23-64094_Approved_Specifications.pdf

PDF 3 MB Posted

Attached to
23-64094: Foundations, Utilities, Data Connections, etc. Install Services
Solicitation number
0000031149
Issued by
California

About this file

This document is a set of specifications for the construction of a mobile clinic site and utilities at the Department of State Hospitals (DSH) - Coalinga facility in California. The project is being managed by the State of California and is designated as JCCA #23791-6. The specifications cover the demolition, concrete work, electrical systems, communications systems, earthwork, paving, and utilities required for the project. The specifications were approved by the Office of the State Fire Marshal on January 5, 2024. No additional details are provided regarding the solicitation process, response dates, award, or contract term.

The specifications do not include any information on pricing, set-asides, incumbent contractors, funding sources, or other commercial terms. The document focuses solely on the technical requirements and scope of work for the construction project.

View the file

Other files

File Type Posted
23-64094,_Addendum__1.pdf PDF
23-64094_IFB,_Revised_5-9-2024.pdf PDF
23-64094,_Addendum__2.pdf PDF
4440-2364094000_IFB.pdf PDF
23-64094_IFB,_Revised_5-16-2024.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

22 December 2023

100% Submittal

JCCA #23791-6

MOBILE CLINIC SITE AND UTILITIES

DSH-COALINGA

SPECIFICATIONS

Prepared for:

DEPARTMENT OF STATE HOSPITALS

1215 O Street , 2ND Floor

Sacramento, California 95814

Phone: (916) 562-2314

Prepared by:

Architects • Engineers

385 Van Ness Avenue, Suite 208

Torrance, California 90501

Phone: (310) 212-7644 www.jccainc.com

OFFICE OF THE STATE FIRE MARSHAL

APPROVED FIRE AND PANIC ONLY

01/05/24

Approval of this plan does not authorize or approve any omission or deviation from applicable regulations. Final approval is subject to field inspection. One set of approved plans shall be available on the project site at all times.

23-4865 http://www.jccainc.com

J.C. Chang & Associates, Inc. Mobile Clinic Site and Utilities JCCA No. 23791-6 DSH-Coalinga

TABLE OF CONTENTS 1

TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

Contractor to obtain Division 00 from the Owner.

000105 Certifications Page

DIVISION 01 - GENERAL REQUIREMENTS

Contractor to obtain Division 01 from the Owner.

DIVISION 02 - EXISTING CONDITIONS

024119 Selective Demolition

DIVISION 03 - CONCRETE

030130 Maintenance of Cast-In-Place Concrete 031000 Concrete Forming and Accessories 032000 Concrete Reinforcing 033000 Cast-In-Place Concrete

DIVISION 05 - METALS

055000 Metal Fabrications

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

078413 Penetration Firestopping

DIVISION 26 - ELECTRICAL

260519 Low-Voltage Electrical Power Conductors and Cables 260526 Grounding and Bonding for Electrical Systems 260529 Hangers and Supports for Electrical Systems 260533 Raceway and Boxes for Electrical Systems 260543 Underground Ducts and Raceways for Electrical Systems 260553 Identification for Electrical Systems 262816 Enclosed Switches and Circuit Breakers

DIVISION 27 - COMMUNICATIONS

TABLE OF CONTENTS 2

270526 Grounding and Bonding for Communications Systems 270528 Pathways for Communications Systems 270529 Hangers and Supports for Communications Systems 270553 Identification for Communications Systems 271323 Communications Optical Fiber Backbone Cabling

DIVISION 31 - EARTHWORK

311000 Site Clearing 312000 Earth Moving 312333 Trenching and Backfilling 312500 Erosion and Sedimentation Controls

DIVISION 32 - EXTERIOR IMPROVEMENTS

321123 Aggregate Base Course 321216 Asphalt Paving 321313 Concrete Paving 321373 Concrete Paving Joint Sealants 321723 Pavement Markings 321726 Tactile Warning Surfacing

DIVISION 33 - UTILITIES

330500 Common Work Results for Utilities 331415 Site Water Distribution Piping

END OF TABLE OF CONTENTS

CERTIFICATIONS PAGE 000105 - 1

DOCUMENT 000105

CERTIFICATIONS PAGE

PROJECT TITLE: Mobile Clinic and Utilities

CLIENT AGENCY: Department of State Hospitals

LOCATION: Department of State Hospitals - Coalinga

24511 W. Jayne Avenue Coalinga, CA 93210

PROJECT NUMBER: JCCA #23791-6

OWNER: STATE OF CALIFORNIA

PROJECT DIRECTOR: Francisco Ramirez

Project Coordinator

Department of State Hospitals - Coalinga

Phone: (559) 707-8762

Email: Francisco.Ramirez@dsh.ca.gov

CONSULTANT: J.C. Chang & Associates, Inc.

James P. Redmond, PE. LEED AP

CIVIL ENGINEER

MyoungJin Kang RA

ARCHITECT

Sevag Avanessian, PE.

ELECTRICAL ENGINEER

Robert Onishi SE

STRUCTURAL ENGINEER

AUTHORITY HAVING

JURISDICTION

Date Signed: 10/27/23 Date Signed: 10/27/23 Date Signed: 10/27/23

Date Signed: 10/27/23

DSA

DEPARTMENT OF GENERAL SERVICES

DIVISION OF THE STATE ARCHITECT

DSA

DIVISION OF THE STATE ARCHITECT

DSADSA

IDENTIFICATION STAMP

DIV. OF THE STATE ARCHITECT

APP: INC:

REVIEWED FOR

SS FLS ACS

DATE:

02-121725

01/02/2024

CERTIFICATIONS PAGE 000105 - 2

THIS PAGE IS INTENTIONALLY LEFT BLANK

SELECTIVE DEMOLITION 024119 - 1

SECTION 024119

SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Demolition and removal of selected portions of building or structure.

