipment and allow all

July 12, 2023 01 50 00-5

CONSTRUCTION FACILITIES &

TEMPORARY CONTROLS

contractors to use it as the progress of the work requires. This equipment shall be installed according to State and local requirements and shall be removed by the Contractors at the completion of the Work. The permanent elevator may not be used.

D. Temporary Enclosures

1. Provide temporary weather-tight enclosures of exterior walls for successive areas of the building as work progresses, as necessary to provide acceptable working conditions, provide weather protection for interior materials, allow for effective temporary heating, and to prevent entry of unauthorized persons.

a. Provide temporary exterior doors with self-closing hardware and padlocks.

b. Other enclosures shall be removable as necessary for work and for handling of materials.

c. Exterior partitions or enclosures shall be covered with 3 inch insulation on interior face.

2. Provide temporary enclosures to separate work areas from the areas of existing building occupied by Owner; to prevent penetration of dust or moisture into occupied areas, to prevent damage to existing equipment, and to protect Owner’s employees and operations.

a. Temporary partition and ceiling enclosures: Framing and sheet materials which comply with structural and fire rating requirements of applicable codes and standards.

(1) Close joints between sheet materials, and seal edges and intersections with existing surfaces, to prevent penetrations of dust of moisture.

E. Installation

1. Preparation: Consult with Architect, review site conditions…

This is the start of the file's text. The full file is on GovTribe.