This document is an Addendum No. 1 issued by Tower Pinkster for the Mattawan Consolidated School, located in Mattawan, Michigan, for Bid Package 1F: High School Gym Cooling. The addendum, dated September 23, 2025, modifies the original bid documents from the August 11, 2025 issue, specifically updating the coil schedule and Air Handling Unit (AHU) sections to show split coils on Drawing M 501. The project involves mechanical system improvements for the high school gymnasium, focusing on cooling infrastructure.
The addendum includes detailed mechanical specifications for existing AHUs (AHU-3 and AHU-4), with precise information on cooling coils, pumps, and system components. The documentation provides technical details such as flow rates, pump models, coil dimensions, and performance specifications, indicating a comprehensive upgrade to the existing HVAC system. The mechanical design incorporates chilled water systems with 30% propylene glycol, specific pump and coil configurations, and includes provisions for temperature controls, variable frequency drives, and building management system communications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Nurturing curiosity through design since 1953 • towerpinkster.com
©2025 Tower Pinkster Titus Associates, Inc.
ADDENDUM NO. 1
DATE OF ISSUANCE: September 23, 2025
PROJECT: MCS – BID PACKAGE 1F: HIGH SCHOOL GYM COOLING
Western St.
Mattawan, MI 49071
OWNER: Mattawan Consolidated School
ARCHITECT’S PROJECT NO.: 23-106.037
ORIGINAL BID ISSUE DATE: August 11, 2025
SCOPE OF WORK
This Addendum includes changes to, or clarifications of, the original Bidding Documents and any previously issued addenda, and shall be included in the Bid. All of these Addendum items form a part of the Contract Documents. The Bidder shall acknowledge receipt of this Addendum in the appropriate space provided on the Bid Form. Failure to do so may result in disqualification of the Bid.
DOCUMENTS INCLUDED IN THIS ADDENDUM
This Addendum includes 1 pages of text and the following documents:
• Bidding Documents: None.
• Contract Conditions: None.
• Specification Sections: None.
• Drawings: M 501
CHANGES TO SPECIFICATIONS
NONE.
CHANGES TO DRAWINGS
ADD-1 Item No. D-1 - Coils
Refer to Sheet(s): M 501
Updated coil schedule and AHU sections to show split coils.
END OF ADDENDUM.
REFER TO THE TABLE
FOR UPSTREAM
DISTANCE
5 DIA
SHUT-OFF VALVE
ELECTROMAGNETIC
FLOW METER
10 DIA
OBSTRUCTION
PIPE SIZE REDUCTION / EXPANSION IN STRAIGHT RUN
UPSTREAM
MINIMUM UPSTREAM STRAIGHT RUN REQUIRED (1)
SINGLE BEND PRECEDED BY ≤ 9 DIAMETERS OF STRAIGHT PIPE RUN
OUTFLOWING TEE / PUMP OUTFLOW
SINGLE BEND PRECEDED BY ≥ 9 DIAMETERS OF STRAIGHT PIPE RUN
MULTIPLE BENDS OUT OF PLANE
INFLOWING TEE
VALVE
10 DIA
15 DIA
20 DIA
30 DIA
30 DIA
30 DIA
1. BASED ON "ONICON" MODEL F3500
• ACCEPTABLE TO INSTALL IN
VERTICAL PIPE.
• POSITION METER ANYWHERE IN
UPPER 240° FOR HORIZONTAL PIPE.
PRESSURE GAGE
IN
LI
N E
P U M
P
ECCENTRIC REDUCER
W/ LEVEL SIDE UP
CHECK VALVE
BALL VALVE
FLANGED CONNECTION
BALL VALVE
BALL VALVE
STRAINER, INSTALLED
PER MANUFACTURE'S
RECOMMENDATIONS
SECOND FLOOR
213' - 4"
THIRD FLOOR - MEZZANINE
228' - 1"
ROOF LOWER
116' - 0"
ROOF LOWER
116' - 0"
DC.5
TOM
118' - 0"
TOM
118' - 0"
SECOND FLOOR
113' - 4"
SECOND FLOOR
113' - 4"
ROOF LOWER
116' - 0"
ROOF LOWER
116' - 0"
DC.5
TOM
118' - 0"
TOM
118' - 0"
SECOND FLOOR
113' - 4"
SECOND FLOOR
113' - 4"
EXIST. AHU-4
CC-4.1
EXIST.
24"x60"
"x
EXIST. 40"ø
EXIST. HC
CC-4.2
SECOND FLOOR
213' - 4"
THIRD FLOOR - MEZZANINE
228' - 1"
ROOF LOWER
116' - 0"
ROOF LOWER
116' - 0"
DC.5
TOM
118' - 0"
TOM
118' - 0"
SECOND FLOOR
113' - 4"
SECOND FLOOR
113' - 4"
ROOF LOWER
116' - 0"
ROOF LOWER
116' - 0"
DC.5
TOM
118' - 0"
TOM
118' - 0"
SECOND FLOOR
113' - 4"
SECOND FLOOR
113' - 4"
EXIST. AHU-3
CC-3.1
EXIST.
30"x72"
"x
EXIST. 40"ø
EXIST. HC
CC-3.2
THERMOMETER
BALANCING VALVE
CHECK VALVE
STRAINER
PRESSURE GAUGE
C.P.
