23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion
Solicitation number
PE-72155-NONST-2023-000000013
Issued by
Richmond County, Atlanta City, Georgia

About this file

This document is an Addendum to a Request for Proposals (RFP) issued by the Maryland Department of Transportation (MDOT) for general engineering and construction services. The RFP covers a 5-year base period with an option to extend for up to 5 additional years. The services requested include general engineering, construction management, and related support services for MDOT's capital improvement program. The addendum provides clarifications and additional requirements, including a revised project schedule, additional proposal submission requirements, and changes to the Scope of Work. Key dates include a revised proposal due date of April 15, 2023, and an anticipated award date of June 1, 2023.

The RFP includes Disadvantaged Business Enterprise (DBE) participation goals, and allows for the use of Joint Ventures and/or Mentor-Protégé relationships to meet those goals. Pricing is to be submitted on a time and materials basis, with fully-burdened hourly labor rates. Funding for the contract will be provided through a combination of federal, state, and local sources. The current incumbent contractor is ABC Engineering, Inc., whose contract expires on May 31, 2023.

View the file

Other files

File Type Posted
23_237_ADD1_1.pdf PDF
23_237_ADD1_2.pdf PDF
23_237_ADD1_4.pdf PDF
23_237_ITB.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART 1 - GENERAL

1.01 SUMMARY

SECTION 01 20 10

PROJECT MEETINGS

This Section specifies administrative and procedural requirements for project meetings including but not limited to:

A. Pre-construction Conference

B. Progress Meetings

C. Coordination Meetings

1.02 DESCRIPTION

A. The Owner will schedule and administer a preconstruction conference, weekly construction progress meetings, and specially called meetings throughout the progress of work. The Engineer or Owner will be responsible for preparing the agenda, making arrangements, preparing the meeting summaries, and presiding at these meetings.

B. Representatives of Contractor, Subcontractor(s), and Suppliers attending these meetings shall be q~alified and authorized to act on behalf of the entity each represents.

C. the Contractor shall attend meetings to ascertain that work is expedited consistent with Contract Documents and construction schedules.

1.03 PRECONSTRUCTION CONFERENCE

After award of the contract, but prior to the notice to proceed, a joint meeting shall be held with representatives of the Owner, Engineer, Contractor, including the Project Superintendent, and other invited parties which may be affected by the project.

This meeting is intended to introduce the various key personnel from each organization and to discuss the Contract Documents, the start of construction, order of work, labor and legal requirements, names of the major subcontractors, method of payment, shop drawing submittal schedule, protection of existing facilities and other pertinent items associated with the Project. The Contractor shall bring five (5) copies of a construction schedule~ schedule of values, and shop drawing submittal log to this meeting.

The suggested agenda for the preconstruction meeting is as follows:

A. Introduction of key personnel and roles

Augusta Engineering and Environmental Services Department Deans Bride Road Landfill 2023 GCCS Expansion

Project Meetings 012010-1

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion

B. Overview of project

1. Project summary

2. Contract completion time

3. Liquidated damages

4. Guarantee of work

C. Project schedule

D. Critical work sequencing

E. Labor requirements

F. Relationship and coordination with:

1. Other Contracts

2. On-going landfill operations

G. Use of premises

1. Site access and traffic control

2. Office, work and storage areas

3. Temporary facilities/utilities

4. Safety and first aid procedures

5. Security procedures

6. Posting of signs

7. Clean-up procedures

8. Other Owner requirements

H. Procedures and processing of:

1. Shop drawings

2. Applications for payment

3. Partial payments

4. Change orders

Augusta Engineering and Environmental Services Department Deans Bride Road Landfill 2023 GCCS Expansion

Project Meetings 012010-2

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion

1.04

5. Requests for information

6. Record documents

I. Construction facilities controls

J. Staking of work

K. Equipment to be used

L. Material/manufacturers/suppliers to be used

M. Major equipment/material deliveries

N. On-site material storage requirements

0. Project inspections

P. Record documentation

PROGRESS MEETINGS

During the course of the Contract, progress meetings will be organized weekly, or as needed, and conducted by the Owner and/or Engineer to discuss the progress of the Work. Depending on the project progress and schedule, the Owner reserves the right to request meetings every other week instead Qf weekly. The Contractor and Project Superintendent shall attend these meetings.

The suggested agenda for these meetings:

A. Review summary of previous meeting

B. Work progress

1. Since last meeting

2. Expected progress during next work period

C. Field observations, problems, conflicts

D. Construction schedule

1. Problems which impede the construction schedule

2. Revisions to schedule

3. Critical/long-lead items

4. Off-site fabrication and delivery schedules

Augusta Engineering and Environmental Services Department Deans Bride Road Landfill 2023 GCCS Expansion

Project Meetings 012010-3

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion

E. Coordination of work items with the Owner's activities

F. Shop drawing submittals

1. Status of reviews

2. Submittal requirements

3. Remaining submittals

G. Record documents

1. Well logs, pipe installation records

2. Photographs

3. Red-line mark-ups

4. Survey Notes

H. Maintenance of quality standards

I. Pending changes and substitutions

1. Effect on construction schedule and on completion date

2. Effect on other Contracts of the project

J. Other Business

1.05 COORDINATION MEETINGS

Coordination meetings will be organized as needed unless the specific subject warrants an immediate meeting and cannot wait to be discussed during the next scheduled progress meeting. The Contractor and Project Superintendent shall attend these meetings.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION

Augusta Engineering and Environmental Services Department Deans Bride Road Landfill 2023 GCCS Expansion

Project Meetings 012010-4

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion

SECTION 01 30 10

CONTRACTORSUBMITTALS

PART 1 - GENERAL

1.01 PRE-CONSTRUCTION MEETING SUBMITTALS

A. At the pre-construction meeting, the Contractor shall submit the following items to the Engineer for review:

1. A preliminary schedule of Shop Drawings submittals and target dates for the project prior to start of construction.

2. Schedule of values that will be used for payment applications.

3. A list of any and all permits and licenses the Contractor shall obtain indicating the agency required to grant the permit and the expected date of submittal for the permit and required date for receipt of the permit.

4. Insurance certificates.

5. Health and Safety Plan.

1.02 SHOP DRAWINGS

A. Wherever called for in the Contract Documents, or where required by the Engineer, the Contractor shall furnish to the Engineer for review, one (1) copy of each submittal. The term "submittal" as used herein shall be understood to include detail design calculations, shop drawings, fabrication and installation drawings, lists, graphs, operating instructions, catalog sheets, data sheets, samples, and similar items. Said submittals shall be submitted to the Engineer, 15 days minimum prior to planned work activity to allow review of same by the Engineer, and to accommodate the rate of construction progress required under the Contract, unless otherwise required and authorized by the Engineer. Should any submittal be a part of any schedule milestone and considered to be unacceptable by the Owner, the appropriate milestone shall be considered as not having been met until a complete and properly detailed submittal is received.

B. The Contract Drawings shall not be traced or reproduced by any method for use as or in lieu of detail shop drawings. Show dimensions and note which are based on field measurement. Identify materials and products in the work shown.

Indicate compliance with standards and special coordination requirements.

C. Attach to the front of each submittal a title sheet stating the pertinent product information submitted and reference the appropriate Specification Section and Paragraph. Apply stamp, signed or initialed, certifying that all quantities, dimensions, field construction criteria, materials, catalog numbers, and specified

Augusta Engineering and Environmental Services Department Deans Bride Road Landfill 2023 GCCS Expansion

CONTRACTORSUBMITTALS

013010-1

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion performance criteria has been reviewed in accordance with the requirements of the Work and the Contract Documents.

If this information is not provided with each submittal, the submittal shall be returned to the Contractor without action taken by the Engineer, and any delays caused thereby shall be the total responsibility of the Contractor.

D. All shop drawings or other submittals shall be accompanied by the form mutually agreed upon at the pre-construction meeting. Any submittal not accompanied by the approved form or if all applicable items on the form are not completed, the submittal will be returned to the Contractor without action taken by the Engineer.

E. Normally, a separate transmittal form shall be used for .each specific unrelated item or class of material or equipment for which a submittal is required.

Transmittal of a submittal of various items using a single transmittal form will be permitted only when the items taken together constitute a manufacturer's "package" or are so functionally related that this helps speed the review of the group or package as a whole. A multiple-page submittal shall be collated into sets, and each set shall be stapled or bound, as appropriate, prior to transmittal to the Engineer.

F. Except as may otherwise be provided herein, the Engineer will return prints of each submittal to the Contractor, with comments noted thereon, within 15 calendar days following their receipt by the Engineer. It is considered reasonable that the Contractor shall make a COll].plete and acceptable submittal to the Engineer by the second submission of a submittal item. The Owner reserves the right to withhold monies due the Contractor to cover additional costs of the Engineer's review beyond the second submittal.

G. If a submittal is returned to the Contractor marked "NO EXCEPTIONS TAKEN," formal revision and resubmission of said submittal will not be required.

H. If a submittal is returned to the Contractor marked "MAKE CORRECTIONS NOTED," formal revision and resubmission of said submittal will not be required. However, Contractor shall address the comments/corrections in the final Work. Revisions indicated on submittals shall be considered as changes necessary to meet the requirements of the Contract Documents and shall not be taken as the basis of claims for extra work.

I. If a submittal is returned to the Contractor marked "AMEND - RESUBMIT," the Contractor shall revise said submittal per Engineer's comments and shall resubmit the required number of copies of said revised submittal to the Engineer.

J. If a submittal is returned to the Contractor marked "REJECTED - RESUBMIT," the Contractor shall revise said submittal and shall resubmit the required number of copies of said revised submittal to the Engineer. •

Augusta Engineering and Environmental Services Department Deans Bride Road Landfill 2023 GCCS Expansion

CONTRACTOR SUBMITTALS

013010-2

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion

K. Fabrication of an item shall not commence before the Engineer has reviewed the pertinent submittals and returned copies to the Contractor marked either "NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED." Revisions indicated on submittals shall be considered as changes necessary to meet the requirements of the Contract Documents and shall not be taken as the basis of claims for extra work.

L. All Contractor submittals shall be carefully reviewed by an authorized representative of the Contractor prior to submission to the Engineer. Each submittal shall be dated, signed, and certified by the Contractor as being correct.