2. Demolition and removal of selected site elements.

3. Salvage of existing items to be reused or recycled.

1.2 DEFINITIONS

A. Remove: Detach items from existing construction and dispose of them off-site unless indicated to be salvaged or reinstalled.

B. Remove and Reinstall: Detach items from existing construction, in a manner to prevent damage, prepare for reuse, and reinstall where indicated.

C. Existing to Remain: Leave existing items that are not to be removed and that are not otherwise indicated to be salvaged or reinstalled.

D. Dismantle: To remove by disassembling or detaching an item from a surface, using gentle methods and equipment to prevent damage to the item and surfaces; disposing of items unless indicated to be salvaged or reinstalled.

1.3 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.

1. Carefully salvage in a manner to prevent damage and promptly return to Owner.

1.4 PREINSTALLATION MEETINGS

A. Predemolition Conference: Conduct conference at Project site.

1. Inspect and discuss condition of construction to be selectively demolished.

2. Review structural load limitations of existing structure.

SELECTIVE DEMOLITION 024119 - 2

3. Review and finalize selective demolition schedule and verify availability of materials, demolition personnel, equipment, and facilities needed to make progress and avoid delays.

4. Review requirements of work performed by other trades that rely on substrates exposed by selective demolition operations.

5. Review areas where existing construction is to remain and requires protection.

1.5 INFORMATIONAL SUBMITTALS

A. Engineering Survey: Submit engineering survey of condition of building.

B. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property, for environmental protection, for dust control and, for noise control. Indicate proposed locations and construction of barriers.

C. Schedule of Selective Demolition Activities: Indicate the following:

1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity. Ensure Owner's building manager's on-site operations are uninterrupted.

2. Interruption of utility services. Indicate how long utility services will be interrupted.

3. Coordination for shutoff, capping, and continuation of utility services.

4. Use of elevator and stairs.

5. Coordination of Owner's continuing occupancy of portions of existing building and of

Owner's partial occupancy of completed Work.

D. Predemolition Photographs or Video: Show existing conditions of adjoining construction, including finish surfaces, that might be misconstrued as damage caused by salvage and demolition operations. Comply with Section 013233 "Photographic Documentation." Submit before Work begins.

E. Statement of Refrigerant Recovery: Signed by refrigerant recovery technician responsible for recovering refrigerant, stating that all refrigerant that was present was recovered and that recovery was performed according to EPA regulations. Include name and address of technician and date refrigerant was recovered.

F. Warranties: Documentation indicating that existing warranties are still in effect after completion of selective demolition.

1.6 CLOSEOUT SUBMITTALS

A. Inventory: Submit a list of items that have been removed and salvaged.

1.7 FIELD CONDITIONS

A. Owner will occupy portions of building immediately adjacent to selective demolition area.

Conduct selective demolition so Owner's operations will not be disrupted.

SELECTIVE DEMOLITION 024119 - 3

B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.

1. Before selective demolition, Owner will remove the following items:

C. Notify Architect of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

D. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.

1. Hazardous materials will be removed by Owner before start of the Work.

2. If suspected hazardous materials are encountered, do not disturb; immediately notify Architect and Owner. Hazardous materials will be removed by Owner under a separate contract.

E. Hazardous Materials: Present in buildings and structures to be selectively demolished. A report on the presence of hazardous materials is on file for review and use. Examine report to become aware of locations where hazardous materials are present.

1. Hazardous material remediation is specified elsewhere in the Contract Documents.

2. Do not disturb hazardous materials or items suspected of containing hazardous materials except under procedures specified elsewhere in the Contract Documents.

3. Owner will provide material safety data sheets for suspected hazardous materials that are known to be present in buildings and structures to be selectively demolished because of building operations or processes performed there.

F. Storage or sale of removed items or materials on-site is not permitted.

G. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain fire-protection facilities in service during selective demolition operations.

1.8 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials and using approved contractors so as not to void existing warranties. Notify warrantor before proceeding. Existing warranties include the following:

B. Notify warrantor on completion of selective demolition, and obtain documentation verifying that existing system has been inspected and warranty remains in effect. Submit documentation at Project closeout.

1.9 COORDINATION

A. Arrange selective demolition schedule so as not to interfere with Owner's operations.

SELECTIVE DEMOLITION 024119 - 4

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ANSI/ASSP A10.6 and NFPA 241.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations.

B. Review Project Record Documents of existing construction or other existing condition and hazardous material information provided by Owner. Owner does not guarantee that existing conditions are same as those indicated in Project Record Documents.

C. Perform an engineering survey of condition of building to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during selective building demolition operations.

1. Perform surveys as the Work progresses to detect hazards resulting from selective demolition activities.

D. Steel Tendons: Locate tensioned steel tendons and include recommendations for de-tensioning.

E. Verify that hazardous materials have been remediated before proceeding with building demolition operations.

F. Survey of Existing Conditions: Record existing conditions by use of measured drawings, preconstruction photographs or video, and templates.

1. Inventory and record the condition of items to be removed and salvaged.

2. Before selective demolition or removal of existing building elements that will be reproduced or duplicated in final Work, make permanent record of measurements, materials, and construction details required to make exact reproduction.

