This document is a Proposal Form for Project Number 230001 - AASF #1 Chiller Compressor Replacement, issued by the State of Florida's Department of Military Affairs. The project involves the removal of an existing circuit #2 compressor and the installation of a remanufactured compressor on a York YVAA Air Cooled Chiller. The bid proposal requires completion and submission of the form, along with a certified check or bid bond, by the specified deadline. The contract will be awarded to the successful bidder, who must then enter into a formal written agreement, provide the required performance and payment bonds, and obtain the necessary insurance coverage prior to commencing work.
The proposal form includes instructions for submitting the bid, which must remain valid for 40 calendar days after the bid opening. The bidder must also acknowledge any addenda issued during the bidding period. The successful bidder will be required to complete and submit a Bid Breakout Form, if requested by the Owner, and ensure that all permit fees have been included in the bid.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FNG 4004
EXHIBIT 4
PROPOSAL FORM
SUBMIT ORIGINAL PROPOSAL FORM IN DUPLICATE ON CONTRACTOR'S LETTERHEAD AND
INCLUDE BUSINESS NAME, ADDRESS, FEDERAL ID NUMBER, TELEPHONE, FACSIMILE AND
SIGNATURE
Note: NO conditional, incomplete, unsigned, undated, ambiguous, or improper bids/proposals will be accepted.
DATE:
TIME:
TO: State of Florida, Department of Military Affairs
Attention: Construction & Facility Management Office (Contract Management Branch)
2305 State Road 207
Saint Augustine, Florida 32086
To Whom It May Concern:
The undersigned, hereinafter called "Bidder", having for the proposed project familiarized himself with the local conditions, nature, and extent of the work, and having examined carefully any drawings or specifications, the
Form of Agreement, and other Contract Documents with the Bond Requirements, therein, proposes to furnish all labor, materials, equipment, and other items, facilities, and services for the proper execution and completion of
Project Number: 230001 - AASF #1 Chiller Compressor Replacement, in full accordance with any drawings and specifications prepared by Jack Trendler - CFMO Project Manager, in full accordance with the advertisement for bids, Instruction to Bidders, Agreement, and all other documents relating thereto on file in the Construction & Facility Management Office (CFMO) and if awarded the contract, to complete the said work within the time limit specified for the following bid price:
Base Bid: $
Enclosed is certified check, cashier's check, treasurer's check, bank draft, or Bid Bond in the amount of not less than five percent of the Bid, payable to the Owner as a guarantee for the purpose set out in Instructions to Bidders.
MARK ENVELOPES: ATTN: SEALED BID for Project Number: 230001 - AASF #1 Chiller Compressor
Replacement.
ADDRESSED TO: Department of Military Affairs, ATTN: CFMO-Contract Management Branch, 2305 State Road 207, St. Augustine, Florida 32086
The Bidder hereby agrees that:
a. The above proposal shall remain in full force and effect for a period of 40 calendar days after the time of the opening of this proposal and that the Bidder will not revoke or cancel this proposal or withdraw from the competition within the said 40 calendar days.
b. In the event the contract is awarded to this Bidder, he will abide by and fulfill all requirements as specified in the Non-Technical Specifications provided with the Invitation to Bid.
c. In the event the contract is awarded to this Bidder, he will enter into a formal written Agreement with the
Owner in accordance with the accepted bid within 10 calendar days after said contract is submitted to him and, (if requirement is not deleted per Section C-2 of the Conditions of the Contract), will furnish to the Owner a Contract
Performance Bond and a Labor and Material Payment Bond with good and sufficient sureties, satisfactory to the
Owner, in the amount of 100% of the accepted bid, the form of which is shown by Exhibits 7 and 8 of the
Conditions of the Contract and terms of which shall fully comply with Section 255.05, Florida Statutes. The
Bidder further agrees that in the event of the Bidder's default or breach of any of the agreements of this proposal, the said bid deposit shall be forfeited as liquidated damages.
d. In the event the contract is awarded to this Bidder, he will not commence any work in connection with the contract until he has obtained all insurance as specified in the Non-Technical Specifications, and such insurance has been approved by the Owner, nor shall the contractor allow any subcontractor to commence work on his subcontract until all similar insurance required of the subcontractor has been so obtained and approved by Owner.
All insurance policies shall be with insurers qualified to do business in Florida through an authorized licensed
Florida Resident Agent. The insurance requirements shall be completed in a timely manner in order not to delay the construction schedule.
e. In the event the contract is awarded to this Bidder, he will (if requested by Owner) complete and submit a preliminary and final Bid Breakout Form supplied by the Department of Military Affairs, Construction & Facility
Management Office.
Acknowledgement is hereby made that this proposal includes required permit fees as directed in the Non-
Technical Specifications.
Acknowledgement is hereby made of receipt of the following addenda issued during the bidding period.
Addendum No. Dated
Florida Construction Industries Licensing Board Certification.
(Name of Holder) (Certificate No.)
In witness whereof, the Bidder has hereunto set his signature and affixed his seal this day of
(Month) (Year)
(SEAL)
By: Address:
Title:
Company:
Telephone No.:
Tax ID No.:
Unique Entity ID
(UEID):
EXHIBIT 5
LIST OF SUBCONTRACTORS
(To be submitted in duplicate on the Bidder's letterhead and attached to Contractor's proposal.)
DATE:
THIS LIST IS ATTACHED TO, AND IS AN INTEGRAL PART OF THE BID SUBMITTED BY:
FOR THE CONSTRUCTION OF: PROJECT NUMBER: 230001
PROJECT NAME & LOCATION: AASF #1 Chiller Compressor Replacement.
THE UNDERSIGNED, HEREINAFTER CALLED "BIDDER", LISTS BELOW THE NAME OF EACH SUBCONTRACTOR WHO WILL
PERFORM THE PHASES OF THE WORK INDICATED. FAILURE OF THE BIDDER TO SUPPLY SUFFICIENT INFORMATION TO ALLOW
VERIFICATION OF THE CORPORATE AND DISCIPLINE LICENSE STATUS OF THE SUBCONTRACTOR MAY DEEM THE BID AS BEING
NON-RESPONSIVE. Only one (1) copy of this list is required with your bid. You may also just list the names of subcontractors, the additional information (license #, telephone number) need not be listed until after the bid and only from the contractor awarded the project.
SUBCONTRACTOR
DISCIPLINES NAME OF SUBCONTRACTOR
1. ___________________________________________________
(Name)
(Telephone No.) (Sub License #.)
2. ___________________________________________________
(Telephone No.) (Sub License #.).)
3. ___________________________________________________
4. ___________________________________________________
5. ___________________________________________________
(Telephone No.) (Sub License #.)
By (Signature)