Contractor shall use the Owner-approved shop drawing stamp agreed upon at the pre-construction meeting. No consideration for review by the Engineer of any Contractor submittals will be made for any items which have not been so certified by the Contractor. All non-certified submittals will be returned to the Contractor without action taken by the Engineer, and any delays caused thereby shall be the total responsibility of the Contractor.

M. The Engineer's review of the Contractor submittals shall not relieve the Contractor of the entire responsibility for the correctness of details and dimensions. The Contractor shall assume all responsibility and risk for any misfits due to any errors in the Contractor submittals. Any fabrication or other work performed in advance of the receipt of approved submittals shall be entirely at the Contractor's risk and expense. The Contractor shall be responsible for the dimensions and the design of adequate connections and details.

N; Product Data

1. Product data includes standard printed information (e.g., specifications) on materials, products and systems, not specially prepared for this project, other than the designation of selections from among available choices printed therein. Submit only pages which are pertinent; mark each copy of standard printed data to identify pertinent products, reference it to Specification Section and Paragraph number. Show reference standards, performance characteristics, and capacities; dimensions; and required clearances. Said submittals shall be submitted to the Engineer, minimum 15 days prior to obtaining the material to review of same by the Engineer, and to accommodate the rate of construction progress required under the Contract, unless otherwise required and authorized by the Engineer.

2. Collect required data into one submittal for each unit of work or system, and mark each copy to show which choices and options are applicable to project. Modify manufacturer's standard schematic drawings and diagrams to supplement standard information and to provide information specifically applicable to the Work. Delete information not applicable.

3. Failure to follow the guidelines in paragraphs 1 and 2 above.shall be grounds for rejection of Contractor submittals.

Augusta Engineering and Environmental Services Department Deans Bride Road Landfill 2023 GCCS Expansion

CONTRACTORSUBMITTALS

013010-3

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion

0. Contractor shall notify Engineer in writing, at time of submittal, of proposed deviations from requirements of Contract Documents.

1.03 CONTRACTOR'S PROJECT SCHEDULES

A. The schedule shall be comprehensive, covering both activities at the site of the Work and offsite activities such as design, procurement, and fabrication. The schedule shall be orderly and realistic and shal_l be revised as necessary to meet this requirement. The Contractor shall promptly advise the Owner and Engineer of any occurrence that may impact the schedule. No revision to the schedule can be made without approval from the Owner and Engineer.

B. The detailed schedule and each revision thereof shall be subject to approval by the Owner and Engineer for conformity with the requirements of the Contract Documents. The Contractor shall assist the Owner and/or Engineer in reviewing and evaluating each schedule furnished. Disapproved schedules returned to the Contractor shall be revised to correct the defects noted and shall be resubmitted to the Owner within five (5) calendar days after receipt.

C. When required to perform and complete the changed Work in accordance with the revised schedule, the Contractor shall provide additional labor, materials, equipment, or other factors of production in excess of those in use before the changed Work was ordered.

1.04 SAMPLES

A. Unless otherwise specified, whenever in the Specifications samples are required, the Contractor shall submit one (1) sample of each such item or material to the Engineer for approval at no additional cost to the Owner.

B. Samples, as required herein, shall be submitted for approval a minimum of fifteen

(15) working days prior to ordering such material for delivery to the job site and shall be submitted in an orderly sequence so that dependent inaterials or equipment can be assembled and reviewed without causing delays in the Work.

C. All samples shall be individually and indelibly labeled or tagged, indicating thereon all specified physical characteristics and manufacturer's names for identification and submittal to the Engineer for approval.

D. Unless otherwise specified, all colors and textures of specified items will be selected by the Owner from the manufacturer's standard colors and standard produ,ct lines.

1.05 RECORD DRAWINGS

A. Contractor's Record Drawings shall be maintained in accordance with this Section. The Contractor shall keep and maintain at the job site one set of draft Redline Drawings.

Augusta Engineering and Environmental Services Department Deans Bride Road Landfill 2023 GCCS Expansion

CONTRACTORSUBMITTALS

013010-4

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion

1. On these, the Contractor shall mark all project conditions, locations, configurations, and any other changes or deviations which may vary from the details represented on the original Contract Drawings, including buried or concealed construction and utility features which are revealed during the course of construction.

2. Special attention shall be given to recording the horizontal and vertical location of all buried header, lateral, air supply line, liquid conveyance line and utilities, that differ from the locations indicated or which were not indicated on the Contract Drawings.

3. Redline Drawings shall be supplemented by any detailed sketches or typewritten changes to the specifications, as necessary or directed, to indicate fully the Work as actually constructed.

4. These master Redline Drawings shall be the Contractor's representation of as-built conditions, including all revisions made necessary by addenda, change orders, and the like.

5. Redline Drawings shall be maintained up-to-date during the progress of the Work and available for inspection by the Engineer.

B. The Contractor shall include a survey site plan and pipe route survey table with the Redline Drawings showing coordinates and elevations of all wells, condensate traps, valves, etc., and piping installed.