3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.

SELECTIVE DEMOLITION 024119 - 5

B. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off utility services and mechanical/electrical systems serving areas to be selectively demolished.

1. Arrange to shut off utilities with utility companies.

2. If services/systems are required to be removed, relocated, or abandoned, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.

3. Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC systems, equipment, and components indicated on Drawings to be removed.

a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material.

b. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same or compatible piping material and leave in place.

c. Equipment to Be Removed: Disconnect and cap services and remove equipment.

d. Equipment to Be Removed and Reinstalled: Disconnect and cap services and remove, clean, and store equipment; when appropriate, reinstall, reconnect, and make equipment operational.

e. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove equipment and deliver to Owner.

f. Ducts to Be Removed: Remove portion of ducts indicated to be removed and plug remaining ducts with same or compatible ductwork material.

g. Ducts to Be Abandoned in Place: Cap or plug ducts with same or compatible ductwork material and leave in place.

3.3 PROTECTION

A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

1. Provide protection to ensure safe passage of people around selective demolition area and to and from occupied portions of building.

2. Provide temporary weather protection, during interval between selective demolition of existing construction on exterior surfaces and new construction, to prevent water leakage and damage to structure and interior areas.

3. Protect walls, ceilings, floors, and other existing finish work that are to remain or that are exposed during selective demolition operations.

4. Cover and protect furniture, furnishings, and equipment that have not been removed.

5. Comply with requirements for temporary enclosures, dust control, heating, and cooling specified in Section 015000 "Temporary Facilities and Controls."

B. Temporary Shoring: Design, provide, and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

1. Strengthen or add new supports when required during progress of selective demolition.

SELECTIVE DEMOLITION 024119 - 6

C. Remove temporary barricades and protections where hazards no longer exist.

3.4 SELECTIVE DEMOLITION, GENERAL

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Proceed with selective demolition systematically, from higher to lower level. Complete selective demolition operations above each floor or tier before disturbing supporting members on the next lower level.

2. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.

Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping. Temporarily cover openings to remain.

3. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

4. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.

5. Maintain fire watch during and for at least <Insert number> hours after flame-cutting operations.

6. Maintain adequate ventilation when using cutting torches.

7. Remove decayed, vermin-infested, or otherwise dangerous or unsuitable materials and promptly dispose of off-site.

8. Remove structural framing members and lower to ground by method suitable to avoid free fall and to prevent ground impact or dust generation.

9. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

10. Dispose of demolished items and materials promptly. Comply with requirements per

Department of State Hospital "Construction Waste Management and Disposal" requirements.

B. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

C. Removed and Salvaged Items:

1. Clean salvaged items.

2. Pack or crate items after cleaning. Identify contents of containers.

3. Store items in a secure area until delivery to Owner.

4. Transport items to Owner's storage area designated by Owner.

5. Protect items from damage during transport and storage.

D. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse.

SELECTIVE DEMOLITION 024119 - 7

2. Pack or crate items after cleaning and repairing. Identify contents of containers.

3. Protect items from damage during transport and storage.

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

E. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Architect, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.

3.5 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS

A. Concrete: Demolish in small sections. Using power-driven saw, cut concrete to a depth of at least 3/4 inch (19 mm) at junctures with construction to remain. Dislodge concrete from reinforcement at perimeter of areas being demolished, cut reinforcement, and then remove remainder of concrete. Neatly trim openings to dimensions indicated.

B. Concrete: Demolish in sections. Cut concrete full depth at junctures with construction to remain and at regular intervals using power-driven saw, and then remove concrete between saw cuts.

C. Masonry: Demolish in small sections. Cut masonry at junctures with construction to remain, using power-driven saw, and then remove masonry between saw cuts.

D. Concrete Slabs-on-Grade: Saw-cut perimeter of area to be demolished, and then break up and remove.

E. Resilient Floor Coverings: Remove floor coverings and adhesive according to recommendations in RFCI's "Recommended Work Practices for the Removal of Resilient Floor Coverings." Do not use methods requiring solvent-based adhesive strippers.

F. Roofing: Remove no more existing roofing than what can be covered in one day by new roofing and so that building interior remains watertight and weathertight. See Section for new roofing requirements.

1. Remove existing roof membrane, flashings, copings, and roof accessories.

2. Remove existing roofing system down to substrate.

3.6 DISPOSAL OF DEMOLISHED MATERIALS

A. Remove demolition waste materials from Project site and dispose of them in an EPA-approved construction and demolition waste landfill acceptable to authorities having jurisdiction.

1. Do not allow demolished materials to accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

B. Burning: Do not burn demolished materials.

SELECTIVE DEMOLITION 024119 - 8

3.7 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

END OF SECTION 024119

MAINTENANCE OF CAST-IN-PLACE CONCRETE 030130 - 1

SECTION 030130

MAINTENANCE OF CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Removal of deteriorated concrete and subsequent replacement and patching.

2. Corrosion-inhibiting treatment.

1.3 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site

1. Review methods and procedures related to concrete maintenance including, but not limited to, the following:

a. Verify concrete-maintenance specialist's personnel, equipment, and facilities needed to make progress and avoid delays.

b. Materials, material application, sequencing, tolerances, and required clearances.

c. Quality-control program.

d. Coordination with property owner.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Include construction details, material descriptions, chemical composition, physical properties, test data, and mixing, preparation, and application instructions.

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For manufacturers.

B. Material Certificates: For each type of portland cement and aggregate supplied for mixing or adding to products at Project site.