CWS
SHUT-OFF VALVE
CWR
CWS
CWR
REDUCER IF REQUIRED
ECCENTRIC TYPE W/ LEVEL
SIDE UP. TYPICAL FOR ALL
HYDRONIC HORIZONTAL
REDUCERS.
MANUAL AIR VENTS @
HIGH POINTS (TYP.)
CIRCULATING PUMP
(CONSTANT SPEED)
2-WAY CONTROL
VALVE
CWS
CWR
BRANCHES
TO AHU-4
BRANCHES
TO AHU-3
8" MAINS
COOLING COIL
COOLING COIL
THERMOMETER (TYP.)
UNIONS OR FLANGES (TYP.) OFFSET
PIPING TO ALLOW FOR EASY COIL
REMOVAL
HOSE BIBB DRAIN AT BOTTOM OF
HEADER (TYP.)
BALL VALVE AIR VENT OFF OF
COIL. TERMINATE OUTSIDE AHU
WITH 3/4" HOSE THREAD (TYP.)
PRESSURE
GAUGE
(TYP.)
T O
W E
R P
IN
K
S T
E R
.C O
M
A L L R
IG
H
T S
R E
S E
R V
E D
S H
E E
T T
IT
L
E
S H
E E
T N
U M
B E
R
O W
N E
R P
R O
J E
C T
T
IT
L E
D A
T E
M E
C H
A N
IC
A
L S
C H
E D
U L E
S A
N D
D E
T A
IL
S
-1
.1
M
A U
G U
S T
B
ID
P A
C K
A G
E
F
H
IG
H S
C H
O O
L G
Y M
C O
O L
IN
G
M A
T T
A W
A N
M
IC
H
IG
A N
M A
T T
A W
A N
C O
N S
O L
ID
A
T E
D S
C H
O O
L S
PUMPS BASED ON BELL & GOSSETT
MARK MODEL
FLOW
RATE
(GPM)
HEAD
(FT)
MOTOR DATA
SYSTEM LOCATION REMARKSHP BHP RPM VOLTAGE
P-12 e-90 167 20 3 1.32 2593 480 CC-1 MECHANICAL 2409 1, 2, 3
P-13 e-90 90 20 1 0 1607 480 CC-2 MECHANICAL 2409 1, 2, 3
COOLING COILS - CHILLED WATER (30% PROPYLENE GLYCOL) BASED ON TRANE
MARK SIZE (2) ROWS CFM
TMBH
(1)
SMBH
(1) E.D.B.
(°F) E.W.B.
(°F) L.D.B.
(°F) L.W.B.
(°F) GPM
A.P.D.
(IN WC)
W.P.D.
(FT)
FACE VELOCITY
(FPM) REMARKS
CC-3.1 32.5"x105" 2 26,040 838 716 80 65 55 54 167 0.57 7.84 530 EXISTING AHU-3
CC-3.2 32.5"x105" 2 26,040 838 716 80 65 55 54 167 0.57 7.84 530 EXISTING AHU-3
CC-4.1 20" X 102" 2 13,980 454 384 80 65 55 54 90 0.41 12.32 440 EXISTING AHU-4
CC-4.2 20" X 102" 2 13,980 454 384 80 65 55 54 90 0.41 12.32 440 EXISTING AHU-4
SCALE: NONE
FLOW METER INSTALLATION DETAIL
NOTES:
1. VFD PROVIDED BY TEMPERATURE CONTROLS CONTRACTOR.
2. WET ROTOR PUMP WITH INTEGRATED VARIABLE FREQUENCY DRIVE AND BMS COMMUNICATIONS. ALL AVAILABLE POINTS SHALL BE REVEALED TO THE BMS.
3. LEAD-FREE BRONZE CIRCULATOR
NOTES:
1. BASED ON 45°F EWT, 55°F LWT.
2. FIELD VERIFY COIL DIMENSIONS.
3. PROVIDE 2 DOUBLEWALL CONSTRUCTION THYBAR CW COIL MODULE TO MATCH EXISTING AHU WIDTH AND
HEIGHT. PROVIDE ACCESS MODULE WITH 15 ACCESS DOOR DOWNSTREAM OF COIL MODULE. CW COIL
AND ACCESS MODULE TO BE INSTALLED BETWEEN EXISTING FILTER MODULE AND HW COIL MODULE.
REWORK EXISTING MIXING BOX AS NEEDED TO ACCOMMODATE NEW COIL MODULES.
4. THYBAR TO PROVIDE (1) COIL MODULE, DOUBLE WALL POST AND PANEL CONSTRUCTION, GALVANIZED
STEEL, FIBERGLASS INSULATION THROUGHOUT. SS DRAIN PANS INCLUDED. (2) ACCESS DOORS
DOWNSTREAM OF THE COIL TO BE INCLUDED. DUAL COILS STACKED PROVIDED BY THYBAR. INCLUDE 6"
REMOVABLE BASE RAIL.
5. COIL CAPACITIES LISTED ARE TOTAL FOR THE AHU.
1/4" = 1'-0"
GYM MEZZANINE SECTION - AHU-4
1/4" = 1'-0"
GYM MEZZANINE SECTION - AHU-3
SCALE: NONE
PUMP - INLINE PIPING DETAIL
SCALE: NONE
AHU COOLING COIL PIPING DETAIL - SINGLE COIL 2-WAY VALVE
ISSUED FOR DATE
ADDENDUM 1 SEPTEMBER 23,
A1
A1
A1
A1
File details come from the government source that posted it. Updated .