1. Piping shall be located every 50 feet and at grade breaks and changes in pipe slope and direction, fittings, tie-ins, appurtenances, etc., as required for the conformance survey.

2. For pipe runs of 100 feet or less, the pipe shall be located a minimum of every 20 feet.

3. Coordinates and elevations shall be included in the survey for pipe fittings, changes in pipe slope and direction, valves, buried flanges, appurtenances and other similar connections to the header piping, and the ground surface at each well and appurtenance, and for all pipe location shots.

4. All locations shall be shown in the coordinate system identical to that used for the Construction Drawings.

5. A Georgia Licensed Professional Surveyor shall certify all survey work pertaining to the Record Drawings.

C. Redline Drawings shall be accessible to the Engineer at all times during the construction period and shall be delivered to the Engineer upon Substantial Completion of the Work.

Augusta Engineering and Environmental Services Department Deans Bride Road Landfill 2023 GCCS Expansion

CONTRACTORSUBMITTALS

013010-5

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion

D. Requests for partial payments will not be approved if the Redline Drawings are not kept current and not until the completed Redline Drawings showing all variations between the Work as actually constructed and as originally shown on the Contract Drawings or other Contract Documents have been inspected by the Engineer.

E. Final payment will not be approved until the Contractor -prepared Record Drawings have been approved by the Engineer.

F. Upon Substantial Completion of the Work and prior to final acceptance, the Contractor shall complete and deliver a preliminary set of Record Drawings and Pipe Route Survey Table to the Engineer for review, conforming to the construction records of the CONTRACTOR.

1. The Contractor shall take care in reviewing the preliminary Record Drawings and Pipe Route Survey Data Table for accuracy and completeness.

2. If more than one review of the Record Drawings and Pipe Route Survey Data Table is required, the Contractor shall reimburse the Owner for the time-and-materials cost for the Engineer's subsequent reviews.

3. The Record Drawings shall be generated using AutoCAD 2018 ( or newer version) computer software and consist of corrected plans showing the reported location of the Work.

4. Upon the Engineer's acceptance of the Record Drawings, the Contractor shall provide two (2) complete sets of Record Drawings to the Engineer.

5. The information submitted by the Contractor will be assumed to be reliable, and the Engineer will not be responsible for the accuracy of such information, nor for any errors or omissions, which may appear on the Record Drawings as a result.

1.06 PROGRESS REPORTS

A. A progress report shall be furnished to the Owner with each application for progress payment. If the Work falls behind schedule, the Contractor shall submit additional progress reports at such intervals as requested.

B. Each progress report shall include sufficient narrative to describe any current and anticipated delaying factors, their effect on the construction schedule, and proposed corrective actions. Any Work reported complete, but which is not readily apparent to the Engineer, must be substantiated with satisfactory evidence.

C. Each progress report shall include a list of the activities completed with their actual start and completion dates, a list of the activities currently in progress, and the number of working days required to complete each.

Augusta Engineering and Environmental Services Department Deans Bride Road Landfill 2023 GCCS Expansion

CONTRACTORSUBMITTALS

0130 10-6

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion

1.07 SURVEY DATA

All field books, notes, as-built pipe slope calculations, photographs, sketches and other data developed by the Contractor in performing the surveys required by the Work shall be available to the Engineer for examination throughout the construction period. All locations and elevations shall be identified by qualified survey crews and tied to .the Coordinate System NAD 83 in feet. Survey shall be ·in accordance with the respective pipeline and well installation Specifications. All such data shall be submitted to the Engineer with documentation required for final acceptance of the Work.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION

Augusta Engineering and Environmental Services Department Deans Bride Road Landfill 2023 GCCS Expansion

CONTRACTORSUBMITTALS

013010-7

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion

SECTION 01 40 00

QUALITY CONTROL

PARTl -GENERAL

1.01 SITE INVESTIGATION AND CONTROL

A. Contractor shall verify all dimensions in the field and check field conditions continuously during construction. Contractor shall be solely responsible for any inaccuracies built into the work due to Contractor's failure to comply with this requirement.

B. CONTRACTOR shall inspect related and appurtenant WORK and report in writing to the Owner and Engineer any conditions which will prevent proper completion of the work. Failure to report any such conditions shall constitute acceptance of all site conditions, and any required removal, repair, or replacement caused by unsuitable conditions shall be performed by the Contractor at Contractor's sole cost and expense.

1.02 INSPECTION OF THE WORK

A. All work performed by the Contractor shall be inspected by the Contractor and designated Owner's Project Manager and nonconforming work shall be noted and promptly corrected. The Contractor is respc;msible for the work conforming to the Contract Documents.

B. The WORK shall be conducted under the general observation of the designated Owner's Project Manager and is subject to inspection by representatives of the Owner acting on behalf of the Owner to ensure compliance with the requirements of the Contract Documents. Such inspection may include mill, plant, shop, or field inspection, as required. The Project Manager or any inspector(s) shall be permitted to access all parts of the work, including plants where materials or equipment are manufactured or fabricated.