MAINTENANCE OF CAST-IN-PLACE CONCRETE 030130 - 2

C. Product Test Reports: For each joint-filler for tests performed by manufacturer and witnessed by a qualified testing agency.

D. Field quality-control reports.

E. Quality-Control Program: Submit before work begins.

1.6 QUALITY ASSURANCE

1. Concrete Removal and Patching: Remove and repair an approximately 50 sq. ft. (4.6

sq. m) area of deteriorated concrete deck

1.7 DELIVERY, STORAGE, AND HANDLING

A. Comply with manufacturer's written instructions for minimum and maximum temperature requirements and other conditions for storage.

B. Store cementitious materials off the ground, under cover, and in a dry location.

C. Store aggregates covered and in a dry location; maintain grading and other required characteristics and prevent contamination.

1.8 FIELD CONDITIONS

A. Hot-Weather Requirements for Cementitious Materials: Protect repair work when temperature and humidity conditions produce excessive evaporation of water from patching materials.

Provide artificial shade and wind breaks, and use cooled materials as required. Do not apply to substrates with temperatures of 90 deg F (32 deg C) and above.

PART 2 - PRODUCTS

2.1 BONDING AGENTS

A. Epoxy-Modified, Cementitious Bonding and Anticorrosion Agent: Manufactured product that consists of water-insensitive epoxy adhesive, portland cement, and water-based solution of corrosion-inhibiting chemicals that forms a protective film on steel reinforcement.

B. Epoxy Bonding Agent: ASTM C881/C881M, bonding system Type II and free of VOCs.

C. Latex Bonding Agent, Redispersible: ASTM C1059/C1059M, Type for use at nonstructural and interior locations unless otherwise indicated.

MAINTENANCE OF CAST-IN-PLACE CONCRETE 030130 - 3

2.2 PREPLACED CONCRETE MATERIALS

A. Preplaced Aggregate: Washed aggregate, ASTM C33/C33M, Class 5S, with 95 to 100 percent passing a 1-1/2-inch (37.5-mm) sieve, 40 to 80 percent passing a 1-inch (25-mm) sieve, 20 to 45 percent passing a 3/4-inch (19-mm) sieve, zero to 10 percent passing a 1/2-inch (12.5-mm) sieve, and zero to 2 percent passing a 3/8-inch (9.5-mm) sieve

B. Fine Aggregate for Grout: Fine aggregate according to ASTM C33/C33M, but with 100 percent passing a No. 8 (2.36-mm) sieve, 95 to 100 percent passing a No. 16 (1.18-mm) sieve, 55 to 80 percent passing a No. 30 (0.6-mm) sieve, 30 to 55 percent passing a No. 50 (0.3-mm) sieve, 10 to 30 percent passing a No. 100 (0.15-mm) sieve, zero to 10 percent passing a No. 200 (0.075-

mm) sieve, and having a fineness modulus of 1.30 to 2.10.

C. Grout Fluidifier for Grout: ASTM C937.

D. Pozzolans for Grout: ASTM C618.

2.3 JOINT FILLER

A. Epoxy Joint Filler: Two-component, semirigid, 100 percent solids, epoxy resin with a Type A Shore durometer hardness of at least 80 according to ASTM D2240.

B. Polyurea Joint Filler: Two-component, semirigid, 100 percent solids, polyurea resin with a Type A Shore durometer hardness of at least 80 according to ASTM D2240.

2.4 CORROSION-INHIBITING MATERIALS

A. Corrosion-Inhibiting Treatment: Waterborne solution of alkaline corrosion-inhibiting chemicals for concrete-surface application that penetrates concrete by diffusion and forms a protective film on steel reinforcement.

2.5 MISCELLANEOUS MATERIALS

A. Portland Cement: ASTM C150/C150M, Type I, II, or III unless otherwise indicated.

B. Water: Potable.

2.6 MIXES

A. General: Mix products, in clean containers, according to manufacturer's written instructions.

1. Do not add water, thinners, or additives unless recommended by manufacturer.

2. When practical, use manufacturer's premeasured packages to ensure that materials are mixed in proper proportions. When premeasured packages are not used, measure ingredients using graduated measuring containers; do not estimate quantities or use shovel or trowel as unit of measure.

MAINTENANCE OF CAST-IN-PLACE CONCRETE 030130 - 4

3. Do not mix more materials than can be used within time limits recommended by manufacturer. Discard materials that have begun to set.

B. Concrete: Comply with Section 033000 "Cast-in-Place Concrete."

C. Grout for Use with Preplaced Aggregate: Proportion according to ASTM C938. Add grout fluidifier to mixing water followed by portland cement, pozzolan, and fine aggregate.

PART 3 - EXECUTION

3.1 CONCRETE MAINTENANCE

A. Have concrete-maintenance work performed only by qualified general contractor.

B. Comply with manufacturers' written instructions for surface preparation and product application.

3.2 EXAMINATION

A. Perform surveys as the Work progresses to detect hazards resulting from concrete-maintenance work.

3.3 PREPARATION

A. Ensure that supervisory personnel are on-site and on duty when concrete maintenance work begins and during its progress.

B. Protect persons, motor vehicles, surrounding surfaces of building being repaired, building site, plants, and surrounding buildings from harm resulting from concrete maintenance work.

1. Comply with each product manufacturer's written instructions for protections and precautions. Protect against adverse effects of products and procedures on people and adjacent materials, components, and vegetation.

2. Use only proven protection methods appropriate to each area and surface being protected.

3. Provide temporary barricades, barriers, and directional signage to exclude public from areas where concrete maintenance work is being performed.

