23-LPS-SCNI-01 Addendum 1.pdf

PDF 119 KB Posted

Attached to
STRUCTURED CABLING & NETWORK INFRASTRUCTURE
Solicitation number
RFP - LAPS - 240000000609
Issued by
Macomb County, St. Louis City, Michigan

About this file

This document is an addendum to a state and local contract opportunity for Structured Cabling and Network Infrastructure services in Macomb County, Michigan and St. Louis City. The addendum addresses questions from contractors regarding the project, including the number and configuration of cable runs from the Wheat Building, responsibilities of the electrical contractor, estimated footage for cable runs, and the use of conduit at the Wheat Building. The addendum also confirms that three 24"x36" Quazite handholes will be installed by the electrical contractor, and that all underground duct will be 2" in size.

The original contract opportunity covers the provision of structured cabling and network infrastructure services for the Lakeview Public Schools district. The contract duration and any renewal options are not specified in the provided documents.

View the file

Other files

File Type Posted
23-LPS SCNI-01 Advertisement for Bid.pdf PDF
23-LPS SCNI-01 Advertisement for Bid (1).pdf PDF
T1.01 Network Infrastructure Plan.pdf PDF
23-LPS-SCNI-01 Bid Forms.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

818 West 11 Mile Road | Royal Oak, MI 48067 | Tel 248-594-5850 | Fax 248-594-5851 | http://wrighthunter.com

Addendum #1

Number: 1 W&H Project:

Structured Cabling and Network Infrastructure

Date: December 19, 2023 Project #: 23-LPS-SCNI-01

Type: Addendum Designer: Rob Richcreek

Location: Lakeview Public Schools

Contractor Questions:

1) Is each of the runs from the Wheat Building to be separate 6ct home runs from the Concessions Stand and the Press Box?

Answer: Correct. The Contractor will install (1) six-strand from the Wheat Building to the Concessions Building, and (1) six-strand from the Wheat Building to the Press Box.

2) Will the riser up to the Press Box and the entry into the Press Box be completed by the Electrical

Contractor?

Answer: Yes.

3) What is the estimated interior footage at the Concessions Stand to the Proposed Cabinet/PP location?

Answer: Assume 100ft.

4) What is the interior footage at the Wheat Building?

Answer: Assume 125ft.

5) Will there be interior conduit or raceway at the Wheat Building?

Answer: Yes. A 2” EMT will extend from the Wheat Building point of entry to the MDF room.

6) 3 handholes by E.C. are shown on drawing, are all 3 handholes 24”x36” quazite?

7) Is all underground duct to be installed by the E.C. going to be 2”?

End of Addendum #1