C. The presence of the Project Manager or any inspector(s), however, shall not relieve the Contractor of the responsibility for the proper execution of the work in accordance with all requirements of the Contract Documents. Compliance is a duty of the Contractor, and said duty shall not be avoided by any act or omission on the part of the Project Manager.or any inspector(s). Inspection of work later determined to be nonconforming shall riot be cause or excuse for acceptance of the nqnconforming work. The acceptance of nonconforming work shall be approved by the Owner when adequate compensation is offered and it is in the Owner's best interest.

D. All materials and articles furnished by the Contractor shall be subject to inspection, and no materials or articles shall be used in the WORK until they have been inspected and accepted by the Project Manager or other designated

Augusta Engineering and Environmental Services Department Deans Bride Road Landfill 2023 GCCS Expansion

Quality Control 014000-1

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion representative. No work shall be backfilled, buried, hidden, or otherwise covered until it has been inspected. Any work so covered in the absence of inspection shall be subject to uncovering at the Contractor's expense. Where uninspected work cannot be uncovered, such as in concrete cast over reinforcing steel, all such work shall be subject to demolition, removal, and reconstruction under proper inspection, and no additional payment will be allowed.

1.03 TIME OF _INSPECTION AND TESTS

A. Any samples and test specimens required under these Specifications shall be furnished and prepared for testing in ample time for the completion of the necessary tests and analyses before said articles or materials are to be used.

Contractor shall furnish and prepare all required test specimens at Contractor's own expense. Whenever the Contractor is ready to backfill, bury, hide, or otherwise cover any work under this Contract, the Project Manager shall be notified not less than 24 hours in advance to request inspection before beginning any such work of covering. Failure of the Contractor to notify the Project Manager at least 24 hours in advance of any such inspections shall be reasonable cause for the Project Manager to order a sufficient delay in the Contractor's schedule to allow time for such inspection, any remedial, or corrective work required, and all costs of such delays, including its impact on other portions of the work, shall be borne by the Contractor.

1.04 SAMPLING AND TESTING

A. When not otherwise specified, all sampling and testing shall be in accordance with the methods prescribed in the current standards of the ASTM, as applicable to the class and nature of the article or materials considered. However, the Owner reserves the right to use any generally-accepted system of inspection which, in the opinion of the Engineer, will ensure the Owner that the quality of the workmanship is in full accord with the Contract Documents.

B. Any waiver-of any specific testing or other quality assurance measures, whether or not such waiver is accompanied by a guarantee of substantial performance as a relief from the specified testing or other quality assurance requirements as originally specified, and whether or not such guarantee is accompanied by a performance bond to assure execution of any necessary corrective or remedial work, shall not be construed as a waiver of any technical or qualitative requirements of the Contract Documents.

C. Notwithstanding the existence of such waiver, the Engineer shall reserve the right to make independent investigations and tests as specified in the following paragraph and, upon failure of any portion of the WORK to meet any of the qualitative requirements of the Contract Documents, shall be reasonable cause for the Engineer to require the removal or correction and reconstruction of any such work.

Augusta Engineering and Environmental Services Department Deans Bride Road Landfill 2023 GCCS Expansion

Quality Control 0140 00-2

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion

D. In addition to any other inspection or quality assurance provisions that may be specified, the Engineer shall have the right to independently select, test, and analyze, at the expense of the Owner (only with prior approval by the Owner), additional test specimens of any or all of the materials to be used. Results of such tests and analyses shall be considered along with the tests or analyses made by the· Contractor to determine compliance with the applicable specifications for the materials so tested or analyzed provided that wherever any portion of the work is discovered, as a result of such independent testing or investigation by the Engineer, which fails to meet the requirements of the Contract Documents, all costs of such independent inspection and investigation and all costs of removal, correction, reconstruction, or repair of any such work shall be borne by the Contractor.

1.05 RIGHT OF REJECTION

A. The Project Manager or designated representative, acting for the Owner, shall have the right at all times and places to reject any articles or materials to be furnished hereunder which, in any respect fail to meet the requirements of the Contract Documents, regardless of whether the defects in such articles or materials are detected at the point of manufacture or after completion of the work at the site. If the Project Manager or designated representative, through an oversight or otherwise, has accepted materials or work which is defective or which is contrary to the Contract Documents, such material, no matter in what stage or condition of manufacture, delivery, or erection, may be rejected.

B. Contractor shall promptly remove or replace rejected articles or materials from the site of the work after notification of rejection.

C. All costs of removal and replacement of rejected articles or materials, as specified herein, shall be borne by the Contractor.

D. Failure to promptly remove and replace rejected work shall be considered a breach of this specification and the Owner may, after 7 days notice, terminate the Contractor's right to proceed with the affected work and remove and replace the work and issue a back charge to cover the cost of the work.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION

Augusta Engineering and Environmental Services Department Deans Bride Road Landfill 2023 GCCS Expansion

Quality Control 0140 00-3

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion

SECTION 01 50 30

PROTECTION OF EXISTING FACILITIES

PART 1 - GENERAL

1.01 GENERAL

A. CONTRACTOR shall protect all existing utilities and improvements ·not designated for removal and restore damaged or temporarily relocated utilities and improvements to a condition equal to or better than they were prior to such damage or temporary relocation, all in accordance with requirements specified herein, and in accordance with the requirements of the Contract Documents.