4. Erect temporary protective covers over walkways and at points of pedestrian and vehicular entrance and exit that must remain in service during course of concrete maintenance work.

5. Contain dust and debris generated by concrete maintenance work and prevent it from reaching the public or adjacent surfaces.

6. Use water-mist sprinkling and other wet methods to control dust only with adequate, approved procedures and equipment that ensure that such water will not create a hazard or adversely affect other building areas or materials.

7. Protect floors and other surfaces along haul routes from damage, wear, and staining.

MAINTENANCE OF CAST-IN-PLACE CONCRETE 030130 - 5

8. Provide supplemental sound-control treatment to isolate removal and dismantling work from other areas of the building.

9. Dispose of debris and runoff from operations by legal means and in a manner that prevents soil erosion, undermining of paving and foundations, damage to landscaping, and water penetration into building interiors.

C. Existing Drains: Prior to the start of work in an area, test drainage system to ensure that it is functioning properly. Notify Engineer of Record immediately of inadequate drainage or blockage. Do not begin work in an area until the drainage system is in working order.

1. Prevent solids such as aggregate or mortar residue from entering the drainage system.

Clean out drains and drain lines that become sluggish or blocked by sand or other materials resulting from concrete maintenance work.

2. Protect drains from pollutants. Block drains or filter out sediments, allowing only clean water to pass.

D. Preparation for Concrete Removal: Examine construction to be repaired to determine best methods to safely and effectively perform concrete maintenance work. Examine adjacent work to determine what protective measures will be necessary. Make explorations, probes, and inquiries as necessary to determine condition of construction to be removed in the course of repair.

1. Verify that affected utilities have been disconnected and capped.

2. Inventory and record the condition of items to be removed for reinstallation or salvage.

3. Provide and maintain shoring, bracing, and temporary structural supports as required to preserve stability and prevent unexpected or uncontrolled movement, settlement, or collapse of construction being demolished and construction and finishes to remain.

Strengthen or add new supports when required during progress of removal work.

E. Reinforcing-Bar Preparation: Remove loose and flaking rust from exposed reinforcing bars by wire brushing until only tightly adhered light rust remains.

3.4 REMOVAL OF CONCRETE

A. Do not overload structural elements with debris.

B. Saw-cut perimeter of areas indicated for removal to a depth of at least 4 inches. Make cuts perpendicular to concrete surfaces and no deeper than cover on reinforcement.

C. Remove deteriorated and delaminated concrete by breaking up and dislodging from reinforcement.

D. Where half or more of the perimeter of reinforcing bar is exposed, bond between reinforcing bar and surrounding concrete is broken, or reinforcing bar is corroded, remove concrete from entire perimeter of bar and to provide at least 3/4-inch (19-mm) clearance around bar.

E. Test areas where concrete has been removed by tapping with hammer, and remove additional concrete until unsound and disbonded concrete is completely removed.

MAINTENANCE OF CAST-IN-PLACE CONCRETE 030130 - 6

F. Provide surfaces with a fractured profile of at least 1/8 inch (3 mm) that are approximately perpendicular or parallel to original concrete surfaces. At columns and walls, make top and bottom surfaces level unless otherwise directed.

G. Thoroughly clean removal areas of loose concrete, dust, and debris.

3.5 APPLICATION OF BONDING AGENT

A. Epoxy-Modified, Cementitious Bonding and Anticorrosion Agent: Apply to reinforcing bars by stiff brush or hopper spray according to manufacturer's written instructions. Apply to reinforcing bars in two coats, allowing first coat to dry two to three hours before applying second coat. Allow to dry before placing patching mortar or concrete.

B. Epoxy Bonding Agent: Apply to reinforcing bars and concrete by brush, roller, or spray according to manufacturer's written instructions, leaving no pinholes or other uncoated areas.

Apply to reinforcing bars in at least two coats, allowing first coat to dry before applying second coat. Place patching mortar or concrete while epoxy is still tacky. If epoxy dries, recoat before placing patching mortar or concrete.

C. Latex Bonding Agent, Type I: Apply to concrete by brush roller or spray. Allow to dry before placing patching mortar or concrete.

D. Latex Bonding Agent, Type II: Mix with portland cement and scrub into concrete surface according to manufacturer's written instructions. Place patching mortar or concrete while bonding agent is still wet. If bonding agent dries, recoat before placing patching mortar or concrete.

E. Mortar Scrub Coat for Job-Mixed Patching Mortar Dampen repair area and surrounding concrete 6 inches (150 mm) beyond repair area. Remove standing water and apply scrub coat with a brush, scrubbing it into surface and thoroughly coating repair area. If scrub coat dries, recoat before placing patching mortar or concrete.

3.6 CONCRETE PLACEMENT

A. Place concrete according to Section 033000 "Cast-in-Place Concrete" and as specified in this article.

B. Pretreatment: Apply epoxy-modified, cementitious bonding and anticorrosion agent epoxy bonding agent to reinforcement and concrete substrate.

C. Standard Placement: Place concrete by form-and-pump method unless otherwise indicated.

1. Use vibrators to consolidate concrete as it is placed.

2. At unformed surfaces, screed concrete to produce a surface that when finished with patching mortar will match required profile and surrounding concrete.

MAINTENANCE OF CAST-IN-PLACE CONCRETE 030130 - 7

D. Form-and-Pump Placement: Place concrete by form-and-pump method where indicated.

1. Design and construct forms to resist pumping pressure in addition to weight of wet concrete. Seal joints and seams in forms and where forms abut existing concrete.