B. CONTRACTOR shall determine the exact locations and depths of all utilities indicated on the drawings which affect the WORK. In addition to those indicated, CONTRACTOR shall make exploratory excavations of all utilities. All such exploratory excavations shall be performed as soon as practicable after award of Contract and, in any event, a sufficient time in advance of construction to avoid possible delays to CONTRACTOR's WORK. When such exploratory excavations show the utility location as indicated oil the drawings to be in error, CONTRACTOR shall so notify PROJECT MANAGER.

C. The number of exploratory excavations required shall be that number which is sufficient to determine the alignment and depth of the utility.

1.02 RIGHTS-OF-WAY

A. CONTRACTOR shall not do any work that would affect any oil, gas, sewer, or water pipeline; any fiber, telephone, telegraph, or electric transmission line; any fence; or any other structure, nor shall CONTRACTOR enter upon the rights-of-way involved until notified by the PROJECT MANAGER that the OWNER has secured authority from the property owner. After authority has been obtained, CONTRACTOR shall give said owner due notice of CONTRACTOR intention to begin WORK, and shall give said owner convenient access and every facility for removing, shoring, supporting, or otherwise protecting such pipeline, transmission line, ditch, fence, or structure and for replacing same. When two (2) or more Contracts are being executed at one time on the same or adjacent land in such manner that WORK on one Contract may interfere with that on another, the OWNER shall decide which CONTRACTOR shall have priority to perform and in what manner. When the territory of one Contract is the necessary or convenient mean~ of access for the execution of another Contract, such privilege of access or any other reasonable privilege may be granted by the OWNER to the CONTRACTOR so desiring, to the extent, amount, manner, and times permitted.

No such decision regarding the method or time of conducting the work or the use of territory shall be made the basis of any claim for delay or damage, except as

Augusta Engineering and Environmental Services Department PROTECTION OF EXISTING FACILITIES Deans Bride Road Landfill 2023 GCCS Expansion 01 50 30-1

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion provided for temporary suspension of the WORK in the General Conditions of the Contract.

1.03 EXISTING UTILITIES AND IMPROVEMENTS

A. General. CONTRACTOR shall protect all utilities and other improvements which may be impaired during construction operations. It shall be CONTRACTOR's responsibility to ascertain the location of all possible e~sting utilities and other improvements indicated on the drawings or otherwise that will be encountered in the construction operations, and to see that such utilities or other improvements are adequately protected from damage due to such operations. The CONTRACTOR shall contact the OWNER immediately upon discovery of additional utilities in the area prior to starting and during the performance of the work. CONTRACTOR shall take all possible precautions for the protection of unforeseen utility lines for uninterrupted service and such special protection as may be directed by the PROJECT MANAGER.

B. Utilities to Be Moved. In case it shall be necessary to move the property of any public utility or franchise holder, such utility company or franchise holder will, upon proper application by the CONTRACTOR, be notified by the PROJECT MANAGER to move such property within a specified reasonable time.

CONTRACTOR shall not interfere with said property until after the expiration of the time stipulated.

C. Owner's Right of Access. The rightJs reserved to the OWNER and to the owners of public utilities and franchises to enter at any time upon any public street, alley, right-of-way, or easement for the purpose of making changes in their property made necessary by the WORK of this Contract.

D. Known Utilities. Existing utility lines that are shown on the drawings or the locations of which are made known to the CONTRACTOR prior to excavation that are to be retained an~ all utility lines that are constructed during excavation operations shall be protected from damage during excavation and backfilling and, if damaged, shall be immediately repaired by CONTRACTOR at CONTRACTOR's expense.

E. Unknown Utilities. If CONTRACTOR damages any existing utility lines that are not shown on the drawings or the locations of which are not made known to CONTRACTOR prior to excavation, or were, or could not have been verified or located by the CONTRACTOR prior to starting work, a written report thereof shall be made immediately to the PROJECT MANAGER. If directed by the PROJECT MANAGER, repairs shall be made by CONTRACTOR under the provisions for changes and extra work contained in the General Conditions.

F. Utilities to Be Removed. When utility lines that are to be removed are encountered within the area of operations, CONTRACTOR shall notify the

Augusta Engineering and Environmental Services Department PROTECTION OF EXISTING FACILITIES Deans Bride Road Landfill 2023 GCCS Expansion 01 50 30-2

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion

PROJECT MANAGER a sufficient time in advance for the necessary measures to be taken to prevent interruptions of the service.

G. Approval of Repairs. All repairs to a damaged improvement shall be inspected and approved by an authorized representative of the improvement before being concealed by backfill or other work.

H. Relocation of Utilities. Where the proper completion of the WORK requires the temporary or permanent removal and/or relocation of an existing utility or other improvement which is shown on the drawings, CONTRACTOR shall at CONTRACTOR's own expense, remove and, without unnecessary delay, temporarily replace or relocate such utility or improvement in a manner satisfactory to the PROJECT MANAGER and the OWNER of the facility. In all cases of temporary removal or relocation, restoration to former location shall be accomplished by CONTRACTOR in a manner that will restore or replace the utility or improvement as nearly as possible to its former locations and to as good or better condition than found prior to removal.