2. Pump concrete into place from bottom to top, releasing air from forms as concrete is introduced. When formed space is full, close air vents and pressurize to 14 psi (96 kPa).

E. Wet-cure concrete for not less than seven days by leaving forms in place or keeping surfaces continuously wet by water-fog spray or water-saturated absorptive cover.

F. Fill placement cavities with dry-pack mortar and repair voids with patching mortar. Finish to match surrounding concrete.

END OF SECTION 030130

MAINTENANCE OF CAST-IN-PLACE CONCRETE 030130 - 8

CONCRETE FORMING AND ACCESSORIES 031000 - 1

SECTION 031000

CONCRETE FORMING AND ACCESSORIES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Form-facing material for cast-in-place concrete.

2. Form liners.

3. Insulating concrete forms.

4. Shoring, bracing, and anchoring.

B. Related Requirements:

1. Section 321313 "Concrete Paving" for formwork related to concrete pavement and walks.

1.3 DEFINITIONS

A. Form-Facing Material: Temporary structure or mold for the support of concrete while the concrete is setting and gaining sufficient strength to be self-supporting.

B. Formwork: The total system of support of freshly placed concrete, including the mold or sheathing that contacts the concrete, as well as supporting members, hardware, and necessary bracing.

1.4 INFORMATIONAL SUBMITTALS

A. Field quality-control reports.

1.5 QUALITY ASSURANCE

A. Testing and Inspection Agency Qualifications: An independent agency, in accordance with ASTM C1077 and ASTM E329 for testing indicated.

CONCRETE FORMING AND ACCESSORIES 031000 - 2

1.6 DELIVERY, STORAGE, AND HANDLING

A. Form Liners: Store form liners under cover to protect from sunlight.

B. Insulating Concrete Forms: Store forms off ground and under cover to protect from moisture, sunlight, dirt, oil, and other contaminants.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Concrete Formwork: Design, engineer, erect, shore, brace, and maintain formwork, shores, and reshores in accordance with ACI 301, to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied, until structure can support such loads, so that resulting concrete conforms to the required shapes, lines, and dimensions.

1. Design wood panel forms in accordance with APA's "Concrete Forming Design/Construction Guide."

2. Design formwork to limit deflection of form-facing material to 1/240 of center-to-center spacing of supports.

B. Design, engineer, erect, shore, brace, and maintain insulating concrete forms in accordance with ACI 301, to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied, until structure can support such loads, so that resulting concrete conforms to the required shapes, lines, and dimensions.

2.2 FORM-FACING MATERIALS

A. As-Cast Surface Form-Facing Material:

1. Provide continuous, true, and smooth concrete surfaces.

2. Furnish in largest practicable sizes to minimize number of joints.

3. Acceptable Materials: As required to comply with Surface Finish designations specified in Section 033000 "Cast-In-Place Concrete, and as follows:

a. Plywood, metal, or other approved panel materials.

b. Exterior-grade plywood panels, suitable for concrete forms, complying with

DOC PS 1, and as follows:

1) APA HDO (high-density overlay).

2) APA MDO (medium-density overlay); mill-release agent treated and edge sealed.

3) APA Structural 1 Plyform, B-B or better; mill oiled and edge sealed.

4) APA Plyform Class I, B-B or better; mill oiled and edge sealed.

B. Concealed Surface Form-Facing Material: Lumber, plywood, metal, plastic, or another approved material.

CONCRETE FORMING AND ACCESSORIES 031000 - 3

1. Provide lumber dressed on at least two edges and one side for tight fit.

C. Void Forms: Biodegradable paper surface, treated for moisture resistance, structurally sufficient to support weight of plastic concrete and other superimposed loads.

2.3 INSULATING CONCRETE FORMS

A. Insulating Concrete Forms: Concrete-forming system complying with ASTM E2634, consisting of two panels of insulation connected with cross ties.

1. Insulation: ASTM C578, Type II, expanded polystyrene.

a. Thickness: Not less than 2-1/2 inches each face.

b. Surface-Burning Characteristics: Comply with ASTM E84; testing by a qualified testing agency. Identify products with appropriate markings of applicable testing agency.

1) Flame Spread: 25 or less.

2) Smoke Developed Index: 450 or less.

PART 3 - EXECUTION

3.1 INSTALLATION OF FORMWORK

A. Comply with ACI 301.

B. Construct formwork, so concrete members and structures are of size, shape, alignment, elevation, and position indicated, within tolerance limits of ACI 117 and to comply with the Surface Finish designations specified in Section 033000 "Cast-In-Place Concrete" for as-cast finishes.

C. Limit concrete surface irregularities as follows:

1. Surface Finish-1.0: ACI 117 Class D, 1 inch.

2. Surface Finish-2.0: ACI 117 Class B, 1/4 inch.

3. Surface Finish-3.0: ACI 117 Class A, 1/8 inch.

D. Construct forms tight enough to prevent loss of concrete mortar.

1. Minimize joints.

2. Exposed Concrete: Symmetrically align joints in forms.

E. Construct removable forms for easy removal without hammering or prying against concrete surfaces.

1. Provide crush or wrecking plates where stripping may damage cast-concrete surfaces.

2. Provide top forms for inclined surfaces steeper than 1.5 horizontal to 1 vertical.

3. Install keyways, reglets, recesses, and other accessories, for easy removal.

CONCRETE FORMING AND ACCESSORIES 031000 - 4

F. Do not use rust-stained, steel, form-facing material.

G. Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve required elevations and slopes in finished concrete surfaces.

1. Provide and secure units to support screed strips

2. Use strike-off templates or compacting-type screeds.

H. Provide temporary openings for cleanouts and inspection ports where interior area of formwork is inaccessible.

1. Close openings with panels tightly fitted to forms and securely braced to prevent loss of concrete mortar.

2. Locate temporary openings in forms at inconspicuous locations.

I. At construction joints, overlap forms onto previously placed concrete not less than 12 inches.

J. Form openings, chases, offsets, sinkages, keyways, reglets, blocking, screeds, and bulkheads required in the Work.

1. Determine sizes and locations from trades providing such items.

2. Obtain written approval of Architect prior to forming openings not indicated on

Drawings.

K. Construction and Movement Joints:

1. Construct joints true to line with faces perpendicular to surface plane of concrete.

2. Install so strength and appearance of concrete are not impaired, at locations indicated or as approved by Architect.

3. Place joints perpendicular to main reinforcement.

4. Locate joints for beams, slabs, joists, and girders in the middle third of spans.

a. Offset joints in girders a minimum distance of twice the beam width from a beam-girder intersection.

5. Locate horizontal joints in walls and columns at underside of floors, slabs, beams, and girders and at the top of footings or floor slabs.

L. Provide temporary ports or openings in formwork where required to facilitate cleaning and inspection.

1. Locate ports and openings in bottom of vertical forms, in inconspicuous location, to allow flushing water to drain.

2. Close temporary ports and openings with tight-fitting panels, flush with inside face of form, and neatly fitted, so joints will not be apparent in exposed concrete surfaces.

M. Clean forms and adjacent surfaces to receive concrete. Remove chips, wood, sawdust, dirt, and other debris just before placing concrete.

CONCRETE FORMING AND ACCESSORIES 031000 - 5

N. Retighten forms and bracing before placing concrete, as required, to prevent mortar leaks and maintain proper alignment.

O. Coat contact surfaces of forms with form-release agent, according to manufacturer's written instructions, before placing reinforcement.

3.2 REMOVING AND REUSING FORMS

A. Formwork for sides of beams, walls, columns, and similar parts of the Work that does not support weight of concrete may be removed after cumulatively curing at not less than 50 deg F for 24 hours after placing concrete. Concrete has to be hard enough to not be damaged by form-removal operations, and curing and protection operations need to be maintained.

1. Leave formwork for beam soffits, joists, slabs, and other structural elements that support weight of concrete in place until concrete has achieved at least 70 percent of its 28-day design compressive strength.

2. Remove forms only if shores have been arranged to permit removal of forms without loosening or disturbing shores.

B. Clean and repair surfaces of forms to be reused in the Work.

1. Split, frayed, delaminated, or otherwise damaged form-facing material are unacceptable for exposed surfaces.

2. Apply new form-release agent.

C. When forms are reused, clean surfaces, remove fins and laitance, and tighten to close joints.

1. Align and secure joints to avoid offsets.

2. Do not use patched forms for exposed concrete surfaces unless approved by Architect.

3.3 SHORING AND RESHORING INSTALLATION

A. Comply with ACI 318 and ACI 301 for design, installation, and removal of shoring and reshoring.

1. Do not remove shoring or reshoring until measurement of slab tolerances is complete.

B. Plan sequence of removal of shores and reshore to avoid damage to concrete. Locate and provide adequate reshoring to support construction without excessive stress or deflection.

3.4 FIELD QUALITY CONTROL

A. Special Inspections: Owner will engage a qualified testing and inspecting agency to perform field tests and inspections and prepare test reports.

END OF SECTION 031000

CONCRETE FORMING AND ACCESSORIES 031000 - 6

CONCRETE REINFORCING 032000 - 1

SECTION 032000

CONCRETE REINFORCING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Steel reinforcement bars.

2. Welded-wire reinforcement.

1.2 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1. Review the following:

a. Special inspection and testing and inspecting agency procedures for field quality control.

b. Construction contraction and isolation joints.

c. Steel-reinforcement installation.

1.3 ACTION SUBMITTALS

A. Product Data: For the following:

1. Each type of steel reinforcement.

2. Bar supports.

3. Mechanical splice couplers.

B. Shop Drawings: Comply with ACI SP-066:

1. Include placing drawings that detail fabrication, bending, and placement.

2. Include bar sizes, lengths, materials, grades, bar schedules, stirrup spacing, bent bar diagrams, bar arrangement, location of splices, lengths of lap splices, details of mechanical splice couplers, details of welding splices, tie spacing, hoop spacing, and supports for concrete reinforcement.

3. For structural thermal break insulated connection system, indicate general configuration, insulation dimensions, tension bars, compression pads, shear bars, and dimensions.

1.4 INFORMATIONAL SUBMITTALS

A. Qualification Statements: For testing and inspection agency.

CONCRETE REINFORCING 032000 - 2

B. Delegated Design Engineer Qualifications: Include the following:

1. Experience providing delegated design engineering services of the type indicated.

C. Welding certificates.

1. Reinforcement To Be Welded: Welding procedure specification in accordance with

AWS D1.4/D1.4M.

D. Material Certificates: For each of the following, signed by manufacturers:

1. Epoxy-Coated Reinforcement: CRSI's "Epoxy Coating Plant Certification."

2. Dual-Coated Reinforcement: CRSI's "Epoxy Coating Plant Certification."

E. Material Test Reports: For the following, from a qualified testing agency:

1. Steel Reinforcement:

a. For reinforcement to be welded, mill test analysis for chemical composition and carbon equivalent of the steel in accordance with ASTM A706/A706M.