I. Maintaining in Service. All oil and gasoline pipelines, power, telephone, or other communication cable ducts, gas and water mains, irrigation lines, sewer lines, storm drain lines, poles, and overhead power and communication wires and cables encountered along the line of the WORK shall be maintained continuously in service during all the operations under the Contract, unless other arrangements satisfactory to the PROJECT MANAGER are made with the OWNER of said pipelines, duct, main, irrigation line, sewer,- storm drain, pole, wire, or cable.

CONTRACTOR shall be responsible for and shall make good all damage due to CONTRACTOR's operations, and the provisions of this Section shall not be abated even Tn the event such damage occurs after backfilling or js not discovered until after completion of the backfilling.

1.04 SUBSURFACE OBSTRUCTIONS

A. CONTRACTOR shall field determine, before pipeline trenching and associated excavations are begun, the depth and location of existing utilities. Utility locations indicated on the plans were obtained from the records available, but have not been field verified, nor have depths been measured or observed. CONTRACTOR shall submit descriptions, depths, and locations of subsurface obstructions to the PROJECT MANAGER for review.

B. In excavation, backfilling, and laying pipe, care shall be taken not to remove, disturb, or injure existing pipes, conduits, or structures. If necessary, CONTRACTOR at own expense shall sling, shore-up, and maintain such structures in operation.

C. CONTRACTOR shall obtain the permission of and give sufficient notice to the proper authorities of CONTRACTOR's intention to remove or disturb any pipe, conduit, etc., and shall abide by their regulations governing such work.

Augusta Engineering and Environmental Services Department PROTECTION OF EXISTING FACILITIES Deans Bride Road Landfill 2023 GCCS Expansion 01 50 30-3

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion

D. In the event subsurface structures are broken or damaged in the execution of the WORK, CONTRACTOR shall immediately notify the proper authorities and repair the damage at once at own expense. Repairs shall be made to the satisfaction of the PROJECT MANAGER. CONTRACTOR shall be responsible for any damage to persons or property caused by such breaks or due to own neglect in reporting and/or repairing such damages.

E. OWNER or PROJECT MANAGER will not b_e liable for any claims _made by the CONTRACTOR based on underground obstructions that could have been reasonably identified as being different than that indicated on the plans.

CONTRACTOR shall uncover subsurface obstructions in advance of construction so that the method of avoiding same may be determined before the work reaches the obstruction.

1.05 CONFLICTS WITH OTHER UTILITIES

A. CONTRACTOR shall coordinate and cooperate with the OWNER to ensure that no damages to existing utilities occur.

B. All temporary support or minor adjustment which does not require replacement or direct bypass connections to these existing services (such as all direct-buried telephone cables or two-inch and smaller gas lines) will be the responsibility of the CONTRACTOR.

C. OWNER will not be responsible for any delay or inconvenience to the CONTRACTOR resulting from the existence, removal, or adjustment of any public or private utility that could have been reasonably identified. Additional costs incurred as a result thereof shall be borne by the CONTRACTOR and considered as included in the Contract Price.

1.06 EXISTING FENCE LINES

A. Any fence removed or temporarily relocated shall be restored to its original condition and location.

B. All cost for such temporary removal or replacement shall be included as indicated in the unit prices bid. No direct payment will be made for fence replacement unless specifically noted otherwise.

1.07 UTILITY INVESTIGATION

A. Prior to commencing with trench or other excavations required for the performance of the WORK, CONTRACTOR shall conduct a field investigation for the purpose of determining existing locations of all underground utilities and facilities which are shown on the drawings. The investigation shall be made by hand or machine excavation. All such excavations shall include removal of surface material and obstructions required to perform the excavations.

CONTRACTOR shall provide sheeting, shoring, and bracing, as required, to

Augusta Engineering and Environmental Services Department PROTECTION OF EXISTING FACILITIES Deans Bride Road Landfill 2023 GCCS Expansion 01 50 30-4

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion minimize the required size of the excavation and support adjacent ground, structures, roadways, and utilities. After the data is obtained at each excavation site, CONTRACTOR shall immediately backfill each excavation site. Backfill shall be compacted clean soil for the full depth. The surface shall be returned to its original grade and condition except that paved areas may be temporarily surfaced and maintained where excavations required for the performance of the WORK coincide with the location of the investigative location. CONTRACTOR shall be responsible for all costs associated with repair of roadways, paving, structures, underground and above ground utilities and facilities damaged in conducting the investigations.

B. Findings of the investigation shall be reported to the PROJECT MANAGER. The PROJECT MANAGER shall furnish two sets of full size blueline drawings for CONTRACTOR's field use in recording the findings of the investigation and for CONTRACTOR's office use in transcribing the field investigation information onto same for submission to the PROJECT MANAGER. CONTRACTOR shall clearly designate all found utilities and facilities discovered whether or not shown on the Contract Drawings. CONTRACTOR shall provide written detailed description of any underground utility or facility conflicting with the elevation or alignment of the WORK.

C. CONTRACTOR shall describe size, material, and location of existing underground utilities and facilities. Locations and elevations shall be referenced to project stationing, distance from base line, and project bench marks.

1.08 PROTECTION OF EXISTING LANDFILL

A. The CONTRACTOR shall use extreme care during construction activities on or near the landfill to not damage unnecessarily any existing features.