2. Mechanical splice couplers.

F. Field quality-control reports.

G. Minutes of preinstallation conference.

1.5 QUALITY ASSURANCE

A. Testing Agency Qualifications: An independent agency, acceptable to authorities having jurisdiction, qualified in accordance with ASTM C1077 and ASTM E329 for testing indicated.

B. Welding Qualifications: Qualify procedures and personnel in accordance with

AWS D1.4/D 1.4M.

C. Mockups: Reinforcing for cast-concrete formed surfaces, to demonstrate tolerances and standard of workmanship.

1. Build panel approximately 100 sq. ft. (9.3 sq. m) for formed surface in the location indicated on Drawings or, if not indicated, as directed by Architect.

2. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.

1.6 DELIVERY, STORAGE, AND HANDLING

A. Steel Reinforcement: Deliver, store, and handle steel reinforcement to prevent bending and damage and to avoid damaging coatings on steel reinforcement.

1. Store reinforcement to avoid contact with earth.

CONCRETE REINFORCING 032000 - 3

2. Do not allow epoxy-coated reinforcement to be stored outdoors for more than 60 days without being stored under an opaque covering.

3. Do not allow dual-coated reinforcement to be stored outdoors for more than 60 days without being stored under an opaque covering.

4. Do not allow stainless steel reinforcement to come into contact with uncoated reinforcement.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Delegated Design: Engage a qualified professional engineer, as defined in Section 014000 "Quality Requirements," to design structural thermal break insulated connection system, including attachment to building construction.

B. Structural Performance of Structural Thermal Break Insulating Connection System: Structural thermal break insulated connection system to withstand the following loads and stresses:

1. Dead Loads: As indicated on Drawings.

a. Shear Load: As indicated on Drawings.

b. Bending Moment: As indicated on Drawings.

2. Live Loads: As indicated on Drawings.

a. Shear Load: As indicated on Drawings.

b. Bending Moment: As indicated on Drawings.

C. Seismic Performance of Structural Thermal Break Insulated Connection System: Structural thermal break Insulated connection system to withstand the effects of earthquake motions determined according to ASCE/SEI 7.

2.2 STEEL REINFORCEMENT

A. Reinforcing Bars: ASTM A615/A615M, Grade 60 (Grade 420), deformed.

B. Low-Alloy Steel Reinforcing Bars: ASTM A706/A706M, deformed.

C. Headed-Steel Reinforcing Bars: ASTM A970/A970M.

D. Galvanized Reinforcing Bars:

1. Steel Bars: ASTM A615/A615M, Grade 60 (Grade 420), deformed bars.

2. Zinc Coating: ASTM A767/A767M, Class I zinc coated after fabrication and bending.

E. Epoxy-Coated Reinforcing Bars:

1. Steel Bars: ASTM A615/A615M, Grade 60 (Grade 420), deformed bars.

CONCRETE REINFORCING 032000 - 4

2. Epoxy Coating: ASTM A775/A775M or ASTM A934/A934M with less than 2 percent damaged coating in each 12-inch (305-mm) bar length.

F. Dual-Coated Reinforcing Bars: ASTM A1055/A1055M.

1. Steel Bars: ASTM A615/A615M, Grade 60 (Grade 420), deformed bars.

2. Zinc Coating: ASTM A1055/A1055M Type II.

3. Epoxy Coating: ASTM A775/A775M or ASTM A934/A934M with less than 2 percent damaged coating in each 12-inch (300-mm) bar length.

G. Steel Bar Mats: ASTM A184/A184M, fabricated from ASTM A615/A615M, Grade 60 (Grade 420), deformed bars, assembled with clips.

H. Plain-Steel Welded-Wire Reinforcement: ASTM A1064/A1064M, plain, fabricated from as-drawn steel wire into flat sheets.

I. Deformed-Steel Welded-Wire Reinforcement: ASTM A1064/A1064M, flat sheet.

J. Galvanized-Steel Welded-Wire Reinforcement: ASTM A1064/A1064M, plain, fabricated from galvanized-steel wire into flat sheets.

K. Epoxy-Coated Welded-Wire Reinforcement: ASTM A884/A884M, Class A coated, Type 1, plain steel.

2.3 REINFORCEMENT ACCESSORIES

A. Joint Dowel Bars: ASTM A615/A615M, Grade 60 (Grade 420), plain-steel bars, cut true to length with ends square and free of burrs.

B. Epoxy-Coated Joint Dowel Bars: ASTM A615/A615M, Grade 60 (Grade 420), plain-steel bars, ASTM A775/A775M epoxy coated.

C. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars and welded-wire reinforcement in place.

1. Manufacture bar supports from steel wire, plastic, or precast concrete in accordance with CRSI's "Manual of Standard Practice," of greater compressive strength than concrete and as follows:

a. For concrete surfaces exposed to view, where legs of wire bar supports contact forms, use CRSI Class 1 plastic-protected steel wire, all-plastic bar supports, or CRSI Class 2 stainless steel bar supports.

b. For epoxy-coated reinforcement, use CRSI Class 1A epoxy-coated or other dielectric-polymer-coated wire bar supports.

c. For dual-coated reinforcement, use CRSI Class 1A epoxy-coated or other dielectric-polymer-coated wire bar supports.

d. For zinc-coated reinforcement, use galvanized wire or dielectric-polymer-coated wire bar supports.