B. The CONTRACTOR shall use low ground pressure equipment on final geomembrane cover areas so as to not disturb the certified final cover.

C. Assistance will be given to the CONTRACTOR in determining the toe of the landfill as needed to avoid damage to the liner and existing features. This assistance shall in no way relieve the CONTRACTOR from responsibility and liability in maintaining site conditions.

D. Any damage resulting from the CONTRACTOR's operations shall be repaired by the CONTRACTOR to original conditions or replaced with new materials at no additional cost to the OWNER. Repairs shall be as directed by the PROJECT M~AGER with approved materials.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION

Augusta Engineering and Environmental Services Department PROTECTION OF EXISTING FACILITIES Deans Bride Road Landfill 2023 GCCS Expansion 01 50 30-5

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion

SECTION 01 70 30

PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.01 SUMMARY

A. The Contractor shall maintain at the site one hard copy record set of:

1. Drawings

2. Project Manual

3. Addenda

4. Change orders and other modifications to Contract

5. Project Manager field orders, written instructions or clarifications

6. Approved submittals

7. Field test records

8. Daily logs

9. Survey notes and calculations

10. Construction photographs

11. Associated permits

12. Certificates of inspection and approvals

1.02 SUBMITTALS

A. Upon Substantial C9mpletion the Contractor shall:

Deliver two identical, complete review sets of Record Documents within 14 calendar days after Substantial Completion to the Engineer. Each set of Record Documents shall consist of: one set of 24 x 36-inch redline drawings and one copy of record documentation and vendor and material supply information. The Engineer shall comment and return one set to the Contractor. The final Record Drawings shall be generated using computer software as specified in Part 3.03 F of this Section.

B. Accompany the submittals with a transmittal letter containing the following:

1. Date

2. Facility project title and number

3. Contractor's name and address

4. Title of record document

5. ' Signature of Contractor or authorized representative

C. At Owner's acceptance:

Upon receipt of the Engineer's comments, Contractor shall deliver within 14 days to the Engineer four (4) complete sets of Record Drawings incorporating the

Augusta Engineering and Environmental Services Department Deans Bride Road Landfill 2023 GCCS Expansion

PROJECT RECORD DOCUMENTS

017030-1

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion

Engineer's comments. Record Drawings submitted by the Contractor shall be sealed by a Georgia Licensed Professional Land Surveyor. If the second submittal of the Record Documents is deemed incomplete or does not address all of the Engineer's comments, the submittal shall be returned to the Contractor. The Contractor shall reimburse the Owner for the Engineer's expense for the additional reviews.·

PART 2 - PRODUCTS (Not Used)

PART 3-EXECUTION

3.01 MAINTENANCE OF RECORD DOCUMENTS AND SAMPLES

A. Contractor shall store documents and samples in Contractor's field office apart from documents used for construction.

1. Provide files and racks for storage of documents.

2. Provide secure storage space for storage of samples.

B. Maintain documents in clean, dry, legible condition and in good order. Record Documents shall not be used for construction purposes.

C. Make documents and samples available at all times for inspection by Engineer.

D. Failure to properly maintain Record-Documents as stated herein may be reason to delay a portion of progress payments until the requirements of this Section are satisfied. •

3.02 CONSTRUCTION PHOTOGRAPHS

A. Progress Photos: The Contractor shall provide a photographic record of construction progress every other week to the Owner. For each submittal, at a minimum, the photographic record shall consist of an electronic set of 12 digital color photographs, each formatted to 4 inches by 6 inches. The Engineer shall reserve the right to select the views to be photographed. The photographs shall be of good quality as determined by the Engineer, and date stamped. Each photograph will be captioned with the following items identified:

- Facility project name and number

- Date photograph was taken

- Detailed description identifying location and name of feature photographed

- Name of Contractor

B. Photographs shall be taken weekly or during execution of individual work items, whichever is more frequent, beginning prior to the start of construction and continuing through the completion of all construction.

Augusta Engineering and Environmental Services Department Deans Bride Road Landfill 2023 GCCS Expansion

PROJECT RECORD DOCUMENTS

017030-2

Addendum 1 Bid Item #23-237 Deans Bridge Rd MSW Landfill Ph 3 Gas Collection & Control System Expansion

C. Photographs shall be taken to document each major work item, including:

1. Pre-construction conditions.

2. Mobilization and storage of materials. Materials photographed shall include the pipe, sumps, and fittings to be used in the work.

3. Installation of landfill gas extraction wells.

4. Installation of the gas lateral and header piping, including pipe fusion.

5. Abandonment in-place of limited section of lateral pipes.

6. Road crossing and casing.

7. Connection of gas lateral piping to header.

8. Connection of header, air line, and condensate piping to the existing LFG system.

9. Installation of air supply line ~d condensate discharge line in trench, including cross-over of pipes and appurtenances.

10. Backfilling of installed pipe, including placement of warning tape and compaction.

11. Road crossings, ditch crossings, and stormwater swale crossings.

12. Installation of pneumatic pumps in sumps.

13. Buried blind flanges.

14. Tie-in of each condensate discharge line to traps and leachate collection…